Downpayment Recoupment should be applied in progress billing
o Example: 30% DP, 10% progress billing (2m accomplishment, 20m project cost) o 2m minus downpayment recoupment (2m minus 30% of 2m) minus 10% of 2m o What will be left is 2m – 600k minus 200k (they will pay us this) o Formula: accomplishment less 30% of accomp less 10% of accomp o We will keep doing this up until 100% o We will produce guarantee bond (redeem 10% retention)
21.7m project cost
6.51m DP to start
Progress billing: 10%
2.17m every progress bill- 651k (30% of 2.17m) – 217k (10% of 2.17m)