SCHEDULE PELAKSANAAN PEKERJAAN

Proyek : Pembangunan Jalan Tol Japek 2 Selatan Paket 3


Item Pekerjaan: Pengadaan Batu Kali Belah 20/30, dll
No.SPPM: 573/SPPM/WK/INF2/1319006/2023

Nov-23 Dec-23 Jan-24


No. Uraian Pekerjaan Volume Bobot
M1 M2 M1 M2 M3 M4 M1 M2 M3 M4

1 Pengadaan Batu Kosong / Rockfill 12,739.63 100% 10.00% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 8.11% 4.11%

Rencana 100% 10.00% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 8.11% 4.11%

Komulatif 21.11% 32.22% 43.33% 54.44% 65.56% 76.67% 87.78% 95.89% 100.00%

Realisasi 0 2.58% 15.28% 24.75% 31.61% 18.99% 3.34% 1.15% 1.15% 1.15%

Komulatif 2.58% 17.86% 42.61% 74.22% 93.21% 96.55% 97.70% 98.85% 100.00%

Volume 328.68 1,946.62 3,153.06 4,027.00 2,419.26 425.50 146.51 146.51 146.51

Komulatif 328.68 2,275.30 5,428.36 9,455.35 11,874.61 12,300.11 12,446.62 12,593.12 12,739.63