Professional Documents
Culture Documents
TABLE OF CONTENTS
FIGURES
Figure 8.1: Usual Form of Local Scour Holes at Piers 8-3
Figure 8.2: Scour at an Abutment 8-3
Figure 8.3: Scour at an Abutment and Adjacent Pier 8-4
Figure 8.4: Illustrative Pier Scour Depth in a Sand-Bed Stream as a Function of Time 8-4
Figure 8.5: Guide Bank Details 8-9
Figure 8.6: Chart for Determining Length of Guide Banks 8-10
Figure 8.7: Approximate Length of Embankment Protected by Spurs 8-11
Figure 8.8: The Four Main Cases of Constriction Scour 8-15
Figure 8.9: Definition Sketch for Scour Depths for Case 1(a) 8-17
Figure 8.10: Fall Velocity of Sand-Sized Particles 8-18
Figure 8.11: Definition Sketch for Scour Depths for Case 1(c) 8-19
Figure 8.12: Common Pier Shapes 8-20
TABLES
This chapter presents a methodology for the design of scour protection at inlets and outlets to culverts, in
open channels and at constrictions in channels such as bridges.
In natural channels or unlined floodways the shape of the watercourse may change over time due to scour
and material deposition. A range of factors will influence the rate and extent of change such as:
• Flow regimes (flow may be very seasonal with long periods of low flows);
• Soil characteristics and subsurface geology (this will influence the erodability potential of the channel
and also the sediment loadings from areas upstream);
• Channel grade and alignment;
• Restrictions or changes of flow direction due to structures such as bridges;
• Vegetation (will influence the susceptibility of stream banks to scour and also to accumulate material.
The extent of coverage of vegetation is not normally constant throughout the year and seasonal
changes must be considered).
Scour in watercourses can be addressed in a number of ways one of these is termed scour protection. Scour
protection involves the placement of materials such as rock or concrete lining in areas that may be prone to
scour.
Lining areas prone to scouring is not the only method that can be utilized to address scour. Scour is caused
by either high flow velocities or turbulence such as occurs at a hydraulic jump. Measures can be taken to
reduce the high velocities or turbulence including:
Aggradation and degradation are long term changes to the watercourse profile due to either manmade or
natural processes. These changes in streambed elevation can be due to a range of factors such as dams,
changes in development within a catchment, diversion of flows for irrigation.
Aggradation is the long term process of material being deposited along a channel reach due to erosion from
the upstream watershed. Degradation is the opposite process whereby the stream bed is lowered by erosion
or scouring.
The river morphology of natural streams or rivers is constantly changing. The rate of change can vary greatly
with some channel reaches changing in a single storm event. This process includes general stream bed
movement and scouring at channel constrictions or bends. The outside bank of a river tends to have higher
flow velocities and subsequently prone to scouring whereas the slower velocities at the inside bank allow
sediments to accumulate.
As the name suggests constriction scour is due to a restriction in the normal flow cross section. The reduced
flow area for instance of bridge approach embankments across a floodplain increases velocities in the main
channel.
Constriction scour prevails until enough material has been removed from the channel bed so that flow
velocities and shear stresses are reduced. When an equilibrium condition prevails the amount of material
being deposited in the subject channel reach is equal to that being exported.
Constriction scour at a bridge opening reflects that in a normal channel the process of scour and deposition
undergoes a cyclic nature. During rising flows of a storm event the bed scours and latter as flows decline
material settles filling the void.
A guide bank at an abutment decreases the risk from scour at the abutment by realignment of the stream
lines of the floodplain flow so that they enter the bridge opening clear of the abutments.
Local scour is confined to a small area around an obstruction in a waterway such as a bridge pier. The
obstruction has two many effects; flow velocities increase around the leading edge of the obstruction, and
vortices form at the base of the obstruction.
The vortices remove material from around the base of the obstruction. As with constriction scour once the
material is removed the flow patterns change and erosive forces are reduced till eventually an equilibrium
point is reached.
As well as a horseshoe shaped vortex at the base of an obstruction or pier, there is another vortex
downstream called the wake vortex. Both of these vortices remove material from the stream bed however the
intensity of the erosive forces reduce rapidly with distance downstream. A deposition of material is often
noticed immediately downstream of a long pier.
There two conditions, which affect the duration, required for either a constriction or local scour to reach
equilibrium.
Clear water scour occurs when the upstream channel bed is stable and does not contribute any significant
volumes of material to the point of interest. Clear water scour is most often noted in waterways with very flat
grades, coarse bed material, armoured stream beds or vegetated channels. Live-bed scour however occurs
when the upstream bed is changing.
As shown in Figure 8.4, the clear water scour reaches its equilibrium over a longer period of time than live-
bed scour. Clear water scour occurs during major storm events in coarse bed material streams. Noting the
occurrence interval between such storms it may take numerous years until equilibrium is reached.
Figure 8.4: Illustrative Pier Scour Depth in a Sand-Bed Stream as a Function of Time
Source: AUSTROADS, 1994
8.3.1 General
In considering the effect of scour it should be considered that whilst repairs can generally be made on
approach embankments relatively easily, a structure undermined by scouring can present a significant cost.
In consideration of the cost of a structure becoming unusable the larger social associated with disruption to a
traffic route needs to be evaluated and compared against providing suitable scour protection measures.
