Professional Documents
Culture Documents
BP104
August 2019 Vertical level controls
Mobrey
Vertical level controls for
industrial steam boilers
Switch support
rod Switch unit position
4-way terminal is variable between
marked AA and BB stops on support rods
one per switch unit
Switch head
assembly
Earth terminal
Two 25mm
BS4568 cable
entries
Band indicating
lowest possible Band indicating
operating level lowest possible
operating level
Monel metal float
Monel metal
float
Blow down
connection
Introduction surrounding the float.
It is normal practice to use two independent machines on (iii)Positioning of the controls relative to heating surfaces,
each boiler, one incorporating the pump switch or switches feed water inlets and sparge pipes, steam take-off points.
and first low water cut-out alarm switch, the other with Close proximity to any of these is to be avoided.
either one switch to provide second low water cut-out and
alarm, or two switches to provide second low water cut-out Advice is available to whatever extent possible but no
and high level alarm. responsibility can be accepted for final installations.
Guide tubes are not included with the supply of the
Operation MOBREY Air Break Vertical Control.
A primary permanent magnet attached to the float rod Where necessary the control may be offset from the
slides vertically inside a non-magnetic stainless steel vertical centre line of the boiler in order to avoid the
centre tube and transmits the movement of the float to a furnace or smoke tubes. Where difficulty is met in
secondary magnet in each switch unit. Self-holding switch positioning the guide tube due to the proximity of the
units, located on vertical support rods in proximity to the furnace or smoke tubes the complete mechanism can be
centre tube and positioned by clamp screws, have two lifted provided sacrifice of some of the range adjustment is
pairs of contacts which are operated with a snap action acceptable.
and held by repulsion between the secondary and tertiary
Figure 2
magnets of the switch unit assembly. Single 2 or 3 2 or 3 2 or 3 2 *Continental
Switch Switch Switch Switch Switch designs
62 *120 150 *215 250 only
Installation - external mounting 350
1. Remove all tapes sealing the steam and water Figures in box = Range %
connection holes, and the tapes and packing around the Control range (mm) 250
float assembly, taking care to cut the securing string. 200 55 125
25 50
Note: It will be necessary to withdraw the mechanism NWL
150
from the float chamber in order to remove the packing, see 30 25 38
NWL
25 NWL
“Periodical check” page 7. Care should be taken not to 100 Mean NWL 160 125
bend the float rod. 25
16 operating
75 50
50 level
2. Mount the machine on the boiler and check that the 46 75 90 75 112
level
correctly. See Figures 1, 2 & 14.
Pump control Combined pump Combined
It is important that the MOBREY Vertical Level Control or high or low control and low high and low
operates within the visual limits of the gauge glass at all level alarm level alarm level alarms
Page 2
Method of determining float rod length
Standard Float Rod length for all machines 762mm.
1. Find lowest operating position of the control below
the required operating level by using recommended
percentage of nominal range - see page 2.
2. Check that this lowest operating position does not
uncover any heating surface.
3. From the dimensions of the boiler fill in dimension ‘B’.
4. From GRAPH 1 page 3 find constant ‘K’ for the float
size to be used.
5. Add ‘B’ and ‘K’ to find total rod length ‘L’.
6. If using 152 x 64 float check from GRAPH No. 2 that
the maximum rod length ‘L’ has not been exceeded for
the boiler working pressure.
Page 3
Operation of Hydraulic Test Device Method of determining float rod length with hydraulic test
The pump control must be overridden in order to start the device
feed water pump. A hand start push button for the feed Standard float rod length for all machines 1016mm
pump contactor starter is recommended so that the 1. Find lowest operating position by using
operative must hold it “on” during the test. recommended percentage of nominal range.
Opening the test device stop valve will allow water to flow 2. Check that this lowest operating position does not
into the control where it is directed into the cup fixed to uncover any heating surface.
the float rod, causing it to sink. The stop valve should be 3. From the dimensions of the boiler determine
closed when the alarm sounds. The water in the cup will dimension ‘B’.
drain away and the float will return to its original position. 4. From GRAPH 3 find Constant ‘K’ for the float type
to be used.
5. Add ‘B’ and ‘K’ to find total length ‘L’.
6. Check from GRAPH No. 4 that the maximum rod
length ‘L’ has not been exceeded for the boiler
working pressure.
NOTE : Maximum rod length 1016 for all cases.
7. Check that the distance between underside of
flange and highest water level is not less than
minimum shown.
8. Calculate guide tube dimensions :
Length = 8 + 180
Minimum Inside Dia. = Float diameter + 13
9. Check clearance between guide tube and heating
surface (recommended minimum 25).
Electrical Characteristics
Important:
The temperature of the switch head may at times approach
the temperature of the boiler and suitable heat-resisting
cables should therefore be used.
