You are on page 1of 99

FTVET, 2023 March 2023

FDRE TVET INSTITUTE

Department of Building Construction Technology


Organized by: Belachew Asteray (PhD)

MSc program- Construction Technology and Management


Construction Contracts Law (CoTM 525)
CHAPTER TWO
ADVANCED CONSTRUCTION CONTRACTS AND
APPLICABLE LAWS AS APPLIED TO
CONSTRUCTION PROJECTS
By: Belachew Asteray (PhD)
March 2023
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 1

CHAPTER TWO
ADVANCED CONSTRUCTION CONTRACTS AND APPLICABLE LAWS
AS APPLIED TO CONSTRUCTION PROJECTS
2.1. Overview of Contracts in Construction Projects
Organized by: Belachew Asteray (PhD)

2.2. Contract Document and Legal Considerations


2.3. Construction Contract Types: Local and International
Practices
2.4. Local Construction Contracts and Laws: Analysis of Case
Studies
2.5. International Construction Contracts and Laws: Analysis of
Case Studies
2.6. Sub-contracting: Local and International Practices
2.7. Construction Audit
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 2

Organized by: Belachew Asteray(PhD) 1


FTVET, 2023 March 2023

2.1. Overview of Contracts in Construction Projects


• In general, a Contract is
• an agreement or willful promise between two parties
Organized by: Belachew Asteray (PhD)

• legally enforceable at law for both parties


• obligations to be distinct from those required by law.
• “Enforceable at law” means that if the agreement reached
between the two parties breached (deviations occur from the
promises) by one of the parties, the aggrieved party may bring a
legal action against the other to demand the enforcement of its
rights with the support of law.
• However, not all agreements or promises are contracts. Some may
lack enforceability at law.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 3

2.1. Overview of Contracts in Construction Projects …


• The general Law of Contract is governed under the Civil Code
from Article 1675-Article 2026.
Organized by: Belachew Asteray (PhD)

• A contract is
• an agreement whereby two or more persons as between
themselves create, vary or extinguish obligations of a
proprietary nature ( Article 1675 of the Civil Code).
• The definition contains the following elements:
• the contract is an agreement;
• The agreement is to be made between two or more persons;
• the agreement is binding between such two or more persons;
• The agreement is to create, vary & extinguish obligations;
• The agreement is to create obligations;
• That the nature of obligations is proprietary.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 4

Organized by: Belachew Asteray(PhD) 2


FTVET, 2023 March 2023

2.1. Overview of Contracts in Construction Projects …


• Contract can be between
• Individuals
Organized by: Belachew Asteray (PhD)

• Businesses/public institutions
• Businesses/public institutions to individual
• Contracts can be of:
• Civil,
• Commercial,
• Industrial (labour relation),
• economic (construction contract) or
• others.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 5

2.1. Overview of Contracts in Construction Projects …


• Contracts can be
• Bilateral or unilateral
Organized by: Belachew Asteray (PhD)

• Bilateral: obligations on both parties


• Unilateral: a promise made by one party in return for the
performance of an act by the other party

• Executory or executed
• Executory: a contract that has not been fully
performed.
• Executed: a contract that has already been
performed.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 6

Organized by: Belachew Asteray(PhD) 3


FTVET, 2023 March 2023

2.1. Overview of Contracts in Construction Projects …


is
• a legally binding agreement between the parties identified
Organized by: Belachew Asteray (PhD)

in the agreement
• to fulfil all the terms and conditions outlined in the
agreement.
• Contracts can be made
• Orally and

• in writing.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 7

2.1. Overview of Contracts in Construction Projects …


• According to Article 1678 (Elements of Contract) of the Civil
Code:
Organized by: Belachew Asteray (PhD)

• No valid contract shall exist unless


a. The parties are capable of contracting and give their consent
sustainable at law.
b. The object of the contract is sufficiently defined and is possible and
lawful.
c. The contract is made in the form prescribed by law.
• The following are the fundamental elements of contract:
• Capacity of the contracting parties;
• Consent of the contracting parties;
• Object of the contract; and
• Form of contract, if any;
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 8

Organized by: Belachew Asteray(PhD) 4


FTVET, 2023 March 2023

2.1. Overview of Contracts in Construction Projects …


• Capacity (Article 1678(a) of the Civil Code…
• Capacity means competence to enter in to a legally binding
agreement.
Organized by: Belachew Asteray (PhD)

• Parties entering in to an agreement or contract shall,


therefore, be capable of contracting.
• Legal capacity is of two types:
i. Personal (Own) capacity and
ii. Representative(Agent) capacity.
• Capacity of persons is legally presumed unless the
contrary is proved.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 9

2.1. Overview of Contracts in Construction Projects …


• Capacity (Article 1678(a) of the Civil Code…
•Persons could be:-
Organized by: Belachew Asteray (PhD)

• natural (physical) persons or


• juridical (legal) persons
• Natural Persons
• Natural or physical persons are human beings.
• Their legal capacity is determined by law.
• The scope of capacity of physical persons is relatively
unlimited unless the contrary is proved.
• Physical persons are the subject of rights & duties from
birth to death (Article 1 of the Civil Code).
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 10

Organized by: Belachew Asteray(PhD) 5


FTVET, 2023 March 2023

2.1. Overview of Contracts in Construction Projects …


• Capacity (Article 1678(a) of the Civil Code…
• Legal Persons
• Legal persons are of two types in terms of determining their coming in to
being & their legal capacity:
Organized by: Belachew Asteray (PhD)

• By legislation (In case of public bodies)


• The existence of public bodies (Ministries, Commissions, Bureaus,
Authorities, Agencies …) & their legal capacity to enter in to
contract & bind themselves emanates from the Civil Code & the
special legal instrument (legislation), which establishes that
specific public body.
• By registration (In case of non-public bodies)
• The legal capacity of non-public bodies (PLC’s, Share Companies,
Corporations…) & their legal existence comes in to being by
registration. The act of registration by competent public authority
confers legal personality & therewith (limited) legal capacity to
enter into contract & bind themselves.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 11

2.1. Overview of Contracts in Construction Projects …


• Capacity (Article 1678(a) of the Civil Code…
• The following may not have (legal) capacity to enter in to contract & bind
themselves:
Organized by: Belachew Asteray (PhD)

• Minors (under the age of 18);


• Companies adjudged or declared bankrupt;
• Judicially interdicted persons;
• Legally interdicted persons;
• Persons, whose civil rights are suspended by the judgment of the court;
• Non-nationals, unless permitted by law or special prerogative;
• Non-authorized Agents;
• Agents, whose Power of Attorney has been revoked;
• Agents, the Scope of their Power of Attorney does not cover the intended
transaction (ex. Tendering or Negotiation or Contract Signing, …)
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 12

Organized by: Belachew Asteray(PhD) 6


FTVET, 2023 March 2023

2.1. Overview of Contracts in Construction Projects …


• Capacity (Article 1678(a) of the Civil Code…
• Natural persons or legal persons may enter in to contract
Organized by: Belachew Asteray (PhD)

• directly by themselves (in their own capacity) or


• through other persons called Agents.
• The power of agents (i.e. their representative capacity)
should always be checked, with respect to construction
project, at:
The Power of Attorney creates a
• The tendering stage;
derivative legal capacity for agents.
• The negotiation stage;
• The contract signing stage and
• The Contract implementation stage.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 13

2.1. Overview of Contracts in Construction Projects …


• Capacity (Article 1678(a) of the Civil Code…
• A contract concluded by the person not capable under the
Organized by: Belachew Asteray (PhD)

law may be invalidated at the request of such incapable


person, who is party to the contract.

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 14

Organized by: Belachew Asteray(PhD) 7


FTVET, 2023 March 2023

2.1. Overview of Contracts in Construction Projects …


• Consent (Article 1678 (a) and Article 1679- Article 1710 of the Civil Code)
• Consent
• is a declared will of the individual to enter in to contract.
Organized by: Belachew Asteray (PhD)

• is the willingness of the parties to enter in to a legally binding


relation.

• Consent of the intended contracting parties decomposes in to :-


• Offer and
• Acceptance.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 15

2.1. Overview of Contracts in Construction Projects …


• Consent …
• Offer
Organized by: Belachew Asteray (PhD)

• Is a proposal expressing the declared willingness of the offeror


to enter in to an agreement, if the offer is accepted.
• is a legal process which is a declaration of willingness or
intent to be bound by specific terms set out.
• Acceptance
• is a declaration of will to enter in to a legally binding contract.
• By acceptance, a contract shall be completed, where the offeree
accepts the offer without any reservation.

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 16

Organized by: Belachew Asteray(PhD) 8


FTVET, 2023 March 2023

2.1. Overview of Contracts in Construction Projects …


• Consent…
Organized by: Belachew Asteray (PhD)

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 17

2.1. Overview of Contracts in Construction Projects …


• Consent…
Legal Sanction
Organized by: Belachew Asteray (PhD)

•Defects in consent:
• Mistake (Art. 1697-1703 of the Civil Code) –law or fact
• Fraud (Art. 1704-1705 of the Civil Code)
• a false representation conduct made knowingly or recklessly
• Duress (Art. 1706-1709 of the Civil Code)
• a threat of imminent danger- future or immidate
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 18

Organized by: Belachew Asteray(PhD) 9


FTVET, 2023 March 2023

2.1. Overview of Contracts in Construction Projects …


• Object of Contracts
•Object of Contracts
• Stated in Article 1678 (b),
Organized by: Belachew Asteray (PhD)

• Article 1711 – Article 1718 of the Civil Code.


•The object of contract is the very obligations of
the contracting parties
•For Example: in the construction contract
• the obligations of the Employer and the
Contractor

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 19

2.1. Overview of Contracts in Construction Projects …


• Object of Contracts…
• The possible objects
Organized by: Belachew Asteray (PhD)

• The obligations of the contracting parties could be divided in to two broad


terms: Promises and Considerations.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 20

Organized by: Belachew Asteray(PhD) 10


FTVET, 2023 March 2023

2.1. Overview of Contracts in Construction Projects …


• Object of Contracts…
• Promises and Considerations in Construction Contracts
• In the construction contract, the whole purpose of all parts of the
Organized by: Belachew Asteray (PhD)

contract documents is to sufficiently define the object of the


construction contract, i.e. the very respective obligations of the
contractor & the employer.
Contract documents
• the BOQ,
• the Drawing,
• the Technical Specification,
• the Conditions of Contract (both
General and Special Conditions of
Contract), and
• other documents

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 21

2.1. Overview of Contracts in Construction Projects …


• Object of Contracts…
• Promises and Considerations in Construction Contracts…
• In the construction contract, the obligations are the very promises &
Organized by: Belachew Asteray (PhD)

considerations of the contractor & the employer.


• The contractual obligation of the contractor (i.e. Promises)
What to do: i.e. to construct:- In terms of its:-
• water supply dam & • scope;
systems; or
• quality;
• irrigation dam; or
• Hydropower dam; or • cost;
• other hydraulic structures; or • time;
• road; or • safety; and
• building; or • Other aspects of its
• other type of structures; promises
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 22

Organized by: Belachew Asteray(PhD) 11


FTVET, 2023 March 2023

2.1. Overview of Contracts in Construction Projects …


• Object of Contracts…
• Promises and Considerations in Construction Contracts…
• Obligations of the Employer
Organized by: Belachew Asteray (PhD)

• The Payment, obligation to do, or (Considerations) and other


contractual rewarding obligations of the Employer:
• Payment obligation • other obligations in terms of
• extent of contract price • other benefits,
• types of payment • exchanges, &
• timing for payment
• conditions of payment
• rewards.
• other related issues
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 23

2.1. Overview of Contracts in Construction Projects …


• Object of Contracts…
• The object of contract shall be lawful.
• If the contract found to be unlawful or immoral, the legal remedy
Organized by: Belachew Asteray (PhD)

available is invalidation of the contract at the request of any contracting


party or interested third party (Art. 1808(2) of the Civil Code).

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 24

Organized by: Belachew Asteray(PhD) 12


FTVET, 2023 March 2023

2.1. Overview of Contracts in Construction Projects …


• Form of Contracts
• Form of Contract under the Civil Code
• Article 1678 (c)
Organized by: Belachew Asteray (PhD)

• Article 1719 – Article 1730

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 25

2.1. Overview of Contracts in Construction Projects …


• Form of Contracts…
• Form may mean types of contract.
• Form may also mean the making of the contract orally or
Organized by: Belachew Asteray (PhD)

in writing.
• in certain prescribed form
• with the validity & proof of the contract itself.

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 26

Organized by: Belachew Asteray(PhD) 13


FTVET, 2023 March 2023

2.1. Overview of Contracts in Construction Projects …


• Form of Contracts…
Organized by: Belachew Asteray (PhD)

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 27

2.1. Overview of Contracts in Construction Projects …


• Form of Contracts…
Organized by: Belachew Asteray (PhD)

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 28

Organized by: Belachew Asteray(PhD) 14


FTVET, 2023 March 2023

2.1. Overview of Contracts in Construction Projects …


• Effects of Contracts
• Effects of contract may have two dimensions:
• The time when the contract is considered bound by the
Organized by: Belachew Asteray (PhD)

contracting parties; and


• relates to the effectiveness of the contract
• The fulfillment or performance of the set of promises
prescribed in the contract
• related to the performance of obligations of the contracting
parties under the contract
• Effects of contract may bring
• Contractual effects and /or
• Legal effects;
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 29

2.1. Overview of Contracts in Construction Projects …


• Effects of Contracts…
• Major Areas of Effects of Contract in the Civil Code
• Effects of contract basically concerned with the following
Organized by: Belachew Asteray (PhD)

four issues:
1. Interpretation of Contracts (Article 1732-Article 1739)
2. Performance of Contracts (Article 1740-Article 1762)
3. Variation of Contracts (Article 1675 & Article 1763-1770)
4. Non-performance of Contracts (Article 1771-1805)

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 30

Organized by: Belachew Asteray(PhD) 15


FTVET, 2023 March 2023

2.1. Overview of Contracts in Construction Projects …


• Effects of Contracts…
1. Interpretation of Contracts (Article 1732-Article 1739)
• Interpretation is the process of determining the true
Organized by: Belachew Asteray (PhD)

meaning of a written document.

