Professional Documents
Culture Documents
Laurentian University
SUDBURY. Ontario.
APPDEMCAoc
The author has granted a non- L'auteur a accordé une licence non
exclusive licence allowuig the exclusive permettant à la
National Library of Canada to Bibliothèque nationale du Canada de
reproduce, loan, distribute or sel1 reproduire, prêter, distribuer ou
copies of ths thesis in microform, vendre des copies de cette thèse sous
paper or electronic formats. la forme de microfiche/film, de
reproduction sur papier ou sur format
électronique.
The destressing project. the research. and compilation of this thesis was carrird out
with the help and encouragement of a number of people. Sincerr thanks are due to al1 of
them. In particular. I wish to acknowledge: Doctors C. D. Martin and D.H. Rousell for their
guidance and suggestions for the manuscript: INCO Limited. C. Langille for his
encouragement and Cor sreking approval for the project as a thesis topic fiorn Mines
Technical Services management: M. Sylvestre for approvd of the project as a thesis. Thanks
are aiso extended to management at Stobie Mine particularly: J. Loring ( Manager): G . Elliott
(Grneral Foreman) for supplying the required support to kerp the project moving. Thanks
are also extended to: Colin McAnulty (Division supervisor): Micliarl Paventi (plamer): and
Chris Wereley (technical representative with Dyno Nobel): for their direct involvement in
the project. The author wishes also to acknowledge Chris Preston. research scientist with
Dyno Nobel and guest Professor of the Advanced Explosives course at Laurentian
University. for his encouragement and guidance at the on-set of the project.
In particular I wish to thank my wife. Susan O'Donnell. and my farnily for their
encouragement. and patience during my absence while taking courses and panicularly during
Page
Abstract
Acknowledgements
Table of Contents
List of Appendices
List of Figures
Chapter 1 Introduction
2.1 Introduction
Insta bility 11
2.6.2 Support
3.63 Destressing
2.8 Summary
3.1 Introduction 35
Spaced Joints
3.8 Summary
4.4.2 E~plosives
4.5 Instrumentation
Appendices
B.3 Conclusion
References 131
List of Figures
Breakthrough destressing
Abutment destressing
List of Tables
Rockbursts are the result of the sudden release of stored strain energy derived £iom
the stresses induced by rnining at depth or to a high extraction ratio. Conml methods range
fiom modifiing geometries to altering the rock properties by destressing. The physical
expression of the release of stored strain energy includes dog-earing, core disking, slabbing,
pillar failure and bursting. A review of the histoncal development and a comprehensive list
of the various rnethods of destressing are outlined. Special interest is paid to destressing of
pillars, culminating in the description of the destressing of 25 Pillar, a regional pillar at
NCO's Stobie Mine (world's Iargest destress blast to date). The destress slot, which was
designed to promote failure in the core of the pillar, provides a dot dong which mining can
safely proceed. The nsk of bursting has been reduced for the possible extraction of 1.8
million tons of ore between the 550 and 520-m levels.
Resume
Les coupes de troit sont la consequence de soudaine liberation d'energie accumulée.
Cet energie denve des tensions provoquées par la profondeur ou un haut rapport d'extraction.
Les methodes de control vont de la modification de la geomeüie a l'alteration des proprietés
de terrain par des tires de relaxation. L'expression physique de cette liberation d'energie
inclus la formation d'elipse dans les trous forages et de disques carrotes, I'ecaillage, et les
coups de toit. La revue du developement historique et un appercu detaillé des methodes
utilisées pour modifiées les tenains sont exposés. Un interest special est donné aux methodes
utilisées pour les pilliers, suivi par la description du cas particulier du pillier # 25, un pillier
regional a la mine d'MC0 Stobie. La rainure de tires de relaxation qui a été dessiner dans
le but de promouvoir l'échec au noyau du pillier, represente le terrain au long duquel
l'opération de minage peut continuer avec securité. Le risk de coups de roche a été reduit
pour l'extraction de minerai entre les niveaux 550 et 520-m.
Chapter 1 Introduction
Underground mining is subject to a number of risks that have safety and economic
reconditioning costs. The cornmon physicai phenomena associated with these risks are an
unexpected in-rush of water. fire. methane explosions. falls of ground and rockbursts. Of
these physical phenomena. rockbursts are the most rlusive. difficult to prevent. and have the
potential to significantly impact the operational economics. eg.. die cost of rockbursts in the
Coeur d' Alene Mining district has been pegged at 8 to 18% of the total mining costs or $10
The cause o f rarthquakes associated with major faults. such as the San Andreas. is
the sudden release of stored strain enerpy (Scholz. 1990). Slip does not proceed smoothly
and uniformly dong the rntire fault surtàce. Instead. it is local and abrupt. A rockburst is an
instantaneous. violent failure of rock whereby fragments of rock are ejrcted into mine
openings (Hedley 1992). Rockbursts are also associated with the release of stored strain
energy and generally occur at great depths. However. rockbursts c m also occur at shallow
depths. in pillars under high mining-induced stresses. and in shallow areas of high tectonic
stress.
The classic rnethods of rockburst aileviation are proper mining sequences: reasonablr
opening dimensions. geometries and mining rates: stringent filling practices: the use of
damage. Of these methods destressing and support are the o d y ones that c m be used by the
excavation personnel. While the role of support has been extensively investigated as a
mitigative measure to control rockbursts. destressing has not (Camiro 1995).
Destressing is a ground control technique. whereby explosives are used to release the
stored strain energy in a controlled manner by.(l) creating or estending a Fracture zone
around openings or ( 2 ) fracturing pillars that are likely to burst. A successhl destressing
program reduces the potential occurrence of a rockburst and also reducés the need for costly
This thesis is arranged in five chapters. Chapter 2 introduces the topic of rockbursts
as a mining hazard that must be rnanaged. highlights the indicators for increased rockburst
potential and summarises rockburst mitigation measures comrnonly used in mines. Chapter
3 is a summary of case studies where destressing. particularly pillars. bas been used as a
regional pillar at Stobie Mine. Sudbury. To the author's knowledge. this application of
destress blasting. is the largest undenaken by the international mining industry. Finally
Several appendices are included to accommodate data and figures from numerical
Lirnited since 1962. with special ernphasis on applications developed by the author and his
Kaiser (1988) proposed that rock mass failures are of iwo types: falls of ground (non-
violent. gradua1 failures) and rockbursts (violent. instantaneous. brinle failures). Hedley
(1991)suggested there are three types of rockbursts: (1) strain bursts. ( 2 ) pillar bursts and
causes ofrockbursts are: (1) surface instabilitirs at or near a working face characterised by
spalling at the free face: ( 2 ) propagation of shear fractures in the rock mass ahead of the
stope face: (3) sudden collapse of over stressed pillars: and (4) slip dong Faults or bedding
planes. Rockbursts are always associated with rrgions of over-stressed rock. Factors which
lead to over stressing include: high hydrostatic and tectonic stresses. high extraction ratio and
Ground stresses are caused by geological and artificial phenornena. The most comrnon
environment where a rock will be subject to high in-situ stress is at depth. Where the in-situ
stress is caused by lithostatic and the locked in stresses of tectonic ongin (Franklin &
Dusseault 1989). A mine opening dismpts the local stress field and a new set of stresses is
induced in the surrounding rock. A knowledge of the magnitudes and directions of the in-situ
and induced stresses is essentiai for the design of mine openings, because if the strength of
the rock is exceeded the resulting instability may have serious consequences on the
length x rock density) and has a range of 0.026MPalm to 0.0324MPdm (Fig. 2.2). Brown
and Hoek (1 978) use 0.027MPa /mas the average fiorn rnining and civil engineering projects
around the world. Accordingly the vertical stress at the 550m level at Stobie is 15MPa. In
the Sudbury area the maximum principal tectonic stress is horizontal and in a NE-SW
direction (Cochrane 1991). The ratio of the horizontal to vertical stress decreases with depth
Most mining methods require the leaving of pillars between stopes to reduce closure
and to afford stability to adjacent openings. In some mines. pillars can be placed in Iow grade
ore where as in others. the pillars are within the ore body and may be permanent or
trmporary. In some cases the pillars have been designed for recovery at the final phase of
mining. As rnining proceeds. the extraction ratio (mined material/original volume) x 100
increases (Fig. 2.3). At 25% extraction the stress acting on a pillar is 1.33 times the stress
acting on the orebody plane. Reference to the plane of the orebody is significant because
generally the stress acting on a pillar is a vector component of the vertical and the tectonic
stresses perpendicular to the plane of the orebody. At Stobie Mine the hangingwall (HW)
contact (70°.3 15') best represents the plane of the orebody. Assuming that the pillar stress
is caused by the gravitational and tectonic forces (Galbraith 1992), the average pillar stress
at Stobie Mine at the 550m level. with a 75% extraction ratio is 4 times the stress normal to
the orebody plane, rquivalent to the stress at the 2.200m level of the rockburst-prone
Creighton Mine (Fig. 4.3b). Pillas in a mine with a high extraction ratio usually fail. This
DRIFT ON 2195m L N E L
-
O
SCALE
10m
FLOOR HEAVE -
TRqCK DISPLACED
c - 4
- 1585m LEVEL
LONG. SECTION
-
ROCK OISPLACE0 8Y ROCK8URST
O
SCALE
1 Om
Fic. 2.1 Exarnples of the types of bunts ai Creighton mine. a) a strain burst
in a drift at the 2195m level, b) pilla burst in a rib between two cut and fil1 stopes on the si11
cut and c) a fault-slip burst at the 1585m level caused by slip dong the 6 Shafi shear induced
about 1.5 at depths below 1 Km, but rapidly increases to values greater than 5 in the 100 m
environments in which mine openings are subject to high stress. The stress associated with
the movement of the North American plate accounts for the high horizontal stresses
indicated by mine seismic networks (Ryder 1988). Stress magnitudes and orientations are
Pinawa. Manitoba (Martin and Chandler 1993).. For rxarnple stress magnitudes mrasured
above and below a fracture zone ranged from -1 to +43 MPa and stress orientations rotated
Strain rnergy is a function of the stress state and the elastic conditions (Young's
modulus and Poisson's ratio) of the rock mas. The stress distribution around an underground
EXAMINE 3D. These programs provide the stress distribution in klimensions for irregular
shaped geometries.
To determine the snalli energy. the Young's modulus of the rock mass must be known.
This parameter is seldom known with any confidence and hence elastic strain eneqy is not
widely used in evaluating burst potential in mines. Pnctitioners instead rely mainiy on the
identification of regions in the mine where mining induced stresses exceed stress magnitudes
that have k e n empincally determined as cntical for a particular mine or rnining camp. A value
of a,= 125 MPa has been used for Creighton and other Sudbury Basin mines as a stress level
at which bursting is highly likely (P. H. Oliver. retired iNCO Rock Mechanics supervisor.
persona1 communication 1986). Particular attention should be paid to areas that the mode1
stress. Based on cornparisons of numerical mode1 results with field evidence. the author has
considers any areas. with o,2 70 MPa and o;ranging fiom a negative value (tension) to half
A rock mass is made up of intact blocks separated by discontinuities. The rock mass
strength is rmpirically determined using Rock Mass Rating (RMR) and Tunnelling Quality
Index (Q) values. while intact rock strengths or unimial compressive strengths (03 c m be
deterrnined in the lab from intact fracture-free specimens. The fiequency and orientation of
joints. significantly reduces the rock mass strength rock relative to oc.The presence of
geological structures influence stress magnitudes and orientations. Rousell (1 984) indicares
numerous joint sets exist in the rocks of the Sudbury Basin. with as many as 7 joint sets at a
given station. P. H. Oliver (personal communication 1988) recommended the use of a rock
mass strength of 62MPa for the strongly jointed rocks of the Sudbury Basin with a a, of
155MPa.
Rock must be subjected to stress greater than its compressive strength to fail
violently. However. the overail far field in-situ stress regime need not be greater than the
strength of the rock to cause failure because the geomeû-y of openings induce local zones of
stress concentration which may locally exceed the breaking stren-gth. Martin et al. (1998)
have indicated that brittle failure occurs at approximately a stress level of 115 of the (03of
a rock.
Hoek and Brown (1980) and Stacey and Page (1986) suggestrd that the ratio o,/q
0.5-0.67 Very dangerous and di fficult to keep open. Support heaw and costly.
Martin et al. (1998) proposed that brittle failure occurs at a ratio of o,/o, = 0.33 and that
this simple index could also be useci to mess the burst potential of a pillar. They suggested that
if the stress in the pillar falls below one third of the cc(c& W 3 ) the burst potential in a pillar
is significantly reduced.
Using the average pillar stress of 100MPa at mid height of 25 pillar at Stobie Mine and
the average ocfor disseminated quartz diorite of 2 12MPa. then o& = 0.47. Burst potential
exists at mid height of 25 Pillar (375m)and it would increase towards 55Om level.
As rnining progresses. pillas and abutments are subject to increased stress. which may
lead to early gentle failure or later violent failure. Hence it is important to establish which
regions in a mine are overstressed and if possible. to determine by what mode the energy wdl
likely be released.
testing trame. When a rock specimen yields in a stiff testing framr. the testing frarne looses
its load with only small arnounts of yielding by the specimen. Al1 of the energy released from
the loading system is used in deforming the yielding rock sample. Thus the stiff testing t h m e
cannot drive the yielding sarnple to failure unless additional energy is supplied by pumping
more oil into the hydraulic system. When a rock specirnen yields in a sofi testing frame. the
testing frame tends to maintain its load over large amounts of deformation. More energy is
released from the loading system than can be used in deforming the yielding rock smple.
