Professional Documents
Culture Documents
02 - Loading, Off Loading and Spotting of Degasser, ADNOC
02 - Loading, Off Loading and Spotting of Degasser, ADNOC
Description of Crane
Description of the endless 2-wire rope sling 60mm x 1.5mtr attached to the Crane Main Hook. = SWL 55.5 Tons each
Description of the Shackle attached to the 2 slings = 2.5” Dia Nut & Bold Bow Shackle (4 Piece) SWL 55 Tons
State the lifting Accessories to be used: (Slings, Jib, Shackles, Eye Bolts, etc.)
4 Legs wire Rope sling with master link having the cap of 13 MT.(HB 10)
4-piece shackles having the capacity of 13.5 MT each serial number (HB10 ((A,B,C,D))
Note: There are Two extra Shackles on the Top Side to enable the load to be lifted Balanced in the Horizontal Position for Transport.
4-piece shackles having the capacity of 8.5 MT each serial number (B78, B71)
To Rig Up.
The slings from the base will be detached and secured. The degasser will be rigged up from the other 4-piece shackles having the capacity of 13.5 MT and wire
TITLE: HALLIBURTON MANAGEMENT
Lift Plan- Critical Lifts SYSTEM
REGION: FUNCTION/PSL: DOCUMENT NUMBER:
SGULF HSE-SQ CL-UAE-HAL-HSE-007B
OWNER: APPROVED BY: REVISED BY: REV. DATE: REV. NO: PAGE:
Area HSE-SQ Area HSE-SQ Manager HSE-SQ Supervisor 05-JAN-2022 2 Page 2 of 4
4 Certified lifting points/ pad eyes having capacity of Max gross Weight 6.8 MT,
Identify and Document the Personnel who will be involved in the Lifting operation:
Crane Operator _____________________________________
Rigger/Banksmen ______________________________________
This is not a definitive checklist but a prompt for items that need to be considered prior to a lifting
Operation taking place, the implications of which need to be incorporated into the lift plan.
6. Physical Dimensions.
7. Outriggers fully extended. 7 Clear of the lift and clear lines of sight
Sequence of steps required to complete the lifting operation Safely Responsible Party
Task Details (step by step)
Site Supervisor or
Task Details (step by step) Designated Lead Person
Loading degasser from truck to wellsite and back loading. Site Supervisor or
Position truck as close and safe is possible to the crane and load. Designated Lead Person,
Position Crane over Center of Lift and Connect to Master Link.
Crane operator
Connect a tag line as needed. Rigger/Banksmen
Gently lift degasser and control the load. Site Supervisor or
Land and secure load at designated place. Designated Lead Person,
Detach Slings from the Base of the Degasser. Crane operator
Slowly lift the load while slowly swinging boom towards the base end until it is completely tilted
to the Vertical Position and base is sitting firmly on the ground.
Slack off Load and detach Slings from Crane. Site Supervisor or
Detach tag lines. Designated Lead Person,
Crane operator
Swing Crane out for Next Lift.
Do in reverse order for Rigging down and Loading onto Truck
TITLE: HALLIBURTON MANAGEMENT
Lift Plan- Critical Lifts SYSTEM
REGION: FUNCTION/PSL: DOCUMENT NUMBER:
SGULF HSE-SQ CL-UAE-HAL-HSE-007B
OWNER: APPROVED BY: REVISED BY: REV. DATE: REV. NO: PAGE:
Area HSE-SQ Area HSE-SQ Manager HSE-SQ Supervisor 05-JAN-2022 2 Page 4 of 4
7. Has the lift plan for non-routine lifts been reviewed with the lift team? ☐ ☐
Are hands free devices such as push/pull poles, tag lines or guide ropes
8.
available? ☐ ☐
Are hands free devices attached to the load and not the rigging? Device Used:
9.
______________________ ☐ ☐
Have no-lift conditions been identified? (e.g., Maximum wind speed, radius,
10.
percent of capacity) ☐ ☐