Professional Documents
Culture Documents
Project Costing Terms
Project Costing Terms
A company department responsible for run Projects of the Company profitably by Contract & Subcontract Management, Cost Control,
Planning & Scheduling, Project Auditing & constant Monitoring over all project aspects.
CONTRACTS
Agreement
Mutually agreed terms between two parties about proposals & acceptance on paper duly signed by both parties.
Contract
Mutually agreed terms between two parties about proposals & acceptance on paper duly signed by both parties bound by enforcement
Law.
Type of Contract
Contracts fall into following categories
1) Fixed Price (Lump Sum)
2) Unit Rate
A performing Contractor has to complete the agreed qty’ of work for an agreed fixed Contract Value. Risks of all Cost escalation rest on
performing Contractor.
Contractor is legally bound to perform the following for a fixed Contract Value against approved Rules & Credit
a. Design,
b. Engineering,
c. Procurement,
d. Construction,
e. Commissioning,
f. Hand over
Contractor is legally bound to perform the following for a Provisional Contract Value against Agreed Rules & Credit
a. Full or Partial Procurement,
b. Construction,
c. Commissioning,
d. Hand over
Advance Payment
The Part of Payment made to Contractor by Client Initially (5% to 20 % of CV) against mobilization of Resources & Start Temporary
Facilities .it shall be recovered against Each Progress Invoice submitted by Contractor by the same %
Retention Payment
The part of payment with held by Client against each progress payment (5% to 10 %) in order to ensure satisfactory performance
completion of contract terms. Client shall release the retention upon successful completion of the works agreed
Work
Total amount of resources & time required to complete an activity
Bill of Quantity (B.O.Q)
Total Qty of the Work specified in Main Contract
Material Take OFF (M.T.O)
Total Qty of the Work obtained from IFC drawings against B.O.Q
LD (Liquidate Damage)
Debt imposed by the owner on the Performing Contractor against delayed work completion which Affect total project completion and/or
a part of the project completion by performance wise & cost wise.
COSTING
Budget
The planned cost for an activity or project.
Revenue
Income against work performed as per agreed contract terms & conditions
Cost
Incurred expenditure against performed work
Profit
Saved cost against performed work (Revenue - Cost)
Committed Cost
Cost incurred to be paid against work performed
(GVWP – GVWI) Gross Value of Work Performed (GVWP) minus Gross Value of Work Invoiced (GVWI)
Earned Man-hour
The time in standard hours credited as a result of the completion of a given task or a group of tasks
(Unit Man-hour x Completed Work Qty)
Actual Man-hour
Time consumed in standard hours to the completion of a given task or a group of tasks
Productivity
Ratio between Earned Man-hours & Actual Man-hour
Trade /
Sl General Responsibilities
Designation
1) Site Tracking
2) Progress Updating,
1 Jr.Qs
3) PC Preparation
4) Assists to Site QS for preparation of MTO .
1) MTO
2) Preparation of Monthly Progress Valuation
3) Preparation of C.O Request,
2 Site QS 4) Costing Reports to H.O
5) Preparation of Star Rate for a Non-BOQ Items / Works
6) Verify & Certify the S/C Invoices & Process the Payments
4 Sr.QS
1) Control the Cost with in the Budget
2) Revise the Operating Budget for approved Changes in Contract Value
3) Review of MRP & ERP prior to get approval from top management
4) Claim Negotiation with Client for Star Rate ,Additional Works
5) Ensuring all Executive Mgmt’ reports prior to Sr.PM Approval
6) Maintaining & Control Over the All contract Documents
7) Co-ordinate with Execution team & H.O regarding Cost issues & Reports
8) Carry-Out the Commercial Close-out & arrange all necessary backup documents for the release
of retention money from client