Thus the sofi testing framr drives the yielding sample to Failure without any additional
rnergy being supplied. This example is directly analogous to a pillar. abutment or fault
the element (e.g. pillar = widthheight) and the properties of the surrounding rocks. When
a stope panel is blasted. the reduction in confinement dong one or twrosides of a block of
rock is accompanied by a release of the stored strain energy as the block expands. This
process of energy release is M e r driven by the expansion and energy release of adjoining
blocks. This aggregate of energy releasing blocks is the loading system. The loading system
has properties that define the t p e of failure, which will occur. It is the enerw of the loading
system. which dictates the behaviour subsequent to initial failure. whether yielding is
induced by over stressing, loss of confinement. reduction OF the clamping forces on a fault.
creep. fatigue. asperity shearing. large hcnire Formation or even blasting (Wiles et al. 1998).
Equally important is the stiffness of the loading system. which is the slope of the Ioad versus
the displacement. The total energy released by the loading system. c m be calculated by
intrgrating the load through the displacement denvrd by a boundary element nurnencal
Releases of stored d n energy by slip dong faults causes earthquakes. Failure releases
energy and this released energy c m produce additional Mure. which in tem releases additional
energy. Tlius failure and releasc: of stored strain energy once initiated c m be self-propagating.
Failure and cnergy relerises occur on scales. ranging fiom earthquakes dong plate margins. to
Diamond drill core. of any diameter. rxtracted h m regions of high stress oRen
fractures into thin discs (Fig. 7.4). This discing is the result of high stresses perpendicular to
to relate the direction and magnitude of the principal stresses with the concavity and thickness
major principal stress is shown. Spalling initiates at points of maximum compressive stress
concentration which occur at right angles to the major principal stress direction (fiom Hoek et
ai. 1995).
Damage or breakout inthe wall of a borehole is cornmonly referred to as "dog earing"
following: (1) failure of the borehole wall is due to shearîng in bands parallel to
(perpendicular to O , ) (Fig. 2.5); (2) spalling occurs at the intersection of shear surfaces and
extensional zones: (3) block failure follows as fngments slough into the borehole. The extent
of the borehole elongation increases with increase in the stress parallel to the hole avis and with
the increase in magnitude of the difference between the stresses in the plane perpendicular to
the hole a i s (Fig. 2.5). Because the breakout is formed in a direction perpendicular to a,.
variations in the near field stress direction. Because rock hilure is scale invariant (Tschalenko
& Ambraseys 1WO), borehole breakout occurs in holes of al1 siws. Martin and Young ( 1993).
Lee and Hamison ( 1993)and Martin ( 1997) document the formation of borehoie breakout type
notches in a 3.511 diameter t m e l driven in massive uniform. granite using perimeter lim
drilling and mechanical breaking of the rock stub (Fig. 2.6). Boreholr breakout. occuned within
a few hours d e r drilling a raise bore pilot hole (d = 28cm) at Creighton Mine (Fig. 2.7) The
formation of borehole breakouts in production holes (dia = 16.5cm)in the 25 pillar at Stobie
mine signalled the advent of failure and the need for destressing (Fig. 2.8).
Another indicator of high stress mapinides is the slabbing and spalling From the roof
and walls of underground excavations (Hoek et al 1995). Exarnples of slabbing include the
following: (1) shear failure in the corner of a drift (Fig. 2.9~1);(2) sidewall spdling (Fig. 2.9b);
(3) curved slabbing due to shear failure in corners (Figs. 2.10% 3.1Ob): and (4) progressive
three. 10k long headrace tunnels for the Tianshengqiao hydro povier station in SE China to
mechuiisms of failure obsemed in tests of rock specimens at different confining pressures. The
three mechanisms of failure observed were failure by brittle splitting, tensile failure associated
with the shear process and failure by pure shear fracture. These mechanisms occurred at low.
moderate and high confining pressures. respectively. The location of the failure in a drift
c o h e d this. The splitting mechanism ofa rockbwst vas hcturing of high-strength materiai
under low confining stress. The slabbing on the sidewdls occurred in areas of intermediate
confinement. The shear failures. in corners of drifts rvere in tightly confined zones. with high.
induced stress and high confining pressures. The strain rnergy released due to spalling is less
mining sequencrs: reasonable dimensions. geometrirs and mining rates: and stringent filling
practices. These are strategic methods. The "tactical" methods (Morrison and MacDonald
1989) are the use of destressing or preconditioning and the installation of enhanced support
Hedley (1992. p 725) in the Rockburst Handbook for Ontario Hardrock Mines.
reconfirms the validity of the conclusions reached by the Rockburst comminee 10 years
prior. "The prediction of the time of occurrence of a rockburst is of little actual value to a
mine operator and it wodd be far more usefd to delineate areas predisposed to bursting and
Underground Research Laboratory test tunnel over a five-month period fiom Martin (1 997).
FIG.2.7 Borehole breakout that occurred within a few hours of drilling a raise bore pilot
hole (dia. = 28cm) at Creighton Mine. The tricone bit jamrned with debis fiom the breakout.
FIG.2.8 The formation of borehole breakouts in production holes (dia = 16.5cm)in the
25 pillar at Stobie mine signalled the advent of failure and the need for destressing.
Frc. 2.9. a) Shear failure surfaces in the corner of an underground excavation in highly
South African gold mine (both after Hoek & Brown 1980).
FE. 2.10. a) Stanrock Mine, Eiiiot Lake, Ontario. Note curved sidewall of service way.
b) Lac-nor Mine Elliot Lake, showing a pillar face fomiing the curved sidewall of a stope (both
properties of the rock mass. and the support and geometry of the excavations. as the major
variables contributing to rock failure. graduai or sudden. He considered the pre-mining stress
distribution and rock mass properties as facts that had to be accrpted and concentrated his
rockburst control efforts on support and geometry. Today the practitioner attempts to alter
the distribution of the pre-mining stresses and modie the properties of the rock mass in and
about the excavations using destressing techniques. The following are a few specific
exampies. The methods of stress shdowing developed in South Africa. to suit the geornetry
of shallow-dipping. deep. tabular. goid veins include: over stoping (Leih 1990): driving "TM
shaped driRs (Jager et al 1990): over slotting: mining of over-reefs first: and rnining hanging
Areas of hipher stress and associated risk of rockbiirsting in the Creighton 1 1 shah
transfer drifi. defined by discing of core in pre-development diamond drill holrs. were
subjected to additional destressing (Garrood 1982). These "structure" holes were drilled
solely for the purpose ofdefining the zones with high stress. Emphasis has been placed
recentiy on imaging systems such as Tomography (Fridel et al. 1996) at the Homestake
Mine. Successful identification of high stress zones would natiirally direct one to use
destressing techniques to reduce the risks of bursting, and increase the ground support to
Back analysis of bursting sites to define the conditions and causes of bursts have
entailed numerous new techniques. Over coring detailed stress risee (Whyatt et ai. 1993) and
first motion analysis confi~rmedfault slip mechanism (Jenkins et al. 1990) at the Lucky
A Fault-slip event at the Falconbridge mine in 1984. resulted in four fatditirs (Bharti
& West 1984). The subsequent Stevenson Inquiry. recomended a Canadian Rockburst
Research Program. whose purpose was to investigate rockbursts in Canadian mines. The first
five years of the research program. directed by Dr. D. Hedley of CANMET. concentrated
from its onset on developing seisrnic systems to; (1) locate the rvents. (2) capture wave
forms and (3) determine source mechanisms. and culminated in the publication of the
'Rockburst Handbook for Ontario Hardrock Mines'. The handbook documents fundarnentals.
a historical review of bursting in Canadian Mines. and a list of destressing techniques used
by Canadian companies. During the subsequent five yrars (1 990-1 995) the Canadian
Rockburst Research Program. which was funded by the Industry through the Mining
Research Directorate ( M m ) and both the Federal and Provincial Governments. concentrated
its efforts on seismology. mine design. support. backfill and monitoring. The results are
contained in a six-volume set. bound in two tomes (Camiro. 1995). Drstressing was not
An analysis of bursting that occurred during the mid 1980's in the Copper Cliff
North Mine indicated abnormally low confinhg pressures as the cause of bursting (Momson
& Galbraith 1990). The lower confining pressure produced a lower rock strength than
expected.
The conditions that cause rockbursts are numerous and their interplay is cornplex. A
study by O'Donnell (1995) documented the influence of solar and lunar tides on the
frequency of rockbursts and falls -ofground at ten INCO Lirnited mines during the period of
1985 to 1994. A frequency of rockburst occurrence of 1.5 times the average was
0.15 -
014 -
0.13 -
Olt -
0.11 -
01 -
009 -
O08 -
O07 -
006 -
26-40
FIG. 2.12 a) Histogram of the fiequency of rockbursts and major seismic events recorded at
Creighton Mine between 1985 and 1994 versus total tidal force. b) Histogram of the fiequency of ground falls
recorded at al1 MC0 mines between 1985 and 1994 versus total tidal force (O'Donnell 1995).
observed on days with the lowest total tidal force. tnterestingly. the frequency of falls of
ground was highest when the total tidal force was the highest (Fig. 2
Blake et al. (1998) state that there have been few well instrumented field tests to
validate the mechanisms by which destressing reduces the rockburst potential. However. a
recent request for submissions on destressing resrarch has some possibility of advancing the
state of the art. conditional on the sponsorship fiom indus- and the availability o h suitable
2.6.2 Support
Standard support systems (e. g. mechanical bolts. grouted rebars. friction bolts and
welded wire) are inadequate in areas subject to heavy rockbursts. brcause the. cannot
accommodate the larger displacements. Accordingly speciality support systems such as cable
Cable lacing is a three-tiered support system consisting of grouted bars. chain link
mesh and cables. The grouted smooth bars knoiçn as shepherd's crooks. or hairpins. (Fig.
link mesh is fastened to the rock with tensioned cables that are interlaced through the pins
or shepherd's crooks (Hedley 1992). This robust support is commonly used in deep South
African gold mines and occasionally in Sudbury. Swan ( 1989) defines cable k i n g as the
Other suppon systems include: (1) the Cone bolt. a grouted yielding tendon
developed by the Charnber of Mines Research Organisation (COMRO) (Ortlepp 1994); and
(2) shotcrete, which is used as a coupling element with rock bolts and meshing (Cook et al.
I
I
HAlR PIN
SHEPHERD'S CROOK
( 5 O m thick), is greater than 16mm rebar shepherd's crooks. The performance of steel-fibre
reinforced shotcrete is erntic (Stacey et al. 1995). .4t the Lucky Friday Mine. before dnlling
the next round. shotcrete is applied to the back and \vails which are reinforced with bolts and
to control the timing and rate of failure. Controlled bilure may be achieved by one or more
of the following methods: designing slender pillars, allowing time in the mining sequence
The geornetry of a pillar affects its strength and ability to store strain energy (Parker
1974). A slender pillar will fail under low stress conditions. A squat pillar with a height to
width ratio of 0.25 or less will devrlop conf nement in its core and will build up stress. Thus
regional or b o u n d q pillllars should be squat and pillars that are required to fail should be
times when a natural luIl in activity would follow. during which time energy could safely
dissipate by bursting when no one is around. The blasting of footwall slots in the silling
process on the 2075111 level at Creighton had a high potential of inducing rockbursts. To
ailow the groound to release stress safely, the blasts were detonated at the end of the 4-1 2 shifi
on Fridays. giving till Monday rnorning for the ground to release the excess energy.
The decay time of a block of ground affected by a vertical retreat mined 0or
crown blast can be detemined by monitoring seismicity over a number of blasts. Once the
decay time has been defined, entry to a workplace or a portion of a mine c m be delayed. to
The installation of a stiff support element. shortly afier blasting a drift that is under
high stress. c m rupture the support. A case in point is the insrallation sequence used in drifts
at Creighton. Since the drifts are destressed. considerable deformation is expected in the drift
back and walls. Mechanical bolts are installed as the first pass of support. Rebars are only
installed a day to a week later. because if they are installed earlier. they will rupture at
approximatrly 0.3m from the collar. The installation of mechanical bolts has a second-.
safety feature in that they are quicker to install and thus the exposure time for the miner is
much less than for a rebar installation. Anempts have bren made to develop macro-delayed
resins for placement at the collars of rebar for use in conjunction with the qui& setting
The diminishing pillar. created as a cut and fil1 stope is mined. and the pillas in a
stope and pillar bulk mine attract stress and may burst. Some major initiatives that have been
implemented to reduce rockbursts are: (1) conversion from the cut and fil1 method to a
primary undercut and fil1 method at the Lucky Friday Mine (Noyes et al. 1988): (2) centre
out mining with reduced spans in VRM topsills at the Copper Cliff North Mine (O'Donnell
1991): and (3) designing and excavating a stress relief dot at Creighton Mine (Oliver et al..
1987 and MacDonald et al.. 1988). Changes of this nature bring out other questions: (1) c m
a consolidated fil1 be developed that wilI accommodate the mining method (Brackebusch
1988) and (2) will the support potential of the cernented-fil1 influence rockbursts. The fil1
v u w/ / HEIGHT : WlOTH RATIO
-
CENTER OF PILLAR
IS CONFINED
HENCE VERY STRONG
-
PlLtAR HEIGHT : WlDTH RATIO IS AROUNO 1:4 or 0.25
DEC1F4.ûWC
Fic. 2.14 Examples of slender and squat pillas (Parker 1971).a) Height: Width =
1 :1; The edges of the pillar fail in shear then tension cracks open up in the centre. b) H:W
= 1 :2; Gradual deterioration of the outer part of the pillar decreases confinement on the
centre and increases the load on the remaining central portion. c) H:W = 1:4; The roof
the ability of the fil1 to develop resistance to closure that would re-induce wall stresses of a
magnitude. for bursting to develop. Bursting would be more likely to develop due to
relaxation and slip associated with reduced clarnping forces (Whyatt et al. 1989).
2.6.5 Destressing
reason for this uncertainty is that destressing was developed as a practitioner's tool. While
there have been several attempts to quantify the rffects of destressing through field
rxpenments. to the author's knowledge nonr of these experîments have shed any light on the
numerical modelling. Attempts have been made to compare different destress hole locations
(Mitri et al 1988) and calibrate mode1 results with field observations. Design tools developed
in South f i c a to assess different stratrgies included: ( 1) Energy Rrlease Rate (Cook 1966);
and (2) Excess Shear Stress (Ryder 1988). Wiles et al. ( 1998) used numencal modelling to
correlate the occurrence of bursting to an rnergy release density. The Local Energy Release
Density was equated to the area under the loading system stiffness curve divided by the
sample volume. Reasonabie correlation has been indicated in his preliminary srudies.