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 31

2.1. Overview of Contracts in Construction Projects …


• Effects of Contracts…
1. Interpretation of Contracts…
• Formal interpretation • Informal interpretation
Organized by: Belachew Asteray (PhD)

• By the Conditions of Contract itself


• By the court; • under the Harmonised Edition
• By the arbitral • Sub-Clause 1.1 Definitions; and
• Sub-Clause1.2 Interpretation
tribunal; • By the contracting parties themselves
• In case of negotiation or other forms of amicable dispute settlement;
• Sub-clause 20.6 of the • Article 3307-Article 3324 of the Civil Code;-Compromise
Harmonized Edition & • Article 274-Article 280 of the Civil Procedure Code; Compromise
the applicable law. • By the Engineer
• by giving Clarification for ambiguities or discrepancies in the Contract Document
• under the Harmonised Edition- Clause 1.5- Priority of Documents
• by Determination -under the Harmonised Edition
• Clause 3.5 cum Clause 20.1 on the Claims of the Contractor;
• Clause 2.5 on the Claims of the Employer ; and
• on any requests of the Contractor & of the Employer;

• By the Adjudicator (DB)


• Clause 20.3 of the FIDIC Harmonized Edition

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 32

Organized by: Belachew Asteray(PhD) 16


FTVET, 2023 March 2023

2.1. Overview of Contracts in Construction Projects …


• Effects of Contracts…
2. Performance of Contracts (Article 1740-Article 1762)
• Performance of Contract may mean the carrying out or
Organized by: Belachew Asteray (PhD)

discharge of the obligation under taken by the contracting


parties.

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 33

2.1. Overview of Contracts in Construction Projects …


• Effects of Contracts…
2. Performance of Contracts…
• Under the Construction Contracts, the effect of contract is
Organized by: Belachew Asteray (PhD)

fulfilled by performance of the very contractual


obligations of the contracting parties:
• the Contractor must execute the works
• within the time for completion,
• within the cost agreed,
• as per the quality specified…; and
• the Employer have to pay fully the Contract price, and any
other sums agreed in or implied from the contract, to the
Contractor.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 34

Organized by: Belachew Asteray(PhD) 17


FTVET, 2023 March 2023

2.1. Overview of Contracts in Construction Projects …


• Effects of Contracts…
2. Performance of Contracts…
Organized by: Belachew Asteray (PhD)

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 35

2.1. Overview of Contracts in Construction Projects …


• Effects of Contracts…
3. Variation of Contracts (Article 1675 & Article 1763-1770)
• Variation of Contract could be done:
Organized by: Belachew Asteray (PhD)

1. By the contracting parties, contractual variation, (as a rule); or


2. By the Court, judicial variation, (as an exception)
• Variation of Contract by the Parties
• The contracting parties, in principle, are free to create & vary their contractual agreement
( Article 1675 of the Civil Code).
• Variation of contract & its effect are regulated under the Conditions of Contract
(Harmonized
• Variation ofEdition Sub-clause
contract, under the13-Variations & Adjustments).
construction contract, may result from:-
• Requirement change by the Employer
• Design change by the Engineer
• Proposal by the Contractor
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 36

Organized by: Belachew Asteray(PhD) 18


FTVET, 2023 March 2023

2.1. Overview of Contracts in Construction Projects …


• Effects of Contracts…
3. Variation of Contracts…
• Judicial Variation of Contract (Article 1763-Article 1770 of the Civil Code)
Organized by: Belachew Asteray (PhD)

• Judicial variation or variation of contracts by the court is not


allowed, in principle (Article 1763 of the Civil Code).

• Contracts may get their effect through judicial variation, by way of


exception, however (Article 1763 of the Civil Code).
• Judicial variation of Contracts, as opposed to variation of Contract
by the parties, is regulated by the applicable law.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 37

2.1. Overview of Contracts in Construction Projects …


• Effects of Contracts…
3. Variation of Contracts…
• The Ethiopian court may vary the terms of the contract:
Organized by: Belachew Asteray (PhD)

• Where it is expressly provided by law (Article 1763);


• Where a special relationship between the contracting parties exists
(Article 1766);

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 38

Organized by: Belachew Asteray(PhD) 19


FTVET, 2023 March 2023

2.1. Overview of Contracts in Construction Projects …


• Effects of Contracts…
3. Variation of Contracts…
• The Ethiopian court may vary the terms of the contract:
Organized by: Belachew Asteray (PhD)

• Where one of the contracting parties is a state or one of its institutions (Article 1767)

• Where it is partially impossible to perform the contract (Article 1768);

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 39

2.1. Overview of Contracts in Construction Projects …


• Effects of Contracts…
4. Non-performance of Contracts (Article 1771-1805)
•Non-performance of contracts means
Organized by: Belachew Asteray (PhD)

• the failure of the contracting party or parties to carry out


the obligations they have undertaken under the contract.

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 40

Organized by: Belachew Asteray(PhD) 20


FTVET, 2023 March 2023

2.1. Overview of Contracts in Construction Projects …


• Effects of Contracts…
4. Non-performance of Contracts …
• Non-performance involves the following legal concepts:
Organized by: Belachew Asteray (PhD)

• Notice requirement
• Notice necessary (Article 1772-Article 1774)

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 41

2.1. Overview of Contracts in Construction Projects …


• Effects of Contracts…
4. Non-performance of Contracts …
• Non-performance involves the following legal concepts:
Organized by: Belachew Asteray (PhD)

• Notice requirement;
• Notice unnecessary (Article 1775)

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 42

Organized by: Belachew Asteray(PhD) 21


FTVET, 2023 March 2023

2.1. Overview of Contracts in Construction Projects …


• Effects of Contracts…
4. Non-performance of Contracts…
• Non-performance involves the following legal concepts:
Organized by: Belachew Asteray (PhD)

• Specific performance (Article 1776-Article 1783)

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 43

2.1. Overview of Contracts in Construction Projects …


• Effects of Contracts…
4. Non-performance of Contracts…
• Non-performance involves the following legal concepts:
Organized by: Belachew Asteray (PhD)

• Cancellation of contract;
• Cancellation by court (Article 1784-Article 1785);

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 44

Organized by: Belachew Asteray(PhD) 22


FTVET, 2023 March 2023

2.1. Overview of Contracts in Construction Projects …


• Effects of Contracts…
4. Non-performance of Contracts…
• Non-performance involves the following legal concepts:
Organized by: Belachew Asteray (PhD)

• Cancellation of contract;
• Cancellation by the contracting party (Article 1786-Article 17890);

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 45

2.1. Overview of Contracts in Construction Projects …


• Effects of Contracts…
4. Non-performance of Contracts…
• Non-performance involves the following legal concepts:
Organized by: Belachew Asteray (PhD)

• Damages;
• Liability for damages (Article 1791-Article 1798)
• Quantum of damages (Article 1799-Article 1805)

• Damages may be requested due to


• Non-performance of the contract; and
• 2023
March Invalidation of the contract.
CoTM 525 Organized by: Belachew Asteray (PhD) 46

Organized by: Belachew Asteray(PhD) 23


FTVET, 2023 March 2023

2.1. Overview of Contracts in Construction Projects …


• Extinction of Obligations
Organized by: Belachew Asteray (PhD)

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 47

2.1. Overview of Contracts in Construction Projects …


• Extinction of Obligations…
• As per the Civil Code, the obligations of the contracting parties may come to
an end on the following grounds.
Organized by: Belachew Asteray (PhD)

• By performance of the contract (Article 1808 & 1740-Article 1762)


• By invalidation of the contract (Article 1807 & Article 1808-1818)
• By cancellation of the contract (Article 1807 & Article 1808-1818)
• By termination of the contract (Article 1807 & Article 1808-1818)
• By remission of debt (Article 1825)
• By novation (Article 1807 & Article 1826-1830)
• By set-off (Article1807 & Article 1831- 1841)
• By merger (Article1807 & Article 1842-1844)
• By limitation of action (Article 1807 & Article 1845-1856)
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 48

Organized by: Belachew Asteray(PhD) 24


FTVET, 2023 March 2023

2.1. Overview of Contracts in Construction Projects …


• Extinction of Obligations…
• By performance of the contract
• This is the case where the Contractor & the Employer under the
Construction Contract perform all of their obligations under the said
Organized by: Belachew Asteray (PhD)

Contract.
• By invalidation of the contract
• Invalidation of contract may result with respect to void & voidable
contracts.
• A contract is voidable due to vices of or defects in consent & incapacity.
That is the contract was concluded as a result of mistake, duress, or fraud.
• By cancellation
• Cancellation of contract may result from non performance of contract.
• The contract may be cancelled by the party to the contract or by the court.
• By termination
• A contract could be terminated by both parties to the contract (jointly) or by
one of them (unilaterally).
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 49

2.1. Overview of Contracts in Construction Projects …


• Extinction of Obligations…
• By remission of debt
• Remission of debt results where the creditor releases the debtor from its
obligation.
Organized by: Belachew Asteray (PhD)

• By novation
• Novation occurs where the parties agree to substitute therefore a new obligation
which differs from the original one on account of its object or nature.
• By set-off
• Set-off occurs where two persons owe debt to one another.
• By merger
• Merger shall occur & the obligation shall extinguish where the positions of
creditor & debtor are merged in the same person.
• By limitation of action
• This is the effect of time on rights, unless exercised within the legally allowable
time.
• The creditor may lose his rights unless he demands within a given time.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 50

Organized by: Belachew Asteray(PhD) 25


FTVET, 2023 March 2023

2.1. Overview of Contracts in Construction Projects …


• Proof in Relation to Contracts (Article 2001-Article 2026)
• Proof or evidence is important to prove the existence or non
existence of a given fact, which is disputed or denied.
Organized by: Belachew Asteray (PhD)

• Admitted facts do not need proof.


• Laws do not require proof.
• The form of proof in relation to Construction Contract could be:
• Documentary evidence;
• Factual witness;
• Expert opinion;
• Project site visit;
• Others, if any;
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 51

2.1. Overview of Contracts in Construction Projects …


• Proof in Relation to Contracts (Article 2001-Article 2026)
• The form of proof in relation to Construction Contract
Documentary evidence The records may appear in diverse forms:
Organized by: Belachew Asteray (PhD)

• The Construction Contract itself; • Correspondences or Exchange of Letters;


• Records in relation to the Time aspect of the project; • Notices;
• Records in relation to the Cost aspect of the project; • Reports;
• Records in relation to the Quality aspect of the project; • Minutes of Meeting;
• Records in relation to the Safety aspect of the project; • Site Diary;
• Records in relation to Payment aspect of the Contract; • Site Instructions;
• Records in relation to Site & Access thereto; • Payment Certificates or related documents;
• Records in relation to other contractual or legal obligations • Executed Standard Forms;
of the Contractor and/or the Employer; • Others, if any;
• Records in relation to Variation;
• Outside Records;
• Others, if any;
• Factual Witness Statements are prepared by those who have a direct factual knowledge about a given aspect
of the project ( ex, time, payment, …)
• Expert Witness Reports are prepared & submitted to court or arbitral tribunal to show some professional
conclusions about the disputed matter.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 52

Organized by: Belachew Asteray(PhD) 26


FTVET, 2023 March 2023

2.2.Contract Document and Legal Considerations


• The contract documents are some of the most important
pieces that help ensure a successful project.
Organized by: Belachew Asteray (PhD)

• No matter what the construction, having a solid contract


represents one of the first steps toward the success of the
project.
• Construction “Contract Documents” are legally-binding
written documents that define
• the roles and responsibilities of contracting parties,
• description and scope of “Work/service/good” under the
construction Contract.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 53

2.2.Contract Document and Legal Considerations


• Components of Construction Contract Document
• Contract Agreement:
• It's an essential component of the contract documents.
Organized by: Belachew Asteray (PhD)

• It's the main document to which most other documents attach or


reference.
• A construction contract agreement is a document that sets a date and
specifies which parties are going to participate in the construction
process.
• Usually, the contract agreement is signed between the Owner of the
project and the contractor or supplier that is providing the requested
services or works.
• Contract agreement contains several sections of clauses defining the
scope, terms, and conditions of such agreement.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 54

Organized by: Belachew Asteray(PhD) 27


FTVET, 2023 March 2023

2.2.Contract Document and Legal Considerations


• Components of Construction Contract Document…
• Project Description: a blurb or extract of what the project is about
• Contract Price:
Organized by: Belachew Asteray (PhD)

• the type of contract price been awarded and


• the total amount of money being contracted.
• Payment Basis:
• How the money is going to be paid to the service provider.
• Either on a monthly basis or whatever payment method is preferred, it should also
specify what percentage of money should be retained on every application for payment.
• It will also define when the payment is due, the penalty for late payments, interest
being accrued and other applicable situations related to the payment and invoicing
terms.
• Construction Schedule or Calendar:
• The total of days or how the project schedule will be divided.
• It should describe either calendar days or business days and can be presented either
through a CPM, Gantt Chart, or just a bar chart.
• Contract Document List:
•March
A2023
list of all contract documents that form part of the contract agreement.
CoTM 525 Organized by: Belachew Asteray (PhD) 55

2.2.Contract Document and Legal Considerations


• Components of Construction Contract Document…
• Construction Scope:
• Description of all activities including some descriptions of things that will form
Organized by: Belachew Asteray (PhD)

part of the project. The scope normally can be measured or quantifiable.


• Construction Conditions & Responsibilities:
• The section of conditions and responsibilities is the one that sets responsibilities
for the owner and the contractor, and the extents of who is responsible for
providing documents and information.
• It contains specific terms for liens, penalties, withholding, arbitration rules and
specific instructions on how to process claims and proceed with disputes.
• Contract Laws:
• Governing laws, liens requirements, claims procedures, arbitration procedures,
insurance, substantial completion requirements, final completion, and liquidated
damages.
• It can also provide procedures on how to terminate or suspend the work and the
agreement
March 2023 with the contractor.
CoTM 525 Organized by: Belachew Asteray (PhD) 56

Organized by: Belachew Asteray(PhD) 28


FTVET, 2023 March 2023

2.2.Contract Document and Legal Considerations


• Components of Construction Contract Document…
• Conditions of Contract
• Construction Contract: Conditions of contract are terms which rule the
Organized by: Belachew Asteray (PhD)

relationships between the owner and the contractor, define each party’s rights and
obligations, specify method of payment and determine actions required when
existing any disputes between the owner and the contractor.
• General Conditions of Contract: They are standard terms that suit the
majority of projects, they include:
• Definition of the project
• Contract components
• Rights and responsibilities for the owner and the contractor
• Project schedule
• Payment method
• Warranty and delay penalty
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 57

2.2.Contract Document and Legal Considerations


• Components of Construction Contract Document…
• Special Conditions of Contract
• They are the modifications required to suit the uniqueness of the project,
Organized by: Belachew Asteray (PhD)

make the contract flexible for the nature of the project and achieve project
objectives.
• This is usually an extension of the contract and an addendum to the
general conditions.
• It should specify certain conditions and clauses that pertain to each
particular project or job.
• Pay special attention to specific instructions and requirements on how to
perform the work.
• Signed Technical Proposals/documents–Approaches and
Methodology,
• Signed Financial Proposals-
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 58

Organized by: Belachew Asteray(PhD) 29


FTVET, 2023 March 2023

2.2.Contract Document and Legal Considerations


• Typical Tender (Contract) Documents
• The tender documents become contract documents if completed by the
prospective contractor, and finally agreed & signed by the parties .
Organized by: Belachew Asteray (PhD)

• The Legal Part • The Commercial Part • The Technical Part


• The Contract Agreement; • The Performance Security • The Technical
• The (latest) Minutes of Meeting, Form
Specifications;
if any; • The Payment Security
Form; • The Drawing;
• The Letter of Acceptance(Award) • The Bill of Quantities;
• The Advance Payment
• The Tender (NB: Including the
Guarantee Form • Schedule of
Appendix to Tender, if any); • The Bid Security Form;
• The Special Conditions of Requirements, if any;
• The Insurance Forms
Contract • Others, if any.
• The Retention Money
• The General Conditions of Security Form
Contract • Others, if any
• Others, if any;
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 59

2.3. Construction Contract Types


• Construction contract types are usually defined by
• the way, the disbursement is going to be made and
• details other specific terms, like duration, quality,
Organized by: Belachew Asteray (PhD)

specifications, and several other items.


