You are on page 1of 14

(

Drainage

copy 152
Ref. Title Page No.
8.1 Pipe Culverts 8-1

8.1.1 General 8-1


8.1.1.1 Description 8-1
8.1.1.2 Submittals 8-1
8.1.1.3 Installation and Checking 8-1
8.1.2 Materials 8- 1
8.1.2.1 Delivery, Storage and Handling 8-1
8.1.2.2 Precast Reinforced Concrete Pipe 8-1
8.1.2.3 Unreinforced Concrete Pipe 8-1
8.1.2.4 Reinforced Concrete Arch Culvert 8-1
8.1.2.5 Reinforced Elliptical Culvert 8-1
8.1.2.6 Corrugated Steel Circular Pipe and Pipe
Arches 8-1
8.1.2.7 Bituminous Coated Corrugated Steel
Circular Pipe and Pipe Arches 8-1
8.1.2.8 Polymer Coated Steel Circular Pipe and Pipe
Arches 8-2
8.1.2.9 Concrete and Steel 8-2
8.1.3 Construction Requirements 8-2
8.1.3.1 Excavation, Bedding and Backfilling 8-2
8.1.3.2 Pipe Laying 8-2
8.1.3.3 Precast Concrete Pipe and Pipe Arches 8-2
8.1.3.4 Corrugated Metal Pipe and Pipe Arches 8-2
8.1.3.5 Cast-in-Situ Concrete Pipe and Pipe Arches 8-2
8.1.4 Method of Measurement 8-2
8. 1.5 Basis of Payment 8-3
8..1.6 Items in the Bill of Quantities 8-3

8.2 Storm Sewers 8-3

8.2. 1 General 8-3


8.2.1.1 Description 8-3
8.2.1.2 Installation and Checking 8-3
8.2.1.3 Submittals 8-3
8.2.2 Materials 8-3
8.2.2.1 Delivery and Storage 8-3
8.2.2.2 Concrete and Steel 8-3
8.2.2.3 Concrete Pipes 8-3
8.2.2.4 uPVC Pipe 8-3
8.2.2.5 Polyethylene (PE) Gravity Pipe 8-4
8.2.2.6 GRP Pipes 8-4
8.2.2.7 Vitrified Clay Pipes 8-4
8.2.2.8 Joints for Concrete Beds and Pipe Surrounds 8-4
8.2.2.9 Bitumen Emulsion 8-4
8.2.2.10 Pumping Plant 8-4

copy 152
Ref. Title Page No.
8.2.3 Construction Requirements 8-4
8.2.3 .1 Excavation, Bedding and Backfilling 8-4
8.2.3.2 Pipe Laying 8-4
8.2.3.3 Jointing of Pipes 8-5
8.2.3.4 Line and Gradient 8-5
8.2.3.5 Floatation 8-5
8.2.3 .6 Pipe Built Into Structures 8-5
8.2.3.7 Cleaning and Inspecting of Storm Sewer
Pipes 8-5
8.2.3.8 Field Testing: Generally 8-5
8.2.3.9 Air Testing of Pipelines 8-6
8.2.3. 10 Hydrostatic Testing ofPressure Pipelines 8-6
8.2.3 .11 Infiltration Test for Gravity Pipes 8-6
8.2.3.12 Deflection Tests for GRP Pipes 8-6
8.2.3.13 Hydraulic Individual Joint Test for Pipes

( Exceeding I 000 mm 8-6


8.2.-t :Vlethod of Mea surement 8-6
8.2.5 Basis of Payment 8-7
8.2.6 Items in the Bill of Quantities 8-7

8.3 Manholes, Inlets and Chambers 8-7

8.3.1 Description 8-7


8.3.2 Materials 8-7
8.3.3 Constru<·tion Requirements 8-8
8.3.3.1 Manholes 8-8
8.3.3 .2 Chambers for Grated Inlets, Curb Inlets and
Ditch Inlets and Outlets 8-8
8.3.3.3 Ironwork 8-8
8.3.3.4 Cleaning 8-8
8.3.-t Method of Measurement 8-8
8.3.5 Basis of Payment 8-9
8.3.6 Items in the Bill of Quantities 8-9

8.4 Drainage of Structures 8-9

8.4.1 Description 8-9


8.4.2 Materials 8-9
8.4.2. 1 Gully and Channel Gratings and Frames 8-9
8.4.2.2 Pipes 8-9
8.4.2.3 Drainage Backfilling 8-9
8.4.3 Construction Requirements 8-9
8.4.4 Method of Measurement 8- 10
8.4.5 Basis of Pa yment 8-10
8.4.6 Items in the Bill of Quantities 8-10

copy 152
copy 152
r

Ministry ofT1 ansporl & Communi~


Drainage
tiun . OGRt:
8
8.1 Pipe Culverts the gasket during assembly and to produce full water-tightness.
Rubber gasket shall be to ISO 4633 orBS EN 681-2.
8.1.1 General 3 Manufactured pipe shall, if required by the Engineer, be tested,

( 8.1.1.1 Description
prior to delivery to site, for structural strength, crushing strength and
absorption. The manufacturer's specification and certificate shall be
This Sub-section describes requirements for furnishing all submitted for prior approval before pipes are delivered to the site.
materials, constructing and installing concrete and steel pipe culverts 4 Pipes that fail to meet the strength requirements may, with the
including excavation, bedding and backfilling and all work described approval of the Engineer, be incorporated in the work provided the
in this Section of the Specification and as shown on the Drawings. following requirements are met.
i. The strength does not fall below 80% of that specified.
8.1.1.2 Submittals
ii. The pipes are clearly marked and stored separately from
Coordination Drawings: Submit drawings showing culverts pipes which fully comply with strength requirements.
and major system components. Indicate interface and spatial 111. The pipes are bedded in Class 15 concrete.
relationship between culverts, system components, adjacent utilities,
5 If under-strength pipes are installed and bedded in Class 15
and proximate structures.
concrete with pipes fully complying with the strength requirements,
2 Shop Drawings: Submit shop drawings of culverts including the whole run shall be classified as under-strength for record
plan layout and locations, types, sizes, capacities, and flow purposes. No payment will be made for the concrete bed.
characteristics in accordance with the requirements of this
Specification Sub-section 1.11. 8.1.2.3 Unreinforced Concrete Pipe

