You are on page 1of 18

-~..--.-.

ular & Stabilised Subbase,


__,__e & Stabilised Subgrade

copy 152
Ref. Title Page No.
3.1 Materials for Sub-Base and Base
Courses 3-1
3.1.1 Desc.-iption 3- 1
3.1.2 Materials 3-1
3.1.3 General Requirements for Materials 3-1
3. 1.3. 1 Sources and Production 3-1
3. 1.3.2 Stockpiling 3-1
3. 1.3.3 Sampling and Testing 3-1

3.2 Granular Sub-Base Course 3-1


3.2.1 Description 3-1
3.2.2 Materials 3- 1
3.2.3 Construction Requirements 3-2
3.2.3 . 1 Sub-grade Surface Preparation 3-2
3.2.3 .2 Equipment 3-2
3.2.3.3 Construction ofTrial Sections 3-2
3.2.3.4 Stockpiling of Granular Material 3-3
3.2.3.5 Mixing and Spreading 3-3
3.2.3.6 Compaction 3-3
3.2.3.7 Tolerances 3-3
3.2.3 .8 Maintenance of Completed Sub-base 3-4
3.2.3.9 Testing 3-4
3.2.4 Method of Measurement 3-4
3.2.5 Basis of Payment 3-4
3.2.6 Items in the Bill of Quantities 3-4

3_3 Aggregate Base Course 3-4


3.3.1 Description 3-4
3.3.2 Materials 3-4
3.3 .2. 1 Crushed Stone Aggregate 3-4
3.3.3 Construction Requiremen ts 3-5
3.3.3.1 Surface Preparation 3-5
3.3 .3.2 Equipment 3-5
3.3.3.3 Construction ofTrial Sections 3-5
3.3.3.4 Stockpiling of Aggregate Materials 3-5
3.3.3.5 Mixing and Spreading 3-5
3.3.3.6 Compaction 3-6
3.3.3.7 Tolerances 3-6
3.3.3.8 Maintenance of Completed Base Course 3-6
3.3.3 .9 Testing 3-6
3.3.4 Method of 1easurcment 3-7
3.3.5 Basis of Pa yment 3-7
3.3.6 Items in the Bill of Quantities 3-7

copy 152
Ref. Title Page No. Ref. Title Page No.
3.4 Stabilized Base Courses 3-7 3.4.3.21 Lime Stabilization Procedures - Mixed in Place
Procedures 3-11
3.4.1 Description 3-7
3.4.3.22 Lime Stabilization Procedures - Placing and
3.4.2 Materials 3-7
Spreading Stationary Plant Mixes 3-12
3.4.2. 1 Soil for Stabilization 3-7
3.4.3 .23 Lime Stabilization Procedures - Compaction and
3.4.2.2 Cement as Stabilizing Agent 3-7
Finishing 3-12
3.4.2.3 Bitumen as Stabilizing Agent 3-8
3.4.3.24 Lime Stabilization Procedures - Tolerances and
3.4.2.4 Lime as Stabilizing Agent 3-8
Replacement of Unsatisfactory Areas 3-12
3.4.2.5 Water 3-8
3.4.3.25 Testing of Lime Stabilized Courses 3-12
3.4.2.6 Mix Design for Cement Stabilized Base 3-8
3.4.4 Method of Measurement 3-12
3.4.3 Construction Requir·ements 3-8
3.4.5 Basis of Payment 3-12
3.4.3.1 Surface Preparation 3-8
3.4.6 Items in the Bill of Quantities 3-12
3.4.3.2 Construction of Trial Section 3-8
3.4.3 .3 Cement Stabilization Procedures - Plant Mixing 3-8 3.5 Recycled Aggregates for Roadworks 3-12
3.4.3.4 Cement Stabilization Procedures - Batch MixingJ-9
3.5.1 Description 3-12
3.4.3.5 Cement Stabilization Procedures - Continuous
3.5.2 Materials 3-13
Mixing 3-9
3.5.2. 1 Aggregate Material 3-13
3.4.3.6 Cement Stabilization Procedures - Mixed in Place
3.5.2.2 Sampling and Testing 3-14
Procedures 3-9
3.5.3 Construction Requirements for Recycled Fill,
3.4.3.7 Cement Stabilization Procedures - Placing of
Subgrade and S ubbase Course Layer·s 3-14
Stationary Plant Mixes 3-9
3.5.4 Meth od of Measurement 3-14
3.4.3.8 Cement Stabilization Procedures - Compaction and
3.5.5 Basis of Pa yment 3-14
Finishing 3-10
3.5.6 Items in the Bill of Quantities 3-14
3.4.3.9 Curing of Cement Stabilized Courses 3-10
3.4.3. 10 Testing of Cement Stabilized Courses 3-10
3.4.3 . 11 Bitumen Stabilization Procedures - Mix DesignJ-1 0
3.4.3. 12 Bitumen Stabilization Procedures - Stationary Plant
Mixing 3-11
3.4.3.13 Bitumen Stabilization Procedures - Mixed in Place
Procedures 3-11
3.4.3.14 Bitumen Stabilization Procedures - Placing and
Spreading Stationary Plant Mixes. 3-11
3.4.3.15 Bitumen Stabilization Procedures - Compaction and
Finishing 3-11
3.4.3. 16 Bitumen Stabilization Procedures - Tolerances and
Replacement ofUnsatisfactory Areas 3-11
3.4.3.17 Bitumen Stabilization Procedures - Testing of
Bitumen Stabilized Courses 3-11
3.4.3. 18 Lime Stabilization Procedures - Mix Design 3-11
3.4.3.19 Lime Stabilization Procedures - Safety Precautions
3-11
3.4.3.20 Lime Stabilization Procedures - Stationary Plant
Mixing 3-11

copy 152
copy 152
Granular & Stabilised Subbase,
Basecourse & Stabilised Subgrade
Ministry ofTransport & Communications . DGRLT L__ L------/
3
3.1 Materials for Sub-Base and Base 2 Stockpiling procedures shall not result in noticeable degradation
Courses or segregation of the stockpiled material, or introduction of foreign
materials into the stockpile, or coning. Heights of granular material
and aggregate stockpiles shall not exceed 3 m benns.
( 3.1.1 Description
This Sub-section describes general requirements for materials 3.1.3.3 Sampling and Testing
for construction of granular sub-base, aggregate base and stabilized The Contractor shall submit to the Engineer, I 0 days prior to the
base courses, all as and where shown on the drawings. scheduled beginning of crushing and screening operations, a statement
of origin indicating the aggregate source and the quarry location and
3.1.2 Materials qualifications, as well as the types and composition of all stone and/or
Materials for use in the construction of the sub-base and base gravel aggregates and granular materials proposed for use in the work.
courses for flexible and rigid pavements may include any or all of the 2 Samples for testing shall be taken by the Contractor, in the
following: presence of the Engineer. Duplicate samples shall be submitted to the
i. Screened or partially crushed granular material, Engineer for future reference, if instructed. Sampling shall be in
consisting of well graded gravel including sand and silt, accordance with ASTM D75/D75M. The Contractor shall conduct the
or crushed stone or crushed gravel for sub-base course tests in the site laboratory, or have the tests carried out at an approved
construction. external laboratory.
ii. Crushed stone for base course construction. 3 In order to ascertain the properties of granular and aggregate
2 All material sources and the quality of materials shall be materials, the Contractor shall submit for testing representative
( approved prior to procuring or processing material from such sources. samples of all materials intended for incorporation in the work, prior
Inspection, sampling, testing and retesting as necessary, shall be as to starting quarry or borrow pit operations. The representative samples
specified hereunder for specific materials. shall be taken by the Contractor in the presence of the Engineer.

3 Storage and handling of all materials shall conform to the 4 Tests performed by the Contractor shall be utilized in assessing
relevant requirements of this specification and as approved by the the locations, extent of deposits and quantities of materials which,
Engineer. Materials shall be stored on hard, clean surfaces or as when properly processed, will conform to this Specification, and shall
directed by the Engineer. in no way obviate the need for further testing by the Engineer.
Approval of specific sources of materials shall not be construed as
3.1.3 General Requirements for Materials final approval and acceptance of materials from such sources.
5 Processed materials shall be tested and approved before being
3.1.3.1 Sources and Production
stockpiled on Site or incorporated in the work and may be inspected
The Contractor shall be responsible for locating sources and and tested at any time during their preparation, storage and use.
manufacturers of materials in accordance with the requirements of this Materials awaiting testing and approval shall not be unloaded and
Specification in the quantities and rates of production needed to mixed with materials previously approved. If the grading and quality
complete the work on time. of any materials delivered to the Site do not conform to the grading
and quality of the established control samples, the Engineer will reject
2 The Contractor shall satisfY himself as to the location, suitability
such materials.
and quantity of materials available; extent of work necessary to obtain
the materials, and to crush, screen and wash them; and the length of 6 The Contractor shall permit the Engineer to inspect any and all
haul to the Site. materials used or to be used, at any time during or after their
preparation, or while being used. Unsatisfactory materials, whether in
3 Prior to starting quarry or borrow pit operations; the Contractor
place or not, shall be removed promptly from the Site. The Contractor
shall obtain written permission from the authorities or owners
shall furnish all necessary labor, transport, tools and equipment
concerned.
required by the Engineer for such inspections.
4 Screening plants or crushing and screening plants shall not be
put into operation until approved by the Engineer. If, after any plant is
put into operation, it fails to perform as intended, the Contractor shall
3.2 Granular Sub-Base Course
either rectifY the defects in the existing plant to the satisfaction of the
Engineer, or shall provide alternative approved plant. 3.2.1 Description
5 Approval of the crushing and screening plants and other This Sub-section specifies standards for granular sub-base
equipment shall in no way relieve the Contractor of his responsibilities material, mixing, spreading on prepared subgrade, compacting and
in respect of producing granular materials and aggregates which finishing.
conform to this Specification and in the quantities required for the
completion of the work on time. 3.2.2 Materials