Destressing techniques have been developed. by the author and associates at INCO's
essentially use explosives to create and extend Fracture zones or promote pillars to fail.
Before studying the techniques and their development, some of the notions that have been
put fonvard as to why destressing works. are reviewed.
Oliver et al. (1987) States that stability requires the establishment and maintenance
of a skin of hiled material around al1 openings. and recognising this is the key to minimising
the rockburst hazard in development openings at depth. This skin of failed material is
produced by destressing.
Rorke and Brurnrner (1988) suggested destressing serves to release strain energy in
highly stressed rock whereas preconditioning serves to fracture and weaken large areas of
progresses. Thry described the desired results of preconditioning of deep tabulu gold vrin
in South Afiica. as reduction in horizontal clmping forces thus rncouraging the occurrence
and preconditions the rock. The face holes. generally drilled twice the lrngth of the round.
push the stresses ahead of the excavation. where as the shoulder (corner) holes fracture the
ground pnor to blasting even the cut. As the excavation is formed. the stress concentration
at the shoulder induces failure in the weakenrd rock initiating the progressive failure that
promotes wall closure. slippage dong joints and release of energy as the excavation
progresses to the desired state of low potential energy. synonymous with Iow risk of
bursting. The bolting procedure prornotes this process by the injection of water into the rock
mass and along joints. It is indeed at this point that a significant increase in audible rock
2.8 Summary
Rockbursts are associated with: deep mines. areas of high tectonic stress. faults. and
high extraction ratio. Mining sequence. pillar geometry. destressing. as well as timing of re-
entry are steps that c m be taken to reduce the risk of rockbursts. Chapter 2 reviewed: (1) the
various methods by which stored strain energy is released: (2) the causes of rockbursts: and
(!) the solutions available to reduce their risk. The following chapters document significant
pillar destressing projects in order to drvelop a Frmework with which to compare the
3.1 Introduction
The previous chapter deds with stress. strength. stored strain energy. rockbursts and
destressing as an effective tool in releasing stored strain rnergy to reduce the risk of a
rockburst occurring. This chapter documents the application of destressing to drifts. stopes
and tabular ore zones and presents a number of case studies on pillar destressing.
Destressing up to 1980
Dickhout ( 1962) was one of the fints to elaborate on the use of destressing at INCO
Limited's Creighton Mine. During the earl y sixtirs the cut-and-fil1 method was being
introduced to replace the square set mining method. brlow the 1220m Irvel. Expanded rnetal
mesh and rock bolts were being used to replace sets as drift support on the 7010rn Ievel. It
was ai this transitional stage in the development of mining that destressing mrthods were
developed. Ammonium Nitrate and Fuel oil (ANFO). which had been recently introduced as
an explosive. made long destress holes frorn a working face possible. Dickhout indicated the
destressing at that time consisted of two drill holes (d=57mrn). one 7.6m the other l5.2m in
length (Fig. 3.1). The long hole was cornpletely filled with ANFO and collar primed. This
arrangement produced the required degree of destressing and produced a relatively clean hole
that could be readily exarnined and occasionally was used in the cut (Fig. 3.1). New destress
holes were ddled when 1.8m of the previous destress holes remained. Destress was a
success because the openings were stable and there was a marked reduction in overbreak and
spalling. n i e latter was very significant for miner safety since the 2.4m x S.7m drifts were
driven using jack leg drills. The successful use of destressing permitted the continued use of
rock bolts for drift support as opposed to reverting to the more expensive timber or steel sets.
Drilling the long holes and reconditioning after the blast were time consuming and
expensive. Fiirther refinements determined that two face holes, hÿice the length of the round,
NOT TO SCALE
PREVIOUS
DESTRESS HOLE
DESTRESS HOLES 1.8m
1r---
I
I
15mH I
1
, DRIFT
7ma
PlANNED
AOVANCE
FIG.3.1. Plan of a drift showing the general arrangement of destress holes used
drillers were responsible for drilling and breaking rounds. If the rounds break cleanly then
no one interferes with the process. In some cases the only information available is anecdotal
rvidence. For euample. the idea of placing destress holes in the corner of working faces is
credited to a crew working on the 2070m level at Creighton mine. The rule of not drilling
within .l 5m of a previously blasted hole (bootleg), and twin destress holes in a face. make
locating of the cut dificult. The crew noticed during the process ofdrilling bolt holes in the
shoulder. that the magnitude and frequency of rock noises (low level seismicity) increased
above back-ground. When the holes were completed. the seismicity Fe11 below background.
Apparently. corners trigger seisrnicity. Accordingly. destress holès at the corners produce
beneficial results. However. face holes are still required to push the fracture zone ahead of
the face.
For destressing to be readiiy accepted by rniners the following are required: (1) they
must be aware of the risk of rockbursts: (2) the method has to be easily performed with the
tools and supplies that are available: (3) the process rnust not significantly delay the drilling
and blasting of a round: (4) there has to be minimum damage and repair work required
The configuration developed over the years to reduce the risk of strain bursts in
dzvelopment drifts is the drilling of. two face holes twirc: the lèngth of the round. and holes
in the upper corners the sarne length as the round. Wall holrs and holes in the bottom cornes
were required in some cases (Oliver et al. 1987). The method is successful and no
reconditioning of the drifts is required. There is generally an increasr in the fracture pattern
at the face that causes some problems in drilling the next round.
When two drifts are being driven towards each other. die strain enerçy and associated
seismicity increase as the distance between them decreases. The technique developed by the
author in order to reduce the risk of a rockburst is: the headings are stopped four round
lrngths apart. and two holes are drilled. twice the Iength of a round. from each heading (Fig.
3.h). Instead of one meter of ANFO at the toe of each hole. the holes are loaded from the
toe out to a le& of approximately 75% of the length of the hole. It should be noted that
these holes have a strong kick back or shot gun effect. Care should be taken that thesr holes
are not in line with any crucial equiprnent or power lines. The rernaining four rounds are
usually taken from one side using the customary corner and wall holes.
A similar procedure can be used if a drift is to break into a stope and there is a nsk
of bursting (Fip. 3.3 b). The procedure used in the 1290 zone on the 2070m level at Creighton
mine when dnving a cil! drift towards a filled cut and fill block was as follows: A diamond
drill was used to driil two destress holes L5.2m long towards the stope. Approximately 75%
of the hole (from the toe out) was loaded with ANFO and blasted. Access into the area was
Destressing was used in cut and fill stopes on the 195Om and 20 10m levels during
the mid-seventies. A series of holes were drilled in stiff portions of gabbro or granite nb
pillars. These holes were used in both traditional high fill cut and fill and in uppers cut and
fill stopes. In the latter a ten foot slicr was blasted from hanging wall to footwall at once.
using narrow diameter 35mm drill holes. The new back was then bolted off the rnuck pile.
which was subsequrntly mucked out. The destress holes were ?.-lm long and on a 3rn
the walls was required after the destress holes cntered the walls and peeled back the screen
(Fig. 3.4).
Methods developed in the early eighties to dcstress rib pillars on the si11 cut of
mechanized cut and fiIl complexes. and the destressing of extraction drift ribs. are detailed
in O'Donnell (1992). However. to make this document complete the pertinent facts will be
out1ined.
Bursting of pillars on and above the 1950 m level did not occur until removal of the
second to fourth cut (Oliver et al. 1987). Pillar bursts started on the 2010m level. In the early
eighties a program of destressing was developed by the author and associates in cut and fil1
PLAN VlEW
SECTION A-A'
FIG.3.5 Destress pattern in the 2070m level Mechanized cut and fil1 units.
complexes on the 2073m level (Fig. 3.5). The complexes had 7.9m wide stopes and 4.9m
wide pillars with a 9. l m wide central slot. The stope direction was parallel to the least
principal stress.
Destressing included the blasting of 1.jm of ANFO at the base of twvo 6m. face holes.
The first 3 m of these holes were ddled with a 5Jmm cut bit to accommodate the coupling
which was required to extend the hole to 6m with a 43mm bit. The corner holes were 3m
long and J3mm dimeter and contained O.jm of ANFO. These holes were drilled up and out
at 30 degrees to the advance direction. Wall holes at 45 degrees to the direction of advance
(3m long. dia43mrn) were drilled 1.8m back from the face and 1.8mabove the floor. These
holes inclined up a few degrees to allow the drill water to drain out. were destressed with
0.9m of ANFO. The pillars were inspected daily and if they remained competent the destress
holes were re-blasted. Records were kept of the pillars that yielded as a result of proper
destressing.
The yiclding of the pillars was significant. As the stopes rxpanded. a cntical
dimension was reac hrd at which the back and floor converged as indicated by an episode of
elevated seismicity. Pillas that were not properly dcstressed would burst.
The level of support that proved adequate to support the pillars through the episode
of convergence was the following; the pillars (walls) were screened to the floor with f: 4
gauge welded wire mesh. bolted with 1.7m long ss39 split sets and 1.8m long 19mm
Silling of the cut and fil1 unit on the 2134m level proceeded with fewer problems due
Developing the stopes in a wedge fashion (Le. pushing the stress outward). b) Planning stopr
liniits to maintain a smooth outline. c) Blasting of the slots through the pillars on the 16h00
to 24h00 shifis on Fridays. to allow the stresses to redistribute during the weekend, when no
one was present in the workplace. d) Increasing the widths of the dots from 3.6 to j m
reduced the hazard of loose ground to the construction crews. and e) al1 destress holes were
tashed out and the collars painted; the? were treated as bootlegs.
The state of the art progressed from a number of uncontrolled bursts in the initial
silling of the 2073m level cut and fill. to the occurrence with the drvelo~mentblast of 10 out
of the eleven bursts recorded during the silling of the 2 134 levrl mining block. During the
development of the 21 95 m level VRM extraction horizon 85% of the bursts were initiated
2 M m Level
The extraction horizon for the Vertical Rrtreat Mining (VRM) on the 2195m level
contained 4.9 x 4.9 m drifts with 4.9m wide pillars designed to fail easily/sofly with proper
desvessing (Fig. 3.6). The drstress pattern of the extraction drifts was the most involved of
the time w
ith 10 destress holes per round including; two 7.3m face holes with 2.7 meters of
ANFO and four wall and four comer holes each 3.6m long and Mmm in diameter with 0.6m
of ANFO. The four corner holes were ddled up and out and d o m and out at 30" to the
driving direction. The bonom comer holes were drilled about .3m above the si11 to prevent
water fkom entering. The four wail holes were drilled at 45" to the direction of advance and
a few degrees above horizontal to allow drill water to drain. The wall holes were staggered
'C ' SECTION 'C'
Fic. 3.6 Destress hole pattern used on the 2195m level extraction Horizon at
were ddled at the shoulder and Z.4m above the sill. The holes on the right hand wall were
drilled at 1.2m and 3m above the d l . Improper alignment of the wall holes c m destroy the
On a number of occasions cut and fil1 stopes at Creighton have developed stress
problêms. as they reached rnid height between levels (33 m). Evidence included spalling at
the shoulder and an increase in seismicity. The abovr occurred in stopes that had been
destressed at the si11 cut and some that had not. The stress problrm \vas solvrd by destressing
the rib pillars using the up and our 30" holes in the corners and holes at 45" to the advance
at mid height of the cut. This procedure was carried out in stopes that showed the need
At Copper Cliff South Mine during the mid-eighties two drill drifts on the 700m
level were being driven through a stressed pilla. Spalling at the face and shoulden occurred.
This was mitigated by using the standard two face holes twice the length of the round and
The abutments of stopes below the i 83Om level at Creighton would be under stress
and hence prone to burst. The nsk of bursting fiom these sites was diminished by drillhg and
blasting destress holes. In the cut and fiIl stopes. face holes hvice the length of a round were
ddled in the last round on the hanging ivall and footwall of each stope in the rnechmized
unit (Fig. 3.7a). Appro~imately1 meter of ANFO was detonated in these 44mm diameter
holes. If a slice is mined in an under cut and fiIl stope dong the hanging wall or footwall
contact. the destressing is as follows: a ?.-lmlong holr (dia.=32mm) at 45" to the direction
of advance. is drilkd at mid height into the wall with each round. Approximately 0.5 meter
of ANFO is detonated in the holes (Fig. 3.7b). If the under cut is mined transverse to the
contact then face holes are destressed in the last rounds into the hanging wall and foot~vall.
3.2.9 Hanging Wall Destressing to Eliminate Hole Closure, Struck Rods and
Reduce Dilution.
Longitudinal stopes mined by the vertical retreat mined (VRM) rxpenence hole
closure when depths excerd 1800m or whcn stressed pillars are mined. Rods become stuck
Figure 3.8 indicates the geometry of panel #3 mined between the 1830m level and
the 1890m level at Creighton mine. Holrs were drilled parallel to the hanginy wall to reduce
delays and losses due to hole ciosure. Rings of holes (dia.= 170mm)were drillrd 3 meters
apart with a 3m spacing benveen the toes of the holes on the 1890m level. The holes in ring
13 and holes B and C in ring 14 were dnlled without problems. Holes A. D and E in ring 14
and al1 the holes in ring 15 were closing (egging and plugging) and caused delays due to
stuck rods. A row of holes (dia.=[ 70mm)were dnlled dong the hanging wall. at a 1 meter
spacing, parallel to the E holes. The plans were to blast these holes at the end of a 4-12 shifi
>c l m ANFO
44mm DIA,
HOLES.
- - - - pp -
SANOFILL
/ SECTION 0-8'
Fic. 3.7 a) Abutment destressing in Cut and Fil1 klining. b) Abutment destressing in
e
RlNG
LEVEL
ZONE
NOT ~ T OSCALE
PLAN CREIGHTOM MINE
1830m LEVEL
SECTION RlNG 15 RlNG HOLES O O O
NOT TO SCALE HW HOLES
PANEL SIZE 15m x 7.6m x 60m
PANELS 3 &4 HW HOLES DRILLE0
PANELS 5 ON, FRACTURE ZONE EXTENDED BMOND THE NEXT STOPE.
