Professional Documents
Culture Documents
wtc2015 Full Dalnegro
wtc2015 Full Dalnegro
Keywords: Monte Ceneri Base Tunnel, Consorzio Condotte Cossi, Mapei UTT, Sigirino (CH),
superplasticizers and accelerators for shotcrete.
1. Introduction
The Monte Ceneri Base Tunnel is the southernmost portion of the new Alp Transit Railway Line
crossing the Swiss Alps from South to North. After the Gotthard and Lötschberg Base tunnels,
Ceneri Tunnel is the third largest railway tunnel project with his 15.4 km length. Tunnel project
allows fast connection for passengers travelling through the Alps, both reducing goods-traffic
through Switzerland. This important route will make possible to use long, heavy trains to ensure
optimal connections through the Alps and will also shorten passenger-journey time between Zurich
and Milan. The works were commissioned by AlpTransit Gotthard Ltd on behalf of the Swiss
Confederation. In April 2005 the preliminary work began in Sigirino and Camorino on the basis of
the plan approved by the Swiss Department for the Environment, Transport, Energy and
Communicatons. The Consorzio Condotte Cossi (a Consortium of companies formed by Società
Italiana Condotte d’Acqua S.p.A., Cossi S.p.A. and LGV SA) is the contractor of the main section of
the CBT (named Lot 852), consisting in the excavation of two parallel tunnels simultaneously
attacked (northwards and southwards) by the intermediate side-adit of Sigirino (FIS). The side adit
is located roughly in the middle of Ceneri Base Tunnel, consequently divides the twin tunnel into
two parts of similar length (about 2x8 km in north direction and approximately 2x6 km in south
direction).
Jobsite assignment and subsequent excavation works began in 2008, within the contract section
Lot 852. The side adit of 2.308 km-long has been excavated using a TBM, while the main railway
tunnels (CBT) have been excavated by
drill&blast advancing method. A total
length of about 40 km has been
excavated by drill& blast: entire tunnel,
cross-passages, exploration tunnels,
caverns, etc. This paper focuses on
the cooperation held between
Consorzio Condotte Cossi and
technical assistance of Underground
Technology Team division of Mapei,
especially with reference to muck re-
utilization jointly with the technical
assistance and supervision supplied.
More than 80% of the two tubes of
the 15.4 km Ceneri Tunnel has been
excavated at the end of December
Fig. 1 Panoramic picture of access adit Sigirino (FIS) job-site for 2014. So far, also due to the
the CBT Project. cooperation between all the
stakeholders, the project for the
Ceneri Base Tunnel is maintaining cost and timetable predefined in previous design stage. Mapei
has been supplying concrete superplasticizers and accelerators for shotcrete since 2010 for this
important railway project in the Alps. During the excavation and construction of the tunnels and
„SEE Tunnel:Promoting Tunneling in SEE Region“
ITA WTC 2015 Congress and 41st General Assembly
May 22-28, 2015, Lacroma Valamar Congress Center, Dubrovnik, Croatia
cross passages, the use of chemical materials supplied by Mapei has been essential to ensure
efficiency, durability, safety and a sustainable approach to construction. The excavation of the CBT
tunnel is scheduled to be completed in 2018 and the flat route through the Alps will be in
operation by 2019.
3.1 Main Characteristics of the CBT project related to the sprayed concrete
The CBT consists of two parallel twin tube 15.4 km-long. Tunnel cross section area varies from 60
m2 to 300 m2 in correspondance of two big Cavern lacatd along the Tunnel in south direction (Sarè
Caverns). Tunnels are connected by cross-passages each 325 m, for a total number of 48 cross-
passages. No crossovers or multifunction stations are foreseen. The two bores have a standard
distance between tunnel axes of 40 m with a maximum distance of 210 m. The overburden of the
tunnels varies from 10 m to a maximum of 800 m. The cycling works realized for the construction
are the following: excavation (by drill&blast method and mechanical excavators), transport of the
mucking to the crusher, application of sprayed concrete primary support reinforced with or without
fibers to realize the concrete lining of the tunnels. Especially the advancement of the full section in
the unfavourable rock conditions has been done by the placement of the primary support with the
use of steel ribs and anchors for confinement and soil consolidation, followed by the sprayed con-
crete in thicknesses of 25-30 cm in successive layers. The concrete is produced in a big concrete
plant set up in the CAOP “Operative Cavern” located in an underground cavern (system of cham-
bers located at the end of Sigirino Adit). This decision to place the concrete plant underground was
made for construction logistical reasons. The aggregates are supplied by a conveyor system di-
rectly from a dedicated train station located near the job site. Concrete is prepared in a mixing
„SEE Tunnel:Promoting Tunneling in SEE Region“
ITA WTC 2015 Congress and 41st General Assembly
May 22-28, 2015, Lacroma Valamar Congress Center, Dubrovnik, Croatia
plant, then transported to the tunnel for the spraying application. The spraying process used was
the wet method both for safety reasons and to obtain more homogeneous concrete layer able to
respect the technical specifications. Table 1 shows the main project data.