3.1.3.2 Stockpiling Granular material for use in sub-base courses shall be naturally
occurring gravel, blended as necessary with fine or coarse material
Stockpile areas shall be surveyed prior to stockpiling to and screened to produce the specified gradation. Crushing of natural
establish control points and to obtain a record of existing cross granular material shall not normally be required, unless for the
sections for future use in determining stockpile quantities. The areas purpose of meeting the graduation requirements, or, when shown on
shall be adequately drained at all times. the

dar 3-1
copy 152
Granular & Stabilised Subbase,
Basecourse & Stabilised Subgrade > Highway Dt!sign Standards 2017
Sultanate of Oman I Ministry ofTransport & Communications . DGRLT

drawings, to produce a higher quality sub-base with improved mixed with the granular material. Additional fine material for these
mechanical stability. purposes shall be obtained from the crushing of stone, gravel, or slag.

2 Gravel shall consist ofhard, durable and sound stones, free from 10 The granular material shall be free of gypsum (zero gypsum
dirt, organic matter, shale or other deleterious substances. content), when tested according to BS 7533 Part 3 standard, and shall
be free from organic content, unless otherwise specified in the
3 Granular materials shall meet the requirements of Class A, B or
particular specifications.
C shown in Table 3.2.2.1, and as specified on the Drawings, when
tested in accordance with AASHTO T-27 after dry mixing and just II The granular material shall have a minimum sand equivalent
before spreading and compacting. The class of granular material shall value of28, when tested in accordance with ASTM D2419.
be as shown on the Drawings or otherwise as selected by the Engineer 12 The maximum permitted swell for the granular material used in
based upon the test results of the materials survey, and projected the sub-base courses shall be 1.0%, when tested in accordance with
traffic. The actual gradation shall, in all cases, be continuous and ASTM D4829.
smooth within the specified limits for each class. 13 The Granular Sub-base Course material shall have chloride
content ofless than 3.5 percent and sulphate content ofless than 2.0
Percent by weight passing
Sieve Designation percent when tested in accordance with BS 812.
(square openings) OassA ClassB ClassC 14 Only potable water shall be used for mixing granular sub-base
material.
63mm 100 - -
3.2.3 Construction Requirements
50mm 90- 100 100 -
3.2.3.1 Sub-grade Surface Preparation
37.5 mm - 70- 100 -
Prior to subgrade surface preparation, the sub-grade shall be
25mm - 55-85 100 constructed in accordance with the requirements of Sub-section 2.6
and properly maintained and kept well drained thereafter.
19mm - 50-80 -
2 At all special grade control points, such as at bridge structures,
9.5 mm - 40 - 70 50 - 85 existing pavements, etc the sub-grade shall be lowered to a depth
4.75 mm 35-70 30-60 35-65 sufficient to permit construction of the sub-base course to the specified
elevations and thickness. Transitions shall be of sufficient length to
2.00mm - 20-50 25- 50 avoid abrupt changes of grade and shall be within plus or minus 3%
0.425 mm - 10-30 15-30 of the final design grade unless otherwise directed. Surplus material
O.D75 mm 0- 10 4- 12 5- 15 shall be removed and disposed of
3 The sub-grade shall be inspected and approved immediately
Table 3.2.2.1: Gradation of Granular Sub-Base Material by
prior to commencement of sub-base construction. Any soft, yielding
Class
material shall be removed and replaced by approved topping material.
4 The material shall not contain more than 5% clay content at any Holes, depressions and other irregularities shall be made good as
stage of construction when tested in the Hydrometer Test in directed and the subgrade re-compacted as necessary and finished
accordance with AASHTO T88. ready to receive the sub-base course.

5 The loss in weight of granular material shall not exceed 40% 3.2.3.2 Equipment
after 500 revolutions, when tested in accordance with ASTM
Cl31/Cl31M (Los Angeles Abrasion Test), unless otherwise Equipment used to handle, place, spread, water, compact and
specified in the particular specifications. finish sub-base shall conform with the requirements of Section 19 of
these Specifications and with the Contractor's approved equipment list.
6 The granular material shall have a4-day soaked CBR of not less
than 60% when compacted at 100% of modified proctor AASHTO (T 3.2.3.3 Construction of Trial Sections
180-D) and tested in accordance withAASHTO T 193.
If directed by the Engineer, before commencement of sub-base
7 When tested for soundness in accordance with AASHTO T 104,
construction, the Contractor shall lay and compact trial sections of
the material shall not show signs of disintegration, and the percentage
varying thickness of sub-base. Each trial section shall be 2 lanes wide
loss in weight after 5 cycles shall not exceed 12% in the case of the
by 50 m long, at approved locations on or close to the Site. Each trial
sodium sulfate test and 18% in the case of the magnesium sulfate test.
section shall be laid using the same materials, mix proportions, mixing,
8 The portion of granular material, including any blended material, spreading and compaction equipment, and construction procedures,
passing the 0.425 mm (No. 40) mesh sieve shall have a liquid limit proposed for use in the work.
(L.L.) of not more than 25 and a plasticity index (P.I.) not greater than
2 The objectives of these trials shall be to determine the adequacy
6 when tested in accordance with AASHTO T 89 and T 90, unless
of the Contractor's equipment and the loose depth measurements that
otherwise specified in the particular specifications.
will result in the specified compacted layer depths, to verity the field
9 If additional fine material is required to correct the gradation of moisture content, and to identifY the relationship between the number
the granular material, or for adjusting the L.L. or P.l. of the fraction of compaction passes and the resulting density of the sub-base
passing 0.425 mm (No 40) sieve, it shall be uniformly blended and material.

3-2
copy 152
dar
Granular & Stabilised Subbase,
Basecourse & Stabilised Subgrade
Mini try ,/T•ar 'pr'r1 & Co•••rnu.1ic tion . DG>LT
3
(