• These major contract types can have many variations and
can be customized to meet the specific needs of the
project.
• One of the characteristics of construction projects is uniqueness.
• Every project has its special circumstances, so it’s important to
select the contract type which suits the project.
• The process of selecting the type of contract is developed by the
owner.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 60

Organized by: Belachew Asteray(PhD) 30


FTVET, 2023 March 2023

2.3. Construction Contract Types…


• Factors which affect the selection of construction contract are:
1. Project objectives:
Organized by: Belachew Asteray (PhD)

• The type of contract should meet with project objectives.


2. Project constraints:
• There is no any construction project without constraints.
• Thus, project constraints should be considered while selecting
type of construction contracts.
3. Project delivery method:
• Project delivery method determines the relationships
between parties getting involved in the project and how they
interact with each other from project initiation to project
closure.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 61

2.3. Construction Contract Types…


• Types of Construction Contracts
• There are many types of contracts used in construction.
Organized by: Belachew Asteray (PhD)

• Each type has its advantages and disadvantages with respect to


the owner and the contractor.
• They are categorized in two major groups as per method of
payment to the contractor.
• Price-based Construction Contracts
1. Lump Sum Construction Contract
2. Unit Price Construction Contract
• Cost-based Construction Contracts
3. Cost Plus Construction Contract
4. Target Cost Construction
March 2023
Contract
CoTM 525 Organized by: Belachew Asteray (PhD) 62

Organized by: Belachew Asteray(PhD) 31


FTVET, 2023 March 2023

2.3. Construction Contract Types…


1. Lump Sum Construction Contract
• In this type, the contractor bids a single fixed price for overall
activities in the project scope.
Organized by: Belachew Asteray (PhD)

• The contractor is responsible for estimating project costs from


drawings then adds overhead and his profit to determine the price of
the project.
• All risks are assigned to the contractor, there isn’t any risk carried by
the owner.
• The contractor has incentive in this contract as he is rewarded for early
finish and there is penalty for late finish.
• This contract is ideal when the project scope is well defined at the
design stage because there is limited flexibility for modifying the
design during construction period.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 63

2.3. Construction Contract Types…


2. Unit Price Construction Contract
• The total price of the project in unit price contract is based
Organized by: Belachew Asteray (PhD)

on the price of each item’s unit.


• The contractor is paid as per the rates of items specified
in the bill of quantity.
• The risk is shared with the contractor and the owner.
• This type of contract has more flexibility for design
changing than the lump sum contract.
• The construction of the project can be started before
finishing the designs so the total cost of the project will be
uncertain at the early stages of the project.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 64

Organized by: Belachew Asteray(PhD) 32


FTVET, 2023 March 2023

2.3. Construction Contract Types…


3. Cost Plus Construction Contract
• The contractor is paid based on the actual cost of the project including direct
and indirect costs plus specific fee. This fee could be a fixed fee or
Organized by: Belachew Asteray (PhD)

percentage of costs.
• All risks are assigned to the owner and he gets involved with the contractor
in the management of the project.
• The contractor has no risk in case of increasing the cost of the project, also
there isn’t any incentive for early finish.
• This type of contract is ideal when the project scope is uncertain in the
early stages of the project.
• The contractor can start the execution of the project before finishing the
design. It is impossible to estimate the cost of the project before the
construction has been finished.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 65

2.3. Construction Contract Types…


4. Target Cost Construction Contract
• Target cost contract has mutual features of the lump sum and cost
Organized by: Belachew Asteray (PhD)

plus contracts.
• The contractor is paid based on the actual costs plus a certain fee
either fixed or percentage of total cost in case of the cost of the
project doesn’t exceed certain target cost specified by the owner.
• There is risk carried by the contractor in case of increase in cost
of construction project.
• The contractor is also rewarded a percentage of any savings
between target and actual cost.

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 66

Organized by: Belachew Asteray(PhD) 33


FTVET, 2023 March 2023

2.3. Construction Contract Types…


• Construction Contract Delivery Systems
• the way project owners together with project regulators and
Organized by: Belachew Asteray (PhD)

financiers determine the assignment of responsibilities to


Project Stakeholders along the Construction Process.
• It is often determined during the basic planning phase of
the Construction Project.
• Project delivery systems are basically classified in to two
broad areas:
a) Force Account and
b) Outsourced.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 67

2.3. Construction Contract Types…


Construction Contract Delivery Systems
• Force Account • Outsourcing
• When the project owners • Design-Bid-Build (D-B-B)
Organized by: Belachew Asteray (PhD)

engage themselves to • Design-Build (D-B)


undertake the project, it is • Construction Management (CM At Free &
At Risk)
called a force account
• Design –Build- Operate (D-B-O)
delivery system.
• Design-Build-Operate-Maintain (D-B-O-
• Such a system is often M)
promoted if the Project • Design-Build-Finance-Operate (D-B-F-O)
Owners believe that there is • Full Delivery or Program Management
a comparative advantage • Build-Own-Operate (B-O-T)
in cost time & quality. • Build Own Operate Transfer(B-O-O-T)
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 68

Organized by: Belachew Asteray(PhD) 34


FTVET, 2023 March 2023

2.3. Construction Contract Types…


Construction Contract Delivery Systems
• Categories for Outsourcing Delivery Methods
• Based on: Integration, Segmentation & Financing
Organized by: Belachew Asteray (PhD)

Integrated Process Delivery • External Financing


Methods Methods
Design-Build-Operate • Design-Build-Finance-Operate
Design-Build-Operate-Maintain • Build-Own-Operate
Design-Build-Finance-Operate • Build-Own-Operate-Transfer
• Segmented Delivery Methods
• Design-Bid-Build
• Design-Build
• Construction Management
• Pure Operations & Maintenance (O&M)
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 69

2.3. Construction Contract Types…


Construction Contract Delivery Systems
• Design-Bid-Build
• After Project Owners did prepare the Basic Planning that identifies construction project
Organized by: Belachew Asteray (PhD)

programs, they call upon the participation of Design and/or Supervision Consultants.
• This Consultant will carry out the design together with the necessary tender documents
which will be the basis for tendering to select Contractors.
• This process is called Design-Bid-Build and hence the name for such delivery system.

• Advantages • Disadvantages
• Long history of acceptance • Innovation not optimized
• Usually cost overruns
• Open competition
• Disputes between parties
• Distinct roles are clear • Client retains risks
• Owner flexibility • Usually low bid-incentive for change orders
• Easy to tender • Owner responsible for errors & omissions
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 70

Organized by: Belachew Asteray(PhD) 35


FTVET, 2023 March 2023

2.3. Construction Contract Types…


Construction Contract Delivery Systems
• Design-Build or Turnkey
• Design Build reduces numbers of procurement processes
Organized by: Belachew Asteray (PhD)

engaged in the fragmented process and employ only one


procurement process and a single contractor to provide the entire
Construction Implementation Process (Design & Construction
Implementations).
• In this arrangement, both the design & construction liability rests
with the Contractor.
• In the design-build process, the contracting parties:
• There is lack of an independent certification role in the contract.
• There is no architect or contract administrator to settle differences.
• There is no independent quantity surveyor responsible for
preparing the basis up on which contractors tender.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 71

2.3. Construction Contract Types…


Construction Contract Delivery Systems
• Design-Build or Turnkey…
• Advantages • Disadvantages
Organized by: Belachew Asteray (PhD)

• Single source responsibility both for design • Limiting competition


& construction • High tendering costs
• Integrating design & construction • New method &
• Reduction in administration unfamiliarity
• Innovation
• Client needs quicker
• Cost savings
• Constructability optimized decision making
• Most risks transferred to the design-builder • Clients bringing design
• Usually guaranteed maximum price (GMP) requirements(30%)(reduce
• Design reflects s design innovation)
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 72

Organized by: Belachew Asteray(PhD) 36


FTVET, 2023 March 2023

2.3. Construction Contract Types…


Construction Contract Delivery Systems
• Construction Management (CM)
• Under Construction Management, the Owner contracts separately,
Organized by: Belachew Asteray (PhD)

but somewhat simultaneously, with a design consultant and with a


firm whose primary expertise is construction (the Construction
Manager).
• The owner procures the management services of the Construction
Manager (in most cases a general contracting construction firm)
early in the design phase.
• CM is of two types:
• CM At Free/as Agent &
• CM At Risk/as Constructor.
• This distinction determines the contractual approach to CM.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 73

2.3. Construction Contract Types…


Construction Contract Delivery Systems
• Construction Manager (CM) as Agent
• This is a form of CM under which the Construction Manager acts as an agent of,
Organized by: Belachew Asteray (PhD)

and advisor to, the Owner.


• The Owner enters in to multiple trade contracts with the trade contractors
& suppliers.
• The Construction Manager is retained on a fee for services basis & acts on the
Owner’s behalf in managing & coordinating the trade contracts in the best
interests of the Owner.
• The Owner retains all of the contracting risks inherent in each of the trade
contracts.
• It essentially involves the Owner acting as its own general contractor, with the
assistance of a Construction Manager.
• This form of CM is sometimes also referred to as the “CM as Advisor” or “owner
contacted form of CM”.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 74

Organized by: Belachew Asteray(PhD) 37


FTVET, 2023 March 2023

2.3. Construction Contract Types…


Construction Contract Delivery Systems
• Construction Manger (CM) At Risk (as Constructor)
• This is a form of CM under which the Construction Manager
Organized by: Belachew Asteray (PhD)

enters in to multiple trade contracts with the trade contractors


& suppliers.
• The Construction Manager assumes responsibility for the
performance of the trade contracts (subcontracts) much as a
general contractor under the traditional method, and is paid for the
trade contract work on a cost reimbursable basis.
• The Construction Manager may, or may not, also provide a
guaranteed maximum price & schedule to the Owner under a cost
plus type of arrangement, or enter into a stipulated price
contract, when the design is sufficiently complete.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 75

2.3. Construction Contract Types…


Construction Contract Delivery Systems
Advantages Disadvantages
CM At Free CM At Free
Organized by: Belachew Asteray (PhD)

• Provides a managing & administering for all phases of a • No contractual relationship with trade
project;
contractors;
• Treats planning, design, construction as an integrated
tasks; • No contractual responsibility for
• Some costs & schedule control; outcomes of a project;
CM At Risk • Client retains the risks;
• Good for clients with insufficient staff; CM At Risk
• Owner flexibility; • Duplication of administration & additional
• Responsible for time & cost overrun; paperwork;
• Holds & manages the trade contractors; • More paper work for the client;
• Constructability design review; • Some duplication of administration;
• Same legal position as a General Contractor; • Fast tracking difficult to control with designer
• Provides a guaranteed maximum price (GMP); & CM;
• Works closely as a teaming effort & encouraging • Sometimes difficult to manage all phased
partnering & trust; packages with costs, changes & schedules;
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 76

Organized by: Belachew Asteray(PhD) 38


FTVET, 2023 March 2023

2.3. Construction Contract Types…


Construction Contract Delivery Systems
• Design-Build-Operate (D-B-O)
• According to FIDIC, the D-B-O approach to contracting combines
Organized by: Belachew Asteray (PhD)

design, construction, and long term (ex. 20 years) operation


(and maintenance) of a facility in to one single contract awarded
to a single contractor (who will usually be a joint venture or
consortium representing all the skills for in a D-B-O arrangement).
• The FIDIC has now prepared conditions of contract which
facilitate the D-B-O process.