FK. 3.8. Hanging wall destressing used to reduce hole closure, stuck rods and
Fracture zone on the hanging wall would reduce drillinç problerns in rings 15 to 17. Prior to
these holes being blasted. a crack propagated tiom hole to hole. Drilling of the remaining holes
proceeded without problems. Drilling of closely spaced HW holes was required in a subsequent
l j m long panel. Af'ter that the geometry of a 60m by 7.6m by 60m slot induced the fracture
zone to extend beyond the fifth ring in the next panel. allowing holes to be drilled without a
problem. Hanging wall dilution was also reduced by the clean Fracture produced along the
hançing wall .
Destress holes c m pose a risk. for a number of them are located in the side walls that
rnust be bolted. There may be non-detonated powder dur to a rnisfire. Destress holes must
be considered as "bootlegs" or "sockets" as the South Afncans cal1 them. As such they must
be washed out and identified by painting the collar with a circle. This task is assigned to the
bolting crew for they are present at this part of the cycle. they are also at risk ofdrillinç into
un-cleaned holes when bolting. Even with the availability of stick powder (cartridges) ANFO
It is also advisable to have the inspections of destress holes on the ground control
personnel's check list when evaluating workplaces. Destressing has on occasion been
considered ineffective only to find that either the holes were drilled and not blasted or drilled
As mentioned elsewhere destress holes shotgun out with enough impact to tear
screen. This is usually noticed when a drift is tuming. Another case in point was a
destressing request to quiet an active draw point pillar on the 91jm level at C.C. North Mine.
The crew was instmcted to drill the destress holes but not to blast them until they were
inspected. This was a fortunate move because the holes were aiming at the cables canying
main mine power. Needless to say the holes were re-drilled with a different orientation
before blasting.
blasted. as the first holes in a round do not produce any wall or shoulder damage. This would
be due to the confinement of this configuration. However. 3m long holes (dia.=j?rnm) with
0.3 meters of ANFO will blow back the screen and produce a conical-shaped Crater at the
collar (Fig. 3.4). Damage of this type is viewed very negatively by the crews. who have to
do the remedial work. It is important to note that reconditioning of ten such holes would take
one shifi. whereas a burst along the sarne distance of wall could require considenbly longer
to recondition. The damqing desuess blast occurs when the heading is clrared whereas the
location in an a-seismic mine is the effort and time required to convince the group from
miners to management the benefit of destressing. For people to do extra work when on bonus
there has to be immediate pay back. Since the effects of destressing are not always readily
FIG. 3.9. Types of failure which occur in different rock masses under low and high
in situ stress levels. (Afier Hoek, et al. 1995). Destress blasting to reduce primary bursts in
drifts is quite successfbl in heavily jointed rock in high stress levels. The success rate
It is difficult to destress large (4.9mx 4.9m)drifts excavated in hard. brittie rock with
a joint pattern which foms orthogonal blocks approximately 7m by Zm (Fig. 3.9). This type
of ground has led to bursting during the excavation of the r m p between the 21 35m level and
the 2 19511 level at Creighton. despite the drilling and blasting of the standard two face holes
and two comer and two wall holes. Since the rock generally lound below the 201 0m level
at Creighton c m be successfully destressed. then one could assume that the rock quality.
frequency of joints and discontinuities and blast damrigr fractures al1 are significant
It is postulated that. bursting could be climinated if a rock mriss with large blocks
were converted by the judicious use of e.uplosives to a mass with small blocks (Le. a wdl
fractured yielding drift periphery). The configuration and lenyth of the holes and the amount
of explosives would require empincal tests in a controllrd test site. The configuration would
have to be altered to suit the stress directions. Based on the succrss of the pattern used to
develop the extraction drifts on the 2 19511 level at Creighton (O'Donnell 1997) the following
configuration is proposed for destressing a drift in extremely good ground: Four face holes
twice the length of the round: four standard comer holes up and out/down and out. at 30" to
*
the drive direction: two wall holes on each side and an additional long wall hole on each side
of the drift. as well as in the back. These hoies must be angled to locate their destressed
portion beyond the bolt range of the drift (greater than 2 . h ) (Fig. 3.10). The holes. dthough
traditionaily timed to go off al1 at once and pnor to blasting the cut. should in this complex
FIG. 3.10. Proposed destressing pattern for drifts in rock with widely spaced joints.
55
Success of a 1957 destress program at East Rand Proprietary Mines Limited. a deep
high Suess tabular gold mine. was not acknowledged till 1982 (Ortlepp 1984). However the
program had been discontinued due to difficulties drillinç the long holes and loading h e m
with explosives.
At the Blyvoomitzicht Gold Mine in South Africa. a tabular ore body (depth
1.850rn). the design for the destress blasting in the up dip remnants (pillars). called for
several 10rn long holes drilled below the ore seam. in gullies. to accommodate advance of
lm per blast. The intent was to promote loosening and slip dong parting planes. Rorkr et al.
(1990) and Adams et al. (1993) summarize the effect of 57 destress blasts which contained
1 .-I km of holes. This intensive study was monitored by a fiill wave form seismic system.
convergence points were measured for ride and closure. fractures were mapped using stereo
photography. and ground penetrating radar was used before and atier the preconditioning
blasts to quanti@ the changes. The optimums detemined for drstressing were: breast panels
with holes drilled. 3 to 5 meters ahead of the face. drilled parailel to the dip and parallel to
the face and sternmed for 5m using grave1 and clay. Both 76 and 89mm diameter holes were
used; no preferred holr size was reported. A 29% increase in production and proof that
preconditioning could be done safely were the principal results of this project.
Recent destressing trials at the 2600m level of the Western Deep Levels South Mine
were successfd. Over 8000m2of reef was mined without a face burst and a 40% increase in
Rockbursts anse fiom unstable energy changes in the host rock mass of a mine and
involve release of seismic energy fiom the zone of influence of the mining (Brady and BCOWTI
1994). Coats (1977) defined three conditions that are required for a burst to occur: (1) the
breaking strengrh of the rock must be exceeded by the applied stress: (7) the rock must
trmsform the rnajority of the work done on it by stress. into strain energy. rather than shed it
by some form of plastic strain: (3) the failure must be violent brittle fracturing accompanied
Pillar failure may affect only the imrnediate area of the pilla or. in some cases. the
stability of the whole mine. For example. in a room and pillar mine a domino effect c m be
induced by the failure of a pillar. which c m tdce place over a period of months or in a matter
Individuai pillars may fail instantaneously (Fig. 3. I la) or _gadually slough (Fig. 3.1 1b).
Gradua1 sloughing usually occurs when there are numerous discontinuities at a steep angle to
Pillars that burst violently may have one or more of the following properties: the rock
is massive and brinle; discontinuities. if present. are perpendicular to the pillar walls and do not
slide easily; there is a moderate to high level of confinement at the core of the pillar: and the
pillar under hi& stress there is a possibility of triggerîng failure or bursting elsewhere in the
mine
The openings in rock reiease the stored strain energy as yielding occm. Destressing prornotes
the release of stored strain energy by promohg slip dong newly created microhctures as well
The cut-and-fil1 mining mctthod is versatile and widely used in recovering both
irregular. narrow veins and wide orebodies with irregular contacts that require selective
mining to reduce dilution. The problem associated with cul-and-fil1 mining at increased
depths is the creation of pillars which. as mining progresses. load-up and burst. According
to Oliver et al. (1987. p 12) "The key to mining at depth is to rrcognize that failure around
openings is both inevitable and desirable." Pi llars designed with littlr laterai confinement are
weak and will fail under low levels of stress. Ground modification blasts soften pillar
Table 3.1 lists several examples where pilla desuessing was carried out. The pillar
size. quantity of explosives and the criteria used to judge success are listed to indicate the
state of the art at the time the Stobie regional pillar was destressed. The principal examples
are surnrnarized in this chapter. The Stobie 23 pillar blast is described in detail in Chapter
4.
Frc. 3.1 1 a) Individual pillars rnay fail uistantaneousiy or b) through graduai sloughing.
I I I I I I I I I I I I I 1
u idenis\wpfilasWdannelnprildessxls 'Decked with aggregate. "For Stobie the volumes of the destress slot and the piliar are given
I ~ i i i aminm
r WIVI out a burnp or large seismic event
7
Star
I m l
24 10
--C&F
CBF
C&F
C&F
l m l m l m
4.5
6.7
28
6
2200
90
I
Air 1.5
AnFo
AnFo
1
I
1 245
1
1
[RIW minsd wim OUI a km(r oc lvps i«anuc avant
0.2 I ~ 1 1 w m i m
i~urrt
CLF 4.5 7.5 112 Air 1.5 AnFo Fracturd but 6 d not mimi
-
CUF 3 1 20 2.5
UCBF 3 24 1415 6
-
Opwi SloQ 35 36
I I 1 I
901 '~)ecked' 4.5
I I I
Emulsion 1 3480
I
1
I
tndocsd ptUw d o w e nlh wt incrasse in slrasa Mining
CIF 1.2 8.5 7.1 1 128 1 85 38 1 18 1 128 1 Cemenil 3 1 AnFo 1 27 1 O 2 [TM pllw was no1 mnsd but ancrlyzedefîecbvenair of
I 1 1 1 I I I I I I
UCdF 1 1271 1 '70 1 wim out a bural
11 8 ~n wim lm on end ~ t n e d
1
SuMevel 120J 550 4 6 l i 2 ~ 0 0 0 0 l 2 1 3 l 1 0 2 l1 2 l11501 Air 1 2 1 ~Ernulsion1100451 5 6 A 2 4 Mn 45 diys l a l u Mimng ir prograrungwilh l o r i
1 1 1 1 1
-Cave
iI\aUd.ra li!
1.81 21 11.711777"1
1 1
ked with ; jgregate.
1 1 1 I I
1
1
1
I
1
I
"For Slobi the volumes of the destress slot and the pillar are given .
I 1
S~IU~YLTIV
3.6.1 Galena Mine 1970
Blake (1972) describes the destressing of a cut and fil1 croun pillar in the Galena
mine (Coeur doAlene district. Idaho). The pillar. depth of 1.1 3Om. was 3Om long. 3rn wide
and 6.7m high. ANFO was used in srnall diarneter holes. A seismic velocity survey was
conducted on the pillar both before and after destressing in order to determine if the pillar
was tiactured effectively. The project was deemed a success as the pillar was mined without
Four destress blasts were initiated during the 1980's at the Campbell Mine in the Red
Lake district of NW Ontario (Neumann and Makuch. 1984). Destressing of crown and siIl
pillars on the 1 8 levrl. 870m below surface was the most successtùl of the four blrists. These
destress holrs (d. = 14mm)of genenlly less ihan jm. were drillrd at a 1.8m spacing. to
within 1.5 m of the overiy ing drift. in a 4.5m by 45m crown. Six-m long holes were drilled
on a 1.8m spacing into the 25m long si11 pillar above the level (Fig. 3.13). To help stabilize
the ara during and a f r r the blast. the 18 level drift was reinforced with 1.8 and 2.4m long
resin-grouted rebars and welded wire mesh. The stope below was filled with 10: 1 çemented
tailings.
A rockburst occurred 30 seconds afler the blast and nurnerous small seismic events
were recorded dunng the following few hours. There was significant darnage to the back of
the 18 level drifi and 30 cm of broken rock covered the drift floor. The crown pillar was
mined successfùl1y. A small bunt occurring in the pillar above the level following a
Fic. 3.12 Sections illustnting the s t o p pillar and destressing pattern at the Galena
Mine (Blake 1972).
Fic. 3.13 Layout of destress holes in the 1902 and 1802 crown and si11 pillars at the
Campbell Mine (Neumann and Makuch, 1984).
production blast. The fiactured ground made drilling difficult. ï h e destressed si11 pillar above
the level was not mined due to the unconsolidated fil1 above it (Hedley 1992).
The Macassa mine (Kirkland Lake. Ontario) has a history of rockbursts some of
which have caused fatalities (Hanson et al. 1987). Gold bearing zones. 2 to 6rn widr and
dipping at 7 j 0 are associated with a prominent fault and are mined between depths of 1400
and 2 150m.
Cut and fil1 crown pillars brcome burst pronr at 60% extraction when the pillar width
approaches 1 8m.In 1987 the 5840 crown was destressed using O. 15Kg/m3 of ANFO in 16
to ?lm long holes (d. = 64rnm) at a 3m spacing with 2.5m of stemming (Fig. 3.1 4). To
monitor the blast, waveforms were recorded. source locations were determined and
convergence of 25mm was rrcorded in the stope. Subsequent mining of the crown pillar
released a small burst that darnaged raise timbers and increased convergence to 33mm.
Apparently the crown pilla had been only partially destressed. A year later. a series of bursts
displaced a 1000 tons and darnaged adjacent drifts. The stope below the destressed pillar was
not affected.
Since 1986 the use of unconsolidated waste rock as the sole means of filling. was
rrplaced by poured bacWi11. Cut-and-fil1 mining has been replaced by under-cut and fil1 in
order to reduce the number of pillars created. The need to destress p i l l a has been almost
Fit. 3.14 a) Section showing the layout of destress holes in the 58-40 crown pillar
at the Macassa Mine. b) Location of microseismic activity following the destress blast
Gold minenlisation in the Mt. Charlotte mine (Kalgoorlie. Australia, Fig. 3.1 5a) is
hosted in a strong. stiff and competent dolerite located near major faults (Mikula et al. 1995).
Near vertical ore bodies are 30 to 80 m thick with 200 to 300 m strike lengths (Fig. 3.1jb).
The ore is recovered using longhole open-stoping mining methods with sequentially mass-
fired. associated rib and crown pillars. Rib failures have occurred in three modes. by shearing
on steeply dipping structures. violently when they have been formed progressively and
gradually when formed at their final size by sloning the next stope against the future ribs.