Table. 1 Project data – Construction of the CBT
Conventional Driving Data - Daily advance rate The advantages of wet method in
Total length of the entire tunnel 39.780 km comparison to the dry one are re-
Length of the Ceneri Base Tunnel 15.45 km sumed as follows: lower dust produc-
Length of blast 1.5 to 4 m tion, higher spraying efficiency, lower
Maximum advance rate 12 m/wd energy consumption and better ho-
Average advance rate in favorable rock condi- 5.8 m/wd mogeneity of the concrete properties.
tions
Today, particularly in European coun-
Average advance rate in unfavorable rock condi- ca. 2.6
tions m/wd
tries alkali free accelerators are re-
Tunnel boring machine drive (TBM) – FIS Sigirino quired according to the European
Excavation diameter in TBM-driven tunnel 9.70 m standards and the increase in the
sections market is due to the health risks con-
Length access adit Sigirino (FIS) 2.308 km nected. The term alkali-free has the
meaning that the accelerator does not
contains alkali cations. Alkali-free product can satisfy following requirements:
improved durability by reducing the risk of alkali-aggregate reaction, by reducing or even
eliminating the alkalis present in the common alkali silicate and aluminate accelerators;
improved safety conditions of the working environment by reducing accelerator
aggressiveness in order to avoid skin burns, loss of eyesight and respiratory health
problems;
positive environmental impact by reducing the amounts of soluble components in sprayed
concrete and its rebound that are harmful to ground water;
reduction in the loss of concrete final (long-term) strength, which is typically in the range
of 15 to 50% for concrete sprayed with alkali-rich accelerators;
continuous and consistent early age strength development of concrete during the critical
intermediary construction phases, reduction of construction costs;
cleaner and safer job conditions: reduce dust generation and rebound, lower leaching of
alkali ions, higher long term performances of sprayed concrete with the control of quality
and productivity.
In the CBT the wet shotcrete technology employed accelerators with alkali-free characteristics able
to develop and increase the early strength of concrete. The wet methods provide the use of liquid
flash setting accelerators which are pumped to a nozzle and immediately projected to the rock
substrate.
Shotcrete is widely used as rock support in civil engineering projects also for the CBT project in the
Lot 852 sprayed concrete was applied to guarantee the advancement of excavation works in
safety condition.
The main purpose was to consolidate tunnel face with the use of high performance sprayed
concrete.
The type of shotcrete was determined on the basis of the different section types encountered
during the excavations based on predominant features of rock mass.
The internal lining of the section excavated by drill&blast is normally not reinforced. Reinforcement
are only used in presence of geologically sensible and or geometrically complicated area, such as
the Val Colla Area or transversal tunnels crossings.
Moreover the stability of the optimized horseshoe-shaped cross-section is guaranteed by 10 cross-
section types, from SPV1 to SPV10 based on geological and geotechnical conditions and on
probable risk scenarios (falling rocks, loosening, detachment of rock wedges, plastic deformation,
tunnel face instability).
Section types present a different excavation geometry, number and type of rock bolts (friction type,
grouted anchor), shotcrete thickness and steel ribs (from SPV5 to SPV10). Three different
geometries are foreseen for tunnel section: base slab, curved base slab and circular invert.