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 77

2.3. Construction Contract Types…


Construction Contract Delivery Systems
• Advantages of D-B-O
• Time
Organized by: Belachew Asteray (PhD)

• With possibilities to overlap some design & build activities, it will be


possible to minimize delays & optimize the smooth flow of
construction activities.
• Finance
• With cost restraints & commitments & other risks being carried by the
contractor, there is less risk of price over-run.
• Quality
• With the contractor responsible for 20 years operation, he has an interest
to design & build quality plant with low operation & maintenance costs.
• Not only will then plant be “fit for purpose” but it will be built to last.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 78

Organized by: Belachew Asteray(PhD) 39


FTVET, 2023 March 2023

2.3. Construction Contract Types…


Construction Contract Delivery Systems
• Full Delivery or Program Management
• Under full delivery method, the selected contractor shall under
Organized by: Belachew Asteray (PhD)

take the whole range of activities from thought to finish &


operation inclusive of maintenance.
• The possible activities include:
• Planning & acquisition;
• Finance;
• Design;
• Construction;
• Operation;
• Maintenance;
• Upkeep & Improvements;
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 79

2.3. Construction Contract Types…


Construction Contract Delivery Systems
• Full Delivery or Program Management …
• Advantages • Disadvantage
Organized by: Belachew Asteray (PhD)

• Shorter time to project competition; • Difficult to tender & not


• Fully integrated process from project knowing the costs;
inception;
• Compatibility issues wit
• Maximization of planning & reduction
of problems during execution; client;
• Knowledgeable alternative funding • Quality based selection
sources; process(Negotiated);
• Good for large & complex projects; • Client needs to make
• Single source expertise; decisions quicker;

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 80

Organized by: Belachew Asteray(PhD) 40


FTVET, 2023 March 2023

2.3. Construction Contract Types…


Construction Contract Delivery Systems
• Build-Operate-Transfer (BOT)
• BOT is a form of procurement and contract delivery system that
Organized by: Belachew Asteray (PhD)

promotes Public Private Partnership ( PPP) in which a private


company is contracted to finance, design, construct, operate for a
certain period ( usually 10 years) and transfer the facility to the
Project Owner.
• The typical BOT project contract is the process whereby a
government grants a concession to a project development
company to develop & operate what would normally be a public
sector project, for a given period of time known as the
concession period.
• BOT project involves a potentially complex contractual structure.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 81

2.3. Construction Contract Types…


Construction Contract Delivery Systems
Conditions of Contract with respect to the Contract Delivery Systems
• Design-Bid-Build:
Organized by: Belachew Asteray (PhD)

• The Ministry of Works & Urban Development Conditions of Contract for Construction
Works(1994), under which the contractor is responsible for construction;
• The PPA Conditions of Contract for Works (2011), under which the contractor is
responsible for construction;
• FIDIC Conditions of Contract for Construction for Building and Engineering Works
(1999 the New Red Book) under which the contractor is responsible for construction;
• FIDIC MDB Harmonized Edition 2006 Conditions of Contract for Construction(the Red
Book) under which the contractor is responsible for construction;

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 82

Organized by: Belachew Asteray(PhD) 41


FTVET, 2023 March 2023

2.3. Construction Contract Types…


Construction Contract Delivery Systems
Conditions of Contract with respect to the Contract Delivery Systems…
• Design-Build
Organized by: Belachew Asteray (PhD)

• FIDIC Conditions of Contract for plant and Design –Build for Electrical & Mechanical
Plant, and for Building & Engineering Works (the New Yellow Book 1999) under which
the contractor is responsible both for design & construction.
• Engineer-Procure-Construct (EPC)
• FIDIC Conditions of Contract for EPC/Turnkey Projects (the Silver Book, 1999), under
which the contractor is responsible for design, construction and/or financing, operation.
This may also be adaptable to BOT & other related arrangements.
• Design-Build-Operate
• The FIDIC New Conditions of Contract for Design Build & Operate, under preparation,
under the intended contractual arrangement, the contractor is to be responsible for
design, build & operate a given facility.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 83

2.4. Local Construction Contracts and Laws


• Public Procurement Agency (PPA-2011)
• SBD Consultancy
• Standard Bidding Document For Procurement of Consultancy Services Request for Proposals
(RFP) National Competitive Bidding (NCB)
Organized by: Belachew Asteray (PhD)

• Standard Bidding Document For Procurement of Consultancy Services Request for Proposals
(RFP) International Competitive Bidding (ICB)
• SBD Works
• Standard Bidding Document (SBD) For Procurement of Works For International Competitive
Biddings (ICB)
• Standard Bidding Document (SBD) For Procurement of Works For National Competitive Biddings
(NCB)
• SBD Goods
• Standard Bidding Document (SBD) For Procurement of Goods and Related Services For
International Competitive Biddings (ICB)
• Standard Bidding Document (SBD) For Procurement of Goods and Related Services For National
Competitive Biddings (NCB)
• MINISTRY OF WORKS AND URBAN DEVELOPMENT STANDARD
CONDITIONS OF CONTRACT FOR CONSTRUCTION OF CIVIL
WORK PROJECTS (DECEMBER, 1994)
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 84

Organized by: Belachew Asteray(PhD) 42


FTVET, 2023 March 2023

2.4. Local Construction Contracts and Laws


• PPA 2011 Standard Bidding Document (SBD) – General Structure
Part 1 Bidding Procedures I
Organized by: Belachew Asteray (PhD)

Section 1. Instructions to Bidders I


Section 2. Bid Data Sheet II
Section 3. Evaluation Methodology and Criteria III
Section 4. Bidding Forms IV
Section 5. Eligible Countries V
Part 2 Schedule of Requirement VI
Section 6. Schedule of Requirements VI
Part 3 Contract VII
Section 7. General Conditions of Contract VII
Section 8. Special Conditions of Contract VIII
Section 9. Contract Forms IX

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 85

2.4. Local Construction Contracts and Laws…


PPA-2011: Basic Structures
General Conditions of Contract: WORKS- General Conditions of Contract: Consultancy Services
Organized by: Belachew Asteray (PhD)

National/International Competitive Bidding National/International Competitive Bidding


A. General Provisions (Clause 1-6) A. General Provisions (Clause 1-6)
B. The Contract (Clause 7-29) B. The Contract (Clause 7-30)
C. Obligations of the Public Body (Clause 30-33) C. Obligations of the Public Body (Clause 31-35)
D. Obligations of the Contractor (Clause 34-58) D. Payments to the Consultant (Clause 36-42)
E. Payments to the Contractor (Clause 59-69) E. Obligations of the Consultant (Clause 43-55)
F. Performance of the Contract (Clause 70-83) F. Performance of the Contract (Clause 56-68)
G. Acceptance and Defects Liability (Clause 84-89) G. Fairness and Good Faith (Clause 69-70)

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 86

Organized by: Belachew Asteray(PhD) 43


FTVET, 2023 March 2023

PPA 2011 –Works…


• Obligations of the Public Body
• Clause 30 Assistance and Supply of Documents
Organized by: Belachew Asteray (PhD)

• Sub Clause 30.1- copies of laws, regulations and information on local


customs, orders or by-laws of the Federal Democratic Republic of
Ethiopia, which may affect the Contractor in the performance of his
obligations under the Contract.
• Sub Clause 30.2- all efforts necessary to facilitate the procurement by
the Contractor of:
a) all required visas and permits, including work and residence permits, and
such other documents as shall be necessary to enable the Contractor, Sub-
Contractors or Personnel to carry out the Works;
b) any such other assistance as may be specified in the SCC.

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 87

PPA 2011 –Works…


• Obligations of the Public Body…
• Clause 31. Access to the Site
Organized by: Belachew Asteray (PhD)

• Sub Clause 31.1 The Public Body shall, in due time and in conformity
with the progress of the works, place the site and access thereto at the
disposal of the Contractor in accordance with the program of
implementation of tasks

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 88

Organized by: Belachew Asteray(PhD) 44


FTVET, 2023 March 2023

PPA 2011 –Works…


• Obligations of the Public Body…
• Clause 32 Payment
Organized by: Belachew Asteray (PhD)

• Sub Clause 32.1- the Public Body shall make to the Contractor such
payments and in such manner as is provided by GCC Paragraph E
(Payments to the Contractor) of this Contract.
• Sub Clause 59.1 currency as specified in the SCC.
• Clause 6o Advance Payment
• Clause 61. Retention Monies
• Clause 62. Price Adjustments
• Clause 64. -Interim payment
• Clause 65 -Final Statement of Account
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 89

PPA 2011 –Works…


• Obligations of the Public Body…
• Clause 6o Advance Payment
Organized by: Belachew Asteray (PhD)

• Sub Clause 60.1 issue an advance payment which shall not exceed
30% of the total contract price.
• (a) The conclusion of the Contract;
• (b) Provision of the Performance Security in accordance
with GCC Clause 58; and by
• (c) Provision of an advance payment security in an amount
equal to the advance payment they receive

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 90

Organized by: Belachew Asteray(PhD) 45


FTVET, 2023 March 2023

PPA 2011 –Works…


• Obligations of the Public Body…
• Clause 61. Retention Monies
Organized by: Belachew Asteray (PhD)

• Sub Clause 61.1 retain as stipulated in the SCC, provided that it


shall, in no case, exceed 10% of the contract price.
• Sub Clause 61.2 Can be substituted by a retention guarantee
• Sub Clause 61.3 shall be released within 45 days of the issuing
of the signed final statement of account
• 62. Price Adjustments
• Sub Clause 62.1 Adjustments of contract prices shall be allowed after twelve
(12) months from the effective date of the Contract where it is verified that the
performance of the contract requires more than 18 months.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 91

PPA 2011 –Works…


• Obligations of the Public Body…
• Clause 64. -Interim payment
Organized by: Belachew Asteray (PhD)

• Sub Clause 64.1 -Contractor shall submit monthly statement for


interim payment to the Engineer
• Sub Clause 64.5 Within 30 days of receipt of the said statement
for interim payment, it shall be approved or amended in such
manner that, in the Engineer's opinion, the application reflects the
amount due to the Contractor in accordance with the Contract.

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 92

Organized by: Belachew Asteray(PhD) 46


FTVET, 2023 March 2023

PPA 2011 –Works…


• Obligations of the Public Body…
• Clause 65. Final Statement of Account
Organized by: Belachew Asteray (PhD)

• Sub Clause 65.1 Unless otherwise agreed in the SCC, the Contractor
shall not later than 90 days after the issue of the Final Acceptance
Certificate referred to in GCC Clause 89, submit to the Engineer a
draft final statement of account with supporting documents
showing in detail the value of the work done in accordance with
the Contract.
• Sub Clause 65.2 Within 60 days after receipt of the draft final
statement of account and of all information reasonably required
for its verification, the Engineer shall prepare the final statement of
account, which determines:
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 93

PPA 2011 –Works…


• Obligations of the Public Body…
• Clause 33 Delayed Payments to the Contractor's Staff
Organized by: Belachew Asteray (PhD)

• Sub Clause 33.1- Where there is a delay in the payment to the


Contractor's employees of wages, salaries, allowances and
contributions,
• the Public Body may give notice to the Contractor that within 15
days of the notice the Contractor has to pay such wages, salaries,
allowances and contributions.

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 94

Organized by: Belachew Asteray(PhD) 47


FTVET, 2023 March 2023

PPA 2011 –Works…


• The Engineer
• Clause 30.3- the Engineer shall provide to the Contractor a copy of the
drawings prepared for the implementation of tasks as well as two
Organized by: Belachew Asteray (PhD)

copies of the specifications and other contract documents


• within 30 days of the signing of the Contract,
• free of charge,.
• Clause 30.5- The Engineer shall have authority to issue to the
Contractor administrative orders incorporating such supplementary
documents and instructions as shall be necessary for the proper and
adequate execution of the works and the remedying of any defects
therein.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 95

PPA 2011 –Works…


• Obligations of the Contractor
• PART D - Obligations of the Contractor
Organized by: Belachew Asteray (PhD)

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 96

Organized by: Belachew Asteray(PhD) 48


FTVET, 2023 March 2023

PPA 2011 –Works…


• Obligations of the Contractor…
Organized by: Belachew Asteray (PhD)

• Clause 34. General Obligations


• Sub Clause 34.1 shall design the works to the extent
stated in the Contract, and execute, complete and remedy any
defects in the works.
• with due care and diligence, and in accordance with the
provisions of the Contract
• shall provide all control and supervision of the works,
personnel, materials, plant, equipment and all other items
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 97

PPA 2011 –Works…


• Obligations of the Contractor…
• Sub Clause 34.2: shall take full responsibility for the adequacy,
Organized by: Belachew Asteray (PhD)

stability and safety of all operations and methods of construction


under the Contract.
• Sub Clause 34.3: shall respect and abide by all laws and regulations
in force in the Federal Democratic Republic of Ethiopia and shall ensure
that his personnel, their dependants, and his local employees also
respect and abide by all such laws and regulations.
• shall indemnify the Public Body against any claims and
proceedings arising from any infringement by the Contractor, its
Sub-Contractors or their employees of such laws and regulations.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 98

Organized by: Belachew Asteray(PhD) 49


FTVET, 2023 March 2023

PPA 2011 –Works…


• Obligations of the Contractor…
• Sub Clause 34.4
Organized by: Belachew Asteray (PhD)

• The Contractor shall ensure that Works conform to applicable


environmental and quality standards, that no chemical or
other product/equipment is used in such a way as to cause
negative impact on the environment in general and
occupational health hazards and shall employ the most recent
technology, safe and effective equipment, machinery,
materials and methods, as necessary.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 99

PPA 2011 –Works…


• Obligations of the Contractor…
• Sub Clause 34.5
Organized by: Belachew Asteray (PhD)

• The Contractor shall obtain the Public Body's prior approval


in writing before taking any of the following actions:
• (a) Entering into a subcontract for carrying out any part of
the Works, it being understood that the Contractor shall
remain fully liable for carrying out the Works by the Sub-
Contractor;
• (b) Any other action that may be specified in the SCC.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 100

Organized by: Belachew Asteray(PhD) 50


FTVET, 2023 March 2023

PPA 2011 –Works…


• Obligations of the Contractor…
• Sub Clause 34.6
Organized by: Belachew Asteray (PhD)

• The Contractor shall comply with any administrative orders given by


the Engineer.

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 101

PPA 2011 –Works…


• Obligations of the Contractor…
• Sub Clause 34.7
Organized by: Belachew Asteray (PhD)

• The Contractor shall treat all documents and information received in


connection with the contract as private and confidential, and shall not,
save in so far as may be necessary for the purposes of the
performance thereof, publish or disclose any particulars of the
contract without the prior consent in writing of the Public Body or the
specific contract manager after consultation with the Public Body.
• If any disagreement arises as to the necessity for any publication or
disclosure for the purpose of the contract, the decision of the Public
Body shall be final.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 102

Organized by: Belachew Asteray(PhD) 51


FTVET, 2023 March 2023

2.4. Local Construction Contracts and Laws…


MoWUD: Basic Structures
MINISTRY OF WORKS AND URBAN DEVELOPMENT STANDARD CONDITIONS OF CONTRACT FOR
CONSTRUCTION OF CIVIL WORK PROJECTS (DECEMBER, 1994)
Organized by: Belachew Asteray (PhD)

 DEFINITIONS AND INTERPRETATION  PLANT, TEMPORARY WORKS AND


 ENGINEER AND ENGINEER'S REPRESENTATIVE MATERIALS
 ASSIGNMENT AND SUB-LETTING  PROVISIONAL SUMS
 CONTRACT DOCUMENTS  NOMINATED SUB-CONTRACTORS
 GENERAL OBLIGATIONS  CERTIFICATES AND PAYMENT
 MATERIALS AND WORKMANSHIP  REMEDIES AND POWERS
 COMMENCEMENT TIME AND DELAYS  SPECIAL RISKS
 MAINTENANCE AND DEFECTS  FRUSTRATION
 ALTERATIONS, ADDITIONS AND OMISSIONS  SETTLEMENT OF DISPUTES
 NOTICES
 CHANGES IN COST AND LEGISLATION
 OTHER MATTERS

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 103

2.5. International Construction Contracts and Laws


• There are different standard conditions of contract developed by
certain institutions or recommended by international financing or
development institutions;
Organized by: Belachew Asteray (PhD)

• by FIDIC (Fédération internationale des Ingénieurs - Conseils)


• by European Union
• by African Development Bank
• by the World Bank
• Standard Conditions of Contract developed by FIDIC:
• Conditions of Contract for Civil Engineering Works (Red Book);
• Conditions of Contract for Electrical & Mechanical Works (Yellow Book);
• Conditions of Sub-Contract for Works of Civil Engineering Construction;
• Conditions of Contract for Design-Build & Turnkey (Orange Book);
• Conditions of Contract for Consultancy Services (White Book);
• The
March 2023 Sub-Consultancy Agreement;
CoTM 525 Organized by: Belachew Asteray (PhD) 104

Organized by: Belachew Asteray(PhD) 52


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws


• By European Union (through the European Development Fund
(EDF);
• General Regulations for Works, Supply & Service Contracts financed by
Organized by: Belachew Asteray (PhD)

the EDF;
• General Conditions for Works Contracts financed by EDF;
• General Conditions for Supply Contracts financed by EDF;
• General Conditions for Service Contracts financed by EDF;
• By the African Development Bank/Fund (for the procurement of
Works, Goods & Services);
• By the World Bank. These are Standard Bidding Documents for
the procurement works of civil engineering construction.