3.2.3.6 Compaction
3.2.3.4 Stockpiling of Granular Material
The Contractor shall plan the sequence of operations so that the
Stockpiling procedures shall conform to the requirements of
least amount of water will be lost by evaporation from uncompleted
Sub-section 3 .I.
( 2 Methods used for stockpiling granular material and removing it
surfaces. If the uncompleted surface material loses water due to
evaporation, the Contractor shall apply additional water as required to
from stockpiles shall not result in significant degradation or prevent raveling or excessive drying.
segregation or the introduction of significant amounts of foreign
2 The sub-base material shall be compacted by means of approved
materials or extraneous matter.
compaction equipment, progressing gradually from the outside
3 Granular material adversely affected, in the opinion of the towards the center, with each succeeding pass uoiformly overlapping
Engineer, by stockpiling or handling procedures, shall not be the previous pass.
incorporated in the work regardless of previous approval of such
3 Rolling shall continue until the entire thickness of each sub-base
material, until the deficiencies have been rectified in an acceptable
layer is thoroughly and uniformly compacted to 100% AASHTO T
manner.
180 (Method D) maximum density. Final rolling of the completed
3.2.3.5 Mixing and Spreading course shall be by means of an approved self-propelled roller. Rolling
shall be accompanied by sufficient blading, to insure a smooth surface,
Mixing shall generally be performed in hatching plants. Mixing free from ruts or ridges and having the proper shape. When additional
in stockpiles shall be done only if approved by the Engineer and under water is required, it shall be applied in an approved manner.
his supervision. The amount of water added, as approved by the
4 Any areas inaccessible to normal compaction equipment shall
Engineer, shall be such that the material will be uniform and within
be compacted by use of portable mechanical tampers until the required
the specified moisture content range at the time of compaction.
standard of compaction is achieved.
Wetting of granular material in trucks before or during delivery to the
Site will not be permitted. However, water shall be added to the 5 Each layer shall be completely compacted and approved prior
material, if necessary, during placing and compaction of sub-base to delivery of materials for the subsequent layer.
material. 6 Prior to placing a subsequent layer, the existing surface shall be
2 The sub-base material shall be placed on the subgrade in a made sufficiently moist as directed, to ensure proper bond between the
uniform layer or layers not exceeding 200 mm thickness (after layers.
compaction) with the necessary control guide wire requirements. 7 The edges and edge slopes of the sub-base course shall be
Where the required thickness is greater than 200 mm but less than 400 bladed or otherwise dressed to conform to the lines and dimensions
mm, the material shall be placed in layers of equal thickness. shown on the Drawings and to present straight, neat lines and slopes
3 If approved by the Engineer, when heavy duty vibratory as free ofloose material as practicable.
compaction equipment is used the maximum layer thickness may be 8 Material which has dried out prior to final compaction, or which
increased up to 300 mm (after compaction) provided compaction tests has dried and de-compacted subsequent to final compaction, shall be
( with appropriate testing equipment based on successful Site trials watered and re-compacted using approved equipment and procedures.
indicate that the specified compaction standard will be attained and If the Contractor is unable to return the material to its original or
will be uniform through the thickness. specified condition with respect to compaction, thickness and surface
4 The sub-base material shall be placed to the required width tolerances, the Contractor shall remove the material and reconstruct
using an approved paver/finisher or grader if approved by the the sub-base course on a re-approved subgrade.
Engineer. However, any pavers or graders used for placing the sub- 9 The water shall be clean and free from deleterious substances.
base material shall be equipped with calibrated sensors to maintain the Water from doubtful sources shall not be used until tested in
design levels and thicknesses. Water shall be applied by approved accordance with ASTM Cl602/Cl602M and approved.
spraying equipment and thoroughly mixed with the sub-base material. I 0 Sea, brackish or saline water shall not be used in the mixing,
5 The material shall not be handled in such a way as to cause spreading and compacting operations for aggregate sub-base course.
segregation. If the spreading equipment causes segregation in the
3.2.3.7 Tolerances
material, or leaves ridges or other objectionable marks on the surface
which cannot be readily eliminated or prevented by adjustment of the The fully compacted and completed sub-base course shall
equipment, the use of such equipment shall be discontinued and it conform to the lines, grades and cross sections as shown on the
shall be replaced by a spreader or grader capable of spreading the Drawings.
material in a proper manner.
2 The elevations of the finished sub-base course shall be checked
6 All segregated material shall be removed and replaced with by the Contractor in the presence of the Engineer at maximum
well-graded material. 'Skin' patching will not be permitted. Only intervals of20 m and at intermediate points as directed.
minor surface manipulation and watering to achieve the required
3 The tolerances on elevations of finished surface shall be plus 10
surface tolerances will be permitted during the compaction process.
mm to minus 20 mm. Minus tolerance shall be compensated by the
7 Neither hauling nor placement of material will be permitted subsequent layer.
when, in the judgment of the Engineer, the weather or surface
4 When the finished surface is tested with a 3 m long straightedge,
conditions are such that hauling operations will cause cutting or
placed parallel to, or at right angles to the centerline, the maximum
rutting of the subgrade or cause contamination of the sub-base
material.

dar 3-3
copy 152
Granular & Stabilised Subbase,
Basecourse & Stabilised Subgrade > HighW.JY De5ign Stjfl(i rds 2017
Sultan te of Oman I , t1inistry ofTr~nsport & Communication . DGRLT

deviation of the surface from the testing edge between any 2 contact 3.3 Aggregate Base Course
points shall not exceed 10 mm.
5 All areas which exceed the specified tolerances shall be 3.3.1 Description
corrected by removing the defective sections of sub-base and This Sub-section specifies standards for crushed aggregate base
reconstructing them or, if approved, by scarifYing, adding new course material, mixing, spreading on prepared sub-base course or
material, or removing extra material, mixing and re-compacting and sub-grade, compacting and fmishing.
finishing to the specified standard.

3.2.3.8 Maintenance of Completed Sub-base


3.3.2 Materials

Following completion and acceptance of the sub-base course, it 3.3.2.1 Crushed Stone Aggregate
shall be maintained in good condition prior to laying the base course .. Aggregate for use in base course construction shall be either
The sub-base shall be bladed, broomed and otherwise maintained, crushed stone or crushed gravel. The fine aggregate shall consist of
keeping it free from raveling and other defects until such time as the screenings obtained from crushed stone, gravel, or sand. Aggregate
base course is placed. Water shall be applied at such times and in such may be washed, if directed, to remove excessive quantities of clay,
quantities as directed by the Engineer. silty clay or salts.
3.2.3.9 Testing 2 Crushed stone shall consist of hard, durable particles or
fragments of stone, free from dirt or other objectionable matter, and
Every 1000 cu.m. of sub-base material, or whenever there is a shall contain no more than 8% of flat, elongated particles when tested
change in the material source, shall be subject to a full set of tests as according to ASTM 04791 and, soft, or disintegrated pieces when
listed in Table 3.3.3 .1 after placing and, if found satisfactory, shall be tested according to ASTM Cl23/Cl23M.
approved for compaction. This approval shall not be deemed to
3 Crushed gravel shall consist of hard durable stones, rocks, and
constitute acceptance of the sub-base course.
boulders crushed to specified sizes and shall be free from excess flat,
2 Sampling and testing shall conform with the relevant elongated, soft or disintegrated pieces, dirt, or other objectionable
requirements of this specification and to the satisfaction of the matter
Engineer.
4 The method used in production of crushed gravel shall be such
3 Compaction shall be tested in accordance with AASHTO T 191 that the finished product shall be as uniform as practicable. The
or ASTM 02167. If there is a delay between the construction of any crushing of the gravel shall result in a product, which shall have at
layer and the following layer, if necessary and required by the least 90% by weight of particles with at least one fractured face. All
Engineer the compaction of the lower layer may be re-verified to stones, rocks, and boulders of inferior quality occurring in the pit shall
ensure that it has not loosened due to traffic, passage of construction be wasted.
equipment, adverse weather conditions or otherwise.
5 Any material passing 4.75 mm (No. 4) sieve and produced in
the crushing process shall be incorporated in the base material up to
3.2.4 Method of Measurement
the gradation limits required for the base course aggregate.
Granular sub-base course is measured by cu.m. of compacted 6 Crushed aggregate for base course delivered to road site shall
sub-base. Measurement shall be of volumes computed from the cross meet the requirements of Class A, B or C gradations as shown in Table
sections shown on the Drawings and shall be calculated from the top 3.3.2.1 when tested in accordance with AASHTO T 27 after mixing
surface area of each layer, excluding the tapered edges. with water and just before spreading and prior to compacting. The
2 No measurement shall be made for direct payment of overdepth class of aggregate shall be as shown on the Drawings. The actual
construction, regardless of the Engineer's permission for it to remain gradation shall, in all cases, be continuous and smooth within the
in place. specified limits for each class. Gap graded aggregate will not be
accepted. If gradation is tested after compaction a tolerance of 3% is
3.2.5 Basis of Payment allowed in upper limit for percentage of material passing sieve 200.

The amount of completed and accepted work, measured as 7 The amount of the fraction of material passing the 0.075mm (No.
provided for above, will be paid for at the unit rates for the various 200) mesh sieve shall not exceed one half the fraction passing the
items in the Bill of Quantities, which rate shall be full compensation 0.425mm (No. 40) mesh sieve.
for equipment, tools, labor, locating sources of supply, supplying 8 The loss in weight shall not exceed 35% after 500 revolutions,
materials, sampling and testing, screening, crushing, transporting, when tested in accordance with ASTM Cl31/Cl31M (Los Angeles
stockpiling, laying, mixing and compacting and for extra material in Abrasion Test), unless otherwise specified in the particular
tapered edges, and other items necessary for the proper completion of specifications.
the work.
9 The crushed aggregate base course material shall have a 4-day
soaked CBR of not less than 80% when compacted at 100% of
3.2.6 Items in the Bill of Quantities modified proctor AASHTO (Tl80-D) and tested in accordance with
i. Granular Sub-Base Course (Class A) cu.m AASHTO T 193.

ii. Granular Sub-Base Course (Class B) cu.m

iii. Granular Sub-Base Course (Class C) cu.m

3-4
copy 152
dar
Granular & Stabilised Subbase,
Basecourse & Stabilised Subgrade
M;-lislly ofTr nspo'1 & Com111Wication~ . DGRLf
3
Per cent by weigbt passing irregularities shall be made good as directed and the sub-base re-
Sieve Designation compacted as necessary and finished ready to receive the base course.
(square openings) Class A Class B ClassC
3 Where no sub-base course is required or shown on the Drawings,
63mm 100 ... ... and the aggregate base course is placed directly on completed sub-
( grade, preparation of the subgrade surface shall be as specified in
50mm 90 ... 100 ... ...
Paragraph 3.2.3.1 .
37.5 mm 60-90 100 ...
3.3.3.2 Equipment
25mm 42 -77 60 . . 100 100
19mm 35 -70 55 . . 85 80 . . 100 Equipment used to handle, place, spread, water, compact and
finish base course shall conform with the requirements of Section 19
12.5mm 25 . . 60 ... ...
and with the Contractor's approved equipment list.
4.75 mm 15 . . 40 35 . . 60 30 . . 60
2.00mm 10 . . 25 25 . . 50 20 . . 45 3.3.3.3 Construction of Trial Sections