3 As-Built Drawings: At project close-out, submit record Unreinforced concrete pipe shall meet the requirements of the
drawings of installed culverts, in accordance with requirements of Highway Design Standards and shall comply with BS 5911-1 ,
this Specification, Sub-section 1.11. AASHTO M 86M I M 86, DIN V 1201 and DIN EN 1916 or ASTM
( 4 Certificate of Compliance: Submit certificates of compliance C14M and with Paragraph 8.1.2.2 items 2 to 5. Class shall be as
required by the Client Authority and as directed by the Engineer. designated on drawings. Cement used in manufacture shall be
ordinary Portland cement to BS EN 197-1.
8.1.1.3 Installation and Checking
8.1.2.4 Reinforced Concrete Arch Culvert
The work shall be supervised by qualified representatives of
the Contractor and full facilities and assistance shall be provided by Reinforced concrete arch culvert shall comply with AASHTO
the Contractor to enable the Engineer to inspect or check the work at M 206M I M 206 or ASTM C506-02. Unless otherwise specified
any time. Such inspection or checking shall in no way relieve the Class A-IV shall be used for spans of 1300mm or less, and Class A-
Contractor from any of his obligations. III for larger spans.
2 The Contractor shall be responsible for making minor Reinforced Elliptical Culvert
8.1.2.5
adjustments to the location of work as necessary to suit site
constraints and road alignment and profile subject to the approval of Reinforced concrete elliptical culverts shall be to AASHTO M
the Engineer. 207M I M 207 or ASTM C507M-02. Their Class shall be as
designated on drawings.
8.1.2 Materials
8.1.2.1 Delivery, Storage and Handling 8.1.2.6 Corrugated Steel Circular Pipe and Pipe Arches

Deliver piping with factory-applied end caps. Maintain end Corrugated steel culvert pipe shall comply with the
caps through shipping, storage, and handling to prevent pipe-end requirements of AASHTO M36 and be zinc coated.
damage and to prevent entrance of dirt, debris, and moisture. 2 A certificate of guarantee from an approved pipe fabricator
2 Protect stored piping from moisture and dirt. Elevate above shall be submitted by the Contractor for each shipment of pipe
grade. Do not exceed structural capacity of floor when storing inside. delivered to the Site. The Certificate shall show the quantities of
material and state that the listed materials conform to the specified
3 Protect flanges, fittings, and specialties from moisture and dirt.
requirements.
4 Manufacturer's recommendations on handling, repairing,
3 The Engineer may test any material for compliance with the
laying, jointing, anchoring, cutting and other works for pipes and
Specification at any time and reject any material which does not
fittings are to be strictly followed.
meet the requirements even though it has received prior approval
8.1.2.2 Precast Reinforced Concrete Pipe based on a Certificate of Guarantee.

Reinforced concrete pipe shall meet the requirements of 8.1.2.7 Bituminous Coated Corrugated Steel Circular Pipe and
Volume 2 of the Highway Design Standards and shall comply with Pipe Arches
BS 5911-1, BS EN 1916 Class H, ASTM C76-02 Class IV or DIN V
1201 and DIN EN 1916. Cement used in manufacture shall be Bituminous coated corrugated steel circular pipe and pipe
arches shall comply with AASHTO M 190, and with Paragraph
ordinary Portland cement to BS EN 197-1 .
8.1.2.6.
2 Joints shall be gasket type with flexible spigots and sockets.
The shape of the joint shall be designed to prevent any movement of

dar - 8-1
copy 152
Drainage > Highway Design Standards 2017
Sultanate of Oman I Ministry ofTrdn port & Communications . DGRLT

4 Multiple pipe culverts, unless otherwise shown on the I


8.1.2.8 Polymer Coated Steel Circular Pipe and Pipe Arches Drawings, shall be laid with one-half diameter of pipe or a minimum I

Polymer coated metal pipe and pipe arches shall comply with of300mm, whichever is greater, between the pipes.
AASHTO M 246 and with Paragraph 8. I .2.6.
8.1.3.4 Cormgated Metal Pipe and Pipe Arches
8.1.2.9 Concrete and Steel Metal pipe shall be laid with outside laps of circumferential
Concrete, reinforcing steel and reinforced concrete shall joints pointing upstream and with longitudinal laps along the sides. If
conform to the requirements of Sub-sections 5.1, 5.2 and 5.3 pipe sections are jointed on the Site, the ends shall be butted as
respectively. Structural steel and other metalwork shall conform to closely as cormgations will permit and shall be joined with a firmly
Sub-section 6.2. bolted coupling band of the same material as the pipe. Camber shall
be built into the pipe structure to compensate for settlement from fill
8.1.3 Construction Requirements loads,
2 Multiple culverts, unless shown otherwise on the Drawings,
8.1.3.1 Excavation, Bedding and Backfilling shall be laid with one-half span of pipe or a minimum of 300mm
All excavation and backfill shall conform to the requirements whichever is the greater, between pipes.
of Sub-Sections 2.7 and 2.8. 3 The Contractor shall examine material to ensure internal
coating or lining and outer coating or sheathing are undamaged. If
8.1.3.2 Pipe Laying damaged, the Contractor shall make good or dispose of as directed.
Pipes shall not be placed until the foundation has been Damage to bituminous or epoxy resin coatings may be repaired on
approved by the Engineer. Pipes shall be laid accurately to line and site by application of a repair material of a brand and type approved
level and shall have a uniform bearing at each joint and along the by the Engineer. Pipes having any localized bends in excess of 5%
of the nominal pipe diameter or dents in excess of 13mm depth will
entire length of pipe. Pipe laying shall begin at the downstream end
be rejected. Pipes rejected because of these defects may be used if
and progress upstream.
satisfactorily repaired and approved by the Engineer.
2 Manufactured pipe shall be handled and assembled in
accordance, with the manufacturer's instmctions. When pipe laying 8.1.3.5 Cast-in-Situ Concrete Pipe and Pipe Arches
is not in progress, the Contractor shall close open ends of pipes with
properly fitted temporary wooden plugs or standard caps as directed Cast-in-situ pipes shall be constructed in accordance with the
Drawings, or in a manner proposed by the Contractor and approved
3 The Contractor shall use ropes, wire slings, band slings,
by the Engineer.
spreader beams etc. for lowering pipes as recommended by
manufacturer for each type of pipe and as approved. 2 When the Contractor elects to construct the pipe in a trench
with no external vertical forms, 40mm of additional concrete cover
4 All material shall be carefully examined for damage and tested
to the reinforcement steel shall be provided.
in accordance with manufacturer's instructions before laying, to the )
satisfaction of Engineer. 3 Longitudinal construction joints will only be permitted as
shown on the Drawings. Transverse construction joints will be
5 The Contractor shall remove dirt and other materials before
permitted provided prior approval is obtained from the Engineer.
lowering the pipe into the trench and verify the pipe inside is clear
4 Forms for cast-in-situ pipe shall be approved prior to their use.
from constmction debris before making joints.
Inside pipe forms shall be suitably unyielding during placement of
6 Pipe on solid ground: The Contractor shall cut holes in the
concrete. Interior arch forms may be removed after 72 hours if
bottom of trench to allow proper jointing and for barrel of pipe to
approved by the Engineer. The Contractor shall take precautions
bear evenly on solid ground for its full length.
when removing forms to protect the culvert from damage.
7 Pipe on granular bedding: The Contractor shall scoop out Backfilling shall not commence until tests indicate the concrete has
locally at sockets/couplings to enable the pipe to rest uniformly on attained strength of 50% of the requirement for its Class.
the barrel and adjust to the exact line and level. After testing, the
Contractor shall lay and compact further granular material in 150 8.1.4 Method of Measurement
mm layers or as approved to levels shown on the Drawings.
Pipe culverts shall be measured by the linear meter of culvert
8.1.3.3 Precast Concrete Pipe and Pipe Arches laid or constructed as per the contract Drawings. Culverts of each
type, class and size shall be measured separately. For pipe culverts
Pipes shall be laid with hub, bell or groove ends upstream.
without headwalls, measurement shall be taken from end to end
2 Where lift holes have been used, they shall be filled with an along the centerline of the pipe. For pipes connected to structures,
approved cement-sand mortar to provide a watertight section. measurement shall be taken between the inside faces of parapet or
Mortar shall be finished flush on the inside of the pipe. wall along the centerline of the pipe. )
3 Pipe joints shall be sealed with flexible watertight elastomeric 2 The measured length of cormgated metal pipe shall include the
or mbber gaskets, approved bituminous sealers or plastic sealants. length ofbends (elbows) installed.
Bituminous or plastic sealants shall be applied at the time pipe is
3 Headwalls, wing walls, aprons and cut-off walls that are part
being laid. Sealants shall be installed in accordance with the sealant
of a pipe culvert installation are measured separately in accordance
manufacturer's instructions so that the joint is completely filled.
with Sub-Section 5.9.