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 105

2.5. International Construction Contracts and Laws


• The FIDIC (Federation International Des Ingenieurs-Conseils)
• an international federation of national association of independent
consulting engineers.
Organized by: Belachew Asteray (PhD)

• founded in 1913 by five national associations of independent consulting


engineers within Europe.
• The objectives of forming the federation were to promote in common the
professional interests of the member associations and to disseminate
information of interest to members of its component national
associations;
• It has begun to prepare & disseminate standard conditions of contract
since 1957 for international use.
• The FIDIC Conditions of Contract is based on the concepts of the
Common Law Legal System.
• Recently (1999 & 2006) FIDIC has published many conditions of
contract.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 106

Organized by: Belachew Asteray(PhD) 53


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws


FIDIC
Fédération internationale des Ingénieurs - Conseils
Organized by: Belachew Asteray (PhD)

•Contract Conditions for the Construction Market:


• Red Book
• Yellow Book
• Silver Book Editions: 1987, 1999 (2006)
• Green Book
• White Book
• Orange Book
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 107

2.5. International Construction Contracts and Laws

FIDIC: Multilateral Development


Bank(MDB) Harmonized Edition,
Organized by: Belachew Asteray (PhD)

June, 2010, FIDIC.


Conditions of Contract for
Construction: For Building
and Engineering Works
Designed by the Employer
• Important Features
• Delivery System: design, bid & build
(DBB).
• the payment system followed being ad
measurement or BOQ based;
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 108

Organized by: Belachew Asteray(PhD) 54


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws


FIDIC: Structure/ Contents of MDB-FIDIC
(2010) Edition
The MDB-FIDIC (2010) Edition is divided into Twenty
Clauses/ sections:
Organized by: Belachew Asteray (PhD)

• Clause 1: General Provisions


• Clause 2: The Employer
• Clause 3: The Engineer
• Clause 4: The Contractor
• Clause 5: Nominated Subcontractors
• Clause 6: Staff & Labour
• Clause 7: Plant, Materials & Workmanship
• Clause 8: Commencement, Delays & Suspension
• Clause 9: Tests on Completion
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 109

2.5. International Construction Contracts and Laws


FIDIC: Structure/ Contents of MDB-FIDIC
(2010) Edition…
• Clause 10: Employer’s Taking Over
Organized by: Belachew Asteray (PhD)

• Clause 11: Defects Liability


• Clause 12: Measurement and Evaluation
• Clause 13: Variations & Adjustments
• Clause 14: Contract Price & Payment
• Clause 15: Termination by Employer
• Clause 16: Suspension & Termination by Contractor
• Clause 17: Risk & Responsibility
• Clause 18: Insurance
• Clause 19: Force Majeure
• Clause 20: Claims, Disputes & Arbitration
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 110

Organized by: Belachew Asteray(PhD) 55


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws


FIDIC: Structure/ Contents of MDB-FIDIC
(2010) Edition

• This condition of contract has been


Organized by: Belachew Asteray (PhD)

supported by two appendices.


• The appendices are related to
Dispute Board.
• General Conditions of Dispute
Board Agreement; and
• Procedural Rules; i.e. in relation
to the Dispute Board;

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 111

2.5. International Construction Contracts and Laws

Part 2- Contractual Duties of the 3C


Organized by: Belachew Asteray (PhD)

under MDB-FIDIC (2010) Edition


a) Rights and Obligations the Client/
Employer

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 112

Organized by: Belachew Asteray(PhD) 56


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations the Client/Employer…
• Giving Possession of the Site & Access thereto
• Clause 2.1 providing access to the Site to the Contractor;
Organized by: Belachew Asteray (PhD)

• However, the Employer may withhold any such right or possession


until the Performance Security has been received.
• Clause 4.10 providing Site Data to the Contractor;
• all relevant data in the Employer’s possession on sub-surface and
hydrological conditions at the Site, including environmental
aspects.
• Clause 4.13 providing rights of way & facilities to the Contractor;
• provide effective access to and possession of the Site including
special and/or temporary rights-of-way which are necessary for the
Works.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 113

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations the Client/Employer…
• Appointing an Engineer
• Clause 3.1
Organized by: Belachew Asteray (PhD)

• The Employer shall appoint the Engineer who shall carry


out the duties assigned to him in the Contract.

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 114

Organized by: Belachew Asteray(PhD) 57


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations the Client/Employer…
• Supplying Instructions to the Carrying out of the Works
(i.e. instructions, information, consents, approvals,
Organized by: Belachew Asteray (PhD)

notices…)
• Clause 1.13 (a)
• Obtaining the planning, zoning, building permits or similar
permissions for the Permanent Works, and any other
permissions described in the Specification as having been
(or to be) obtained by the Employer; and
• the Employer shall indemnify and hold the Contractor
harmless against and from the consequences of any
failure to do so;
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 115

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations the Client/Employer…
• Payment Obligation
• Payment of the Contract Price
Organized by: Belachew Asteray (PhD)

• Clause 14.2 cum Clause 14.7(a) in relation to Advance Payment


(the Contractor should submits a guarantee);
• The Employer shall pay to the Contractor:
• (a) the first instalment of the advance payment within 42 days
after issuing the Letter of Acceptance or within 21 days after
receiving the documents in accordance with Sub-Clause 4.2
[Performance Security] and Sub-Clause 14.2 [Advance
Payment], whichever is later;
• Clause 14.7(b) in relation to Interim Payment;
• Clause 14.13 cum Clause 14.7(c ) in relation to Final Payment;
• Clause 14.9 in relation to the first half of the Retention Money;
• Clause 14.9 in relation to the second half of the Retention Money;
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 116

Organized by: Belachew Asteray(PhD) 58


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations the Client/Employer…
•Other Payment Obligations…
• due to delay
Organized by: Belachew Asteray (PhD)

• in issuing drawings & instructions by the Engineer;


• caused in providing access to the Site;
• caused by unforeseeable physical conditions;
• due to error in Setting out;
• discovery & reporting of Fossils;
• Testing for which the Employer is responsible;
• suspension of Works;
• interference with Tests on Completion;
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 117

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations the Client/Employer…
• Other Payment Obligations …
• further tests for which the Employer is responsible;
Organized by: Belachew Asteray (PhD)

• Adjustment for Changes in Legislation;


• Adjustment for Changes in Cost;
• additional payment to the Contractor derived from savings due
to the effects of Value Engineering;
• financing charges in case of delay in payment;
• entitlement to a balance of costs, if any, in case of termination
of the Contract by the Employer due to the default of the
Contractor,
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 118

Organized by: Belachew Asteray(PhD) 59


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations the Client/Employer…
• Other Payment Obligations…
• Clause 1.9(b) payment of cost & profit due to delay in issuing drawings &
instructions by the Engineer;
Organized by: Belachew Asteray (PhD)

• Clause 2.1(b) payment of cost & profit due to delay caused in providing access
to the Site;
• Clause 4.7 payment of cost & profit due to error in Setting out;
• Clause 4.12(b) payment of cost due to delay caused by unforeseeable physical
conditions;
• Clause 4.24(b) payment of cost in case of discovery & reporting of Fossils;
• Clause 7.4(b) payment of cost in case of Testing for which the Employer is
responsible;
• Clause 8.9(b) payment of cost in case of suspension of Works;
• Clause 10.3(b) payment of cost & profit in case of interference with Tests on
Completion;
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 119

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations the Client/Employer…
• Other Payment Obligations …
• Clause 11.6 payment of cost in case of further tests for which the Employer
is responsible;
Organized by: Belachew Asteray (PhD)

• Clause 13.7 cum 14.3(b) payment of cost in case of Adjustment for Changes
in Legislation;
• Clause 13.8 payment of cost in case of Adjustment for Changes in Cost;
• Clause 14.3(a) cum Clause 13.2 payment of additional payment to the
Contractor derived from savings due to the effects of Value Engineering;
• Clause 14.8 payment of financing charges in case of delay in payment;
• Clause 15.4( c ) entitlement to a balance of costs, if any, in case of
termination of the Contract by the Employer due to the default of the
Contractor, after completion of the Works by the Employer or another
contractor;
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 120

Organized by: Belachew Asteray(PhD) 60


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations the Client/Employer…
• Other Payment Obligations …
• Clause 16.1(b) payment of cost & profit in case of suspension &
Organized by: Belachew Asteray (PhD)

reduction of the progress of the Works by the Contractor;


• Clause 16.4 payment of any loss or damage sustained by the
Contractor due to termination of the Contract by the Contractor due to
the default of the Employer;
• Clause 17.4(b)cum Clause 17.3(f) & (g) payment of cost & profit in
case of Employer’s risks;
• Clause 19.7 payment of costs in relation to Plant, Materials, other
costs & liabilities, cost of removal of the Temporary Works, cost of the
repatriation of Contractor’s Personnel;
• Clause 20.1 cum Clause 14.3 payment of claims;
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 121

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations the Client/Employer…
• Taking Over / Acceptance Obligation
• Clause 10
Organized by: Belachew Asteray (PhD)

• relative to actual Taking Over;


• Clause 10.1 Taking Over of the Works and Sections
• The Contractor may apply by notice to the Engineer for a Taking-Over Certificate not
earlier than 14 days before the Works will, in the Contractor’s opinion, be complete and
ready for taking over.
• The Engineer shall, within 28 days after receiving the Contractor’s application:
• (a) issue the Taking-Over Certificate to the Contractor, stating the date on which the
Works or Section were completed in accordance with the Contract,
• (b) reject the application, giving reasons and specifying the work required to be done by
the Contractor to enable the Taking-Over Certificate to be issued.
• Clause 10.2 Taking Over of Parts of the Works
• The Engineer may, at the sole discretion of the Employer, issue a Taking-
Over Certificate for any part of the Permanent Works.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 122

Organized by: Belachew Asteray(PhD) 61


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations the Client/Employer…
• Taking Over / Acceptance Obligation…
•Clause 10
Organized by: Belachew Asteray (PhD)

• Clause 10.3 Interference with Tests on Completion


• If the Contractor is prevented, for more than 14 days,
from carrying out the Tests on Completion by a cause for
which the Employer is responsible, the Employer shall be
deemed to have taken over the Works or Section (as the
case may be) on the date when the Tests on Completion
would otherwise have been completed.

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 123

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations the Client/Employer…
• Supplying instructions, information, consents, approvals, notices…
• Clause 2.2 - Laws, permits, licenses or approvals;
Organized by: Belachew Asteray (PhD)

• The Employer shall provide, at the request of the Contractor, such


reasonable assistance as to allow the Contractor to obtain properly:
• (a) to give copies of the Laws of the Country which are relevant to
the Contract but are not readily available, and
• (b) to issue any permits, licenses or approvals required by the
Laws of the Country:
i. which the Contractor is required to obtain under Sub-Clause 1.13
[Compliance with Laws],
ii. for the delivery of Goods, including clearance through customs, and
iii. for the export of Contractor’s Equipment when it is removed from the
Site.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 124

Organized by: Belachew Asteray(PhD) 62


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations the Client/Employer…
• Supplying instructions, information, consents, approvals,
notices…
Organized by: Belachew Asteray (PhD)

•Clause 2.4
• Submission of evidence or information on the
Employer’s financial arrangement;
•Clause 2.5
• Notice of claim by the Employer;
•Clause 4.2
• Approval of the form & financial institution for the
Performance Security;
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 125

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations the Client/Employer…
• Supplying instructions, information, consents, approvals, notices…
• Clause 15.2 To Issue Notice of termination;
Organized by: Belachew Asteray (PhD)

• The Employer shall be entitled to terminate the Contract if the Contractor:


• (a) fails to comply with Sub-Clause 4.2 [Performance Security] or with a notice under Sub-
Clause 15.1 [Notice to Correct],
• (b) abandons the Works or otherwise plainly demonstrates the intention not to continue
performance of his obligations under the Contract,
• (c) without reasonable excuse fails:
• (i) to proceed with the Works in accordance with Clause 8 [Commencement, Delays and Suspension],
or
• (ii) to comply with a notice issued under Sub-Clause 7.5 [Rejection] or Sub-Clause 7.6 [Remedial
Work], within 28 days after receiving it,
• (d) subcontracts the whole of the Works or assigns the Contract without the required
agreement,
• (e) becomes bankrupt or insolvent, goes into liquidation, or
• (f) gives or offers to give (directly or indirectly) to any person any bribe, gift, gratuity,
commission or other thing of value, as an inducement or reward:
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 126

Organized by: Belachew Asteray(PhD) 63


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations the Client/Employer…
• Supplying instructions, information, consents, approvals, notices…
• Clause 15.2 Notice of termination;
• The Employer shall be entitled to terminate the Contract if the Contractor:
Organized by: Belachew Asteray (PhD)

• (a) fails to comply with Sub-Clause 4.2 [Performance Security] or with a notice under Sub-Clause 15.1
[Notice to Correct],
• The Contractor shall deliver the Performance Security to the Employer within 28 days after receiving the Letter of
Acceptance (Sub-Clause 4.2 ).
• (b) abandons the Works or otherwise plainly demonstrates the intention not to continue performance
of his obligations under the Contract,
• (c) without reasonable excuse fails:
• (i) to proceed with the Works in accordance with Clause 8 [Commencement, Delays and Suspension]
• Clause 8.1 Commencement of Works -Except as otherwise specified in the Particular Conditions of Contract, the
Commencement Date shall be the date at which the following precedent conditions have all been fulfilled and the Engineer’s
notification recording the agreement of both Parties on such fulfilment and instructing to commence the Work is received by
the Contractor:
• Clause 8.2 Time for Completion- The Contractor shall complete the whole of the Works, and each Section (if any), within the
Time for Completion for the Works
• Clause 8.3 Programme- The Contractor shall submit a detailed time programme to the Engineer within 28 days after
receiving the notice under Sub-Clause 8.1 [Commencement of Works].
• Clause 8.8 Suspension of Work- The Engineer may at any time instruct the Contractor to suspend progress of part or all of
the Works. During such suspension, the Contractor shall protect, store and secure such part or the Works against any
deterioration, loss or damage.