0.425 mm 5 . . 15 15-30 - If directed by the Engineer, the Contractor shall lay and compact
O.o75 mm 2-9 4- 10 6- 12 trial sections of varying thickness of base. Each trial section shall be
Table 3.3.2.1: Gradation by Class of Aggr·egatt Base Course 2 lanes wide by 50 m long, at approved locations on or close to the
Site. Each trial section shall be laid using the same materials, mix
10 When tested for soundness in accordance with AASHTO T 104,
proportions, mixing, spreading and compaction equipment, and
the material shall not show signs of disintegration and the loss by
construction procedures, proposed for use in the Works.
weight shall not exceed 12% in the case of the sodium sulfate test and
( 18% in the case of the magnesium sulfate test. 2 The objectives of these trials shall be to determine the adequacy
of the Contractor's equipment and the loose depth measurements that
11 The aggregate material shall be free of gypsum (zero gypsum
will result in the specified compacted layer depths, to verity the field
content), when tested according to BS 7533 Part 3 standard, and shall
( be free from organic content, unless otherwise specified in the
moisture content for compaction, and to identifY the relationship
between the number of compaction passes and the resulting density of
particular specifications.
the base course material.
12 The aggregate material shall have a minimum sand equivalent
value of 50, when tested in accordance with ASTM 02419. 3.3.3.4 Stockpiling of Aggregate Materials
13 The maximum permitted swell for the aggregate material used Stockpiling procedures shall conform to the relevant
in the base courses shall be 0.5%, when tested in accordance with requirements of Sub-section 3 .1.
ASTMD4829.
2 Methods used for stockpiling aggregate materials and removing
14 The portion of aggregate, including any blended material, them from stockpiles shall not result in significant degradation or
passing the 0.425 mm (No. 40) mesh sieve shall have a liquid limit
( (L.L.) of not more than 25 and plasticity index (P.I) of not more than
introduction of significant amounts of foreign materials or extraneous
matter.
4 when tested in accordance with AASHTO T 89 and T 90, unless
3 Aggregate materials adversely affected, in the opinion of the
otherwise specified in the particular specifications.
Engineer, by stockpiling or handling procedures, shall not be
15 If additional fine material is required to correct the aggregate incorporated in the work regardless of previous approval of such
gradation, or for adjusting the L.L. or P.L of the fraction passing the material, until the deficiencies have been rectified in an acceptable
0.425 mm (No. 40) sieve, it shall be uniformly blended and mixed manner.
with the aggregate material plant at the crushing plant or by an
approved plant. Reworking of the material in situ to obtain the 3.3.3.5 Mixing and Spreading
specified gradation will not be permitted. Additional fine material for
All components of base course material shall be premixed with
these purposes shall be obtained from the crushing of stone, gravel, or
water in a pugmill mixing plant. The amount of water added, as
slag.
determined, shall be such that the material will be uniform and within
16 The Aggregate Base Course material shall have chloride content the specified moisture content range at the time of compaction. Other
ofless than 3.5 percent and sulphate content ofless than 2.0 percent methods of mixing will be allowed only if directed by the Engineer,
when tested in accordance with BS 812. provided such method(s) do not reduce the quality of work The
17 Only potable water shall be used for mixing aggregate base Contractor shall demonstrate, in the presence of the Engineer, his
material. ability to attain the requirement given in this Specification.
2 The premixed material shall be placed on the sub-base in a
3.3.3 Construction Requirements uniform layer or layers not exceeding 200 mrn in thickness (after
compaction) with the necessary control guide wire requirements.
3.3.3.1 Surface Preparation Where the required thickness is greater than 220 mm but less than 400
The sub-base course shall be in accordance with the mm, the material shall be placed in layers of equal thickness.
requirements of Sub-section 3.2 and properly maintained and kept 3 If approved by the Engineer when heavy duty vibratory
well drained thereafter. compaction equipment is used, the maximum layer thickness may be
2 The sub-base surface shall be inspected and approved prior to increased up to 300 mm (after compaction) provided compaction tests
commencement of base construction. Holes, depressions and other with appropriate testing equipment based on successful Site trials

dar 3-5
copy 152
Granular & Stabilised Subbase,
Basecourse & Stabilised Subgrade > Hiqh\ 3y De ign St nd rds 2017
Sultanate of Oman I Ministry ofTransport & Communic tions. DGRLT

indicate that the specified compaction standard will be attained and watered andre-compacted using approved equipment and procedures.
will be uniform through the thickness. If the Contractor is unable to return the material to its original or
specified condition with respect to compaction, thickness and surface
4 The base course material shall be placed to the required width
tolerances, for the final layer only the Contractor shall scarify the
using an approved paver/finisher. However, any pavers or finishers
material and reconstruct the base course on a re-approved sub-base
used for placing the base material shall be equipped with calibrated
surface or to the satisfaction of the Engineer.
sensors to maintain the design levels and thicknesses. The material
shall be delivered such that it is ready for compaction without further 3.3.3.7 Tolerances
shaping.
The fully compacted and completed base course shall conform
5 The material shall not be handled in such a way as to cause
to the lines, grades and cross sections as shown on the Drawings.
segregation. If the spreader causes segregation in the material, or
leaves ridges or other objectionable marks on the surface which cannot 2 The elevations of the finished base course shall be checked by
be readily eliminated or prevented by adjustment of the spreader the Contractor in the presence of the Engineer at intervals of I Om on
operation, the use of such spreader shall be discontinued and it shall straight lines and of 5m on curves, and at intermediate points as
be replaced by a spreader capable of spreading the material in a proper directed.
manner. 3 The tolerances (for fmal layer only) on elevations of finished
6 All segregated material shall be removed and replaced with surface shall not exceed +5mm or -IOmm.
well-graded material. ' Skin' patching will not be permitted. Only 4 When the finished surface is tested with a 4m long straightedge,
minor surface manipulation and watering to achieve the required placed parallel to, or at right angles to the centerline, the maximum
surface tolerances will be permitted during the compaction process. deviation of the surface from the testing edge between any 2 contact
7 Hauling or placement of material will not be permitted when, in points shall not exceed I Omm.
the judgment of the Engineer, the weather or surface conditions are 5 The tolerances on layer thickness, after being compacted and
such that hauling operations will cause cutting or rutting of the sub- finished, shall not exceed+ 1Omm and -5mm.
base or subgrade or cause contamination of the base course material. 6 The thickness of the fmished base course shall be checked at
20m intervals along the road by taking levels on the centerline and
3.3.3.6 Compaction
both shoulders.
The Contractor shall plan the sequence of operations so that the 7 All areas which exceed the specified tolerances shall be
least amount of water will be lost by evaporation from uncompleted corrected by removing the defective sections of base course and
surfaces. If the uncompleted surface loses water due to evaporation, reconstructing them or if approved, by scarifying and adding new
the Contractor shall apply additional water as required to prevent material, or removing extra material, and re-compacting and finishing
raveling or excessive drying. to the specified standard.
2 The base course material shall be compacted by means of
approved compaction equipment, progressing gradually from the 3.3.3.8 Maintenance of Completed Base Course
outside towards the center, with each succeeding pass uniformly Following completion and acceptance of the base course, it shall
overlapping the previous pass. be maintained by the Contractor until the subsequent pavement layers
3 Rolling shall continue until the entire thickness of each base are laid. The surface shall be broomed, rolled and otherwise
layer is thoroughly and uniformly compacted to 100% AASHTO T maintained, keeping it free from raveling and other defects until such
180 (Method D) maximum density. Final rolling of the completed time as the following course is placed. Water shall be applied at such
course shall be by means of an approved self-propelled roller. Rolling times and in such quantities as directed.
shall be accompanied by sufficient blading, to ensure a smooth surface,
free from ruts or ridges and having the proper shape. When additional 3.3.3.9 Testing
water is required, it shall be applied in an approved manner. Every 1000 cu.m. of base course material, or whenever there is
4 Any areas inaccessible to normal compaction equipment shall a change in the material source, shall be subject to a full set oftests as
be compacted by use of portable mechanical tampers until the required listed in Table 3.3 .3.1 after placing and if satisfactory shall be
standard of compaction is achieved, or to the satisfaction of the approved for compaction and use. This approval shall not be deemed
Engineer. to constitute acceptance of the base course for full payment purposes.
5 Each layer shall be completely compacted and approved prior 2 Sampling and testing shall conform to the requirements of this
to delivery of materials for the following layer. specification.
6 Prior to placing a following layer, the surface shall be made 3 Compaction shall be tested in accordance with AASHTO T 191
sufficiently moist as directed, to ensure proper bond between the or any acceptable method. If there is a significant delay between the
layers. construction of any layer and the following layer, the Engineer may
7 The edges and edge slopes of the base course shall be bladed or require the compaction of the lower layer to be re-verified to ensure
otherwise dressed to conform to the lines and dimensions shown on that it has not loosened due to traffic, passage of construction
the Drawings and to present straight, neat lines and slopes as free of equipment, adverse weather conditions or otherwise.
loose material as practicable.
8 Material which has dried out prior to final compaction, or which
has dried and de-compacted subsequent to final compaction, shall be