-8-2
copy 152
dar
.r

Drainage
Ministry ofTranspo & Communic tion . DGRLT
8
4 Trench excavation, bedding and backfilling for culvert pipe 2 Shop Drawings: Submit shop drawings of storm sewers
runs is measured separately under Sub-sections 2. 7 and 2.8, Clauses systems including plan layout and locations, types, sizes, and
2.7.4 and 2.8.4 capacities of pipes, manholes and stormwater inlets in accordance
with the requirements of the Specification Sub-section 1.12.
5 No separate measurement or payment will be made for
connection to drainage structures or to existing pipes. Nor for 3 As-Built Drawings: At project close-out, submit record
additional reinforcing steel, cover and protection to in-situ concrete drawings showing the installed pipes and related components with
pipe culverts and pipe arches, all of which are considered subsidiary sufficient details to allow for locating the pipes for future
work. maintenance. The As-Built drawings shall be in accordance with
requirements of the Specification, Sub-section 1.12.
8.1.5 Basis of Payment 4 Certificate of Compliance: Submit certificates of compliance
as required by the Client Authority and as directed by the Engineer.
The quantity of completed and accepted work. measured as
provided for above, will be paid for at the unit rate per linear meter
in the Bill of Quantities for 'the various types, classes and sizes of 8.2.2 Materials
pipe and arch culverts, which rate shall be full compensation for the
8.2.2.1 Delivery and Storage
cost of supply, transport, handling, installation of pipe, joints,
materials, labor, equipment, tools and other items necessary for Delivery, storage and handling shall comply with the
proper completion of the work. requirements of Paragraph 8.1.2.1.
2 During storage plastic pipes shall be protected from sunlight
8.1.6 Items in the Bill of Quantities and supported to prevent sagging and bending.

i. Unreinforced precast concrete 8.2.2.2 Concrete and Steel


Pipe culvert (diameter) (lin.m.)
ii. Reinforced precast concrete Concrete, reinforcing steel and reinforced concrete shall
( Pipe culvert (diameter) (lin.m.) conform to the requirements of Sub-sections 5.1 , 5.2, and 5.3
iii. Reinforced precast concrete arch respectively. Structural steel and other metalwork shall conform to
Culvert (size) (lin.m.) Sub-section 6.2.
iv. Reinforced precast concrete
8.2.2.3 Concrete Pipes
Elliptical culvert (size) (lin.m.)
V. Corrugated steel pipe culvert Reinforced and unreinforced concrete pipes shall comply with
(Diameter) (Coating) (lin.m.) the requirements of Paragraphs 8.1.2.2 and 8.1.2.3, respectively.
vi. Corrugated steel pipe arch
Culvert (size) (coating) (lin.m.) 8.2.2.4 uPVC Pipe
vii. Cast in-situ concrete pipe or
Pipes shall conform to DIN 8061 I 8062 Class 6 kg/cm2 or
Pipe arches (size, type) (lin.m)
Class 10 as indicated on the Drawings or the Bill of Quantities. Use
concrete encasement if cover is less than 1 meter or greater than 5
8.2 Storm Sewers meters.
2 Fittings shall be to DIN 8061 I 8062 fabricated from pipe.
8.2.1 General
3 Joints shall be to DIN 8061 I 8062, socket spigot with rubber
8.2.1.1 Description sealing rings to BS EN 681-2.
4 Under-drain pipes shall be perforated plastic pipe conforming
This Sub-section describes requirements for constructing pipes
to DIN 8061 Class 10 kg/cm2 or equivalent. Perforations may be
for the removal of surface water from roads, including connections to
circular holes or slots. Different filter requirements shall apply to
rainwater inlets and discharge to suitable outfall. The work shall
each type of perforation.
include furnishing all materials, installing pipes, excavation, bedding
and backfilling. 5 Circular perforations shall be between 5 mm and 10 mm in
diameter arranged symmetrically in a minimum of 4 rows parallel to
8.2.1.2 Installation and Checking the axis of the pipe. All rows shall be in the lower half of the pipe but
no row shall be closer than 36 degrees to the invert. Perforations in
Installation and checking shall comply with the requirements
each row shall be at a maximum distance of 100 mm center to center.
ofParagraph 8.1.1.3.
6 Slotted perforations shall be between 1.5 mm and 3 mm in
2 Collect site information by performing site survey, researching
width, and between 25 mm and 40 mm in length measured on the
public utility records, and veri tying existing utility locations.
inside of the pipe. Perforations shall be in 2 rows parallel to the axis
8.2.1.3 Submittals of the pipes on each side of the invert. Each row shall be
approximately 45 degrees from the invert. Perforations shall be
Coordination Drawings: Submit drawings showing pipes and spaced between 20 and 30 times the average slot width along each
major system components. Indicate interface and spatial relationship row.
between pipes, system components, adjacent utilities, and proximate
7 Pipes and fittings shall be protected from the direct rays of the
structures.
sun at all times by means of reflective cover sheets.