C
A large rock rib piilar. with a high risk of violent failure. was preconditioned by
blasting in advancr of mining. The objective was to encourage the pillar to close and thus
redistribute loads to the stiffer. stronger abuments. This \vas achieved by blasr-fracturing a
thin zone of rock in the pillar. In situ stiffness was reduced. Gcological structures and small
individual blocks were more likrly to move in the vicinity of the preconditioned zone than
elsewhere.
precondition a zone 55m high. 36m long. and 3 to 4 m wide. at the hanging wall contact of
the lower section of the pillar. khveen the 900m and 95Om levels. The blast design consisted
of a total of seventeen vertical blast holes (d = 14Omm. total length = S m . Fig. 3.16a). Six
pairs of pre-split holes were drilled 3rn apart at a spacing o f 6 . h dong strike. Five decked
charged blast holes were drilled between the pairs of pre-split holes. The holes were surveyed
Fic. 3.15 Preconditioning at the Mt. Charlotte Mine afier Mikula et al. (1995). a)
Location of Mt. Charlotte Mine. b) Long section of Stoping Blocks. c) Plan and section
indicating preconditioning zone. d) Cross section at 1 1 rib pillar. e) Blast design concept.
to ensure they were within the 2% deviation typically achieved for 5Om holes at Mt.
Charlotte mine. The pre-split holes were charged with JO kg of bulk emulsion explosives
placed at the midpoint of the hole and air decked (rmpty) above and below the explosives.
materiai. were loaded in each blast hole. The blast holes were designed to hcture the ground
between the pre-split holes in a direction parallel to the dot (perpendicular to the fractures
The blast was monitored as follows: ( 1 ) ground vibrations were measured both
underground and on surface: (2) seismic monitoring with a full wave form 33 channel PSS
system; (3) stress change monitoring with CSIRO-Hi cells and vibrating wire cells; (4)
extensometer monitoring to mesure dilation or shear across knoun geologic structures: and
(5) closure monitoring on the 900m level. During the mining only a few seismic events were
recorded within the pilla. in contrast to numerous rvents in the stope tloor and surrounding
areas.
The stress changes in an rast-west direction were +9MPa for the vibrating wire ce11
and +2 IMPa for the CSIRO Hi ceil and +2bIPa and 4 M P a in the north-south direction for
the two cells. respectively. Closure monitors recorded 7mm displacement across the
structures. The preconditioning appeared to have k e n successful as the pillar closed with out
150 kg POWERGEL
150 kg POWERCEL
PRIMER
11 rn /1 150 kg POWERGEL
PRIMER 1 I1
PRIMER pJ 150 kg POWERCEL
et al. (1995).
3.6.5 Sigma Mine 1996
A test was carried out in a sill pillar of an abandoned stope at a depth of 1500m (Fig.
3.17) at the Sigma Mine (NW Quebec) to determine the efficiency of pillar destressing in
reducing the potential for violent failure in loaded mining structures (Labne et al. 1997). The
sheared ore zone (dip =5j0). which contains qua-tourmaline veins and secondary sulfide.
The rock is of good quality with a rock mass ratinç (RMR) of over 80 and a Q Index of 1-6
to 3.3.
The drilling pattern consisted of fi fteen 8.5m long (d. = 38mrn) holes. dnlled at 55'
(to the horizontal) dong the vein in the drift back up to the siIl. The holes were dnlled on nvo
lines 1.2m apart. one dong the footwall contact the othrr at the center of the drift. Tne holes
were drilled 1.8m apart dong the line and the holes were staggered 0.9m Crorn one line to the
other (Fig. 3.1 8b). The holes were loaded with ANFO For a lrngth of 5 . h . and stemmed
with 3m of cernent. The cernent was separated from the explosives usine a plastic cover and
jute to prevent any reaction between the explosives and the cernent. The cernent sternrning
extended beyond the I m deep fracture zone caused by the drift. The powder factor of the
The holes were initiated al1 at the same tirne and a 1.O Nuttley magnitude event was
determined fiom the waveforms analyzed. nie cernent sternming was ejecied from the holes.
the screen was peeled back at the collars of the holes and light spalling from the walls was
noted. Geotornographic surveys were conducted before and after the blast. Drspite a
reduction in the velocity of seismic waves in the pillar after the blast. it was not possible to
calibrate the &op to a change in rock properties. Stress variations were recorded in the center
and at both ends of the stope using the doorstopper method. The variations in the maximum
stress were as follows: the stress at the crnter of the pillar dropped Iiom 104 MPa to 59 MPa:
the ce11 on the east end recorded a drop fiom 64 to 19Mpa: whrreas the ce11 on the West end
measured m increase from 3JMPa to 42MPa. Only one of three triavia1 cells remained
operative after the blast. it indicated a change of I or 3 MPa of stress. Dilatometer tests were
conducted in bore holes and the in situ moduius of detomarion average was 55GPa.
A decision on the efficiency of the destress blast could not be made due to the
variability of the rock propenies and the difficulties in drtermining results with the
instrumentation used.
Blake et al. ( 1998). after an extensive review of international practice. concluded that
of pillar destressing is more difficult to determine. It is genrrally accepted that once a pillar
has been destressed mining should be able to proceed without the rockbursting hazard.
However there are only limited comparative records of mining "uith" and "without"
destressing. Hence success in areas where comparative records do not exist is a very
subjective rating .
Fie. 3.17 a) Longitudinal section of the P Zone with 3420E Stope b) Longitudinal
section of the 3420E Stope and the destressed pillar show hatched (Labrie et al. 1997).
A-A'
P
@ Tornographic holes
0
Walls
@ Blastholes
?
B s t view
a)
arnitt of 25 x 2OOmm
Iectric detoaaton
Fic. 3.18 a) Destress hole pattern. b) Loading schematics at the Sigma Mine after
In summary. destressing techniques have been in use since the 1960's. These
techniques have developed such that they are routinely implemented with the equipment used
to drive developrnent headings. Recent tests in South -4frica have demonstrated that
significant planning and the involvement of men and equipment during implementation. the
The Stobie mine. (Fig. 4.1) a large tonnage. low grade deposit. is the largest producer
in iNCO's Ontario Division. The mining methods are sublevel cave in the lower grade. upper
portion of the mine and vertical retreat method (VRM) in the higher grade. deeper levels.
The 25 pillar ertends from surface to the 73Om level and is 190m long and 122m widr
The Sudbury Structure is comprised of three components: the Sudbury Basin. the
Sudbury Ignrous Complex (SIC) which surrounds the basin and an outer zone of shatter-conrd
and brecciated rocks (Rousell et al. 1997). The basin consists of four confomable formations
that form the Whitewater Group. The main mass of the SIC consists of. from top to bottom.
uanophyre. quartz gabbro. norite and contact sublayer (Fig. 1.1).Quartz diorite offset dikes
C
were traditionally interpreted as a component of the sublayer. but recently were linked by trace
element concentrations to the felsic main mass norite. They intrude footwall rocks as ndiating
and parallel dikes. (Lightfoot et al 1997). The inclusion rich sublayer. quartz diorite offset
dykes and Foowall Breccia host the M-Cu-PGE ores. Archean gneisses. rni&patites.ganites
and volcanics of the Superior Structural Province extend from the west. northwest. north and
nonheast of the Sudbury Structure. Supercrustal rocks of die Huronian Supergroup and
Nipissing Diabase of the Southem province are found to the south. south-rast and north-east
of the SIC.
Ftc. 4.1 Geological map of the Sudbury Structure (after Dressler et al. 1992)
Sudbury Breccia is found within 80km of the SIC in al1 of these outlying rocks
(Rousell et al 1997). This breccia and the presence of shatter cones led Deitz (1964) to
The tectonic history includes two periods of crusta1 extension and closure known as
Wilson cycles. The latest being the Grenville Orogeny. at 1000 Ma. which caused a NW-SE
The Frood-Stobir ore deposit occurs in the Frood-Stobie Offset Dike (Fig. 4.2). The
dike consists of pods of the quartz diorite in a zone of mineralized and variably recrystalized
Sudbury Breccia. The offset. lies 2km frorn and parallel to the Main Mass norite contact.
present in the Frood-Stobie area. Thermal metmorphism from the impact event. the SIC
intrusion and the ore emplacement event are masked by the regional metarnorphism.
Okell et ai. (1979) describes the faulting in the Frood Stobie area as block style ~ i t h
NW-SE and NE-SW striking faults intersecting at 90'. The orebody is situated within a
discontinuous envelope of breccia which slightly cross cuts the interbedded metavolcanics
and metasediments of the Stobie formation. The contact between the quartz diorite body and
The three principal ore types at Stobie Mine are disseminated sulphide. inclusion
massive sulphide and contorted schist inclusion sulphide. The Stobie orebody is made up of
a low-grade disseminated ore zone above the 670m level and a hi& &gradeinclusion massive
ore block below the 670111level. The copper-nickel ratio is relatively constant through out the
Fic. 4 3 a) The Frood-Stobie, Kirkwood and Mccomeil Offset Dikes (after Grant and
Bite 1984) b) Geological section of Stobie Mine (after Stobie geological staff).
Stobie deposit at 0.9 to 1.O (Anom. 1993).
The three principal ore types at Stobie Mine are disseminated sulphide. inclusion
massive sulphide and contorted schist inclusion sulphide. The Stobie orebody is made up of
a low-grade disseminated ore zone above the 670m level and a hi& grade inclusion massive
ore block below the 670m level. The copper-nickel ratio is relativeiy constant through out the
The overcoring method was used to Setermine stresses on the 730m level. and the
l O 3 m level (Galbraith 1992). The values determined indicate that the mine openings
influenced somr of the resuits. The parameters in Table 4- 1 were used for numencal
modelling purposes and to calculate field stresses on various lrvels in 25 pillar (Table 4.2).
0 3 (0.039MPdm) --- 90
Table 4.2 Calculated field stresses (MPa) in the 25 Pilla. area and Pillar stresses at 85%
extraction ratio.
op=osX1OO1%P
%P=100-%E
The stress perpendicular to the plane of the orebody (0,) is a vector component of o,,
a, and a, and %P is the percent of the original pillar remaining and %E is the percent
extraction.
The percent extraction of the Frood and Stobie mines down to the 55Om level is
85% (Fig. 4.3a). To calculate an average pillar stress at the center of 23 pillar. at the
175m level. the stress perpendicülar to the ore body is 15MPA. at 85% extraction ratio
the pillar stress is 100 MPa. On the j5Om level the stress perpendicular to the svike of the
ore is 24.5 MPa thus with 85% extraction the average pilla stress is 163MPa (Fig. 43b).
1 1 a) SECTION
STRESS (MPo)
20 40 60 80 1pO 120 140 160 180
1 r
CALCULATEO
STOBIE MINE
1 1 1 1 v
AVERAGE Wp
A 25 PlLLAR
I T
m
3 GUI 85% EXTRACTION
O000 O A
m3 ELASTIC MOOEL Ci AVERAGE ep
STOBIE MINE 25 PILLAR STRESS
85% EXTRACTION
Fit. 4.3 a) Longitudinal section of Frood and Stobie Mines indicating an extraction
ratio of 85% above the 55Om level. b) Plot of stress versus depth. o,,a, & a, = Maximum,
intermediate & least principal stresses respectively. a, = average stress acting on a pillar.
4.1.3 Rock strengths
The ore in 25 pillar consists of disseminated sulphidrs in quartz dionte host rock.
while the hangingwall and footwall rocks are meta-sediments and meta-gabbros. The
strength data determined from core (d=j4mm) specimens fiom a borehole on 27.5 section
Table 4.3 Uniaxiai and Triaxial Compressive Test Results of Rocks from BH 90264
ROCK (MW ROCK (MW
TYPE TYPE
Quartz
Diorite
206.2 Mean = 21 2.1 220 Mean = 307.9
Il
212.6 Std-Dev.= 23.9 H
377 Std.Dev.= 80.2
Maximum = 258.8
H
Il
183.6 326.7
Il
215.9 Minirnum=179.8
1
tt
213.7 -
11
228 Metasab- Mean = 373.3
t1
tI
182.3 41 1.8 Std.Dev.= 54.4 ,
t1
219.7
II
258.8 Amphib. 414 Mean = 361.5
Il
179.8 11
291 -5 Std-Dev.= 76.7
Il 1I
232.6 300
11
, 440.4 ,
T r E i a Compressive
~ Test Results of Rocks from BH 90264
r 1
Diederichs (1997) identiiied three major joint sets in the footwall of 25 pillar on die
120m and 180m levels 89" 333". 85" 242" and "01" 068". Joint sets at deeper levels are set
out in Table 4.5. The joints weaken 25 Pillar and they would becorne the loci for rockbursts.
Table 4.4 Attitudes (Dip & Dip Direction) of Joint sets identitird between 430m and
Sublevel cave mining requires the influx of cave rock as cover to maintain a safe
system. Othenvise. possible catastrophic hangingwall failure would cause an in-rush of air.
The method chosen to mine the top of the block (420m to 165m levels) and to induce caving
in a controlled manner was VRM (Fig. 4.3). This was done by excavating a topsill on the
420m level and a bottom siIl. or extraction horizon on the J65m level. The general
configuration was to mine VRM panels dong the hanging wall and proceed diagonally
towards the foohvail and towards the south. The panels were generally 33m long, 18m wide
and 46m high. with a planned 80% recovery of the broken ore once caving had started. The
remaining 20 % was left as cover. Caving of the back proceeded well with only minor
encouragement required d e r the third stope had been mined. The encouragement consisted
of drilling and blasting a few 100mm-diarneter holes in die back above the open VRM
stopes. The ore outlined behveen the 420m and 465m sublevels enabled the extraction of the
north half of 25 pillar. leaving a segment 90m along strike and S m from footwall to hanging
wall. The resultant pillar had a height to width ratio of 0.43 on the 420111horizon and 0.76
on the 465m horizon. The average height to width ratio for this portion of the block was 0.6.
in the walls and backs of the drifts on 42Om and J65m sublrvels. They were rnapped and
monitored regularly. At this time. the height to width ratio of the remaining pillar was 0.5
on 420m and 1 on the 465m level. Initially. the cracks were thought to represent tàilure along
a preferred plane parailel to fabric in the rock. but splitting of the pillar as stress increased.
sirnilar to the axial splitting observer in uniavial samples of core in a press is the
interpretation proposed by the author. The failure and associated cracking progressed from
single straight cracks in the ore and shotcrete. to the formation of loose blocks. then failure
of the rebar bolts resulting in minor falls of ground. It is important to dari@ that larger falls
of ground were experienced on the 420m level close to the caving front.