3-6
copy 152
dar
Granular & Stabilised Subbase,
Basecourse & Stabilised Subgrade
Ministry ofTr r.spurt & Communication DGRU
.//
"------/
3
,-" ·-

cross sections shown on the Drawings and shall be calculated from the
Sourc:e of Materials Control on Site (fbe Road) top surface area of each layer, excluding the tapered edges.
2 No measurement shall be made for direct payment of overdepth
Repetition
Required Required Repetition construction, regardless of the Engineer's pennission for it to remain
( Tests
Required
for all Tests
Tests Required for in place.
(A) (B) all Tests in (B)
in(A)
3.3.5 Basis of Payment
I. Gradation Minimum I. Proctor Minimum one
of Materials one test for AASHTO test for every The amount of completed and accepted work, measured as
AASHTO each source Tl80-0 1000 cu.m. of provided for above, will be paid for at the unit rates for the various
T27 every layer, or
items in the Bill of Quantities, which rate shall be full compensation
whenever
Materials for equipment, tools, labor, locating sources of supply, supplying
changed, materials, sampling and testing, screening, crushing, transporting,
whichever is stockpiling, laying, mixing and compacting and for extra material in
less tapered edges, and other items necessary for the proper completion of
the work.
2. Plasticity .. 2. Gradation
.
Index of Materials 3.3.6 Items in the Bill of Quantities
AASHTO AASHTO
T89& T90 T27 i. Aggregate Base Course (Class A) cu.m

ii. Aggregate Base Course (Class B) cu.m


3. Abrasion
.. 3. Plasticity ..
iii. Aggregate Base Course (Class C) cu.m
ASTM Index
CJ31/Cl31M AASHTO
T89& T90 3.4 Stabilized Base Courses

3.4.1 Description
4. C.B.R.
..
4 . C.B.R.
.
This Sub-section specifies stabilized base courses composed of
AASHTO AASHTO
Tl93 Tl93 sand, sandy gravel, sandy clay soil or similar, stabilized with cement

( or bitumen or lime as appropriate and as shown on the Drawings.

5.Sand .. 5. Abrasion .. 3.4.2 Materials


equivalent ASTM
( ASTM
02419
CJ31 /Cl31
M
3.4.2.1 Soil for Stabilization

Sand and gravel soils shall have the following particle size
distribution given in Table 3.4.2.1.
6. Percentage .. 6. Sand ..
of fractured equivalent AASHTO Sieve "'o passing (by mass)
Grains ASTM
50mm 100
02419
4.75 mm 50- 100
7. Thin and .. 7. Clay .. 1.80 mm 37-80
elongated lumps& 15-50
425 J.!ffi
pieces friable
ASTM 75 ).liD 0-20
particles
04791 ASTM 2J.!m 0-3
Cl23/Cl23 Table 3.4.2.1: Soil for Stabilization
M

8. Field .. 2 The mix-in-place method of construction shall be used only on


Density sites with naturally occurring sand and gravel mixture. For the central
plant method of construction, the materials shall be selected by the
9. Thickness Test for every Contractor from other sources complying with the requirements of this
2000 sq.m. and Clause and shall be subject to the approval of the Engineer.
for every layer
Table 3.3.3.1: Hequirtd Tests and .\linimum Htpetition for Base 3.4.2.2 Cement as Stabilizing Agent
and Sub- Base Course '\'latcrials Cement for stabilization shall be ordinary Portland cement or
sulfate resisting cement, as shown on the Drawings, or as instructed
3.3.4 Method of Measurement by the Engineer. Portland cement shall confonn to the requirements
Aggregate base course shall be measured by cu.m. of compacted ofBS EN 197-1 Type CEM I 42.5N or AASHTO M85 Type I for
base course. Measurements shall be of volumes computed from the ordinary and rapid hardening types, and BS EN 197-1 Type CEM I

dar 3-7
copy 152
Granular & Stabilised Subbase,
Basecourse & Stabilised Subgrade > Highlt' yo.., ;,~11 St ndard 2Cl17
Suit nate of Oman I Ministry ofTran pr>rt & Corl'fnunic tion . f'lGRLT

42.5N/SR or AASHTO M85 Type V for sulfate resisting cement. 8%, when cylinders are molded and tested in accordance
with AASHTO T 135, Method B.
2 At least two silos shall be used for cement storage. Before
iii. Cement content and water content of the mix on the Site
recharging a silo it shall be emptied completely and cleaned out.
shall each be within- 0.2% to +2% of the approved mix
During the time of charging a silo shall not be used for batching.
design.
3 The stored cement shall be free-flowing and free of lumps.
iv. The total salt content of the cement stabilized base
Cement shall not be stored for longer than 4 months. Cement that has
course mixture shall meet the following requirements:
remained in store for a period greater than 4 months, or of which there
The total chloride content (sum of both acid soluble and
is doubt as to quality shall be re-tested by standard mortar tests to
water soluble chlorides) expressed as chloride ion, when
determine whether it still meets the requirements of the standards.
tested in accordance with BS 1881 , shall not exceed 0.10
4 Curing seal shall consist of approved proprietary curing percent by weight of dry cement. The total sulfate
compound, or MC-70 cutback bitumen to prime coat standard as content expressed as S03, when tested in accordance
specified in Section 4. with BS 1881, shall not exceed 3 percent by weight of
dry cement.
3.4.2.3 Bitumen as Stabilizing Agent

Bitumen may include straight run (penetration grade) bitumen; 3.4.3 Construction Requirements
RC cutback bitumen, MC cutback bitumen, or cationic emulsified
bitumen, Type SS. Penetration grade, cutback bitumen and emulsified 3.4.3.1 Surface Preparation
bitumen shall conform to all relevant requirements herein. Prior to placing of stabilized base on sub-base or subgrade, the
2 The selection of suitable bitumen will depend on the properties subgrade shall have been properly completed and approved as
of the material to be stabilized and shall be subject to laboratory and specified in Sub-section 2.6 and the sub-base shall have been properly
field trials by the Contractor, under the supervision of the Engineer. completed and approved as specified in Sub-section 3.2.
3 When the material moisture content is high, the material must
3.4.3.2 Construction of Trial Section
be dried before the use of penetration grade bitumen or viscous
cutback bitumen and plant mixing of materials as appropriate. If instructed by the Engineer before commencement of
4 When the natural moisture content of the material is low, use stabilization work and after completion of laboratory mix design, the
cutback bitumens or emulsified bitumens as appropriate. Contractor shall lay a trial section of stabilized material 2 lanes wide
by 50m long, at an approved location on or near to the Site.
3.4.2.4 Lime as Stabilizing Agent 2 This trial section shall be laid using the same materials, mix
Hydrated lime (calcium hydroxide) and quicklime (calcium proportions, mixing, spreading and compaction equipment, and
oxide) shall conform to AASHTO M216. Mixing of different brands construction procedures that are proposed for use in the work.
oflime or use oflime from different mills will not be permitted. 3 The trial section shall serve as a field verification of the
2 Lime slurry shall be a homogeneous pumpable mixture oflime laboratory mix design. The results of the dry density and moisture
and water. Slurry shall be a premixed material in which the lime solids content measurements made in the trial section will be used in
content shall be not less than 30% by weight. association with the laboratory tests to establish the moisture content
and minimum per cent compaction to be attained in the stabilization
3.4.2.5 Water work.

The water shall be clean and free from impurities, oil, acid, salts, 4 The trial section shall also demonstrate the adequacy of mixing,
alkali, organic matter, and other potentially deleterious substances. spreading and compaction equipment and the suitability of the
Water from doubtful sources shall not be used until tested in methods and organization proposed.
accordance with ASTM Cl602/Cl602M and approved.
3.4.3.3 Cement Stabilization Procedures - Plant Mixing
3.4.2.6 Mix Design for Cement Stabilized Base When cement and granular or crushed material are to be mixed
Before starting the work of stabilization, soil-cement trial mixes in a stationary plant, the plant shall be an approved type pugmill
shall be carried out. The proposed mix design shall be submitted by mixing plant of either the batch mix type with revolving blade or
the Contractor for approval by the Engineer. It shall show the rotary drum, or the continuous mixing type. Proportioning ofmaterials
percentage of cement and water to be used with the naturally occurring and of water may be by either weight or volume.
soil so as to obtain a stabilized mixture with the following properties: 2 Cement shall be added in such a marmer that it is uniformly
distributed during the mixing operation. Safe, convenient facilities
i. The minimum cube compressive strength shall be 5.0
shall be provided for sampling cement in the supply line to the weigh
N/mm2 after molding and storage at a minimum
hopper or pugrnill.
humidity of 95% for a period of 7 days . The molding
shall be in accordance with AASHTO Tl34 and the 3 Means shall be provided whereby the Engineer may verifY the
strength testing shall be in accordance with BS 1881. The amount of water per batch or the rate of flow for continuous mixing.
cement content of trial mixes shall be adjusted until this The time of the addition of water and the points at which it is
strength is achieved. introduced into the mixer shall be as approved.

