You are on page 1of 1

 Bahan apron corner ( kayu solid ) sebelum diproses/cutting wajib dicek.

“Before the solid wood apron corner material is processed/cut, it must be checked”.
 Proses pertama cutting finish, selesai proses potong wajib di cek untuk ukurannya sesuai gambar
menggunakan alat ukur meteran.
“The first cutting process must finish, and upon completion, the dimensions must be checked against
the drawing using a measuring tape”.
 Selanjutnya proses kedua groving bagian face dan proses bor untuk lubang baut.

“ Next, proceed with the second process of grooving the face section and drilling holes for bolts”.

 Dan lanjut proses bor countersink bagian back, selesai proses wajib di cek untuk groving tempat
hardware metal dan bor untuk pemasangan bautnya.

“ Followed by the countersinking process for the back section, upon completion, it must be checked
for grooving for metal hardware placement and drilling for bolt installation”.

 Semua devisi wajib cek ulang kelengkapan semua proses dan kelengkapan semua hardware dari awal
proses sampai finish.

“All departments must double-check the completeness of all processes and the completeness of all
hardware from the beginning of the process until completion”.

You might also like