To ensure continual monitoring of the reaction of the pillar rock mass to mining, a
novel monitoring method was developed. A band or strip of shotcrete was applied on the
wdls of the drifts. This strip. which was 0.5m wide and 25 to 40mm thick. was applied a
rneter above the floor and started at the entrance to the block on 465m level. The shotcrete
strips were applied to specific drifts at right angles to one another to monitor movement in
different directions. The response of the rock mass to mining was sasily documented by
scanning the ~vallsregularly and painting and dating the cracks. A monitoring prognm using
extensometers. data loggers and control points would have cost in the $50.000 to $100.000
ranges. As expected any tensile failure resulted in a crack and stress failure resulted in
spalling.
The mining method used on the J90m lrvel and subsequent levels was sublevel cave.
The sublevel cave mining from 190m lrvel up to the J65m sublevel k v a s started at the 2650
rock stope in the north west corner of the pillar and progressed towards the footwall. The
progressed. Stobie Mine still has a low level of seismicity and a corresponding low
frequency of rockbunts. Between 1970 and 1988 an average of one rockburst per year
occurred. During the years 1988 to 1998 an average of 5 rockbursts were recordrd per year
with highs of 8 recorded in 1996 and 1997 (Fig. 4.5).Currently three to ten Iow level seismic
events (no displacement) due to re-adjustment of the stresses after blasting, occur per day.
One rock burst per year since 1995 was associated with the marcasite filled shear on 915m
level. Since November of 1995 four 2.4 to 2.8 Nuttli magnitude seismic events. and 4
rockbursts associated with 25 pillar have occurred (Fig. 4.6 and Table 4.5).
FIG.4.1 Longitudinal section indicating the mining in 25 pillar between 420m and
550m leveis.
Rockbunts per year 1970 to 1989
Year
1965 1970 1975 1980 1985 1990 1995 2000
Fic. 4.5 Histograrn indicating the number of rockbursts at Stobie Mine per year.
Table 4.5 List of Seismic Events and Rockbursts Associated with 25 Pillar. See Fig.
1 No.
I / Diqlaced. / Mag.MNn*l
1
ST64
I 1 19:39 I 550m 1 2262 X-C. 1 OSTons
ST66 Jun.03/98 15:35 425m 25 Pil.Gar. lTon -
ST67 Jun.24198 07:19 580m 25 Pillar clTon 2.4
1.* Mn indicates a Nunli Magnitude, which is sirnilar to Richter Magnitude but used
Frc. 4.6 Rockbursts and Seismic Events Associated with 25 Pillar of Stobie Mine
pilla was used as an indicator of the potential of a very large seismic event or rockburst if
25 pillar should fail. Presurnably. filure would occur while mining on the 55Om level. since
it was the first level on which the pillar was to be mined right across from 12 block to 3 1
Numerical modelling was used to evaluate the various scenarios for mining 25 pillar
and assess the consequences of rach mining sequence. Tlie modelling was conductrd using
Map3D, a comprehensive three-dimensional rock stability anal y sis package ( Wilcs 1996)
distributed by Mine Modelling Limited. The package was usrd to construct models. analyze
and then display displacements. strains. stresses and strength factors of various phases of the
mining. The program fonnulation is based on the Indirect Boundary Element Mrthod and
elements. A version of Map3D with linear elastic solutions was used. However zones with
different moduli were used in some of the evaluations. The caved areas on surface and mine
openings down to the 73Om level were includrd in the mode1 (Fig.4.7).
The rnodelling was carried out in two Stages. In stage 1. numerical modelling was
used to evaluate when in the overall mine sequence 25 pillar could be rnined. The models
indicated the selective mining frorn the 420m level to the 55Om level would not have adverse
effect on the pillar or adjacent rocks. However if 25 pillar were to be kept intact and oniy
mined from the 640m level down. the pillar would start to fail before the onset of mining.
Once the rnining on the 640m level would extend across 25 pillar an extensive failure zone
is propagated both above and below the mining horizon. Thus it was of paramount
importance to mine 23 pillar From the 420m level d o m . Another negative impact of mining
the pillar later would be the lower mine grade due to the reduction in high grade ore available
to balance the mine output. If mined early the low grade 25 Pillar would becomes
incremental ore. which could be mixed with a greater portion of the high grade reserves.
In stage 2. a second series of numerical modeis were used to analyze the 25 pilla
destressing project. Specific objectives were as follows: ( 1 ) define the level of stress and
rxtent of failure induced as mining progressed: (3) evaluate the effect of drstressing the
pillar: (3) evaluate the effect of mining without destressing: and (4) determine whether a
destress dot could be usrd. and during which phase of the mining it should be implemented
(Fig. 4.8).
Six phases o r mining were identified For assessrnent purposes: Fig. 4.9 displays
simplified plans of four of them. For each phase the relevant portion of the J90m. 520m. the
55Om and 610m levels were constmcted (indicated as mined) in the model. (See d s o Fig.
4.4.)
The destress slot represented in the numericd model by three methods: (1) a 2m
thick slot with weakened rock. (a, of 10% of the intact value). (2) a 0.311 thick vertical
mined out zone and (3) a 2m thick mined out zone. Phases without the destress slot were
modelled for comparative purposes (Fig.4.10). When dealing with mine-wide geometry it
is often not practical to look at individual openings For detail. Given that the destress slot is
an extremely narrow dit. it was necessary to incrrase the size of the dot in the numerical
mode1 beyond its physical dimensions to ensure that the numerical results were reasonably
correct. It is well known that thin elements or elements with extreme aspect ratios are
numerically inaccurate. Hence to over corne this problem the destress slot was analyzed as
Hoek-Brown strength panmeters were used to determine safetp factors (Hoek et al.
19%). The modi fied Hoek-Brown failure criterion for intact rock. an empirically derived
s and ïr are constants which depend upon the characteristics of the rock mass
o., and o are the axial and confining effective principal stresses
respectively.
The values used were a tende strength of O. a uniaxial compressive strength of 155
0.0326MPalm S. and 0,= 0.029MPdm S where S = depth below surface in meten. The trend
of the principle stress is 100 degrees. The plunge used was O degrees.
stop 1 Stobie Mine - 2S P I U A R Eualuation Destressing Progran SSSPDE62/11/9?
t I
FIG. 4.7 Plot of the numerical mode1 geometry (MAP3D used) indicating the
PHASE 1
b) PHASE 2
C) PHASE 3
d) PHASE 5
MINING IN
amsi
25 PILLAR eza DESTRESS SLOT-
Fie. 4.9.Plans indicating the opening included in each phase modelled. a) Phase 1. J90m level66%
mined, 520m 25% mined, 550m rock stopes, 610m level30 block 50% mined. b) Phase 2,490m level 100%
mined, 520m level50% mined, 550m 25% mined. Conditions prior to blasting the destress dot. c) Phase 3,
49Om level 100% mined, 520m 50% mined, S5Om 35% mined, Destress dot blasted. d) Phase 5,490m level
100% mined, 520m 80% mined, 550m 50% mined, no demess slot. Note Phases 4 and 6 and 6lOm level are
A list of the models analyzed in stage 2, detailed summaries of individuai models and
the key findings are contained in Appendix B. Al1 of the electronic data for stages 1 and 2
of the modelling is archived on the Stobie Mine netsvork. Hard copies of the o,.o,and safety
Model S3PD29I indicates the rffect of the destress slot very well. The destress slot
is represented in this mode1 as a 1.8mwide excavated slot and results are plotted on a vertical
erid through the pillar. The o,plot indicates a band of reduced stress through the pillar. High
C
stress zones are located above and below the destress slot (Fig 4.10). The o;plot indicates
a zone in tension on the HW and FW of the dot. Zones of increased confinement are located
above and below the slot (Fig 4.1 1). The safety factor plot indicates the core of the pillar
Modeling indicated that failure would begin with the removal of between 25 and
50% of the 5jOm level. Also. the central portion of the pillar. above and below the destress
slot (core of the pillar). would either fail early in the mining history with the blasting of the
destress slot. or later in the mining. as the extraction of the 55Om to 52Om level block
proceeds. In surnrnary. destressing was required to promote timely failure of the core of 25
pillar.
(MPa)
al
(Psi)
Fic. 4.10 A G,plot on a vertical _gid through the pillar in Mode1 S25PD29I in which
The objective of destressing 25 pillar was to: promotr failure of the pillar dong the
dot. induce failure above and below the slot at the time of or shortly afier the destress blast.
and to produce a failure zone dong which mining could progress without building up stress.
nie following stcps were taken to promote these objectives: (1) Mining w s directed to
induce the highest level of stress dong the destress slot and (7) Two sets of fan holes were
located on the ends of the destress slot. to provide more of an opening for the destress blast
to break to.
If there were preferences. a destress blast would in itself producr muck. and would
be scheduled or designed before stresses are elevated (before the pillar becomcs a pillar)
which wouid make it a preconditioning blast. Consideration could not be given to designing
a preconditioning blast because in the Stobie case the pillar pre-existed the drcision to
recover a portion of it. However. if there is not a high lrvel of stress. the blast will not have
the potential to fracture and condition the ground to the same rxtent. Mining sequences
require the mining to start at a fault or opening (slot) and progress away from it.
The destress slot contained two parallel rows of holes. which are also parallel to the
strike of the hanging wall contact. Two fans of sublevel cave rings were placed on each end
of the destress slot. one against the rock stope on the north and the other against 20 block on
the south (Figs. 4.14.4.15 and 4.16). The fans and rings of holes. were designed to: (1) create
a positive opening for the first few destress holes to break into; (2) reduce the length of the
STRESS CELL & POINT # 1
POlNT #2
550m LEVEL
PHASE 2
Fie. 4.13 Plan of S5Om level with sirnplified geometry of Phases 2 and 3 indicating
stress regime fiom numencal mode1 and stress change determined by stress cell.
destress dot and (3) concentrate the stress on the slot. The fans (Fig. 4.15) are typical wagon
wheel fans with rings inclined above the horizontal at 50". 65". and 70" grading into 80"
rings. The fans to the north and south of the destress slot were blasted together on the first
blast and the 80" rings were blasted altematively on the subsequent blasts. It is important to
note that the rings were not blasted till al1 the destress holrs were loaded with emulsion. This
was to ensure that if a stress or seismic problem developed the holes could be primed and
wired quickly.
The holes were 2 1.3 rneters long by 102 mm in diameter. The rows were designed
to be 1.8 m apart but ranged from 1.5 to 1.8m due to variations in drill capabilities. The rows
followed the destress drift and essentially were panllel to the hanging wall contact joining
the southeast corner (HW) of the 2340 rock stope and the northeast corner of 20 Block. The
holes were inclinrd at 85" from the horizontal. There were differences in the spacing of the
holes in the hanging wall row of destress holes. The holes on the north half of the drift were
spaced 2.4 meters apart and the holrs on the south half were spaced 1.8mapart.
The holes in the row on the footwall sidr of the drift were drilled 0.61m apart and
every second hole was loaded and blasted. These holes were the pnrnary destress holes. The
empty holes were buffer holes and were to induce stress and promote fracturing. The holes
in the hanging wall row were designed to extend the fracture zone created by the primary
destress holes.
4.4.2 Explosives
The emulsion used in the destress blast was the same product used in regular sublevel
SCALE
Fic. 1.14. Plan of 550m level indicating the geometry of Phase 3 of the numerical
model. This geometry coincides with the position of the mining front when the destress blast
was taken.
Fic. 4.15 Longitudinal section of the destress slot indicating the fan rings on the
North and South ends. The general attitudes of the destress holes are indicated. Not al1 the
standard used in the mine on a daily basis. D p o Nobel Ltd. manufactured the ernulsion w d
under the trade name of RUS Emulsion and its properties are listed in Table 4.6.
Fume Class t
The holes were loaded with a toe loader. The emulsion was purnped through a wand
that was inserted up the hoie to the toe and retracted towards the collar as the emulsion was
pumped. The holes were designed to be loaded to 1.jmand 3m fiom the collar on alternate
holes. In the field. most holes were loaded to 3.lm from the collar. A total of 10,045
kilograrns of explosives was loaded in the destress holes. The rings on the south side and
--.
- 4 . 5m
*I
-#*
a#--
#-* 21 70 OESTRESS ORlfT
-- wu-
t- ~ ~
40 DISTANCE BETWEEN HOLES
DETONATION SEQUENCE
4 DETONATION SEQUENCE
FIG.4.16 Simplified plan of 2170 Destress drift on 55Om Ievel indicating the hole
emulsion Ioaded destress holes. b) Blaster and Dyno Nobel Technicd representative placing
the boosters at the correct distance up the hole with a fiberglass rod.
FIG.4.18 a) Back of the destress dot facing North. Holes are Ioaded and primed.
b) Loaded and primed holes in the back of the destress dot, view facing South.