dar - 8-3
copy 152
Drainage > Highway Design Standards 2017
Sultanate of Oman I Ministry ofTransport & Communications . DGRLT

vi. Joints shall be GRP double socket couplings with


8.2.2.5 Polyethylene (PE) Gravity Pipe rubber rings to ISO 4633 orBS EN 681-2
Polyethylene (PE) pipes and fittings shall conform to ASTM v11. The allowable angular deflection shall conform to the
03035-01 , ASTM F894. and installation shall be in accordance with requirements ofBS EN1796 & BS EN14364.
ASTM 02321-00 and manufacturer's recommendations.
8.2.2.7 Vitrified Clay Pipes
2 Jointing system should be in accordance with ASTM F894.
Vitrified clay pipes and fittings shall be to BS EN 295 and
3 Materials used shall have a standard PE code designation 2406
shall be marked accordingly.
and a minimum hydrostatic design basis of 1250 psi (8.6MPa) for
water at 73.4°F (23°C) according to AWW A C906 Table I. 2 Unless otherwise indicated, pipes and fittings shall be Extra
Strength and shall comply with absorption tests made in accordance
8.2.2.6 GRPPipes with BS 65 .

Pipes and fittings shall conform to BS EN1796 & BS 3 Pipes shall be supplied with approved flexible and telescopic
EN 14364 or American Water Works Association A WWA C950. rubber ring joints which shall be capable of withstanding the
specified tests pressures applied both internally and externally.
2 Pipe and fittings shall include a corrosion resistant liner, a
structural wall and a resin rich exterior surface. 4 Junctions on clay pipe sewers shall be of similar material and
suitable for use with flexibly jointed pipes.
3 The liner shall have a nominal thickness of 1.0 mm. The liner
surface shall be reinforced with C glass. The remainder of the liner 5 Before any length of pipe is laid, it shall be inspected and
thickness shall be reinforced with an acid resistant chopped E glass stood or slung vertically at the side of the trench and ' rung' with a
strand or mat. wooden mallet. Any damaged or cracked pipe shall be rejected.

4 The pipe structural wall shall consist of glass reinforcement, 6 Where shown on the Drawings, pipes for use in the
and fine silica sand, all impregnated with resin. The fine silica sand construction of drains shall be British Standard Surface Water pipes
shall be added to the structural layer to achieve the design thickness glazed or unglazed manufactured in accordance with the
for the required stiffness specified such that the overall hoop flexural requirements ofBS 65, with Type 2 sockets or plain ended supplied
modulus (E) for pipe is not less than 24 GN/m 2 • Silica sand and filler with sleeve couplings.
content shall not exceed 50%. 7 Perforated pipes shall be Type I socketed and sleeve coupled
5 Pipes shall be provided with a resin rich outer layer reinforced pipes.
with one layer of C glass veil. The exterior layer shall have a 8 Field drain pipes shall comply with the requirements ofBS EN
minimum thickness of 0.2 mm. The layer shall be resin rich and 295-5 and BS 1196.
reinforced with one layer of C glass.
8.2.2.8 Joints for Concrete Beds and Pipe Surrounds
6 The resin used for the corrosion resistant liner of the pipe and
fittings shall be high grade polyester resin (isophthalic or better) type. Flexible joints in concrete beds and surrounds to pipes shall be
For the structural wall and exterior layer of the pipe a high grade formed with compressible fibrous board, or similar approved
isophthalic polyester resin shall be used. No dark pigments shall be material, 20mm thick.
used in the pipe or fittings.
8.2.2.9 Bitumen Emulsion
7 Pipes shall be designed for a life of not less than 50 years.
Contractor shall submit calculations for initial and long term Bitumen emulsion shall be to BS 434 and shall contain not less
deflection with truck loads, buckling, vacuum, pressure class, and than 53% of prime bitumen.
strain in accordance with Appendix A of AWWA C-950 or
equivalent. The maximum calculated long term deflection should not 8.2.2.10 Pumping Plant
exceed 3%. Copies of the design calculations shall be submitted to Pumping plant is as specified in Section 17.
the Engineer for approval.
i. Stiffness: Minimum 5,000 N/m 2. Suitability of stiffness 8.2.3 Construction Requirements
shall be verified by Contractor for the various trench
and pipe laying conditions and as recommended by the 8.2.3.1 Excavation, Bedding and Backfilling
manufacturer. Pressure Class; 6 kg/cm2 minimum or as
All excavation and backfill shall conform to the requirements
shown on Drawings.
of Sub-Sections 2.3, 2.7, and 2.8.
II. Longitudinal Strength: Conform to BS EN1796 & BS
EN14364 or ASTM 03262 table 7. 8.2.3.2 Pipe Laying
iii. Hoop strength shall be according to ASTM 03517
Table 8. 1 Pipe laying shall comply with the requirements of Paragraph
IV. Strain corrosion resistance tests shall be carried out as 8.1.3.2.
per ASTM 0 3681 or to BS EN1796 & BS EN14364 2 For pipe on a concrete bed or surround, the Contractor shall
strain corrosion value at 50 years to equal or exceed provide rectangular blocks of concrete Class 25, made in approved
0.7%. moulds at least 14 days before use, and approved hardwood folding
V. Markings shall be to BS EN1796 & BS EN14364 wedges. The Contractor shall provide two concrete blocks for each
Clause 11. pipe, set and boned into the correct level on the trench formation
bottom and will lay the pipe properly centered and socketed.