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 127

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations the Client/Employer…
• Supplying instructions, information, consents, approvals, notices…
• Clause 15.2 Notice of termination;
Organized by: Belachew Asteray (PhD)

• (c) without reasonable excuse fails:


• (ii) to comply with a notice issued under Sub-Clause 7.5 [Rejection] or Sub-Clause 7.6 [Remedial Work], within 28
days after receiving it,
• 7.5 Rejection- If, as a result of an examination, inspection, measurement or testing, any Plant, Materials or workmanship is
found to be defective or otherwise not in accordance with the Contract, the Engineer may reject the Plant, Materials or
workmanship by giving notice to the Contractor, with reasons. The Contractor shall then promptly make good the defect and
ensure that the rejected item complies with the Contract. If the Engineer requires this Plant, Materials or workmanship to be
retested, the tests shall be repeated under the same terms and conditions. If the rejection and retesting cause the Employer to
incur additional costs, the Contractor shall subject to SubClause 2.5 [Employer’s Claims] pay these costs to the Employer.
• 7.6 Remedial Work: Notwithstanding any previous test or certification, the Engineer may instruct the Contractor to:
• (a) remove from the Site and replace any Plant or Materials which is not in accordance with the Contract,
• (b) remove and re-execute any other work which is not in accordance with the Contract, and
• (c) execute any work which is urgently required for the safety of the Works, whether because of an accident,
unforeseeable event or otherwise.
• The Contractor shall comply with the instruction within a reasonable time, which shall be the time (if any) specified in
the instruction, or immediately if urgency is specified under sub-paragraph (c).
• If the Contractor fails to comply with the instruction, the Employer shall be entitled to employ and pay other persons to
carry out the work. Except to the extent that the Contractor would have been entitled to payment for the work, the
Contractor shall subject to Sub-Clause 2.5 [Employer’s Claims] pay to the Employer all costs arising from this failure.

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 128

Organized by: Belachew Asteray(PhD) 64


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations the Client/Employer…
• Supplying instructions, information, consents, approvals,
notices…
Organized by: Belachew Asteray (PhD)

• Clause 15.2 Notice of termination;


• The Employer shall be entitled to terminate the Contract if the Contractor:
• (d) subcontracts the whole of the Works or assigns the Contract without the required
agreement,
• (e) becomes bankrupt or insolvent, goes into liquidation, has a receiving or
administration order made against him, compounds with his creditors, or carries on
business under a receiver, trustee or manager for the benefit of his creditors, or if any
act is done or event occurs which (under applicable Laws) has a similar effect to any
of these acts or events, or
• (f) gives or offers to give (directly or indirectly) to any person any bribe, gift,
gratuity, commission or other thing of value, as an inducement or reward:
• (i) for doing or forbearing to do any action in relation to the Contract, or
• (ii) for showing or forbearing to show favour or disfavour to any person in relation to the
Contract,
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 129

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations the Client/Employer…
• Supplying instructions, information, consents, approvals, notices…
•Clause 18.1
Organized by: Belachew Asteray (PhD)

• in relation to approval of the insurance institution &


form of the insurance policy;
•Clause 20.4
• in relation to notice of dissatisfaction with decision of
the Dispute Board (DB);

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 130

Organized by: Belachew Asteray(PhD) 65


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations the Client/Employer…
• Not Interfering with the Progress of the Works
• Clause 1.13
Organized by: Belachew Asteray (PhD)

• failure to secure the required planning, zoning & other permits;


• Clause 2.1
• failure to give possession of Site & access thereto;
• Clause 4.6 Co-operation
• not to cause delay to the Contractor due to the Employer,
Employer’s Personnel & Employer’s other contractors;
• Clause 1.9 Delayed Drawings or Instructions
• issuing instruction or drawing by the Engineer;
• Clause 13.3
• making variations or other substantive change to the quantity of
Works;
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 131

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations the Client/Employer…
• Nomination of Specialist Sub-contractors & Suppliers
• Clause 5 cum Clause 13.5
Organized by: Belachew Asteray (PhD)

• Permitting the Contractor to Carryout the Whole of the Works


• Clause 12.4 ordering omission of the Works not for the purpose of awarding
the omitted part to be completed by other contractors or itself;
• Clause 13.1(d) in relation to omission of works unless it is to be carried out by
others;
• Clause 4.1 in relation to the Contractor’s general obligation to execute &
complete the whole of the Works & not to interfere therewith by the Employer;
• Supplying Materials & Carrying out Works, if these form Part of the
Works
• Clause 4.6 in relation to employing other contractors to carry out works not
forming part of the Contract with the Contractor;
• Clause 4.20 in relation to supplying Employer’s Equipment & Free-Issue –
Materials to the Contractor,
March 2023
indeed against payment;
CoTM 525 Organized by: Belachew Asteray (PhD) 132

Organized by: Belachew Asteray(PhD) 66


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations the Client/Employer…
• Indemnity Obligation
• Clause 4.2 in relation to Performance security resulting from a claim
under the Performance Security to the extent to which the Employer was
Organized by: Belachew Asteray (PhD)

not entitled to make the claim there under;


• Clause 17.1 in relation to indemnity relative to bodily injury, sickness,
diseases or death, for which the Employer is responsible under the
Contract;
• Clause 17.5 in relation to Intellectual & industrial property
rights(infringement of rights);
• Insurance Obligation
• Clause 17.3 in relation to Employer’s Risks (if the test of insurability has
passed & capable of insuring);
• Clause 18.1 in relation to general requirements for insurance, the
Employer as “insuring party” under the Contract;
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 133

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Rights the Client/Employer
•Clause 3.4 Replacement of the Engineer
• If the Employer intends to replace the Engineer, the
Organized by: Belachew Asteray (PhD)

Employer shall, not less than 21 days before the intended


date of replacement, give notice to the Contractor of the
name, address and relevant experience of the intended
replacement Engineer.

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 134

Organized by: Belachew Asteray(PhD) 67


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Rights the Client/Employer
• Taking Contractual Remedies
• Delay Damages
• Clause 8.7 in relation to delay by the Contractor in completing the Works within the time for
Organized by: Belachew Asteray (PhD)

completion or as extended;
• This is equivalent to liquidated damages;
• Indemnities
• Clause 1.13 in relation to the Contractor’s failure to comply with laws;
• Clause 4.14 in relation to the Contractor’s responsibility for the acts or defaults of any sub-
contractor, his agents or employees;
• Clause 4.16(c) in relation to the transport of Goods;
• Clause 17.1 in relation to bodily injury, sickness, diseases, or death of any person …;
• Clause 17.5 in relation to claims pertaining to intellectual & industrial property rights;
• Deduction from the Contract Price
• Clause 4.19 in relation to the cost of electricity, water & gas;
• Clause 4.20 in relation to Employer’s Equipment & Free-issue-Materials;
• Clause 15.4(c) in relation to payments (of the balance, if any) after termination of the
Contract by the Employer due to default of the Contractor;
• Clause 11.4(c) in relation to failure to remedying defects by the Contractor;
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 135

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Rights the Client/Employer…
• Taking Contractual Remedies …
• Time Extension
Organized by: Belachew Asteray (PhD)

• Clause 11.3 in relation to Defects Notification Period;


• Suspension
• Clause 8.8 in relation to suspension of the Performance of the Works;
• Termination
• Clause 11.4(c ) in relation to Tests on Completion;
• Clause 15.2 in relation to defaults of the Contractor;
• Clause 15.2(f) in relation to corruptive practices of the Contractor;
• Clause 15.6 in relation to corruptive practices of the Contractor;

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 136

Organized by: Belachew Asteray(PhD) 68


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws

Part 2- Contractual Duties of the 3C


Organized by: Belachew Asteray (PhD)

under MDB-FIDIC (2010) Edition

Rights and Obligations the Engineer

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 137

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations of the Engineer…
• Clause 3.1 Engineer’s Duties and Authority
• the Engineer shall be deemed to act for the Employer;
Organized by: Belachew Asteray (PhD)

• The Engineer shall obtain the specific approval of the Employer before
taking action under the following Sub-Clauses of these Conditions:
• (A) Sub-Clause 4.12: agreeing or determining an extension of time and/or
additional cost.
• (B) Sub-Clause 13.1: instructing a Variation, except;
• (i) in an emergency situation as determined by the Engineer, or
• (ii) if such a Variation would increase the Accepted Contract Amount by less
than the percentage specified in the Contract Data.
• (C) Sub-Clause 13.3: approving a proposal for Variation submitted by the
Contractor in accordance with Sub-Clause 13.1 or 13.2.
• (D) Sub-Clause 13.4: specifying the amount payable in each of the applicable
currencies.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 138

Organized by: Belachew Asteray(PhD) 69


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations of the Engineer…
• Clause 3.1 Engineer’s Duties and Authority…
• If an emergency occurs affecting the safety of life or of
Organized by: Belachew Asteray (PhD)

the Works or of adjoining property, he may, without


relieving the Contractor of any of his duties and
responsibility under the Contract, instruct the
Contractor to execute all such work or to do all such
things as may, in the opinion of the Engineer, be
necessary to abate or reduce the risk.
• The Engineer shall determine an addition to the Contract
Price, in respect of such instruction, in accordance with
Clause 13 and shall notify the Contractor accordingly, with
a copy to the Employer.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 139

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations of the Engineer…
•Clause 3.2 Delegation by the Engineer
•assign duties and delegate authority to assistants,
Organized by: Belachew Asteray (PhD)

and may also revoke such assignment or


delegation.
• The assignment, delegation or revocation shall be in
writing and shall not take effect until copies have been
received by both Parties.
• the Engineer shall not delegate the authority to
determine any matter in accordance with Sub-Clause
3.5 [Determinations].

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 140

Organized by: Belachew Asteray(PhD) 70


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations of the Engineer…
• Clause 3.3 Instructions of the Engineer
• The Engineer may issue to the Contractor (at any time) instructions
and additional or modified Drawings which may be necessary for
Organized by: Belachew Asteray (PhD)

the execution of the Works and the remedying of any defects, all in
accordance with the Contract.
• The Contractor shall only take instructions from the Engineer, or
from an assistant.
• If an instruction constitutes a Variation, Clause 13 [Variations
and Adjustments] shall apply.
• Clause 13.3 Variation Procedure
• The Engineer shall, as soon as practicable after receiving such
proposal (under SubClause 13.2 [Value Engineering] or
otherwise), respond with approval, disapproval or comments.
• Each Variation shall be evaluated in accordance with Clause 12
[Measurement and Evaluation]
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 141

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations of the Engineer…
• Clause 12.3 Evaluation
• The Engineer shall proceed in accordance with Sub-Clause
Organized by: Belachew Asteray (PhD)

3.5 [Determinations] to agree or determine the Contract


Price by evaluating each item of work,
• applying the measurement agreed or determined in
accordance with the above Sub-Clauses 12.1 and 12.2 and
the appropriate rate or price for the item.

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 142

Organized by: Belachew Asteray(PhD) 71


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Rights of the Engineer…
• Clause 12.1 Works to be Measured
• The Engineer shall be give notice to the Contractor’s
Organized by: Belachew Asteray (PhD)

Representative, and can get a person who shall:


• (a) promptly either attend or send another qualified
representative to assist the Engineer in making the
measurement, and
• (b) supply any particulars requested by the Engineer.

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 143

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Rights of the Engineer…
• Clause 13.1 Right to Vary
• Variations may be initiated by the Engineer at any time prior to issuing the Taking-
Over Certificate for the Works, either by an instruction or by a request for the
Organized by: Belachew Asteray (PhD)

Contractor to submit a proposal.


• Each Variation may include:
• (a) changes to the quantities of any item of work included in the Contract (however,
such changes do not necessarily constitute a Variation),
• (b) changes to the quality and other characteristics of any item of work,
• (c) changes to the levels, positions and/or dimensions of any part of the Works,
• (d) omission of any work unless it is to be carried out by others,
• (e) any additional work, Plant, Materials or services necessary for the Permanent
Works, including any associated Tests on Completion, boreholes and other testing and
exploratory work, or
• (f) changes to the sequence or timing of the execution of the Works.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 144

Organized by: Belachew Asteray(PhD) 72


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws

Part 2- Contractual Duties of the 3C


Organized by: Belachew Asteray (PhD)

under MDB-FIDIC (2010) Edition

Rights and Obligations the Contractor

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 145

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations of the Contractor
• Clause 4.1 Contractor’s General Obligations –Performance
• The Contractor shall
Organized by: Belachew Asteray (PhD)

• design (to the extent specified in the Contract), execute and complete the Works in
accordance with the Contract and with the Engineer’s instructions, and shall remedy any
defects in the Works.
• provide the Plant and Contractor’s Documents specified in the Contract, and all
Contractor’s Personnel, Goods, consumables and other things and services
• responsible for the adequacy, stability and safety of all Site operations and of all
methods of construction.
• responsible for all Contractor’s Documents, Temporary Works, and such design of
each item of Plant and Materials as is required for the item to be in accordance with the
Contract.
• submit details of the arrangements and methods which the Contractor proposes to
adopt for the execution of the Works whenever required by the Engineer.

