Schedule Pelaksanaan Pekerjaan: No. Uraian Pekerjaan Bobot Nov-23 Dec-23 Jan-24
Schedule Pelaksanaan Pekerjaan: No. Uraian Pekerjaan Bobot Nov-23 Dec-23 Jan-24
1 Pengadaan Batu Kosong / Rockfill 12,739.63 100% 10.00% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 8.11% 4.11%
Rencana 100% 10.00% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 8.11% 4.11%
Komulatif 21.11% 32.22% 43.33% 54.44% 65.56% 76.67% 87.78% 95.89% 100.00%
Realisasi 0 2.58% 15.28% 24.75% 31.61% 18.99% 3.34% 1.15% 1.15% 1.15%
Komulatif 2.58% 17.86% 42.61% 74.22% 93.21% 96.55% 97.70% 98.85% 100.00%
Volume 328.68 1,946.62 3,153.06 4,027.00 2,419.26 425.50 146.51 146.51 146.51
Komulatif 328.68 2,275.30 5,428.36 9,455.35 11,874.61 12,300.11 12,446.62 12,593.12 12,739.63