-8-4
copy 152
dar
Drainage
Ministry ofTransporl & Communi<:< ti<.nc . DGRLT
8

3 The Contractor shall insert two hardwood folding wedges (of a At no time shall there be less than three sight rails in position on
width equal to the width of the concrete block) between the body of each length of pipeline under construction to any one gradient.
the pipe and block, and drive them together until the pipe is brought 2 Where pipes are laid in headings, the Contractor shall provide

( to the exact level required. The Contractor shall leave blocks and
wedges undisturbed while pipes are being jointed and the concrete
and maintain marks to establish line and level of pipeline. Marks
shall be fixed in each working shaft and two further marks
bed and haunch or surround are being placed. The Contractor shall established in each length of heading.
ensure blocks and wedges are of sufficient size and strength to
prevent settlement of pipes. The Contractor shall leave sufficient 8.2.3.5 Floatation
space to enable joints to be made, tested and inspected. Prevention: Whenever water is excluded from interior of pipe,
4 The Contractor shall lay pipes on an even formation true to the Contractor shall place sufficient backfill above pipe to prevent
grade and line, with sockets facing up the gradient. floatation.
5 Tolerances shall be 6 nun in level and 25 nun in line between 2 The Contractor shall remove: any pipe that has floated, correct
manholes or access points unless otherwise specified. Where pipe is the bedding and relay.
to be constructed in straight lines between manholes the length will
not be accepted if a light at each manhole carmot be seen from 8.2.3.6 Pipe Built Into Structures
adjacent manholes. The Contractor shall thoroughly clean outside surface of pipes
to be built-in immediately before installation. Remove protective
8.2.3.3 Jointing of Pipes
coating to metal pipes, and roughen clay and concrete pipes as
Unless otherwise specified, the manufacturer's instructions directed. Plastic pipes shall be painted with appropriate solvent
( shall be followed regarding placement of bedding and backfilling, cement and sprinkled with dry coarse sand whilst wet. The
cleanliness of joint surfaces, lubricant used, correct location of Contractor shall cut away sheathing from sections to be built-in and
components, provision of correct gaps between end of spigot and after installation restore protection up to external face of structure
back of socket for flexible joints etc. with approved bituminous material.
2 Concrete pipes shall have watertight joints sealed with 2 Install two flexible joints or flexible patented joints adjacent to
approved rubber rings or flexible gaskets. Joints shall have a gap structures. The Contractor shall place first joint not more than one
formed between the end of the spigot and the base of the bell of not pipe diameter from face of structure and second not more than the
less than 6nun and not greater than 20nun. The gap shall then be following distances away from first:
filled with a cement mortar composed of I part Portland cement and i. Pipelines not exceeding 450 mm: 2 pipe diameters.
3 parts fine aggregate, mixed with sufficient water to form a 11. Pipelines over 450 mm and not exceeding I 000 nun:
workable paste. As each section of pipe is laid, the bell or hub of the 1.2 m.
preceding pipe shall be wetted and cleaned and the bottom portion iii. Pipelines over 1000 nun: 1.8 m.
filled with mortar. After the pipe is placed, the remaining top part of
the gap shall be filled. 8.2.3.7 Cleaning and Inspecting of Storm Sewer Pipes

3 The inside of the joint shall be finished smooth and wiped After backfilling and completion of connections to manholes,
clean. The mortar on the outside shall, after its initial set, be etc., but before the trench surfaces are permanently reinstated, the
protected from the sun. Plastic joint compound may be used in lieu interior of the sewers shall be cleaned out and ready for inspection by
of Portland cement mortar, in which case it shall be prepared in the Engineer.
accordance with the manufacturer's reconunendations. 2 Pipelines of 700 mm or more diameter will, where practicable,
4 Synthetic or rubber joint rings shall be stored until needed in a be inspected from the inside and the Contractor shall provide a
cool place away from direct sunlight. suitable personnel trolley for this purpose.
5 Properly fitted temporary wooden stoppers shall be used to 3 Pipelines less than 700 mm diameter and larger pipes which
close the ends of uncompleted pipe lines. The stoppers shall only be carmot be inspected from the inside shall have a mandrel formed
removed when pipes are being laid and jointed. from a cylinder, of diameter 25nun smaller than the pipe diameter
6 The Contractor shall not deflect flexible joints beyond and of length not less than the internal diameter of the sewer, passed
maximum permissible angles given by manufacturer and/or relevant through.
Standards. 4 On completion the drains and sewer pipes shall be flushed
7 The Contractor shall strictly comply with special instructions from end to end with water and left clean and free from obstructions
issued by manufacturers of proprietary joints when laying and and debris.
jointing.
8.2.3.8 Field Testing: Generally
8 The Contractor shall joint differing pipe and fitting material
with adaptors as reconunended by the pipe manufacturer. All test equipment and related items shall be provided on site
before the test, i.e. pressure gauges, instruments, water etc .. .
8.2.3.4 Line and Gradient
2 The Contractor shall carry out tests in the presence of the
In open excavation: The Contractor shall provide and maintain Engineer's Representative.
sight rails and boning rods properly painted to ensure correct 3 Fittings and joints shall be permanently anchored before
alignment of pipe runs. Sight rails shall be positioned either testing and all joints shall be exposed for checking.
vertically above the lines of pipes or immediately adjacent thereto.

dar - 8-5
copy 152
Drainage > Highway De ign Standard• 2017
Sultanate of Oman I Mini try ofTr msport & Communications . DuRLT