ii. The maximum volume change (swelling) shall be 2% 4 The charge in a batch mixer, or the rate of feed to a continuous
and the maximum loss in weight shall be not more than mixer, shall not exceed that which will permit complete mixing of all

3-8
copy 152
dar
r

r
Granular & Stabilised Subbase,
Basecourse & Stabilised Subgrade
Ministry ofTransport & Communications. DGRLT
3
of the material. Dead areas in the mixer, in which the material does 2 Plant and equipment for pulverizing (if required) and for mixing
not move or is not sufficiently agitated, shall be corrected. all materials will be approved on the basis of preliminary trials to
establish that such plant and equipment are capable of producing the
5 The moisture content of the completed mixture shall be not
specified degree of mixing and uniformity of stabilized material for
( more than one per cent below optimum moisture content at the point
of delivery to the work area.
the full thickness of each layer. Single pass or multi-pass equipment
maybe used.
3.4.3.4 Cement Stabilization Procedures - Batch Mixing 3 The mixing equipment shall be equipped with a device for
controlling the depth of processing and the mixing blades shall be
Batch mixing plants shall be equipped with a sufficient number
maintained or reset periodically so that the correct depth of mixing is
of paddles of a type and arrangement to produce a uniformly mixed
obtained at all times. Cement shall be spread ahead of the mixer by
batch.
means of a cement spreader, fitted with a device to ensure a uniform
2 The mixer platform shall be of ample size to provide safe and and controllable rate of spread of cement transversely and
convenient access to the mixer and other equipment. longitudinally.
3 The mixer shall be equipped with a timing device which will 4 lfmulti-pass equipment is utilized, the fine cohesive fraction (if
indicate by a definite audible or visual signal the expiration of the any) of the material shall first be pulverized to the required depth with
mixing period. The device shall be accurate to within 2 seconds. successive passes and the moisture content adjusted if it is more than
4 The time of mixing a batch shall begin after all ingredients are 3% below the value required for compaction. Cement shall then be
in the mixer and shall end when the mixer is half emptied. Mixing spread and mixing continued with successive passes until the required
shall continue until a homogeneous mixture of uniformly distributed depth and uniformity have been achieved.
and properly coated materials of uniform appearance is produced. The 5 If it is necessary to adjust the moisture content of the material
time of mixing shall not be less than 30 seconds. When blending of to the optimum for compaction, water shall be added during the
different sizes is required, the materials shall be blended as they enter mixing operation using a water sprayer of such design that the water
the mixer.
( 5 Cement for each batch shall be weighed on scales separate from
is added in a uniform and controllable manner both transversely and
longitudinally.
the aggregate hatching scales. Each cement scale graduation shall be 6 The mixing equipment shall be set so that it cuts slightly into
approximately 0.001 times the total capacity ofthe scales. The total the edge of any adjoining completed lane so as to ensure that all
capacity shall not be greater than twice the amount of cement required material forming the layer has been properly processed. The Engineer
when the plant is operated at full capacity. No scale shall be used with may approve the use of scarifiers or preparizers ahead of the mixing
a capacity less than 500 kg. equipment. The output of the mixing equipment shall be such that a
( 3.4.3.5 Cement Stabilization Procedures - Continuous Mixing
minimum rate of 20 lin.m./h measured longitudinally of completed
stabilized layer can be maintained in order to permit satisfactory
Continuous mixing plants shall be designed such that granular compaction of the mix.
( materials are drawn from the storage facility by feeders which
3.4.3.7 Cement Stabilization Procedures- Placing of Stationary
continuously supply the correct amount of granular material in
Plant Mixes
proportion to the cement and so arranged that the proportion of each
size of granular material can be separately adjusted if more than one Immediately prior to depositing the mix, the surface area to be
size is used. Storage facilities containing fme material shall be covered shall be moistened and kept moist.
equipped with vibrating units which shall vibrate the side walls of the
2 The cement stabilized mix shall be protected against moisture
feeder to prevent any hang-up of materials while the plant is operating.
loss during transporting, by use of suitable covers. The mix shall be
2 A control system shall be provided that will automatically close deposited on the roadbed at a prescribed quantity which shall provide
down the plant when the material in any storage facility approaches the compacted thickness for the width being spread without resort to
( the strike-off capacity of the feed gate. The plant will not be permitted
to operate unless the control system is in proper working order.
spotting, picking up, or otherwise shifting the mixture. Segregation
shall be prevented and the mix shall be free from pockets of coarse or
3 The feeder for the granular material shall be mechanically or fine materials.
electrically driven. Mechanically driven feeders shall be directly 3 The mix shall be spread in widths of not less than 2 lanes,
connected with the drive on the cement feeder. The drive shaft on the insofar as the width of surface permits. Longitudinal construction
feeder shall be equipped with a revolution counter reading to 0.1 of a joints shall fall within 300 mm of lane lines. The mix shall be spread
revolution. Electrically driven feeders shall be actuated from the same by one or more spreaders operating in a staggered position across the
circuit that services the motor driving the cement feeder. surface. If traffic conditions require that less than 2 lanes be spread,
4 The cement feeder and the granular material feeders shall be not more than 2 hours shall elapse between the times of placing the
equipped with devices by which the rate of feed can be determined material in adjacent lanes.
while the plant is in full operation. 4 The compacted thickness of any one layer shall not exceed 200
mm and shall be not less than 80 mm. When more than one layer is
3.4.3.6 Cement Stabilization Procedures - Mixed in Place
placed, the surface of the lower layer of compacted mix shall, until
Procedures covered with the next layer, be kept moist with water or a curing seal
Mixed in place procedures will normally be permitted when the as specified.
granular material to be stabilized is in-situ site material.

dar 3-9
copy 152
Granular & Stabilised Subbase,
Basecourse & Stabilised Subgrade > Highway Design St. ndards 2017
Sultanate of Oman I Ministry ofTransport & Communication . DGRLT

5 In the case of areas inaccessible to mechanical spreading compaction. Final compaction shall be completed within 30 minutes
equipment, the mix may be spread in one layer by approved methods of initial compaction.
only. After spreading, the material shall be thoroughly compacted to 8 At the end of each day's work and when operations are delayed
the required lines, grades, and cross section by means of pneumatic or stopped for more than 2 hours, a vertical construction joint shall be
tampers, or other approved compacting equipment made in the fully compacted layer, perpendicular to the centerline.
6 Use of motor graders will not be permitted during spreading or Additional mix shall not be placed until the construction joint has been
compacting operations. Motor graders may be used only to trim the approved.
edges and surface after compaction in order to finish within the 9 One hour after the stabilized mix has been finally compacted;
specified tolerances. vertical longitudinal joints shall be constructed by cutting into the
7 A motor grader may be classified as a self-propelled mechanical existing edge to a depth of approximately 100 mm. The mix cut away
spreader if it has been equipped with end wings on the blade, has the shall be discarded. The face of the cut joints shall be moistened in
blade locked in a position perpendicular to the direction of travel, and advance of placing the adjacent lane.
is equipped with cross slope and automatic grade controls that meet
3.4.3.9 Curing of Cement Stabilized Courses
the requirements for the specified type of spreading.
8 Each layer of the mix shall be spread in one operation with an Curing seal as specified shall be applied uniformly to the
approved type self-propelled mechanical spreader such that the layer completed surface at a rate of between 0.5 and 1.2 kgJ sq.m. , or as
is made ready for compaction without further shaping. The spreader determined by the Engineer. The curing seal shall be applied on the
shall be provided with a fully automatic and adjustable screed that same day that final compaction is performed and as soon as practicable
strikes off and distributes the material to the full width being spread thereafter. The surface shall be kept moist until the seal is applied.
and to the surface tolerances specified. 2 Damage to the curing seal or stabilized surface shall be
9 The spreader shall be equipped with grade sensing controls to promptly repaired by an approved manner.
automatically control the longitudinal grade and transverse slopes of
3.4.3.10 Testing of Cement Stabilized Courses
the screed. Screed action includes any cutting, crowding, or otherwise
that produces a finished surface texture of uniform appearance. For every 5,000 sq.m. of each stabilized layer or for each day's
completed area (whichever is smaller) the following sampling and
3.4.3.8 Cement Stabilization Procedures - Compaction and testing shall be carried out
Finishing In situ density of a minimum of 3 samples (taken
immediately after final compaction) determined in
Immediately upon completion of spreading or spreading and
accordance with AASHTO T 191 or T 205 and which
mixing in place operations, and completion of shaping, the mix shall
shall be not less than 100% of the density of the approved
be initially compacted by one complete pass using approved type
laboratory mix.
rollers.
Cement content in accordance with AASHTO T 211.
2 If the finished surface after initial compaction is outside the
Gradation of mix in accordance with AASHTO T 27.
specified tolerance, all high spots shall be trimmed off to within the
specified tolerance. Filling of low areas by drifting or hauling of Moisture - density relationship for mix sampled fresh
trimmed material will not be permitted. from the Site, in accordance with AASHTO T 134 if the
source of the material is changed.
3 Following trimming, the finished surface shall be finally
Compressive strength of a set of3 test specimens molded
compacted to not less than 100% of the laboratory density of the
and cured in accordance with AASHTO T 134 and
approved job mix specimens as determined by AASHTO T 134. Final
ASTM Cl92/Cl92M, and tested in accordance with
compaction shall be accomplished in such a manner that no loose
AASHTOT22.
material remains on the surface and all tear marks are eliminated.
4 The surface tolerances shall conform with the tolerance 3.4.3.11 Bitumen Stabilization Procedures - Mix Design
requirements for Aggregate Base Course. Where any areas are lower
The material to be stabilized shall be a sand, sandy gravel or
than the allowable tolerance, the stabilized layer shall be removed and
silty or clayey gravel and sand material with a P.L not exceeding 12%
fresh stabilized mix placed and properly compacted and finished,
unless filling of the low areas with bituminous concrete or cement and LL not exceeding 25% and with not more than 30% passing a
concrete is approved. 0.075 mm (No. 200) sieve.