„SEE Tunnel:Promoting Tunneling in SEE Region“
ITA WTC 2015 Congress and 41st General Assembly
May 22-28, 2015, Lacroma Valamar Congress Center, Dubrovnik, Croatia
Fig. 6 Section type (SPV 4) utilized for the project. (Cross section and Longitudinal profile )
between the shotcrete and the rock was one of the most important properties required. Other re-
quirements for Sprayed concrete quality for this project were: high economy due to rebound re-
duction, increase in compressive strength and tensile bond strength, thicker sprayed layers due to
increased cohesion, better waterproofing and high frost and freeze/thaw resistance.
Table. 2 Technical basic requirements of the CBT
The main requirements that were
respected are summarized in the
Type of shotcrete CPG SB1/ CPG SB2/ CPG SB3/ CPG SB4
following table 2.
Destination Use L1 (for SB1,SB2) L2 / L3 (for SB3,SB4) Generally in sprayed concrete technol-
Waterproofing under 1/400 1/200 1/400 1/200 ogy application setting times and me-
pressure (m3) (SB1) (SB2) (SB3) (SB4) chanical strength developments are
Strength Development J2 (SIA 198, annex B) the most important factors. The main
Compressive Strenght (28 days) C20/25 – C25/30
Preliminary Tests Yes
types of sprayed concrete for the tun-
W/C < 0.5 nel were with high performance con-
Granulometry 8 mm crete (CPG): CPG SB1: securing the
Type of cement 42.5 II ALL work zone L1 (according to SIA 198),
Workability time 2 hours
CPG SB3: lining and safety works in
Cement content 425 kg/m3
Consistence Class F5 (560-620 mm) areas L2 / L3 (according SIA198). The
conditions established in the technical
specifications before starting the projects and works are respected.
Many tests were carried out by the Underground Technology Team both on mortar samples in
Mapei R&D laboratory of Milan and in the job-site in order to establish the perfect type of products
related to: type of cement and type of aggregate, water-to-cement ratio (W/C), consistency, tem-
perature, etc. Those tests were carried out to reach performance and to confirm that the right
materials had been selected in order to demonstrate the effectiveness of the proposed system and
to establish the Mix-design. Figure 8 shows an application of shotcrete lining in a cross-passages.
During the excavation works Technical Assistance of Mapei UTT has kept under control:
performances of the automatic pump for sprayed concrete;
accelerator consumption in relation to shotcrete pumping ;
temperature;
properties of concrete and water eventually added;
checking of the strength development of concrete sprayed;
timing and speed of production rate;
state of the equipment.
Many trials and preliminary tests were performed primary and secondary lining by Mapei Team to
demonstrate the achievement and overcoming of all requirements, as indicated in the SN EN 206-1.
Also, periodically in accordance with SN EN 206-1 were subjected at the production controls with
all measures to ensure shotcrete performances. Also, all the compliance checks have been fulfilled.
4.2 Alkali-free accelerator products used in the CBT tunnel for shotcrete.
In order to guarantee good and durable performance during the shotcreting phases, Mapei UTT
provided a wide range of products (superplasticizers, accelerators etc..).Two types of products
were used in different times and for different types of lining. Two different types of alkali-free
agents were used to speed up and accelerate the setting process: MAPEQUICK AF 1000 for “ordi-
nary” working conditions and MAPEQUICK AFK 888 when the early resistances were required in
case of extremely case of securing during excavation through problematic geological condition (es:
Val Colla ). The shotcrete was set in place in one single uninterrupted operation.
The shotcrete with development curve J2 has required the use of the setting accelerator based on
liquid inorganic salts without alkali, MAPEQUICK AF 1000. Thanks to its high accelerating action
allows to obtaining quality shotcrete with high mechanical strength at very short curing times (un-
der 60 minutes), short (60 minutes to 24 hours ) and long stages of curing. The absence of alkali
allows to reduce the risk of ignition of the alkali-aggregate reaction and avoid leaching phenomena.
Thus ensures fast setting and hardening rates and, at the same time, good resistance strength
ratings (at 28 days Rck=40-50 N/mm2) quicker setting time with a very low rebound.
For the shotcrete with development curve J3 was adopted another setting accelerator liquid, the
MAPEQUICK AFK 888, which is also free of alkali and can be used with the presence of water in
the tunnel. Due to its even quicker setting time, it produces self-supporting cast concrete in a high
resistance strength. Such an high-
performance concrete (at 28 days
Rck=40-50 N/mm2) allowed to control
convergence in the tunnel cavity even
in presence of unstable materials.