4 Sections of pipeline under test shall not exceed 500m in length 8.2.3.11 Infiltration Test for Gravity Pipes
for any one test.
The Contractor shall carry out infiltration test after total
5 Test plugs at the ends of each section shall be secured by struts. backfilling oflength under test.
6 The Contractor shall apply pressure by manually operated test 2 All inlets to the section under test shall be plugged and the
pump or, in the case of large diameter mains, by power driven test residual flow measured by an approved method.
pump, if approved.
3 The following limits are not to be exceeded:
7 The Contractor shall examine exposed joints and repair visible i. Pipelines not exceeding 700 mm: 0.02 liters/hour/100
leaks. linear meters/mm diameter,
8 Should a test fail , the Contractor shall locate leak and replace ii. Pipelines over 700 mm: 0.03 liters/hour/! 00 linear
or make good defective pipe or replace and make good faulty joint meters/mm diameter.
and retest main. 5 The section shall be deemed to have failed if allowable
9 The Contractor shall keep test records in an approved form and infiltration of water is exceeded. The Contractor shall locate source
hand original copy to the Engineer immediately after completion of of excessive infiltration by approved means i.e. traversing light and
test. mirrors or inflated rubber plug etc., make good, and repeat tests until
I0 The Contractor shall carry out hydrostatic test while pipeline is successful.
partially backfilled.
8.2.3.12 Deflection Tests for GRP Pipes
8.2.3.9 Air Testing of Pipelines The Contractor shall conduct deflection tests for GRP pipes
As soon as practicable after a length of pipe has been (as % of overall pipe diameter) as required by the Engineer at three
completed it shall be subjected to an air test to BS EN 1610. The stages. Deflection shall be measured at the spigot end at mid-point
length shall be plugged and sealed and air pumped into the pipe by and at socket end.
approved method (i.e. hand pump) until a pressure 100 mm head of i. Stage 1: at completion of primary backfill (deflection at
water is indicated on a U -tube connected to the system this stage should be below 0.5%).
ii. Stage 2: at final backfill (maximum allowable
2 The Contractor shall allow 5 minutes for stabilization of air
deflection 2.5%).
temperature and adjust pressure to 100 mm. The section will not be
iii. Stage 3: six months after final backfill (maximum
considered satisfactory if the air pressure fails from IOOmm to 75mm
allowable deflection 4.0%).
head of water in 5 minutes or less.
2 Pipes not passing the deflection tests at Stage 2 or Stage 3 will
3 Failure to pass the air test is not conclusive and if no leakage
be removed and replaced.
can be traced by external application of soapy water to all sealing
areas then a hydrostatic test shall be carried out before final rejection 8.2.3.13 Hydraulic Individual Joint Test for Pipes Exceeding
1000 mm
8.2.3.10 Hydrostatic Testing of Pressure Pipelines
The Contractor shall carry out procedures to BS 5886, Type 2
The pipeline shall be filled slowly with water from the lowest
testing after backfilling, or equivalent. The Contractor shall
point. After filling with water, absorbent pipes shall be allowed to
pressurize the joint to 2 bars and wait for 10 minutes then re-
stand for at least 24 hours before testing to allow for complete
pressurize to 2 bars and again wait for 5 minutes. No pressure drop
absorption.
should be observed at the end of the latter period. If a pressure drop
2 Entrapped air shall be bled and pressurizing shall then proceed is observed, the Contractor shall remedy the failed joint to the
until the specified test pressure is reached in the lowest part of the
Engineer's approval.
pipeline section under test. Further quantities of entrapped air shall
be bled while the pressure is being raised.
8.2.4 Method of Measurement
3 Unless otherwise specified, the test pressure shall be equal to
1.0 m head of water above pipe soffit at highest point and not greater Trench excavation, bedding and backfilling are measured
than 6 m head of water at lowest point of section under test but shall under Sub-section 2.8, Clause 2.8.4.
in no case exceed 75% of the· factory hydrostatic test pressure. If 2 Pipes shall be measured in linear meters; each type, class and
maximum head is exceeded, the Contractor shall test section in size is measured separately. Measurement shall be as a straight line
stages. between the inside wall faces of manhole, inlet, sump or gully
4 The test pressure shall be maintained for one hour by pumping connection. No allowance will be made for cut ends and waste.
using a separate test pump. Pumping shall then be stopped for 2 3 No separate measurement will be made for jointing materials,
hours, at the end of which time the line shall be re-pressurized to the junctions and pipe fittings , nor for ancillary work such as breaking
original test pressure and the volume of water pumped into the line into existing pipelines or chambers, cleaning, protection and testing
recorded. of pipelines, or any other item necessary for the proper completion of
5 The pipeline shall be deemed to have failed the test if visible the work, but shall be considered subsidiary work the costs of which
leaks are detected (regardless of leakage being within the allowable shall be deemed to be included in the rates and prices for pipes stated
specified limit) or if the volume of water pumped to restore original in the Bill of Quantities.
test pressure after the period when pumping was stopped exceeds
0.05 liter/linear meter/meter d.iameter/30 minutes.

-8-6
copy 152
dar
(

r
I
Mir, istry ofTr n c t ·'~~ C, .1m· :P' :-
Drainage
,;on~ . r:JRLT
8
diameter. Frames shall be provided with openings for fixing bolts
8.2.5 Basis of Payment which ensure solid frame embedment into the concrete manhole neck.
Covers and frames shall be coated to BS 3416, Minimum thickness
The amount of completed and accepted work. measured as
250 microns. Manholes covers shall have the words "Stormwater
( provided for above, will be paid for at the unit rates listed in the Bill
of Quantities, which unit rates shall be full compensation for
Drainage" inserted, unless instructed otherwise by the Concerned
Authority.
installation, fitting, supplying materials, transport, labor, equipment,
forms, tools and other items necessary for the proper completion of 6 Grated inlets and channel gratings and frames shall comply
( the work as specified in Section 1. with BS EN 124 or equivalent. Grated inlet grating shall have a clear
open area of not less than 600x600 mm and shall be coated to BS
2 Excavation, bedding and backfilling shall be paid for as
3416. Minimum thickness 250 microns. The Contractor shall submit
indicated in Sub-section 2.8, Clause 2.8.5.
manufacturer's details of the proposed grated inlet grating and frame
3 Rates for pipes shall include for the following: for prior approval by the Engineer.
i. Staking out, field surveying and preparation of shop 7 Bricks shall be to BS EN771-l. Net volume of clay masonry
and coordination drawings. units shall be determined according to BS EN 772:3. Water
ii. Pipe fittings, specials and couplings. absorption of clay masonry shall be determined according to BS EN
iii. Transportation to and hauling about the Site, loading, 772:7.
unloading and lowering materials in the trench.
8 Steel ladders shall be mild steel to BS 4211 , galvanized to BS
IV. Lubricating agent used for assembling the pipe sections.
EN ISO 1461 with 200 grams ofzinc per square meter.
v. Cutting, machining, chamfering, etc. of standard length
pipes. 9 GRP ladders shall be obtained from an approved experienced
vi. Assembling the pipes and couplings and connecting to manufacturer, fabricated to an approved pattern and purpose made to
inlets, manholes and/or structures as applicable. suit the depth of each installation as shown on the Drawings. The
vii. Testing as per the specification. ladders shall be drilled for wall fixing at both ends and additional