4.4.3 Timing of Holes and Kilograms of Explosives per Delay
Due to the number of holes in the destress blast. both Nonel Unidets (short period
detonators) and Nonel long period detonators were usrd to ensure that al1 the cap delays
would have been initiated before the first hole would detonate (Werely 1998). The holes
were double primed at 1O.7m and 7.2m from the collar (Figs. 4- 17a. b and 4.1 8a. b). The
short period detonators used were. 1-22.24.26.18. 30.32. 36.40. The timing for the short
800ms (#40 =1000ms). The Long Period (LP) detonators used. ranged fiom a X3LP
(1 100ms) and ended with #17LP (7700ms). The longest delay a number 17 would have
extended the duration of the blast to 7.2 seconds. Since two holes on the foohvall and 3 holes
on the hanging wall were crushed and were not successfully initiated. the blast only lasted
4.9 seconds. Emulsion was observed after the blast at the collars of the crushed holes on the
South end of the destress slot. Two delays had 5 6 4 g of explosives: the remainder had 1 87kg
3.5 Instrumentation
A CSIRO HI stress ce11 (Council for Scientific & Industrial Research Organization
of Australia Hollow Inclusion Cell) was installed February 17Lh.1998 in a 10 . b long hole
ddled in the back of 21 85 X cut (Figs. 4.13.4.23 and 4.24). The hole was inclined at 85"
towards the destress slot and the cell was located 14 m from the slot. The ce11 was wired to
a multiplexer and data logger on February 25th. Readings were taken every hom. The data
An Electrolab MPXO microseismic system has been used at Stobie since 1988 to
monitor strength and location of seismic events. This system does not capture waveforms or
plot wave traces of the blasts or events recorded. Active areas c m be identified and the çvent
frequency and density (number of events per hour and volume) c m be determined. The decay
Instantel digital seismographs. rquipped with triaxial çeophones (Fig. 4.1 9). The geophones
have a Peak Particle velocity range of up to 254mmls and a frequency response of 2 - 3 0 Hz.
in addition to the digital seismograph a microphone with ri Peak Sound Pressure Level
(PSPL) range of up to 1J2dB was used to record overpressure at the site in a sub-division
Stress had been evident on the 55Om level fiom September of 1997 when the "in the
hole" (ITH) holes of 2260 rock stope (fiom 5jOm to 610m level) started dog-earing. The
formation of these borehole breakouts in production holes. in the 25 pilla. at Stobie mine
signalled the advent of failure and the need for destressing (Fig. 2.8). The presence of egging
in drill holes is used as an hdicator that the stress level is sufficient for primary destressing to
be effective. Considenble squeezing and sloughing with associated seismicity occurred
during the blasting of the sublevel cave rings in the minor pillar between 2340 rock stope
(55Om to 565rn level) and 2530 rock stope (490m to 55Om level) during the months of
J a n u q and February of 1998. Sloughing occurred in the walls of 2260 rock stope at the
55Om level topsill in late February of 1998. Cracking and shear failure of the shotcrete and
egging of the destress holes in the south end of the destress slot were noted on the 1' of April
1998. On May 4Ihadditional egging was noted in the destress holes at rings 2066 and 2077.
The last ring on the South side that was double primed. as per the design. was ring 2079.
Rings 2066 and 2077 were collar-primed. On May 4'. Rockburst ST-64 displaced 1 ton from
the back of 7262 driti on the 55Om lrvel. On May Yh spalling was noted in the shotcrete at
2080 orepass drift on the 55Om level. The sequence of rvents described above indicates the
increase in stress as mining progressed and the release of stored strain energy that occurred
wiith the Failure around the openings. The timr to blast the drstress slot was close at hand.
The destress blasr was detonated at l4:Q on May 9Ih1998. Al1 three adjoining mines
(Stobie. Little Stobie and Frood) were cleared for the blast in case a Richter (Nuttli)
magnitude rockbunt should occur. Access to 490.520.550 and 580 m levels was resuicted
tiil 7:00the day following the blast. Work was performed on the b e l s below 590m during
the afternoon shift of the 9Ihafter the smoke and fumes cleared.
Conditions in the destress slot were reviewed on May 10Ih.There was no damage to
any of the mine openings outside of the destress slot (Fig. 4.20). The back of the destress slot
was cratered up to twelve feet above the original back. The muck was relatively fine with
The stress ce11 rneasured changes induced by blasts taken on the Zorn. 550 and
610m levels. As expected the destress blast had a marked effect compared with the other
blasts (Fig. 4.23). The slope of the plot of the values is an expression of the creep of the
The changes in stress calculated from the strain changes recorded by the stress ce11
between F n d g May 8Ih the day before the blast and Tuesday May 12Ih.3 days after the blast
The minor stress drop c m be compared to the values calculated using the numerical
modeling of phases 2 and 3 (Fig. 4.13). While a large drop in stress would be desirable the
failure of the core of the pillar was considered a primary goal of the blast. The mode1
indicated the destress blast would promote failure of the core of the pillar above and below
the destress dot. however it is difficult to assess this in the tield. The 1.4 Nuttli Magnitude
ment that occurred at 07: 15 on June 24th in the north wall of 3 pillar on 1900 level is
Table 4.7 Changes in stress caused by the destress blast rneasured by the stress ceil
% +3.8 57 O 23 O
b 3 +1.1 14 O 135.6
I
Figure 4.13 indicates the stress regime in phases 2 and 3. calculated at two grid
points, one at the location of the stress cell. and the other 18m to the footwall. at the same
elevation as the stress cell and on the same section. The stress drop indicated by the stress
The destress blast \vas classed as a mild blast with minimal vibrations felt and
recorded on surface. A strong reaction was expected on surface due to the confinement of the
explosives (lack of free face) in the centrr of the destress dot and the high stress the pillar
was subjected to. which would promote better transmission of the shock waves from the
blast. A greater that 7 Nunli magnitude (Mn) seismic event was anticipated within 24 hours
of the blast as the pillar failrd and released its stored strain energy. Neithrr a large shock
wave nor a seismic rvent was associated rvith the blast. The low kilograms of explosives per
delay producrd acceptable Peak Particle Vclocity (PPV) on surface and at the garage on the
550m level. 150m fiom the destress dot. A 3.4 hiln seismic event occurred at 07:19 on June
24Ihon the 58Om level dong the north wall of 75 pillar (Figs. 4.6 and 4.2).
The destress blast was recorded over five "event-windows" by the microseismic
system due to its long duration. Thirty-four events were recorded over the two days
following the blast. On the third day afier the blast only 3 events were recorded. By
comparison 3 1 events were recorded on the 24 Ih of June. the day the 2.4 Mn seismic event
There were an average of 17 seismic events recorded per day during the month of
April and an average of 12 and 1 1 per day during the months of May and June respectively.
By comparison the month of October had 2.4 events per day. The data recorded during the
July vacation shut d o m indicated an increase in activity in the areas of the marcasite shear
on the 91jm level but no activity in the 23 pillar area. The events recorded during a
production shut d o m are a good indicator of the areas in the mine. which are eidier retuming
to their naturai stress strtte. or are naturally active without mining induced stress. One could
postulate that the destress blast and the 2.4Mn event transferred stress to the abutmrnt dong
the rnarcasite shear. The recorded vibrations and overpressure induced by the blast are
Table 4.8 Peak Particle Velocities and Peak Sound Pressure Levels recorded of the
A complete evaluation of the success of the destress blast can only be properly made
once the 55Om level is completely mined. A preliminary evaluation indicates the destress
blast was a success. based on the stress drop recorded by the stress cell. the reduction in daily
seismicity through out the mine and the absence of any new stress related problrrns on the
FIG.4-19 Plot of the wave form of the destress blast recorded by Explotech
the hanging wall. Note there is approximately 6 feet of ore in the slot. b) Close up view of
Fit. 4.22 Plot of the traces captured by the Eastern Canada seismological network of
---Gauge 6
- -. .
-Gauge 3
Gauge 4
I -Gauge 5
2 RINGS SdUW
' -Ref 120
STAR ' OF DESTRESS
R O T FAN MNGS
"ORrn
-Gauge 1
M E 0 NORTH h M U T H
8 RINGS SCUTH
-Gauge 2
I -Gauge 7
JUUAN DATES
Fie. 4.23 Plot of the suain change data capnired by the stress ce11 and data logger.
Rockbursts are the result of the sudden release of stored strain energy derived from
the stresses induced by mining at depth or to a high extraction ratio. Control methods range
frorn modi@ing geometries to altering the rock properties by destressing. The physical
expression of the release of stored strain energy includes dog-earing. core disking. slabbing,
pillar failure and bursting. A review of the historical development and a comprehensive lis1
of the various methods of destressing are contained in this thesis. Special interest is paid to
destressing of pil1;ü.s. culminating in the description of the drstressing of the regional pillar
The significant milestones of this project are: (1 ) mining was directed to induce stress
along the destress slot and the pillar was succcssfully brought to a point that failure was
eminent: (2) over 10.000 kg of rsplosives was used to destress the pillar without damaging
the mine infrastructure and (3) the drstress slot. which was designed to promote failure in
the core of the pillar above and below the dot provided a zone from which mining could
safely proceed.
The risk of bursting has been reduced for the extraction of 1.8 million tons of ore
between the 550 and 520-m levels. Another 5.6 million tons of ore is available if mining
proceeds io the 64Om level. It is recommended that the seismicity induced as mining
proceeds in 25 pillar be reviewed in the final evaluation of this project once the ore on the
June 1994 First VRM Production blast between 420m and 465m levels
June 1996 Joint Preliminq Report on Destressing 25 Pillar Preston and O ' D o ~ e l l .
February 1997 Approval From MC0 to Use the destressing project as a Thrsis
September 8th 1997 Photographed ITH holrs egging in 2260 rock stopc on 55Om
May 4th increase in the deformation (egging) of the holes in the south end of the
destress slot at rings 2066 to 2077, the lnst ring primed is 2079.
June 24th Major seismic event of 2.4 Mn. Magnitude at 07:l-l on 580m level
December 1998 No new stress related detenoration noted in 25 pillar on the 520 and
55Om levels.
Appendix B Numerical Analysis.
The purpose of the numerical modeling analysis of the 25 pillar destressing project
evaluate the effect of destressing the pillar and 3) evaluate the effect of mining without
destressing. Al1 numerical analyses were camed out with the three-dimensional boundary
0.0326MPdm S. and flj = 0.029MPdm S where S = drpth below surface in rneten. The trend
of the principle stress is 100 degrees. The plunge used was O drgrrrs. Hoek Brown strength
parameters were used to determine saîèty factors. The values used were a tensile strength of
Five phases or stages of the mining process have been identified for assessrnent
purposes. The first phase represents the mining grorneûy to Janu.; of 1997 at which time
the following was rnined: (1) 66% of 25 block on 490m level was mined (sublevel cave): (2)
25% of 520m level: (3) 100% of the 55Om lrvei rock stopes and (4) 50% of 30 block on
6 10m level were mined. Figure 4.9a shows this initial phase of the mining in 25 block.
Phase 1 of the mining was evaluated using models S25PDESl to 4. The efiect of the
georneûy on the stress regime and the extent of failure in 25 Pillar are displqed on 4 grids.
Grid # I is a vertical transverse section frorn 38Om level to 6 10m level along 2 140 section.
this is referred to as view SXPSTRN. Grid #2 is a vertical longitudinal section along 1060
line fiom 380m level to 610m level and is Iabeled view S2SPSLNG. Grid #3 is a horizontal
grid at 5201-11 level, the view is from the bottom up. with the footwall at the top of the page.
This view is referred to as S25PPUDR. Gnd #J is aiso a horizontal grid. it is located at 55Om
level and is viewed from the bottom looking up. the same view as used for grid #3.
Phase 2 of the mining represents the geometry of mining at Aprii 1997 with 100%
of 490m 1eveI mined. 50% of 52Om level mined. and 25% of SSOm mined. Models
The mining conditions projected for June 1997 are representrd by Phase 3. which
was modeled by the runs S2jPDES9. S2ZPDElO to 12. The geometry of phase 3 represents
100% mined on 490m level. 50% of 52Om levrl. and 25% of 55Om level. Mining in this
phase includes a vertical 6' thick soti zone from j20m to 5ZOm level joining 12 block to the
Phase 4 has 100%of -F9Orn mined. 80% of S X m 50% of 550m level and the 6 Z Om
level foot wall drift rnined. A 6' wide softened zone represents the destress slot. The models
Phase 5 has the rame mining configurations as phase 4 but without the destress slot.
Models S25PDE29 to 32 evaluate the geometry of phase 3 with a 1' thick slot to
simulate the destress slot. Models 33 to 36 have the geometry of phase 3 without the softened
6' thick slot of models 39 to 32 nor the 1' thick slot of modeis 9 to 12.
B.2 Summary of Key Findings
average of 60MPa 0,stress in the core of the pillar. The confining stress sigma 3 is about
13.8MPa. The strength factor used is the most appropriate to use when assessing pillar
failure. it is the factor that gives the smallest value thus it is the most conservative. The
strength factor is defined in terms of the o,strength divided by the current stress assuming
a constant value of sigma 3. The analysis indicated a short to long term stability in the core
of the pillar. a safety factor of 1 -3 to 1.6. Failure is limited to the periphery of 17 block and
30 block.
confinement in the core of the piilar from an average of 13.8MPa in phase 1 to 9.6MPa in
phase 2. This drop in confinement reduces the stability of the pillar and an increase in the
rxtent of the failure zone is ctvident in the plots cornparrd to phase 1 plots.
plots indicate little if any increase in the principlr stress in the core of the pillar but a further
strength in phase 3 follows the reduction in confinement. The edge of the mining on 55Om
level induces a rise in confinement just below 550m level as well as an increase in
confinement to above 20.6MPa in the hanging wall and footwall. This local increase in
Models S25PDES9 and S25PDE10 to 12 represent phase 3 with a 1.8m thick destress
slot sirnulated by reduced rock strengths of 25MPa pillar strength and an angle of intemal
122
a destress slot of similar properties. Modelling the destress zone in this fashion has not
shown any change in the results. In comparing models SZSPDE 13 to 16 (Le. phase 4 with
difference in the results. This would indicate the material properties assigned are not low
A cornparison of the results of phases 3 and 4 without destressing indicates very linle
change in confinement and extent of failure caused by the increase in mining in phase 4.