Electrical connections
Page 5
Boiler Steaming Weekly routine
1. Switch on the electric supply To test low water alarm and cut-out switch
When fitted with Mobrey sequencing valve: Shut off the feed water to the boiler, either by closing
2. a). Slowly open steam isolating valve. down the feed pump or in certain cases closing the feed
b). Operate sequencing valve fully anti-clockwise to valve.
open. With a competent attendant standing by, allow the water
or level to fall by evaporation until the low alarm level is
When fitted with separate isolating and blow-down valves: reached. At this point the machine should operate the low
a). Check that the blow-down valve is open. alarm and the firing apparatus should cease to operate.
b). Slowly open steam isolating valve With the feed pump under hand control, restore the feed
c). After a period of at least 15 seconds, slowly water to the boiler. Upon a short rise in water level the
open water isolating valve. low alarm should be re-set and the firing apparatus should
d). Slowly close blow-down valve. commence to operate. Restore normal feed water control
3*. a). Raise the water level in the boiler to a point to the boiler.
where the highest switch unit should operate Any change in operating level from the set positions may
for a rising water level condition. be indicative of blocked connections to the float chamber,
b). Check that the switch and its associated a waterlogged float or a loose switch unit and should be
circuit operate correctly. investigated immediately.
c). Drop the water level in the boiler to a point To test pump control switch
where the lowest switch unit should operate for a Under normal operating conditions:
falling water level condition. a). Allow the water level to rise until the ‘Pump Cut-
As the level falls, check that all switch units and out’ level is reached. At this point the pump should stop.
associated ciruits operate correctly and at the b). Allow the water level to fall until the ‘Pump Cut-in’
desired levels. level is reached. At this point the pump should start.
If it is necessary to adjust the levels : To test high water alarm
1. Loosen the centre screw and remove the switch a). With the feed pump under hand control, allow the
head cover. water level to rise until the high alarm level is reached. At
2. Position switch units to provide operation at water this point the alarm should operate.
levels desired within a range of the control when it b). Shut off the feed water. After a short fall in water
has been mounted on the boiler. Loosen the level, the high alarm should re-set.
clamp screw(s) of the switch unit(s) and adjust the c). Restore normal control of feed water to boiler.
switch unit(s) to the required level(s) on the vertical Warning :
support rods to provide pump control and/or alarm(s). Any unauthorised interference or modifications to the
Note : Switch unit clamp screw(s) must be securely mechanisms of these machines can be detrimental to their
tightened after the adjustments to the switch unit(s) are correct operation.
made.
3. Replace cover and tighten screws. “Periodical check”
The above procedure will ensure that the switch units are At such times as the boiler plant is inspected MOBREY
operating correctly. Vertical Level Controls should be dealt with in the
The control is now ready for use. following manner :
After replacing a fuse in a level control or alarm circuit 1. Isolate the float chamber from the boiler. (See
following a failure, carry out the operation in Paragraph 3*. “Commissioning and operating instructions” to put the
control out of operation).
To put the control out of operation 2. Remove nuts holding chamber cover to chamber and
1. Switch off the electric supply. lift away the complete switch head, chamber cover and
When fitted with MOBREY Sequencing valves : float assembly, locating it temporarily by means of one
2. a). Operate sequencing valve fully clockwise toclose. stud over the edge of the float chamber.
b). Slowly close steam isolating valve. 3. Remove clip securing stop cap and withdraw float
or assembly.
When fitted with separate isolating and blow-down valves : Important
a). Slowly open blow-down valve; The magnet must not touch any magnetic material such as
b). Slowly close water isolating valve; the float chamber, tools, steel benchtops, etc., and the
c). Slowly close steam isolating valve; assembly must only be put down in a clean place where
there is no danger of the magnet collecting magnetic
Operational tests particles.
Daily routine 4. Check that the float is not waterlogged. Examine float
It is important that the control should be blown down at rod for alignment and wear. Check that the float locking
least once per day while the boiler is under pressure. nut is tight and ensure that the whole assembly is clean
An operating Instruction Card BP/109 suitable for and free from deposit. Offer float rod assembly magnet
permanent display in the boilerhouse is available on into centre tube and check that it moves freely up and
request. down. Withdraw float assembly and put to one side.
Page 6
5. After ensuring that the unit is isolated electrically, Methods of Mounting
withdraw screw on top of switch head and remove cover.
6. Examine the ceramic body for damage or cracks.
Ensuring that wiring is in good order and that all screws Side and bottom entry
are tight. Dismantling of switch units is not recommended chamber with sequencing
and replacment of the complete switch unit will be found
blow down valve
to offer the quickest and most economical solution in the
event of faulty operation.
7. a) Examine valves and pipe connections between
float chamber and boiler to make sure they are clean.
Reseat and repack stop valves if necessary.
b) Check that the chamber is clean and position a new
joint in its recess in the chamber.
c) Check that the inside of the centre tube is clean
and that no swarf is attached to the float magnet.
Before refitting the switch head and chamber cover Side and side entry
assembly to the chamber it is essential that the switch continental chamber
head is checked for correct operation. N.W.L
d) Fit the float rod assembly with its magnet into the
centre tube and secure the stop cap with the clip
provided.
e) Move the float assembly slowly to the top of it
travel.
f) Lower the float assembly slowly, checking that Side and bottom entry
the switch units are operated by the float rod magnet as it chamber with sequencing blow
passes them. down valve on vertical boiler
g) Replace switch head cover and tighten securing screw.
h) Position the switch head complete with float on to the
chamber, securing the cover with the nuts.
Switch units
If a switch unit is adjusted or replaced (at any time) it
must be checked according to the operating instructions Side and side entry
or the instructions covering periodical checks. chamber on steam drum
of water tube boiler
Figure 14
Page 7
Installation / Operating Leaflet
BP104
Vertical level controls January 2006