( viii.
1x.
Ancillary works and materials.
Flushing, cleaning, painting, lining and coating.
intermediate fixing connections shall be provided at centers not
greater than 1.5 meters. Rungs shall be at 300 mm centers and at a
distance of not less than 150 mm from the wall.
8.2.6 Items in the Bill of Quantities i. The resins, glasses and synthetic fabrics used in the
manufacture of the ladders shall be chosen to produce a
i. Storm sewer (type) (diameter) (lin.m.) chemically resistant product with a resin-rich surface
layer suitable for use in aggressive atmospheres likely
8.3 Manholes, Inlets and Chambers to the encountered in sewers and sewage pumping
stations.
8.3.1 Description ii. Rungs of tubular construction shall be no less than 30
( This Sub-section specifies works related to manholes, grate
mm outer diameter and stringers shall be of a
rectangular or channel section, no less than 70 mm x 25
inlets, chambers, grated channels, curb inlets, ditch inlets and ditch
mm in size. The upper face of non-tubular rungs shall
outlets.
be finished with a non-slip surface such as silica sand.
All remaining surfaces shall be free of sharp edges,
8.3.2 Materials
protrusions etc.
Concrete, reinforcing steel and reinforced concrete shall iii. Each rung shall be able to withstand a point load of
conform to the requirements of Sub-sections 5.I , 5.2 and 5.3 5000N.
respectively. Structural steel and other metalwork shall conform to iv. When supported horizontally over a span of 1 m with
Sub-section 6.2. the climbing face uppermost and with a load of 1000 N
2 Plain (blinding) and reinforced concrete shall be Class 15 and applied at the center of the span the ladder shall not
25, respectively. Cement shall be ordinary Portland cement to BS EN deflect more than 15 mm at the point of application of
197. the load and shall show no permanent deflection after
3 Concrete manholes shall comply with BS EN 1917 and BS removal of the load. Each ladder fixing shall be
5911 Part 3. Thickness shall be as indicated on the Drawings. capable of withstanding shear and pull-out loads of
5000 N.
4 Manholes and chambers covers, gratings and frames shall
v. All ladders shall comply with BS 5395: Part 3. All
comply with BS EN 124 or equivalent. Two sets of lifting keys
fixings shall be stainless steel.
shall be supplied with each removable cover. Covers and frames
shall be non-rock, locking, solid top. Grades shall be as follows: 10 Fixing bolts shall be steel, type suitable for particular purpose
i. For roadways: heavy duty test load 40 tons. and use and to approval. When used to fix galvanized material,
ii. For sidewalks, carriage drive and cycle tracks: medium washers are to be galvanized and fixing bolts and nuts cut to pre-
duty test load 25 tons. plating limits and electroplated with zinc to BS ENISO 2081.
iii. For footpaths and fields: light duty, test load 7 tons. 11 Steel castings shall be mild to medium strength castings and
5 Manhole covers shall be of circular pattern unless otherwise shall conform to AASHTO Ml03MIM103. Unless otherwise shown
indicated on Drawings with a clear opening of not less than 560 mm on the Drawings or instructed by the Engineer, castings shall be

dar -8-7
copy 152
Drainage > Highway Doe ign Standards 2017
Suit n te of Om.m I Ministry ofTr· n po11 & Communications. DGRLT

grade 65-35 fully annealed. Steel castings shall conform to the 7 The Contractor shall test manholes as follows:
dimensions shown on the Drawings. Test bars shall be prepared and i. Plug manhole inlets and outlets.
tested as specified in AASHTO MI03MIM103. ii. Fill manhole with water and allow it to stand for at least
24 hours or such longer period to allow for complete
12 Mortar for masonry shall be mixed in the proportions 1:3
absorption.
(cement::sand) by volume, or 1:4:4 (cement; lime: sand). The sand
iii. Re-top with water.
shall be well graded.
iv. Allowable leakage over 24 hours shall not to exceed
13 The Contractor shall submit to the Engineer manufacturers'
1% of total volume of manhole, otherwise necessary
Certificates of Guarantee for steel, cast iron cast steel and wrought
repair and re-testing shall be carried to achieve the
iron parts, stating that the materials supplied meet the applicable
required results.
AASHTO or ASTM specification and Standards. The submission of
such test certificates shall not relieve the Contractor of his 8.3.3.2 Chambers for Grated Inlets, Curb Inlets and Ditch
obligations to carry out independent tests at an approved laboratory,
Inlets and Outlets
as directed by the Engineer, at his own expense.
Construction shall be in situ concrete, precast concrete or
8.3.3 Construction Requirements blockwork as indicated on the Drawings.
2 Brick and blockwork shall be laid on a full bed of mortar.
All excavation and backfill shall conform to the requirements
Whole bricks and blocks shall be used except where closers must be
of Sub-Sections 2.7 and 2.8.
cut.
2 Form work for cast in place concrete chambers, and the placing,
3 Courses (layers of concrete blockwork) shall be stepped back
curing, and protection of the concrete shall conform to the
and not raised above the general wall level more than 900 mrn.
requirements of Sub-section 5.3, Clause 5.3.3.
Courses shall be horizontal. Reinforcement in the masonry shall be
8.3.3.1 Manholes fully embedded in the mortar joint.
4 If pointing is required, the joint shall be raked out to a depth of
Precast units shall be cast in steel watertight forms at least 3
12mm after completion of the entire face.
weeks before sections are used. Lowest unit shall be bedded on in
situ concrete base and bed and haunch in cement mortar. Joints of 5 Brick and blockwork shall be protected by impermeable
units shall be liberally coated with approved bituminous material of sheeting or damp cloth for 3 days after completion oflaying.
troweling grade prior to fixing. Joints shall be filled solid and neatly 6 The nearest pipe line joint to any chamber or grated inlet shall
stroked off surplus compound. Work shall remain undistutbed for 7 be not more than 500mrn from the inner wall face and shall not be
days thereafter. Alternatively joints may be sealed with approved restricted by concrete or masonry from the structure.
preformed jointing strip in accordance with manufacturer's
instructions. The precast concrete cover slab shall be bedded in 8.3.3.3 Ironwork
cement mortar on the top unit.
Frames for covers and gratings shall be solidly bedded in
2 Channels in bottom of manhole shall be smooth, semi-circular mortar and fixed firmly using fixing bolts. They shall be positioned
and sized equal to diameter of adjacent sewers. For straight through centrally over the opening and level and square with surrounding
manholes, channels of half pipe sections shall be installed. Changes finishes. Covers shall be set in position to prevent twisting.
in direction of flow shall be made with smooth curves as large as
2 The upper surface of grated inlet gratings shall be flat. Slots
manholes permit. Changes in size and grade of channels shall be
shall not be parallel to traffic flow unless the slots are less than
gradual and even.
150mm long or less than 20mm wide.
3 Benching shall be formed with sulfate resisting concrete Class
25/20 to rise vertically from top of channels to a height not less than 8.3.3.4 Cleaning
soffit of outlet pipe, then it shall be sloped upwards 1 in 10 to walls.
Manholes, grated inlets, grated channels, curb inlets, ditch
Floating shall then be carried out within 3 hours with a coat of
inlets and ditch outlets shall be thoroughly cleaned on completion,
sulfate resisting cement -sand mortar 1:2. Smooth finishing shall then
and shall be free from dirt and debris at the time of final inspection.
be accomplished with a steel trowel. For concrete strength, refer to
structural specifications.
8.3.4 Method of Measurement
4 Manholes and chambers shall be coated externally with three
layers of asphaltic composition that shall be applied by brush in Manholes and inlets shall be measured by the number of each
accordance with manufacturer's instructions. Minimum thickness structure constructed and installed including the supply and
shall be 600 microns. installation of chambers, frames, grates, covers and ladders as
5 Internal faces of manholes and chambers shall be coated with applicable. Grated channels shall be measured per linear meter.
four coats of coal tar epoxy paint, 70% epoxy and 30% coal tar. The 2 No separate measurement or payment shall be made for any
coating shall be applied by brush in accordance with manufacturer's other concrete works, excavation, shoring, sheeting or backfilling, or
instructions. Minimum thickness shall be 1000 microns. for breaking into existing pipes or culverts in order to install new
6 Adjustment oflevel shall be accomplished with top courses of manholes, chambers, inlets and the like. All such work prescribed in
brickwork or concrete rings after completion of surrounding levels. this Sub-section shall not be measured for direct payment, but shall
Final levels shall be even and accurate. be considered as subsidiary work, the costs of which shall

