INSTRUCTIONS ON UG PRODUCTION SCHEDULE REPORTING

Underground Production Schedule Reporting

Keep in mind that your schedule starts in year 2024. The screenshots
in this document is for a schedule that starts in 2021.

Part 1 – Monthly Report

Developments

A. In reporting mode, select Pivot ➔ Prorated Activities.

B. Give it a descriptive name…Right click in the data as shown to bring up the filed list.

1
INSTRUCTIONS ON UG PRODUCTION SCHEDULE REPORTING

C. Select the required fields as shown below…

2
INSTRUCTIONS ON UG PRODUCTION SCHEDULE REPORTING

D. Only display development activities…

E. Display the report with a lot as shown below.

3
INSTRUCTIONS ON UG PRODUCTION SCHEDULE REPORTING

Production

A. Create a monthly report for stope production. Include Stope_extraction as activity


type…also include Tonnes and Au in the report.

4
INSTRUCTIONS ON UG PRODUCTION SCHEDULE REPORTING

Part 2 – Quarterly Report

Developments

Production

5
INSTRUCTIONS ON UG PRODUCTION SCHEDULE REPORTING

Part 3 – Yearly Report

Developments

Production

6
INSTRUCTIONS ON UG PRODUCTION SCHEDULE REPORTING

Part 4 – Adding more Scheduling Periods

Keep in mind that your schedule starts in year 2024. The screenshots
in this document is for a schedule that starts in 2021.
A. Go back to the backstage area in your Atlas project and Select Configuration ➔
Scheduling Periods.

B. Auto-populate as shown…

7
INSTRUCTIONS ON UG PRODUCTION SCHEDULE REPORTING

C. New 12 months will be added.

D. Create new quarterly reporting periods.

8
INSTRUCTIONS ON UG PRODUCTION SCHEDULE REPORTING

E. Create new yearly reporting periods.

F. Click OK to continue…

9
INSTRUCTIONS ON UG PRODUCTION SCHEDULE REPORTING

G. All the reports will be updated for the new added periods.

Add more periods as


required…
THE END
10