5 If the superimposed course will be cement concrete, the low 2 Bitumen-soil mix proportions shall be established by field
areas may, if approved, be filled with concrete at the time and during laboratory trial mixes, carried out in the presence of the Engineer. The
the same operation that the concrete pavement is placed. compressive strength shall be determined in accordance with
AASHTO T 167 and in such a way as to ensure that the optimum
6 When the superimposed course will be bituminous concrete, the
composition of the mix is established.
low areas may, if approved, be filled with bituminous concrete to the
same standard. This filling shall be carried out as a separate operation 3 The laboratory trial mixes, after being air cured for a period of
prior to placing the bituminous concrete course (unless the thickness 7 days and tested in accordance with AASHTO T 167, shall have a
to be placed is too small to make this practicable). minimum compressive strength at 25 degrees C, of2 MN/sq.m. (20
kg/sq.cm.) and a Marshall stability at 60 degrees C, of2,000 N (204
7 Not more than 2 hours shall elapse between the time water is
kg). The Index of Retained Strength when tested using a Marshall
added to the mixed materials and the time of completion of initial
mould shall be not less than 70%.

-3-10
copy 152
dar
(

r'
Granular & Stabilised Subbase,
Basecourse & Stabilised Subgrade
Ministry ofTransport & Communications . OGRLT / 3
determined in accordance with AASHTO T 191 or T 205
Bitumen Stabilization Procedures - Stationary Plant and which shall be not less than 100% of the density of
Mixing the approved laboratory mix.

When approval is given to utilize stationary plant for mixing, ii. Composition of the mix by extraction in accordance with
whether batch mixing plant or continuous type mixing plant, the plant AASHTO T 164. The variation from the approved job-
and equipment and handling and mixing procedures shall conform mix, based on results of 4 tests, shall not exceed the
with the relevant requirements of Section 4- "Bituminous Pavement" following:
and with the appropriate requirements specified herein for plant Aggregates passing
mixing of cement stabilized materials. No. 200 (0.075 mm) ±1 percent
Asphalt content ±0.2 percent
3.4.3.13 Bitumen Stabilization Procedures - Mixed in Place
iii. Compressive strength in accordance with AASHTO T
Procedures 167, of samples before compaction. The minimum
Approved type multi-pass or approved type purpose-built, compressive strength value shall be not less than the
single-pass equipment shall be utilized for on Site mixing and placing. value specified under Item 3 of Paragraph 3.4.3.11.
Operators shall be trained and fully experienced in the operation of iv. Marshall stability in accordance with AASHTO T245, of
such equipment. samples before compaction. The minimum Marshall
stability value shall be not less than the value specified
2 Multi-pass equipment may consist of suitable bitumen
under Item 3 of Paragraph 3.4.3.11.
distributor and motor graders or as otherwise approved.
3 The process of pulverizing the fine grained cohesive fraction (if
( any) of the granular material shall be as specified for cement stabilized
3.4.3.18 Lime Stabilization Procedures - Mix Design

courses. Bitumen, of the type and grade selected by the Engineer, The material to be stabilized shall be a clayey gravel, clayey
shall then be applied to the surface using approved type heating and sand or lean clay soil with not more than 50% passing 0.425 mm (No.
( pressure distribution equipment. Emulsified bitumen shall not 40) sieve and plasticity index greater than I 0%.
normally require heating. 2 The lime content and optimum moisture content shall be
4 Spreading and mixing of the bitumen and granular or other determined in the field laboratory and in the presence of the Engineer.
material shall be carried out as specified for cement stabilized courses. Cylinders molded in accordance with AASHTO T 220 shall be cured
and tested at 7 days and 28 days. Load rate of application shall be in
3.4.3.14 Bitumen Stabilization Procedures- Placing and accordance with AASHTO T 22. The minimum compressive strength
( Spreading Stationary Plant Mixes. at 7 days after molding shall be one MN/sq.m. (10 kg./sq.cm.).
3 Lime content and water content of the mix shall each be within
The placing and spreading of stationary plant mixes shall be as
-0.2% to +2.5% of the approved mix design percentages.
specified for cement stabilized courses.
3.4.3.19 Lime Stabilization Procedures - Safety Precautions
3.4.3.15 Bitumen Stabilization Procedures - Compaction and
Finishing Special precautions shall be taken when handling quicklime as
it will rapidly corrode equipment and can inflict severe skin burns to
Compaction of bitumen stabilized courses to I 00% of personnel coming in contact with it.
laboratory density of approved job mix specimens, finishing, and
2 Suitable methods for handling quicklime shall be adopted,
provision of longitudinal joints, shall be as specified for cement
including fully mechanized or bottom dump handling equipment and
stabilized courses.
protective clothing worn by the operators. Working operations should
3.4.3.16 Bitumen Stabilization Procedures - Tolerances and take into account the wind direction to minimize the dust problem and
consequent eye or skin irritation to any personnel in the vicinity.
( Replacement of Unsatisfactory Areas
3 When hydrated lime is used, precautions shall also be taken
Finished surface tolerances and the rectification procedures for against the effects of prolonged exposure to the skin.
any areas which fail to meet such tolerances, shall be as specified for
cement stabilized courses. 3.4.3.20 Lime Stabilization Procedures - Stationary Plant
2 Where high spots require trimming after initial compaction, Mixing
raking or similar procedures may be required. If the area is unduly
When approval is given to utilize stationary plant for mixing,
damaged or pitted, the stabilized mix shall be removed and replaced
whether batch mixing plant or continuous type mixing plant, the plant
with fresh stabilized mix spread and properly compacted and finished.
and equipment and handling and mixing procedures shall be as
3.4.3.17 Bitumen Stabilization Procedures - Testing of Bitumen specified for cement stabilization and as specified herein for plant
mixing oflime stabilized materials.
Stabilized Courses

For every 5,000 sq.m. of each stabilized layer or for each day's 3.4.3.21 Lime Stabilization Procedures -Mixed in Place
completed area (whichever is the smaller) the following sampling and Procedures
testing shall be carried out:
Mixed in place procedures will normally be permitted when the
i. In situ density of a minimum of 3 samples (taken
soil to be stabilized is in-situ site material.
immediately after completion of final compaction)

dar 3-11
copy 152
Granular & Stabilised Subbase,
Basecourse & Stabilised Subgrade > Highway Design Standards 2017
Sultanate of Oman I Ministry ofTransport & Communications . OGRLT

2 Spreading and mixing of the lime and soil material shall be 2 Curing seal shall be measured by sq.m. of areas computed from
carried out as specified for cement stabilized courses. the length and width of the completed sections shown on the Drawings.