-8-8
copy 152
dar
Mini :ry ofT1 n pc 1
Drainage
& Commdnic,ltiow . C3RLT
8
be deemed to be included in the unit rates for manholes etc. stated in
the Bill of Quantities.
Pipe Material Pipe Standard
3 No separate payment shall be made for blinding, painting,
equipment, forms, tools, furnishing and placing materials, labor, Ductile Iron BS EN 545 [I]
transport, or any other item necessary for the proper completion of BS EN 1452 [9] or to DIN 8061/8062,
the work. All such items prescribed in this Sub-section shall not be uPVC
Series 4 and 5
measured for direct payment, but shall be considered as subsidiary
ISO 4427, DIN 8074/8075 or AWW A
work, the costs of which shall be deemed to be included in the unit Polyethylene (PE)
C906 Class I 0
rates for manholes etc. stated in the Bill of Quantities.
Table 8A.2- I: Drainage Pipe Standards for Bridge Deck
8.3.5 Basis of Payment
2 Pipes for filter drains shall be to the standards listed in Table
The amount of completed and accepted work measured as 8.4.2.2 or equivalent and as specified in Clause 8.2.2.
provided for above, will be paid for at the unit rates of 'Manholes',
'Grated Inlets', 'Curb Inlets', 'Grated Channels', 'Ditch Inlets' and Pipe Material Pipe Standard
'Ditch Outlets' in the Bill of Quantities, which rates shall be full uPVC DIN 8061 Class 10 kg/cm2
compensation for excavation, installation, fitting, testing, backfilling, ASTM D3035and ASTM
supplying materials, labor, transport, equipment, forms, tools and Polyethylene (PE)
F894
other items necessary for the proper completion of the work.
Vitrified clay BS 65
8.3.6 Items in the Bill of Quantities AASHTO M175MIM175 or
Concrete
ASTMC444M
i. Manholes (size and type) nr.
Table 8A.2.2: Drainage Pipe Standards for Filter 01·ains
nr.
( ii. Grated Inlet (type)
8.4.2.3 Drainage Backfilling
iii. Curb inlet (type) nr.
Permeable backfilling to structures shall be crushed rock or
iv. Ditch inlet (type) nr.
precast porous concrete blocks to BS 6073-2 laid in stretcher bond
v. Ditch outlet (type) nr. with dry joints. The minimum thickness of backfilling shall be
225mm.
vi. Chamber (type and depth) nr.
2 Granular backfill to structures shall be natural sand and gravel
vii Grated Channel (width and depth) lin.m. or with a particle size distribution as given in Table 8.4.2.3.

AASHTO sieve size ~. passing (by mass)


8.4 Drainage of Structur·es
75.0mm 100
8.4.1 Description 37.5 mm 85-100
This Sub-section describes requirements for gully and channel 9.5 mm 45-100
gratings and frames on bridge decks, subways and underpasses with
the associated pipework. It includes the supply and placing of 4.75 mm 25-85
permeable drainage backfilling to structures. Table 8A.2.3: Granular Batklill to Structure

8.4.2 Materials 8.4.3 Construction Requirements

8.4.2.1 Gully and Channel Gratings and Frames Drainage pipes cast into the concrete structure shall be firmly
supported to prevent their displacement during the concreting
Gully and channel gratings and frames shall be heavy duty operation. Pipes located within the cellular sections of a bridge deck
with locking and shall conform to the requirements ofBS EN 124 or where access after completion of the deck is limited, shall be
equivalent. Integral hoppers shall be of the same grade and quality as installed, tested and approved by the Engineer before the deck
the gully or channel grate and frame. Molded uPVC or GRP shall be construction is allowed .to proceed to the stage where access to the
to the approval of the Engineer who may require material and load pipes will not be possible
testing. 2 Pipe joints in bridge decks shall be flexible and watertight
Seals and gaskets shall be appropriate for the pipe material- used.
8.4.2.2 Pipes
3 Joints between bridge deck waterproofing and drainage
Pipes used in bridge decks shall be to the standards listed in components shall be watertight and the sealants shall be compatible
Table 8.4.2.1 or equivalent with a minimum internal diameter of with the waterproofmg system.
IOOmm.

dar -
8-9
copy 152
Drainage > Highway De ion St ndards 2017
Suit n t of Omdn I Mini try ofTr nspe>r1 & Communications . DGRLT

4 Granular drainage backfill shall be placed and compacted in


accordance with Sub-section 2.5, Paragraph 2.5.4.2.
5 Drainage pipes and connections in bridge decks shall be tested
for water tightness on completion in accordance with Clause 8.2.3.
6 All excavation and backfill shall conform to the requirements
of Sub-Sections 2.3 - ' Roadway Excavation' and 2.7- ' Excavation
and Backfilling for Structures.
7 PE pipes installation shall be in accordance to ASTM 02321
and manufacturer's recommendations.

8.4.4 Method of Measurement


Gully gratings and frames shall be measured by number; each
type shall be measured separately
2 Pipework shall be measured in linear meters, measured as the
actual length installed, including nominal length of bends and
fittings; each type and size shall be measured separately.
3 Permeable backfilling shall be measured in cubic meters of the
volume placed in position.
4 Granular backfill shall be measured in cubic meters of the
volume placed in position.
5 No separate measurement shall be made for blinding, painting,
equipment, forms, tools, furnishing and placing materials, labor, or
any other item necessary for the proper completion of the work. All
such items prescribed in this Sub-section shall be considered as
subsidiary work, the costs of which shall be deemed to be included in
the rates and prices stated in the Bill of Quantities.

8.4.5 Basis of Payment


The amount of completed and accepted work measured as
provided for above, will be paid for at the unit rate for the various
items of'Drainage for Structures' in the Bill of Quantities, which rate
shall be full compensation for supplying, fabricating, connecting and
testing, and for labor, transport, materials, equipment, tools, and
other items necessary for the completion of the work.

8.4.6 Items in the Bill of Quantities


i. Gully grate and frame (type) nr.

ii. Drainage pipe in structure

(type) (diameter) (location) lin.m.

iii. Permeable backfilling cu.m.

iv. Granular backfill cu.m.

-8-10
copy 152
dar

You might also like