Professional Documents
Culture Documents
Construction Industry
By Uditha Tharanga
BSc (Hons) QS, LLM, MRICS, MAIQS, FCIArb.
https://chamberofconstructionlaw.com/
2
Progress Payment
Suspension/Termination
Finance Charges/Interest
Purpose of progress payment
The Contractor has sufficient cash flow to continue with his works
Motive to maintain proper resources
Reduce unjust results Contractor’s having to wait till end of the project negotiation
In line with Fiscal policy
There are legal precedence mandating Progress payments in Construction
“Instalments payments are in their nature provisional liabilities. As has been frequently
said, they are to provide the cash flow for the contractor or sub-contractor to enable
him to perform his duties under the contract”
Melville Dundas Ltd v George Wimpey UK Ltd [2007] UKHL 18
Progress Payment
Right to make a progress claim and receive progress payment will be
governed by the relevant terms of Contract
Making a progress claim
Assessment of Progress by Engineer/CA/PM
Making a payment to the Contractor
There is no general right unless there is a right in the Contract or Statue
It is implied to the Contract
The Schedule of Payments [Sub-Clause 14.4]
Monthly Claims
Milestone Payment Claims
The Employer’s are not having sufficient fund to discharge Payment obligations
Deliberate Refusal to pay
Pay when paid/Pay if Paid clauses in Subcontract Agreements
Delay Payment certificates by Engineer/CA/ER/PM
Issues related to correctness of Payment certificates/in adequate supporting
information
Contractual clauses that permit to withhold payment due to
Delays, Non submission of Programmes, Defects
Contractual Provisions for
Withholding Payments
Contractual Requirement to
Provide Supporting Information
Can Engineer/ CA / ER reject the Payment Claim due to Error?
Erroneous Payment Claim vs fraudulent payment claim
The Contractor is to act honestly when making payment claims
Fraudulent payment claims has no contractual effect
Evidence of the nature and values of works performed (WIR,
Photographs, Joint site walks)
Some Contractor’s do not supply adequate information
Can we make the certificate condition
Compelled to supply those in dispute resolution procedure
precedent to receiving adequate details
The Engineer can not make assessment if adequate information is
from the Contractor ?
not given to him Solution?
Dispute regarding adequacy of information provided
How does FIDIC manage this?
Contractual Provisions
Supreme Court of California in the case of Wm. R. Clarke Corp. v. Safeco Insurance Company (1997) 15
Cal.4th 882 (Clarke v. Safeco) also in Cosmo Construction, Inc. v. Travelers Casualty
The Main Contractor remains liable to the employer for the
subcontractor’s performance
In many cases, the UAE courts emphasized that the main
contractor remains contractually liable
“conditional payment clause was subject to general principles of contract which require the
courts to have regard to ‘meaning and intention, not mere words’ and to the ‘common interest’ of
the parties Court went on to conclude that: There is no justification for subcontractors to be
concerned with recovering the balance of their dues if they have completed their work”
Thus, with clear wording it remains possible to create a conditional payment obligation
Dubai Cassation No. 281/95 dated 6 July 1996
that survives beyond handover. Conversely, reliance on imprecise drafting or contractual
shorthand is likely to be ineffective
• Suspension of Works
• Termination of Performance
• Financial Charges
Dubai Cassation No. 170/1998 dated 3 January 1998 and Dubai Cassation No. 102/2007 dated 19
June 2007.
“It is for the Court of Merits to determine whether the obligations are mutual
and whether suspension of performance is justified in the circumstances”
UAE Civil Code, Article 272. Bahrain Civil Code, Article 140, Kuwait Civil Code, Article 209,
Oman Civil Code, Article 171 and the Qatar Civil Code, Article 183
• Financing charges are not defined
• Term “interest” adopted in the FIDIC Red Book 4th edition
• If there was no financing in fact, would there be no right to financing charges
and/or interest?
• Experts (England & Wales) suggests that if Sub-Clause 14.8 is deleted, The Late
Payment of Commercial Debts (Interest) Act 1998 may apply under English law
• Although it is accepted by Islamic jurists that riba is prohibited absolutely
• There is no consensus on precisely what constitutes riba. Excessive interest or
usury is widely accepted as an indicator
- Financing charges are the costs of money
- practice in the construction industry for contractors and
subcontractors to resort to a claim for financing charges
- Interest is permitted on the basis that this represents
Compensation for ‘presumed’ damage for delaying
payment
- Financing charges are more typically a component of a
damages claim
- The provision of evidence to satisfy the burden of proof
that financing charges have been incurred by virtue of
non payment
- Read the Contract carefully to identify your rights,
obligations and risks
- Seek Expert opinion prior to Suspension and Termination
- The identifying and proving time impact/losses and
Expenses due to delay payments are challenging
- The Presentation is not alternative to any
legal/Contractual advice
- The circumstance of the each case need to be
considered
- Do not forget to leverage and Negotiate
Uditha Tharanga
BSc (Hons), LLM, MRICS, MAIQS, FCIArb
Email : udtharangaw@gmail.com