Figure 9 shows the shotcrete works.
The accelerator rate was chosen in
order to have a good adhesion of the
sprayed material on the rock wall. The
dosage employed for the first type
MAPEQUICK AF 1000 were 6.5% and
the second one MAPEQUICK AFK 888
were 9% by cement mass (normally
the dosages depend on cement and
accelerator type and for the perform-
Fig. 9 Shotcrete works in safety condition in a single attack face. ance as specified in the technical spe-
cific). According to the practice and
job-site experience, shotcrete in the phases immediately after application needs an initial and final
setting times able to guarantee self-sustaining performance with a low rebound rate. In this specif-
ic case, the dosage tested and chosen of accelerants has allowed the achievement of the stand-
ards considered necessary to perform the shotcrete in safety condition with a minimum percentage
„SEE Tunnel:Promoting Tunneling in SEE Region“
ITA WTC 2015 Congress and 41st General Assembly
May 22-28, 2015, Lacroma Valamar Congress Center, Dubrovnik, Croatia
of rebound. Also the most important guidelines (EFNARC, CEN, and Austrian Concrete Association)
have been followed by Technical assistant of Mapei UTT and job-site personnel for the application
of sprayed concrete. Thus the efficiency of the alkali-free setting agents have allowed a safely and
quickly advance within the difficult excavations conditions of the job-site.
5.1 Measurements of the sprayed concrete early strength for mixes with both types
of aggregate.
In the CBT for the measurement of the sprayed concrete compressive strength at the job site was
used Standard SN EN 206-1 according to the specifications required by the project. The early
strength classes J1, J2 and J3 are derived from the Austrian Concrete Society: Code of Practice for
Sprayed Concrete, is used to define the behavior of the early strength (concrete with a maximum
age of 24 hours). Test methods specifications of Österreichischer Betonverein (Austrian concrete
association) was followed. The method basically consists of correlating the initial strength
development of fresh shotcrete to the penetration of different size needles (depending on defined
strength classes) in sprayed concrete specimens and to measure the compressive strength by
needle penetration methods. The resistances were measured as follows: with penetrometer needle
up to 1 hour, with 103 mm nails and green cartridges after 6 hours and with 60 mm nails and
green cartridges after 24 hours. The early strength of the young concrete is explicate through the
curves J1, J2 and J3. The J1 class is considered to be applied only in case of stable rocks. But in
the case of CBT project, at least the class J2 must be used. Also, in special section is used the
class J3 especially in the case of unstable faces. In order to evaluate the strength development a
standard box with dimension of: 60x60x25 cm is filled with shotcrete. The control must be
completed within the first 60 minutes taking a needle penetrometer according to the recently
„SEE Tunnel:Promoting Tunneling in SEE Region“
ITA WTC 2015 Congress and 41st General Assembly
May 22-28, 2015, Lacroma Valamar Congress Center, Dubrovnik, Croatia
released UNI EN 14488-2 “Testing sprayed concrete - Part 2: Compressive strength of young
sprayed concrete” and with the range resistance expected.
The resistance values of the compressive strength at early curing ages till the first hours (when
the samples are still too soft) is measured with the digital penetrometer.
Then the values is obtained by relating the depth of insertion of nails, by means of the gun nail
HILTI DX 450 and using green cartridges, special nails are used to measure the mechanical
resistance (from 6 hours to 24 hours).
Each resistance value is the average of ten measurements (firing and extraction of the nails)
performed in ten different points on the surface of the sprayed concrete box. Generally results
are plotted in graph with superimposed onto the J-curves specified by the Austrian Concrete
Association. Sprayed concrete falling in the J1 envelope are considered to be suited for placing in
thin layers, on a dry rock substrate, and no load-bearing capacity is required. However, if concrete
is to be sprayed in thick layers, overhead, at high delivery rates, and sustain immediate loading,
then it must have a strength development that falls in the J2 envelope. J3 sprayed concrete
typically exhibits rapid development of high early strength, and this typically leads to dust
formation and high rebound, which can cause health and environmental risks. In this case in order
to achieve J3 and J2 behaviour (depends of the type section we worked), concrete is sprayed with
accelerators. Therefore, it is strictly specified by the EFNARC, CEN, and Austrian Concrete
Association guidelines that only alkali-free accelerators should be used for spraying concrete falling
in the J3 category. At later curing ages (when the samples be-come harder), the mechanical
strength is measured according to the EN 196/1 by a compressive test machine.