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 146

Organized by: Belachew Asteray(PhD) 73


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations of the Contractor…
• Completion Obligation
• Basic Obligation
Organized by: Belachew Asteray (PhD)

• Clause 4.1 During Performance Period


• Completion of the whole of the Works in accordance with the Contract up to Take Over(Clause 10) of the
Works
• Clause 11.1 During Defects Liability Period
• Executing outstanding works; and
• Remedying of defects & damages in the works;
• Extent of Completion Obligation
• Clause 15.1 to execute variations orders;
• Clause 17. 4 rectification of losses or damages to the works arising out of the Employer’s
Risks;
• Clause 7.6 executing remedial or urgent works;
• Clause 9.1 cum Clause 8.2(a) carrying out of works to achieve tests on completion for the
purpose of Taking Over (Clause 8.29b));
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 147

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations of the Contractor…
• Completion Obligation…
• Excuses from Completion Obligation
Organized by: Belachew Asteray (PhD)

• Clause 19. 7 due to legal or physical impossibility;


• Clause 17. 3 in case of the occurrence of the Employer’s Risks;
• Clause 8.8 in case of suspension of the Works by the Employer;
• Clause 16.1 in case of legitimate suspension of the Works by the Contractor;
• Clause 16.2 in case of termination of the Contract by the Contractor due to the
default of the Employer;
• Clause 15.5 in case of termination of the Contract by the Employer for its
convenience;
• Clause 8.11 in case of termination of the Contract for the whole of the Works due to
prolonged suspension caused by the Employer;
• Clause 19.6 in case of optional termination of the Contract by the Contractor or by
the Employer due to prevention of performance by force majeure;
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 148

Organized by: Belachew Asteray(PhD) 74


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations of the Contractor…
• Quality Performance Obligation
• Clause 4.1 & Clause 7.1 using materials, plant & workmanship
Organized by: Belachew Asteray (PhD)

as provided in the Contract specifically in the Technical


Specifications;
• Timely Performance Obligation
• Commencement Clause 8.1 (Commencement of the Works);
• Progress: Clause 8.1 cum Clause 8.6 (Rate of Progress)
• Completion: Clause 8.2 (Time for Completion);
• Passing of Tests on Completion: Clause 9 (Tests on
Completion)

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 149

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations of the Contractor…

•Obligation to provide Securities


•Clause 4.2 in relation to Performance Security;
Organized by: Belachew Asteray (PhD)

•Clause 14.2 in relation to Advance Payment


Guarantee;
•Clause 14.9 in relation to Retention Money
Guarantee;

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 150

Organized by: Belachew Asteray(PhD) 75


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations of the Contractor…
• Obligation to provide Indemnities
• Clause 1.13 in relation to compliance with laws;
Organized by: Belachew Asteray (PhD)

• Clause 4.14 in relation to avoidance of interference the convenience of the


public or the access to & use & occupation of all roads & footpaths…;
• Clause 4.16 in relation to transport of goods;
• Clause 17.1 in relation to bodily injury, sickness, diseases or death, of any
person whatsoever arising out of or in the course of or by reason of the
Contractor’s design(if any), the execution & completion of the Works &
remedying of any defects therein;
• Clause 17.5 in relation to intellectual & industrial property rights against &
from any other claim which arises out of or in relation to the manufacture,
use, sale or import of any Goods, or any design for which the Contractor is
responsible;
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 151

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations of the Contractor…
• Obligation to provide Insurance
• Clause 18.1 in relation to general requirements (choice of the
Organized by: Belachew Asteray (PhD)

insurer, terms of insurance, making the insurance in the joint


name, providing the policy, providing evidence for the payment
of premium, use of the insurance money for the purpose of the
Contract,…) in providing specific insurance arrangement;
• Clause 18.2 in relation to insurance of Works & Contractor’s
Equipment;
• Clause 18.3 in relation to insurance against injury to persons
& damage to property;
• Clause 18.4 in relation to insurance for Contractor’s Personnel;
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 152

Organized by: Belachew Asteray(PhD) 76


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations of the Contractor…
• Administrative Obligation
• Clause 1.6 entering into a Contract Agreement;
Organized by: Belachew Asteray (PhD)

• Clause 1.7(a) securing prior consent for assignment from the Employer;
• Clause 3.5 duty to consult with the Engineer;
• Clause 4.4(b) securing prior consent from the Engineer for Sub-contracting;
• Clause 4.6 providing appropriate opportunities for the Employer’s Personnel and
any other contractors employed by the Employer & for personnel of public
authorities;
• Clause 6.1-making arrangement for the engagement of staff & labour;
• Clause 6.1 Affording opportunity of access to the Site to the Engineer, other
personnel & for the public authorities;
• Clause 7.8 payment of royalties;
• Clause 20.5 attempting amicable settlement;
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 153

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Obligations of the Contractor…
• Obligation upon or after Completion
• Clause 11.1 remedying defects & completion of outstanding
Organized by: Belachew Asteray (PhD)

works, if any;
• Clause 11.11 clearance of Site upon completion;
• Clause 14.10 submission of Statement at Completion to the
Engineer;
• Clause 14.11 submission of draft Final Statement to the
Engineer;
• Clause 14.11 and 14.12 submission of further information
relative to the finalization of the draft Final Statement;

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 154

Organized by: Belachew Asteray(PhD) 77


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Rights of the Contractor…
• Clause 3.4 To raise objection during Replacement of the Engineer
• If the Contractor considers the intended replacement Engineer to be unsuitable, he has the
right to raise objection against him by notice to the Employer, with supporting
Organized by: Belachew Asteray (PhD)

particulars, and the Employer shall give full and fair consideration to this objection.
• Contractual Remedies to obtain Cost
• Clause 1.9(b) due to delayed issuance of drawings & instructions to the Contractor
caused by the Engineer;
• Clause 2.1(b) due to delay caused in providing access to the Site caused by the
Employer(Initial Delay);
• Clause 4.7 due to delay suffered by the Contractor in case of error in setting out;
• Clause 4.12(b) due to delay caused by unforeseeable physical conditions;
• Clause 4.24(b) due to delay caused in case of discovery & reporting of fossils;
• Clause 7.4(b) due to delay suffered by the Contractor caused by the Employer in case of
testing;
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 155

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Rights of the Contractor…
• Contractual Remedies to obtain Cost…
• Clause 8.9(b) due to delay caused by the effect of suspension as ordered by the
Engineer;
Organized by: Belachew Asteray (PhD)

• Clause 10.3(b) due to delay caused by the interference of the Employer with Tests on
Completion;
• Clause 11.6 due to incurring of costs by the Contractor with respect to repetition of
Tests;
• Clause 13.7 cum 14.3(b) due to incurring of cots in relation to adjustment for changes
in legislation;
• Clause 13.8 due to incurring of costs in relation to adjustment of changes in cost;
• Clause 14.3(a) cum Clause 13.2 entitlement to additional cost in case of cost
reduction in relation to Value Engineering;
• Clause 15.4( c ) getting the balance, if any, in relation to termination of the Contract
due to the default of the Contractor & the completion of the project by the Employer
or third part;
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 156

Organized by: Belachew Asteray(PhD) 78


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Rights of the Contractor…
• Contractual Remedies to obtain Cost…
• Clause 16.1 (b) due to suspension of works by the Contractor, as caused
Organized by: Belachew Asteray (PhD)

by the problem of payment & thereby incurred cost;


• Clause 16.1(b) due to reduction of the progress of the works by the
Contractor as caused by the problem of payment & thereby incurred cost;
• Clause 16.4 (c) due to termination of Contract by the Contractor due to the
default of the Employer & recovering costs incurred thereby;
• Clause 17.4(b) costs incurred due to consequences of the Employer’s
Risks;
• Clause 19.7 (b) entitlement to some payment in case of release from
performance of the Contract (Frustration);
• Clause 20.1 cum Clause 14.3(f) payment of additional payment due to
claims of the Contractor;
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 157

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Rights of the Contractor…
• Contractual Remedies …
• Profit, where applicable
Organized by: Belachew Asteray (PhD)

• Clause 1.9(b) in case of delayed issuance of drawings & instruction by the


Engineer;
• Clause 2.1(b) in case of delay in providing access to the Site;
• Clause 4.7(b) in case of error in Setting out;
• Clause 7.4(b) in case of delay suffered by the Contractor caused by the
Employer in relation to Testing;
• Clause 10.3(b) in case of interference with Tests on Completion by the
Employer;
• Clause 16.1(b) in case of suspension & reduction of the progress of the
work by the Contractor caused by payment problem;
•March
Clause
2023 17.4(b) cum Clause 17.3(f)
CoTM 525 Organized by:&(g) in case
Belachew Asteray (PhD) of Employer’s Risks; 158

Organized by: Belachew Asteray(PhD) 79


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Rights of the Contractor…
• Contractual Remedies …
• Financing Charges
Organized by: Belachew Asteray (PhD)

• Clause 14.8 in case of delayed payment by the Employer;


• Indemnity
• Indemnity includes claims, damages, losses, & expenses including legal
fees & expenses;
• Clause 4. 2 in case of calling the Performance Security by the Employer
to the extent to which the Employer was not entitled to make the claim;
• Clause 17.1 general obligation in relation to indemnifying the
Contractor by the Employer;
• Clause 17.5 indemnifying the Contractor in relation to intellectual &
industrial property rights;
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 159

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Rights of the Contractor…
• Contractual Remedies…
• Extension of Time
Organized by: Belachew Asteray (PhD)

• Clause 8.4(a) due to Variation;


• Clause 8.4 (c) due to exceptionally adverse climatic conditions;
• Clause 8.4 (d) due to unforeseeable shortages in the availability of
personnel, or Goods caused by epidemic or governmental action;
• Clause 8.4(e) due to any delay, impediment or prevention caused
by or attributable to the Employer, the Employer’s personnel
(including the Engineer see Clause 1.1.2.6) or the Employer’s other
contractors;
• Clause 8.4(b)cum Clause 1.9(a) due to delay in issuing drawing &
instructions by the Engineer to the Contractor;
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 160

Organized by: Belachew Asteray(PhD) 80


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Rights of the Contractor…
• Contractual Remedies…
• Extension of Time
Organized by: Belachew Asteray (PhD)

• Clause 8.4(b) cum Clause 2.1(a) due to delay in providing access to the Site by the
Employer;
• Clause 8.4(b) Clause 4.7(a) due to delay caused due to error in Setting out;
• Clause 8.4(b) cum Clause 4.12(a) delay due to unforeseeable physical conditions;
• Clause 8.4(b)cum Clause 4.24(a) delay caused due to discovery & reporting of Fossils;
• Clause 8.4(b)cum Clause 7.4(a) delay caused by the Employer in relation to Testing;
• Clause 8.4(b)cum Clause 8.8 delay caused by suspension as ordered by the Engineer;
• Clause 8.4(b)cum Clause 8.11 delay caused due to prolonged suspension provided the
Contractor opted for resuming the performance of the Works after such prolonged
suspension;
• Clause 8.4(b)cum Clause 16.1(h) delay caused to the Contractor due to suspension or
reduction in the progress of the Works by the Contractor due to delay in payment;
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 161

2.5. International Construction Contracts and Laws


Part 2- Contractual Duties of the 3C under FIDIC…
• Rights of the Contractor…
• Contractual Remedies…
• Deceleration (reduction) of the progress of the Works;
Organized by: Belachew Asteray (PhD)

• Clause 16.1 due to delay in payment;


• Suspension of the performance of the Works;
• Clause 16.1 due to delay in payment;
• Termination of the Contract;
• Clause 8.11 cum Clause 16.2 (f) due to prolonged
suspension of the Works by the Employer;
• Clause 16.2 (a) through (j) due to the default of the
Employer;
• Clause 16.2(h) due to delay in payment & other payment
related grounds;
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 162

Organized by: Belachew Asteray(PhD) 81


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws

Communication Modalities of the 3C under FIDIC


• Overview of Communication in Construction

•Communication
Organized by: Belachew Asteray (PhD)

•is an essential process in our day-to-day life, and


the entire world revolves around it.
•definition “who says what to whom in what
channel with what effect”. (Lasswell's Maxim)
•is exchanging of information from one point of
the project to the other point in an efficient
manner.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 163

2.5. International Construction Contracts and Laws

Communication Modalities of the 3C under FIDIC…


• Communication Modalities
•Information
Organized by: Belachew Asteray (PhD)

• Clause 4.1(a) & (b) design information, in case where


the Contractor is required under the Contract to design
part of the permanent Works;
• Clause 4.24 geological or archeological finds(Fossils);
• Clause 5.4 submitting evidence in relation to
payments made to the nominated sub-contractors, as the
Engineer requests;
• Clause 6.10 details of Labour & Equipment;
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 164

Organized by: Belachew Asteray(PhD) 82


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws

Communication Modalities of the 3C under FIDIC…


• Communication Modalities…
• Information …
Organized by: Belachew Asteray (PhD)

• Clause 8.3 programme & revised programme;


• Clause 12.1 particulars as requested by the Engineer in formation
pertaining to measurement of Works;
• Clause 13.5 in relation to provisional sums submission of quotations,
receipts , vouchers & accounts or receipts for substantiation of the use of
the said sums;
• Clause 13.6 on use of Day Work items, on daily basis;
• Clause 14.3 submitting monthly statements to the Engineer for payment
purposes;
• Clause 20.1 contemporary records as per the request of the Engineer;
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 165

2.5. International Construction Contracts and Laws

Communication Modalities of the 3C under FIDIC…


• Communication Modalities…
• Notices
Organized by: Belachew Asteray (PhD)

• Clause 1.9 giving of notices in relation to delayed drawings or instructions by the


Engineer;
• Clause 1.13 giving of all notices…in relation to the execution & completion of the
Works & remedying any defects therein;
• Clause 2.1 giving notice to the Employer in case of failure of the Employer in
providing possession of Site;
• Clause 4.2 in case of submission of the Performance Security copy to the Employer;
• Clause 4.12 in case of encountering unforeseeable physical conditions: to the
Employer;
• Clause 4.16 notice to be given to the Engineer in relation to transport of Goods &
Plant to be delivered to the Site;
• Clause 7.3 giving notice to the Engineer in case of any work is ready & before it is
covered
March 2023
up, put out of sight, or packaged for storage or transport or inspection; 166
CoTM 525 Organized by: Belachew Asteray (PhD)

Organized by: Belachew Asteray(PhD) 83


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws

Communication Modalities of the 3C under FIDIC…


• Communication Modalities…
• Notices…
Organized by: Belachew Asteray (PhD)

• Clause 8.4 giving notice to the Engineer in case of request for extension of time(EOT) for
completion;
• Clause 8.9 giving notice to the Engineer in case of suspension of work instructed by the
Engineer;
• Clause 8.11 giving notice to the Engineer in case of prolonged suspension of the Works;
• Clause 10.1 giving notice to the Engineer in case of requesting the Taking Over of the
Works & Sections, if any;
• Clause 13.1 giving notice to the Engineer the reasons(with supporting particulars) not to
execute the variation order or instruction;
• Clause 17.4 giving notice to the Engineer in case of the effects or consequences of the
Employer’s Risks;
• Clause
March 2023
18.1 giving notice to the Engineer in case of submission of insurance policies
CoTM 525 Organized by: Belachew Asteray (PhD) 167
to
the Employer;

2.5. International Construction Contracts and Laws

Communication Modalities of the 3C under FIDIC…


• Law and Language in FIDIC
• Clause 1.3 Communications
Organized by: Belachew Asteray (PhD)

• Wherever these Conditions provide for the giving or issuing of approvals,


certificates, consents, determinations, notices, requests and discharges, these
communications shall be:
• (a) in writing and delivered by hand (against receipt), sent by mail or courier, or
transmitted using any of the agreed systems of electronic transmission as stated
in the Contract Data; and
• (b) delivered, sent or transmitted to the address for the recipient’s communications
as stated in the Contract Data. However:
• (i) if the recipient gives notice of another address, communications shall thereafter
be delivered accordingly; and
• (ii) if the recipient has not stated otherwise when requesting an approval or
consent, it may be sent to the address from which the request was issued.