A destress dot in phase 3 was simulatrd by creating a O.3m thick dot (mined not
sofiened) tiom 52Om to SjOm level in models S2jPDE29 to 33. In comparing these rnodels
up to 13.8MPa to the footwall of the destress dot. A signiticant reduction in o3and a tensile
zone occurs to the hanging wall of the slot. This causes the two hilure zones in mode1 33 to
In cornparhg models 3 1 and 33 with 35 and 36. the destress dot greatly extends the
evaluate whether a 1.8m wide sofiened zone with a unimial compressive strength of 1 SMPa
( 10% of the intact value) and m = 0.0 14 and s = 0.000 1 could simulate a destress slot. There
is absolutely no difference between the results of models 13 to 16 and the results of 37 to 40.
They have 75% of 550m level mined. To evaluate the conditions in the center of the
remaining pillar the vertical transverse grid was moved to 3080 section. In comparing the
results of models 41 to 44 with models 17 to 20. which have 50% of 5Om level mined. an
increase in 0,is noted. The a; plot indicates an increase in confinement in the hanging wall
of model 4 1 and a decrease in the confinement in the core of the pillar. A large increase in
the extent of the failure zone is indicated by plot S25D4 1SF. The increase in failure zone is
not as evident on the long section plot S25D42SF nor on the plans at 520m and 55Om leveis
Plots S25D43SF and S25D44SF respectively. It c m be surmisrd that the pillar has îàiled
when 50 % of 55Om level has been minrd. This is why the destress dot is pianned to bc
blasted when the rnining on 5Wrn is confined to hanging wall area and only 35% of j5Om
B.3 ConcIusion
The purpose of the destrrss slot was to promotc a tirnely tàilure of 35 pillar and
reducr the risk of injury by controlliny the failure with blasting the destress dot. Numerical
modeling and comparing the changes in the sxtent of srress and failure zones as rnining
progresses provided an indication of early tàilure pnor to destressing. This early failure may
result from the safety factor used. There have been no previous cases that could be used to
calibrate the model. Assuming that failure will start prior to rnining the destress dot. there
is still a need to destress since the core of the pillar does not fail till the destress slot is taken.
In summary. the modeling indicates a need to destress 23 block to promote a tirnely failure
Mining
Phase
Comments I
1
additional models were run to attempt to define or elirninate the stress riser visible in models
S35PDE29 to 3 1.
The problem was partially eliminated by adding joiner plates between the destress
slot and the large mining blocks. However it required a wider destress slot to eliminate the
problem. With a O.3m \vide slot. the image of the destress slot was transparent when viewed
frorn the foohvall. When viewed from the hanging wall it was opaque. Increasing the destress
slot to a 1.8m width eliminated both the transparency problem and the stress riser. Models
S25PD32H and S25PD321 were used to plot the stress values at two points. Models
Model S25PD29I has a vertical gnd through the pillar. The o,plot indicates a band
of reduced stress through the pillar. High stress zones are located above and below the
destress dot. The ojplot indicates a zone in tension on the HW and FW of the slot. Zones
of increased confinement are located above and below the slot. The Safety factor plot
indicates the core of the pillar above and below the slot has failed.
Model SXPD321 has a horizontal grid through the destress dot at 533m level. The
a,plot indicates the stress level through the pillar is at the background level. The o3plot
indicatrs tension dong the destress dot. The Safety factor plot indicates a zone !O the
foot~vallof the destress slot which has not failed. This is due to the increase in conilnement
in this area.
Model S25PD3 11 has a horizontal gridjust above the destress dot at 5ZOm level. At
the destress slot the grid cuts the stress riser above the dot. The Strength factor plot indicates
Model S25PD3OI has a vertical grid just to the footwall of the destress dot. Failure
is indicated across the pillar along the top half of the destress slot. The zone with a strength
factor greater than 1.6 that coincides with an increase in confinement is indicated at the
bottom half of the destress dot.
In summary models S25PD29I to 321 indicate the destress slot causes a &op in stress
in 25 pillar between 520m and 55Om levels. Failure is promoted in the core of the pillar
Collar The Collar of a hole is the opening or start of the hole. The term collaring or
starting a hole is commonly used. The end of a hole is referred to as the toe.
6 are of a larger diarneter and usually are not charged with explosives. The purpose of the
cut is to provide a free Face to which the remriinder of the round may break (Singh !990).
Cut The cut in a stope designates the lifi or slice mined. (i-e. The crew is mining
on the Yd cut.)
Crown Blast The c r o w blast in a Verticai Retreat Mined (VRM) or VerticaI Crater
Retreat (VCR) stope is the final blast taken through to the topsill. Usually the c r o w is 8 to
Primary Undercut and fil1 Method. A mining method that uses multiple slices
driven from a main dot to recover a block of ore. Each slice is tilled with a tirnber and screen
mat and cemented till. Once a cut has been completed the n e n slice is taken below the
previous cul. This is an underhand stoping method. It is usrd in extremely high grade. where
complete recovery is desirable. in ore that cannot be supported conventionally using bolts.
and in areas of high stress where the diminishing pillars created by ciit and fil1 mining are
likely to burst. The term primary differentiates the method from a pillar or secondary
Rebar Rebar bolts are sti ff bolts made of 400 grade steel (same as reinforcement
rods used in concrete) which can have a forged head or threaded end. Rebar bolts are grouted
in the rock using resin or cernent.
Silling Silling is the term used to denote the preliminary development phase
of a stope during which the blasting requires a cul. This is to differentiate between silling the
INCO LIMITED
Stobic mine expcrienced a 2.3 Mn (Richter) magnitude rismic event on Damiber 18,
1996. at 8: 13. A signifcant stress buüd up is cxpectcd as miaiDg continues in 25 block. This
stress wilî dissipate whcn the geometry of the diminishhg piliar U such tbat fulm taktq place.
Failurc may bc acçompanied with bursting. Once mining has pmgrcsd to rbc point that 30 block
ud 12 block arc jowd by the mining of 25 block the Iiicclihood of seismic events king inducd
wouid k vcry smaii. It might bc desirable to &stress the diminLching pillar to rclease this energy
at a prcscnil tiw rathcr than it failhg at an Uhdctenninablc the.
Destrcssing of pülars is rclaiively new, with some data availabfe on prcconditioning blasts
at the Mt. Cbarfottc mine in Australia.
INCO LIMITED
Further to our conversation, 1 request approval to write an MSc thesis on the destressing
of 25 Pillar between 1700 and 1800 levels at Stobic Mine. The d e s w i n g of this pilla is required
to induce failure of this pillar at a desirable lime. Documentation of this project will increase
INCO's profile in the mining and academic community. The cost to iNCO will be minimal as the
thesis would be written on my own t h e .
Denis O'Donnell
Rock Mechanics Specialist
Frood, Stobie and Shebandowan mines,
U--N.
ANONYMOUS. 1993. Frood Mine 5 Yrar Plan. W C 0 Limited. Interna1 Report. 278 p.
BHARTI. S.. and WEST. D. 1984. A Technical Assessrnent of the Rockbursts on June 20-23.
1984 at the Faiconbridge Mine. Report to the Ontario Ministry of Labour. Occupational
Health and Safety Division Mining Health and Safety Branch. Toronto. On. 45 p.
BLAKE.W. 1972. Rock-burst blechanics. Colorado School of Mines Quarteriy. 67. No. 1.
BLAKE.W.. BOARD.M. and BRUMMER.R. 1998. Drstrrss Blasting Practices. Report for
BOLSTAD.D. D. 1990. Rock burst Control Resrarch by the US. Bureau of Mines. In 19th
R.L. &
US Symposium on Rock Mcchanics. Etlited by CUNDALL.PA.. STERLING.
Consolidated Backfill System at the Lucky Friday Mine. Interna1 report. Hecla Mining
stresses and depth. lnremational Journal of Rock Mechanics. Mining. Science and
CANMET1998. Seismic profile of the 1.4Mn Rockburst. June 24'h. 1998 at 07: 1.1 local time.
3 p.
COATS.D. F. 1972. Rock Mechanics Principles. Department of Energ Mines and Resources.
COCHRANE.L. B.. 1991. Analysis of the structural and tectonic environments associatrd
with Rockrnass failures in the mines of the Sudbury District. PhD. Thrsis Queens
G. 1966. Rock Mechanics Applied to the study of Rockbursts. Journal of the South
and Rockfalls. compiled by the High Level Cornmittee on Rockbursts and Rock Falls.
DIEDERICHS.
M. 1997. Geomechanics Stability Assessrnent for Closure Planning Frood-Stobie
Cornplex. INCO Limited. Ontario Division. Klohn Crippen Consultants Ltd. PM 6880 04.
Sudbury. ON. 56 p.
DEITZ.R. S.. 1964. The Sudbury Structure as an astroblrme. Journal of ûrology. 72. pp. 412-
434.
DYKE.C. G.1989. Core discing: It's potential as an indicator of principal in situ stress
directions. In Rock at Great Depth. Etlitrd by Ma;. V. and Fourmaintrau. D.. Bakema,
600 p.
3-D tomographic imaging of anomalous stress conditions in a deep US gold mine. Joumd
Ore Deposits of the Sudbury Structure. Edired &y Pye. E.G.. Naidrett. A.J.. and Giblin.
HANSON.
D.. QUESNEL. W. and HONG.R. 1987. Destressing a rockburst prone crown pillar.
Macassa Mine. Division Repon MRL 87-82 (TR). C.LWMET. Energy. Mines and
Resourses Canada. 66 p.
HEDLEY.D. G. F.. 1987. Rockburst Mechanics. Canada Centre for minerai and Energy
HEDLEY.D. G. F.. 1992. Rockburst Handbook for Ontario Hardrock Mines. CANMET
HERGET. G. 1986. Changes of Ground Stresses with Depth in the Canadian Shield.
HOEKE.. WOOD. D. and SHAH. S. 1992. A modified Hoek-Brown critenon for jointed rock
Mechanics. In Eurock "92. Edired by J.A. Hidson. British Geological Society. London.
and Support of Tunnels under High Stress Conditions. In International Deep Mining
pp 11551177.
LU. J.. DU. L.. ZOU. C.and WANG.2. 1989. The brinle fàilure of rocks around underground
Rotterdam. pp 567-574.
hard rock mining. Editetl by P.K. Kaiser. Professional Development Seminar. Laurentian
South Affican Institute of Mining and Metallurgy. Johannesburg. pp. 1 147-1 1%.
of the Sudbury Igneous Complcx- An Introduction and Field Guide. Ontario Geological
745-752.
International Journal of Rock Mechanics. Mining Science and Geomechanics Abstracts Vol.
strength of Lac du Bonnet granite. In Rockbursts and Seismicity in Mines 93, Edired by
MARTN.C. D. 1997. The Effect of cohesion loess aiid stress path on brittle rock strength.
pp. 698-735.
Australia. 14 p.
zone at Campbell Red Lake Mine Limited. In: Microseismic Monitoring in Canadian
at the Lucky Friday Mine in Idaho. Proceedings Amencan Mining Congress Convention.
iNCO Limited. 8 p.
Sr.. J. Denis P. 1991. Support Standards and Revised Mining Sequence for
O'DONNELL
O'DONNELL
Sr.. J. D. P. 1992. The Use of Destresshg at INCO's Creighton Mine. lil Massmin
92. EJirrd by Glen. H. W.. South Afncan Institute of Mining and Metallurgy. Johannesburg.
pp. 71-74.
INCO Limited. 4 p.
Sr.. J. Denis P. 1995b. Variations in Solar and Lunar Tides and Their Influence
O'DONNELL
on the Frequency of Rockbursts and Falls of Ground (1985-1994). BSc Thesis. Laurentian
A. C. and OSBORNE.
OKELL.J. N.. SMEETH. R. C. 1979. The geology of the Frood Ore
Deposit. Vol. 1. Mines Exploration Dept.. Intemal Report. INCO Limited. 220 p.
and an effective test procedure. The Journal of the South Afncan Institute of Mining and
RORKE. A. J.. and BRUMMER.R. K. 1988. The use of explosives in rockburst control
Small Up-Dip Remnant with the Aid of Preconditioning Blasts. In International Deep
ROUSELL. D. H. 1984. Structural Geology of the Sudbury Basin. In The Geology and Ore
Deposits of the Sudbury Structure. Edi~edby Pyr. E. G et al.. Ontario Grological Survey.
ROUSELL.D. H.. GIBSON.H. L. and JANASSON. 1. R. 1997. The Tectonic. Magmatic and
Mineraiization History of the Sudbury Structure. Exploration and Mining Geology. Vol. 6.
NO. 1. pp.1-22.
situations. Journal of the South Afncan Institute of Mining and Metallurgy. Vol. 88. No. 1
pp. 37-39.
STACEY.T. R. & PAGE C. H. 1986. Practical Handbook for Underground Rock Mechanics.
of the South African Institute of Mining and Metallurgy. bIarshalltown Vo1.95. pp. 1 37-
140.
SWAN. G. 1989 Research into rockburst alleviation. Intemal Report. Falconbridge Limited.
Falconbridge. ON. 6 p.
SMGH. S. P. 1 990. Empirical guidelines for drifi blast design. bl ining. Science and Trchnology
pp. 37-44.
TSCHALENKO.
J. S. and AMBIUSEYS. N. N. 1970. Structural analysis of the Dasht-e Bayaz
(Iran) rarthquake fractures. Bulletin of the Geological Society of Arnerica. 81. pp. 41-60.
WERELY.C. 1998. Recommended Delays for the Destress blast in 25 Pillar. Intemal memo
to WC0 Limited. 2 p.
potential of cemented fills for rock burst control. In Innovations in Mining Backfill
and in situ stress at the Lucky Friday Mine. In Rockbursts and Seismicity in Mines Enired
WILES.T. D. 1996. MAP3D User's Manual. Mine Modelling Pty. LTD. Victoria. 3930.
Australia. 33 1 p.
WILES.T. D.. MARISETT.S. D. and MARTIN.C. D. 1998. Correlation Between Local Energy
Release Density and Observed Bursting Conditions at Creighton Mine. Report prepared