Figure 10 shows the comparison of
the compressive resistance evolution
curves in the class J2 and J3, of the
two type of superplasticizer versions
in combination with the two alkali
free accelerators MAPEQUICK AF
1000 and MAPEQUICK AFK 888 for
shotcrete (with the same quantity
admixed of the percentage of recy-
cled aggregate and external aggre-
gate) The prefix “DYSXMC(1)” indi-
cates the first version of superplasti-
cizer and with “DYSXMC(2)” it is indi-
cates the second version of super-
6. Conclusions
The salient aspect of this project is the collaboration between Mapei and Consorzio Condotte Cossi,
mainly with the promotion and the management of excavated materials, possible thanks to
logistics of the construction site both outside and inside the tunnel as well as the development of
important high-tech sprayed concretes. The Underground Technology Team, has been always
present at the jobsite, to ensure a specialized technical support and facilitate the construction work
in relation to different aspects of the conventional excavation. Mapei UTT was an active part in the
supply of the materials used for the production of the sprayed concrete as primary support and for
„SEE Tunnel:Promoting Tunneling in SEE Region“
ITA WTC 2015 Congress and 41st General Assembly
May 22-28, 2015, Lacroma Valamar Congress Center, Dubrovnik, Croatia
final support of the completed tunnel. The application of a high quality sprayed concrete, by the
use of an alkali-free accelerator and superplasticizer, allowed to achieve very rapid setting times
and therefore safe working conditions and the quick development of mechanical strengths,
according to the job site requirements. In this case, Consorzio Condotte Cossi created the
conditions for optimum works progression, particularly focusing to a good selection of plants,
concrete trucks, pumps and trained nozzle man: the result were primarily construction cost savings
and improvement of safety. Essential economical and safety aspects have also been taken into
account for the CBT, granting better condition and improved safety, both maintaining the required
heading performance, deadlines and costs. Also, this new Rail Link through the Alps led to a
rationalization of the construction sequences, to a remarkable increase in productivity.
The technologies used for the development of this project have been of great importance in the
international area, due to the special attention to environmental protection orientation, durability
and safety of the works. Finally, the Ceneri Base Tunnel is one of the first project where the good
quality rock was recycled and used as aggregate for concrete and shotcrete within the tunnel.
References
[1] EFNARC. 1999. “European Specification for Sprayed Concrete”, European Federation of Producers and Applicators
of Specialist Products for Structures. Österreichischer Betonverein. October 1998. Guideline Sprayed Concrete,
Richtlinie Spritzbeton “Anwendung und Prüfung”, 1040 Wien.
[2] http://www.alptransit.ch/en/project.html
[3] GROSSO N. “Aspects of Geological Risks in Advancing with High Overburden Ceneri Base Tunnel “Swiss Tunnel
Congress 2012.
[4] AUSTRIAN CONCRETE ASSOCIATION, Sprayed Concrete Guideline, Wien, March 1999
[5] MALTESE, C., CERULLI, T., PISTOLESI, C., SALVIONI, D., DAL NEGRO, E., and HANSEN, R. September 2002.
“Alkali Free and Alkali Rich Accelerators for Shotcrete: Effects on Cement Hydration.” Fourth International
Symposium on Sprayed Concrete, Davos, Switzerland, 238-252.
[6] ZAFFARONI, P., PISTOLESI, C., DAL NEGRO, E., COPPOLA, L., and COLLEPARDI, M. 2000. “High Performance
Shotcretes” Sixth Canmet/ACI on Superplasticizers and Other Chemical Admixtures in Concrete, Supplementary
Papers, Nizza, Francia, p.55-64.
[7] SANTARELLI S., CAMEROTTO A., GROSSO N. “Galleria di base del monte Ceneri uno scavo in tradizionale ad
elevate meccanizzazione” October 2014.Expotunnel 2014 (BO) Convegno SIG.
[8] Österreichischer Betonverein (Austrian concrete association, Sprayed Concrete Guideline, Wien, March 1999)