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 168

Organized by: Belachew Asteray(PhD) 84


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws

Communication Modalities of the 3C under FIDIC…


• Law and Language in FIDIC…
• Clause 1.4 Law and Language
Organized by: Belachew Asteray (PhD)

• The Contract shall be governed by the law of the


country or other jurisdiction stated in the Contract Data.
• The ruling language of the Contract shall be that stated
in the Contract Data.
• The language for communications shall be that stated
in the Contract Data. If no language is stated there, the
language for communications shall be the ruling
language of the Contract.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 169

2.5. International Construction Contracts and Laws


Organized by: Belachew Asteray (PhD)

Claim Management
Under FIDIC

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 170

Organized by: Belachew Asteray(PhD) 85


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws


Claim–Management: Procedure to follow
Clause 20.1: The contractor consider himself to be The contractor The contractor
entitled to any extension of the time for consider himself to consider himself to be
Completion and/or any additional payment, under be entitled to any entitled to any legal
any Clause of these Conditions or otherwise in claim in connection claim
Organized by: Belachew Asteray (PhD)

connection with the contract. with, or arising out


of, the Contract or
If so, the contractor shall give notice to the
Engineer, describing the event or circumstances
the execution of the
giving rise to the claim.
works

28 days

Clause: 20.4: If a dispute (of any kind whatsoever) arises between the Parties in connection with, or
arising out of, the Contract or the execution of the Works, including any dispute as to any certificate,
determination, instruction, opinion or valuation of the Engineer, either Party

may refer to the dispute in writing to DB for its decision, with copies to the other Party and Engineer

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 171

2.5. International Construction Contracts and Laws


Claim–Management: FIDIC-Extensions: Time + Money
The 14 Contractor’s Claims documented in the MDB FIDIC -
own fault of the Contractor has to be excluded always:
1. Clause 1.9: Delayed Drawings or Instructions
Organized by: Belachew Asteray (PhD)

After Delay of an issued demand by the contractor


2. Clause 2.1: Right to Access to the Site
Clause 8: Commencement: after 7 but within 42 days
3. Clause 4.7: Setting Out
….if the delay could be avoided by “an experienced contractor”

4. Clause 4.12: Unforeseeable Physical Conditions


Including sub-surface and hydrological conditions not climatic
5. Clause 4.24: Fossils
All findings to the care and authority of the employer!
6. Clause 7.4: Testings
Ordered 24 h before: If the Engineer is absent they are accepted
7. Clause 8.4: Extension of Time for Completion
In 4 cases: Variations, Climatic, Shortages, Employer’s Personal
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 172

Organized by: Belachew Asteray(PhD) 86


FTVET, 2023 March 2023

Claim–Management: FIDIC-Extensions: Time + Money


The 14 Contractor’s Claims documented in the MDB FIDIC -
own fault of the Contractor has to be excluded:
Organized by: Belachew Asteray (PhD)

8. Clause 8.9: Consequences of suspensions


The suspension has to cause a delay!
9. Clause 10.2: Taking over of Parts of the works
Used parts without taking-over certificate are as certificated
10.Clause 10.3: Interference with Test on Completion
The contractor should not be prevented carrying out tests >14d
11.Clause 13.7: Adjustments for Changes in Legislation
Changes of laws after “Base Date” (28 d prior submission date)

12.Clause 16.1: Contractor’s Entitlement to Suspend Work


After 21 d of an issued notice of an entitled payment: Clause 14
13.Clause 17.4: Consequences of Employer’s Risks
Like war and riots, forces of nature
14.Clause 19.4: Force Majeure
Reasons compare above 17.4, notice shall be given <14 d

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 173

2.5. International Construction Contracts and Laws


Claim-Management: Typical Sequence to Assert a Claim

42 d 42 d
Organized by: Belachew Asteray (PhD)

28 d

Clause 8.4: Clause 8.4: Clause 20.1: Clause 20.1:


Contractor and 20.1: Contractor Clause 3.5: Engineer
consider Contractor issues detailed Equitable Solutionanswers with
himself to be Yes issues a notice Yes claim within approval or
entitled to a within 28 42 days disapproval
claim days within 42 days
Claim at all !!!!
Loss of the
the deadline:
Fail to observe

decision
bearing on the
May have a
the deadline:
Fail to observe

Engineer

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 174

Organized by: Belachew Asteray(PhD) 87


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws


Claim-Management: Typical Sequence of Dispute Events
Organized by: Belachew Asteray (PhD)

Dispute Board (DB)

8.1 20.2 20.4 20.4 A Party may 20.6 A Party may


Commence- Parties appoint A Party refers to issue a “notice of initiate arbitration
ment Date
DB
(1 or 3 Prs.)
the DB
NO Dissatisfaction”

Parties present DB gives its Amicable Settlement


submissions to Clause
the 3.5:
decision Arbitrator/s
DB Equitable Solution appointed

<28 d <84 d <28 d <56 d

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 175

2.5. International Construction Contracts and Laws


Claim-Management: Adjustments
Organized by: Belachew Asteray (PhD)

Claims for Adjustments for:

• the Contract Price


• the Extension of Time for Completion

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 176

Organized by: Belachew Asteray(PhD) 88


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws


Claim-Management: Adjustments of the Contract Price
•The contract price has to be adjusted because of
changes in:
Organized by: Belachew Asteray (PhD)

• Variations: Clause 13.1


• Legislation: Clause 13.7
• Made after the Base Date
• Will affect the Contractor in the performance of obligations
under the Contract
• Costs: Clause 13.8
• Only if there is a table included (Appendix to Tender)!

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 177

2.5. International Construction Contracts and Laws

Claim-Management: Adjustments because of Variations

• Clause 13.1: Right to vary


Organized by: Belachew Asteray (PhD)

• Variations may be initiated by the Engineer at any time


prior to issuing the Taking-Over-Certificate for the Works,
either by an instruction or by a request for the Contractor
to submit a proposal ………

=> Clause 13.2: Value Engineering


=> Clause 13.3: Variation Procedure

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 178

Organized by: Belachew Asteray(PhD) 89


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws

Claim-Management: Adjustments because of Variations


Kinds of Variations:
Organized by: Belachew Asteray (PhD)

• (a) Changes of Quantity


• (b) Changes of Quality
• (c) Changes of levels, positions and/or dimensions
• (d) Omissions of work unless it is to be carried out by others
• (e) Any additional works for the Permanent Works
• (f) Changes of the Sequence or Timing of the
execution of the Works

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 179

2.5. International Construction Contracts and Laws

Claim-Management: Adjustments
Organized by: Belachew Asteray (PhD)

Claims for Adjustments for:

•the Contract Price


•the Extension of Time for Completion

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 180

Organized by: Belachew Asteray(PhD) 90


FTVET, 2023 March 2023

2.5. International Construction Contracts and Laws


Claim-Management: Adjustments of the Contractual Time
Risk of the Employer:
Change of Quantities Extension of Time + Costs
Organized by: Belachew Asteray (PhD)

Change of Qualities Extension of Time + Costs

Insufficient Assistance Extension of Time + Costs


+ Payment of damages
Reasons of
Force Majeure Extension of Time + Costs
delays on site

Risk of the Contractor:


Lack of Organisation
NO Claims!!!
Insufficient Capacity

Mistakes of Workmanship

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 181

2.5. International Construction Contracts and Laws

Final Helpful Messages


• A smart look into the Text of the Contract &
Understand.
Organized by: Belachew Asteray (PhD)

• Keep a Daily Report Book and let it signed by the


Engineer!
• Confirm in writing all verbal orders!
• An un - priced Bill of Quantity should be in hands of
Resident Engineers on site!
• So he can detect additional works!
• Update carefully our Time Schedule!
• Detect the claims as soon as possible!
• Update our Skills on Key Areas of Project Management:
Procurement Guidelines, Principles, Softwares
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 182

Organized by: Belachew Asteray(PhD) 91


FTVET, 2023 March 2023

2.6 Subcontracting
• Subcontractor is a common term used in construction.
• Due to the uniqueness of each construction project, the work force
is transient, multiple craft are involved, each project are planned
Organized by: Belachew Asteray (PhD)

and worked in short time frames, and variety of materials and


equipments required, one single construction project is often sublet
to many subcontractors.
• Subcontractors can contribute more than 50%, and can be as much
as 90% of total project value to a construction process.
• Subcontractors are specialist in the execution of a specific job,
they act as a agents of the production system of the contractor
company in supplying materials, manpower, equipment, tools or
designs.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 183

2.6 Subcontracting
• A subcontractor is a construction firm that contracts with a
general contractor to perform some aspect of the general
Organized by: Belachew Asteray (PhD)

contractor’s work.
• In most construction projects, a vital role is played by
subcontractors who are hired to perform specific tasks on a
project.
• In the usual case, the general contractor will perform the basic
operations and subcontract the remainder to various specialty
contractors.

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 184

Organized by: Belachew Asteray(PhD) 92


FTVET, 2023 March 2023

2.6 Subcontracting
• What is Subcontracting?
• Subcontracting is the practice of assigning part of the
Organized by: Belachew Asteray (PhD)

obligations and tasks under a contract to another party known


as a subcontractor.
• Subcontracting is especially prevalent in areas where complex
projects are the norm, such as construction and information
technology.
• Subcontractors are hired by the project's general contractor,
who continues to have overall responsibility for project
completion and execution within its stipulated parameters and
deadlines.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 185

2.6 Subcontracting
• Why Subcontract?
• Subcontracting is very useful in situations where the range of
required capabilities for a project is too diverse to be carried out
Organized by: Belachew Asteray (PhD)

by a single general contractor.


• In such cases, subcontracting parts of the project that do not form
the general contractor's2.7. core competencies
Construction Audit may assist in
keeping costs under control and mitigate overall project risk.
• Some large government contracts or contracts that impact local
community development may require the primary contractor to
hire a certain number of subcontracting entities from the
community as part of the contract. • FIDIC
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) • PPA 2011 186

Organized by: Belachew Asteray(PhD) 93


FTVET, 2023 March 2023

2.7. Construction Audit


• Construction Audit is responsible for determining whether
necessary operational and financial internal controls are in place
and operating properly across the construction service.
Organized by: Belachew Asteray (PhD)

• Types of Audits
• Construction Contract Audits
• Process Audits
• Vendor Procurement Audits

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 187

2.7. Construction Audit…


• Construction Contract Audits
• Compliance with contract terms is the focus of this audit.
• A detailed review of the contractor’s invoicing activity is
Organized by: Belachew Asteray (PhD)

completed to insure only allowable costs have been reimbursed.


• Cost recovery opportunities identified in the audit are pursued
with the contractor.
• Audit findings are presented as follows:
• Contractor Related — cost recovery opportunities for contractually
unallowable costs reimbursed
• Project Specific — typically non-functioning internal controls creating
contract non-compliance
• Global — project specific observations which are applicable to a variety
Marchof
2023 capital projects CoTM 525 Organized by: Belachew Asteray (PhD) 188

Organized by: Belachew Asteray(PhD) 94


FTVET, 2023 March 2023

2.7. Construction Audit…


• Process Audits
• A process audit is designed to evaluate the efficiency and
effectiveness of a particular workflow and the associated function
Organized by: Belachew Asteray (PhD)

of the internal controls within the process.


• Examples of available process audits include:
• Bid Process — evaluate compliance with institutional Policies
and Procedures
• Funding Process — confirm funding sources are being utilized
in the manner intended
• System Implementation — serve as a team member to insure
controls are being developed
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 189

2.7. Construction Audit…


• Vendor Procurement Audits
• Operations and Maintenance provides a variety of services to the
institutions dealing with multiple vendors and contract structures.
Organized by: Belachew Asteray (PhD)

• The price of individual transactions is varied.


• Data analysis — objective review and quantification of
General Ledger or Work Order transactions
• Contract Audits — major contracts are reviewed to evaluate
compliance with contract terms
• Process reviews

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 190

Organized by: Belachew Asteray(PhD) 95


FTVET, 2023 March 2023

2.7. Construction Audit…


• Function
• A construction auditor’s primary function is to provide a
systematic and independent examination of data, records,
Organized by: Belachew Asteray (PhD)

operations and performance of a construction project for a stated


purpose.
• For construction auditing this means:
• Contract review for risk mitigation and management
• Compliance with the design and/or construction contract
• Validity of the records for billing, expenses, equipment, etc.
• Accuracy of the calculations for mark-up, insurance, labor
burden, overhead, etc.
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 191

2.7. Construction Audit…


• Benefits of construction audits
• Detection of fraudulent behavior
• Increased accuracy and efficiency for future projects
Organized by: Belachew Asteray (PhD)

• Document Lessons Learned at Close-out


• Auditing should be considered a tool and not a weapon.

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 192

Organized by: Belachew Asteray(PhD) 96


FTVET, 2023 March 2023

2.7. Construction Audit…


• Ethiopian Practice
Organized by: Belachew Asteray (PhD)

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 193

2.7. Construction Audit…


•S
Organized by: Belachew Asteray (PhD)

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 194

Organized by: Belachew Asteray(PhD) 97


FTVET, 2023 March 2023

2.7. Construction Audit…


Organized by: Belachew Asteray (PhD)

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 195

References
• Public Procurement Agency, Standard Bidding Document, 2011
• International Federation of Consulting Engineers
Organized by: Belachew Asteray (PhD)

http://www.fidic.org/
• FIDIC (2010) Conditions of Contract for Construction, For
Building and Engineering Works Designed by The Employer,
Multilateral Development Bank Harmonised Edition, June 2010
• Zewdu Tefera, Lecture Notes for Construction Contracts Course
• Wubishet Jekale (PhD), Lecture Notes for Construction
Procurement Management Course

March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 196

Organized by: Belachew Asteray(PhD) 98


FTVET, 2023 March 2023

Organized by: Belachew Asteray (PhD)

Thank you!
•Questions
•Comments
March 2023 CoTM 525 Organized by: Belachew Asteray (PhD) 197

Organized by: Belachew Asteray(PhD) 99

You might also like