3.4.3.22 Lime Stabilization Procedures - Placing and Spreading 3.4.5 Basis of Payment
Stationary Plant Mixes
The amount of completed and accepted work, measured as
Placing and spreading of stationary plant mixes shall be as provided for above, will be paid for at the unit rates for the various
specified for cement stabilized courses. items in the Bill of Quantities, which rate shall be full compensation
for equipment, tools, labor, locating sources of supply, supplying
3.4.3.23 Lime Stabilization Procedures - Compaction and materials, sampling and testing, screening, crushing, transporting,
Finishing stockpiling, laying, mixing and compacting and for extra material in
tapered edges, and other items necessary for the proper completion of
Compaction of lime stabilized courses to I 00% of laboratory
the work.
density of approved job mix specimens, finishing and provision of
longitudinal joints, shall be as specified for cement stabilized courses
3.4.6 Items in the Bill of Quantities
with the following modifications:
i. When quick lime is used, the layer shall not be compacted I. Cement Stabilized Base Course (thickness) cu.m
immediately after spreading the lime, as hydration of the ii. Bitumen Stabilized Base Course (thickness) cu.m
lime will cause damage to the compacted layer. The time
within which the compaction shall be completed will be as iii. Lime Stabilized Base Course (thickness) cu.m
estimated in the laboratory.
IV. Curing Seal sq.m
ii. Compaction shall not take place after lime hydration. Any
lime stabilized material that has been mixed or deposited 3.5 Recycled Aggregates for Roadworks
after lime hydration, shall be removed and replaced with
fresh material, mixed and treated as specified.
3.5.1 Description
3.4.3.24 Lime Stabilization Procedures - Tolerances and This Sub-section specifies the requirements of recycled
Replacement of Unsatisfactory Areas aggregate material resulting from the crushing of demolishing and
excavation wastes for use in embankment fill layers, subgrade layers
Finished surface tolerances and the rectification procedures for
and subbase courses under flexible and rigid pavements of roads
any areas which fail to meet such tolerances shall be as specified for
receiving low traffic volumes, and that are classified as: Secondary
cement stabilized courses.
Roads, Service Roads, Residential Access Roads and Agricultural
3.4.3.25 Testing of Lime Stabilized Courses Roads, provided that the material satisfies the specification
requirements stated here below.
For every 5,000 sq.m. of each stabilized layer or for each day's
2 The prime environmental advantage of recycling is that they
completed area (whichever is the smaller) the following sampling and
reduce the haulage from quarries and hence reduce the consumption
testing shall be carried out:
of non-renewable hydrocarbons and the consequential emission of
i. In situ density of a minimum of 3 samples (taken
greenhouse gases. However, collecting demolition debris, transferring
immediately after completion of final compaction)
it to a reprocessing facility, crushing, removing steel and other
determined in accordance with AASHTO T 191 or
impurities, grading, testing, and transporting to the construction site
ASTM D2167 and which shall be not less than 100% of
each uses substantial energy and combine to armul the advantage. The
the density of the approved laboratory mix.
distances for transportation and the mode of transport are therefore
ii. Lime content in accordance with AASHTO T 232.
critical and the Contractor shall carry out a Life Cycle Cost Analysis
iii. Gradation of mix in accordance with AASHTO T 27.
and justifY the environmental advantages of using recycled material in
iv. If the source of materials changes, the moisture -density
the project.
relationship in accordance with AASHTO T 134 and
gradation of the new mix in accordance with AASHTO 3 Recycled materials from construction processes or from
T27. existing pavement layers shall be separated according to type or
v. Compressive strength of a set of3 test specimens molded processing and shall be stockpiled at suitable locations to allow proper
and cured in accordance with AASHTO T 134 and separation of the different sources of material and to ensure uniformity
ASTM C192/Cl92M, and tested in accordance with and consistency of the material properties. The separated processed
AASHTOT22. material shall be stored in stockpiles and separated for testing and
approval by the Engineer prior to use in the construction works.
3.4.4 Method ofMeasurement 4 Recycled aggregate shall consist of clean, hard, durable, angular
fragments of concrete, rock and sand particles of uniform quality and
Cement stabilized course, bitumen stabilized course and lime
shall be free from organics, deleterious material, and inert material
stabilized course shall each be measured by cu.m. of compacted
such as pieces of steel, plastic or wood which may affect its reuse. The
stabilized course. Measurements shall be of the area and thickness
aggregate material shall be non-plastic and chemically stable
dimensions shown on the Drawings.

3-12
copy 152
dar
Granular & Stabilised Subbase,
Basecourse & Stabilised Subgrade
Ministry ofTran port & Com'Tlunicdtions . DGRLT
/
/_ _ ' - - - - - - - '
3
5 The optimum percentage of recycled material in the Swell(%), - 2.0 max 1.0 max .
soil/aggregate mixtures should be determined based on the results of (ASTM 04829)
laboratory testing on the recycled aggregate/soil blends to determine Clay Lumps(%), 3.0 max. 2.0 max. Free
(ASTM C l42)
( the relevant strength and the deformation and quality properties of the
end product. The actual percentage of recycled aggregate content Requirement Embankment Subgrade Aggregate
would depend on various factors including: gradation, quality Fill Layer Subbase
requirements and engineering properties of the processed material as Layer
well as on the Contractor' s experience and resources (plants, Gypsum Content 3.0 max. 1.0 max. Free
equipment, and expertise). (%), (BS 7533-3)
6 The use of recycled aggregate material shall be prohibited in Elongation Index - - 35 max.
areas and locations subject to sever exposure conditions such as highly (%), (BS 812)
sulphate contaminated exposures. Flakiness Index - - 35 max.
(%), (BS EN
3.5.2 Materials 933-3)
Los Angeles - - 40 max .
3.5.2.1 Aggregate Material Abrasion Wear
(%), (ASTM
The recycled aggregate subbase material shall be crushed and
Cl31)
mixed with virgin aggregates so as to conform to the requirements of
Tables 3.5.2.1 and 3.5.2.2.
Soundness, (%), - - 15 max.
(5 cycles of
2 Aggregates retained on the No. 4 (4.75 mm) sieve shall be Magnesium
capable of withstanding the effects of handling, spreading, and Sulphate),
compacting without degradation production or deleterious fmes. (ASTMC88)
( 3 Natural sand, or finer mineral matter, or both, may be added Crushed - - 50 min.
where available and suitable. Aggregate (%
Material
Requirement Embankment Subgnde Aggregate Retained on 3/8
Fill Layer Subbase inch sieve (9.5
Layer mm)bywt.,
( Particle Size Less than Less than - having at least
two (2) fractured
75mm and not 75mm and
more than Y, not more faces)
the layer than Y, the Maximum% 40 max. 35 max. 9.0 max
thickness layer passing No. 200
thickness (75 Jllll)
Grading, (ASTM - - Table Sand Equivalent 35 min. - 35 min.
Cl36) 3.5.2.2 Value, (ASTM
Organic Material 2.0 max. 2.0 max. Free 02419)
(%)(AASHTO Table 3.5.2.1: Required Properties for Recycled Aggregate
T267) Material for Roadworks
Liquid Limit 35 max. 30 max. 25 max. 4 The fine and coarse aggregate material in the aggregate subbase
(%), (ASTM course mixture shall be combined proportionally to meet the gradation
04318) requirements of Table 3.5.2.2.
Plasticity Index 15 max. lOmax. 4 max .
(%), (ASTM
AASHTO Sieve Reeycled Aggregate
04318)
Opening Size, mm Subbase Course-
Chloride Content 2.0 max. l.Omax. l .Omax.
•.4 Passing (by mass)
(water soluble)
50mm 100
(%), BS 812
37.5 95- 100
Sulphates 2.0 max. 1.5 max . 1.5 max.
25 90- 100
Content (Water
9.5 50-85
Soluble)(%), BS
4.75 mm 25-45
812
4-days Soaked 2.36 mm 15-40
15 min. 25 min. 120min.
CBR Value, 4251-lm 10-25
(AASHTO Tl80, 751-lm 2-9
Tl93) Table 3.5.2.2: Gradation Rcquir·ements for Recycled
Aggregate Subbase Material

dar 3-13
copy 152
Granular & Stabilised Subbase,
Basecourse & Stabilised Subgrade > Highway Design Standards 2017
Sultanate of Oman I Ministry ofTransport & Communications . OGRLT

3.5.2.2 Sampling and Testing

A sample of material delivered to the project shall be taken for


each 700 cu.m. placed or for each day' s placement, whichever is
greater, and shall be tested for the set of properties and gradation
specified under Tables 3.5.2.1 and 3.5.2.2 above, depending on the
area of application of the material.
2 Noncompliant material shall be resampled and retested for
compliance. Material not in compliance after the initial and follow-
up testing shall be removed and replaced by the Contractor at no cost
to the Contract.

3.5.3 Construction Requirements for Recycled


Fill, Subgrade and Subbase Course Layers
The construction requirements for the embankment fill layer,
subgrade layer and subbase layer, including surface finishing, mixing
and spreading, laying and compaction of each layer, protection of
surfaces, acceptable tolerances and field quality control testing, shall
comply with those specified under Section 2 "Earthworks" and
Section 3 "Granular Subbase, Aggregate Base Course and Stabilized
Base Courses" of the Sultanate of Oman Standard Specifications for
Road and Bridge Construction.

3.5.4 Method of Measurement


The method of measurement of recycled material used in
embankment shall comply with the requirements of sub-section 2.5.2
of Specification Section 2 "Earthworks" of the Standard
Specifications.
2 The method of measurement of recycled material used in
subgrade layer shall be in accordance with sub-section 2.6.4 of
Specification Section 2 "Earthworks" of the Standard Specifications.
3 Recycled aggregate subbase course shall be measured in
accordance with subsection 3.2.4 above.

3.5.5 Basis of Payment


The amount of completed and accepted work, measured as
provided for above, will be paid for at the unit rates for the various
items in the Bill of Quantities, which rate shall be full compensation
for equipment, tools, labor, locating sources of supply, supplying
materials, sampling and testing, screening, crushing, transporting,
stockpiling, laying, mixing and compacting and for extra material in
tapered edges, and other items necessary for the proper completion of
the work.

3.5.6 Items in the Bill of Quantities


i. Recycled Subgrade layer in cut cu.m

ii. Recycled Aggregate Subbase Course cu.m

3-14
copy 152
dar )

You might also like