The floods that should be used for scour estimation are as follows (AUSTROADS 1994):
• For the evaluation of bridge foundations – the 200 year ARI flood or overtopping flood if this
produces more severe scour;
• For the design of protection works to the fill around the bridge abutments and to bridge abutments –
the total waterway design flood. The total waterway design flood is the event utilised for the overall
design of the total waterway, generally this is either a 50 or 100 year ARI event.
Waterway investigations of bridge sites should address both the sizing of the bridge waterway and the
designing of the foundations to resist scour. The scope and depth of the investigation should be
commensurate with the importance of the road and the consequences of failure.
As most methods available for estimating depth of scour lack field verification and may not give credible
estimates, it is recommended that abutments be protected against scour by the use of rock riprap and/or
guide banks. Properly designed, these two protective measures provide adequate protection to abutments
and make the estimation of the depths of scour less critical.
1. select either the total waterway design flood or a lesser flood, if it is expected to produce the most
severe scour conditions. When a bridge is designed to be overtopped with a flood with an ARI less
than the total waterway flood, it is quite likely that this flood will produce the worst conditions.
3. Using the procedures detailed in Section 8.5, estimate the constriction scour and local pier scour.
4. Plot the total scour depths on a cross section of the stream at the bridge site. The cross section
should include the soil profiles obtained from geotechnical investigations.
5. Using engineering judgment consider if the calculated scour depths are reasonable or if an
alternative depth should be utilised.
6. Consider the form and extent of protection required at the abutment with respect to the following
criteria:
1. Determine whether the bridge will or will not be overtopped with a flood with an ARI less than 2000
years. If it will be overtopped, use the overtopping flood to evaluate the foundation design. If not,
then the 2000 year ARI flood should be used to evaluate the foundation design.
3. Using the procedures detailed in Section 8.5, estimate the total depths of scour.
4. Plot the total scour depths on a cross section of the stream at the bridge site. The cross section
should include the soil profiles obtained from geotechnical investigations.
5. Using engineering judgment consider if the calculated scour depths are reasonable or if an
alternative depth should be utilised.
6. Evaluate the proposed substructure type, size and location and modify them, if necessary. The
overall flood flow pattern at the bridge site should be visualized to assist in identifying those
elements of the bridge at risk from scour.
7. Substructure design should be carried out on the basis that all stream bed material above the total
scour line has been removed and is not available for bearing or lateral support.
Scour counter measures in relation to bridges can be classified into following groups (HEC 23 1997):
For spread footings on soil the top of the footing should be located beneath the estimated level of scour.
Where there is any risk of scour undermining spread footings, deep foundations in the form of piles should
be used.
The base of the footing should be placed on solid clean rock. Small embedments should be avoided since
blasting to achieve keying frequently damages the rock structure and makes it more susceptible to scour. If
lateral restraint is required, it should be provided with steel dowels drilled and grouted into the rock.
Excavation into erodible rock should be made with care. All loose rock should be removed from the
excavation and any overbreak beneath the footing made up with lean concrete. The footing should be
poured against the sides of the excavation for the full depth of the footing. The excavation above the top of
the footing should be backfilled with rock riprap sized to withstand flood flow velocities.
The top of the pile cap should be placed at a level below the constriction scour depth. This will minimize the
obstruction to flood flows and resulting scour.
A number of other factors should also be considered to minimize the potential for scouring at bridges:
Designers should not only consider the localized effect of constructing a restriction to flow but also the
broader effect of the works on the environment.
Clearing vegetation or excavating borrow pits to source material for approach embankments will change flow
regimes in the area. These changed flow regimes will consequently have an effect on bridge piers,
abutments and approaches.
Strict controls should be placed on clearing and excavation in the immediate vicinity of a structure and the
associated road embankments.
Hydraulic countermeasures relevant to Addis Ababa city conditions essentially consist of river training
structures. Of the river training structures the longitudinal structures such as guide banks are considered
appropriate to Addis Ababa city conditions. The transverse structures like spurs also have some application
to the city conditions. These two types of countermeasures are treated in the following description.
(a) Guide Banks
Guide banks are an effective method of decreasing the risk of abutment scour at bridges. Guide banks
transfer the location of the constricting streamlines and associated vortices away from the bridge abutment
to the nose of the guide bank. Guide banks also assist in the protection of approach abutments from scour
by reducing the flow along the face of the embankments.
X2 Y2
+ =1 (8.1)
L S2 (0.4 L S )2
Q30 = Q/b x 30 = discharge (m3/s) in 30m of stream adjacent to abutment, measured at a point
sufficiently upstream so as the flow paths are not affected by the constriction
b= length (m) of bridge opening
An2 = water area (m2) underbridge referred to normal stage
Vn2 = Q/An2 = average velocity (m3/s) through bridge opening
Qf / Q30 = guide bank discharge ratio
Ls = top length (m) of guide bank
Figure 8.6 is read by entering the ordinate with the proper value of Qf / Q30, moving horizontally to the curve
corresponding with the computed value of Vn2 and then downward to obtain from the abscissa the length of
the guide bank required.
As a general rule, if the calculated length of guide bank is less than 10m then a bank is not required. If the
length from the chart is between 10 and 30m then a 30m minimum should be adopted to ensure that flow
paths are perpendicular when passing under the structure.
The selection of Class of rock protection, as described in latter section, required for impinging and parallel
flow is based on the following assumption:
where
Vp = velocity of parallel flow along tangent bank
Vm = mean velocity through bridge opening
Vi = velocity of impinging flow against curved bank.
(b) Spurs
Spurs, retards or groynes are structure utilised to deflect flows from along a stream bank or embankment. It
is often cheaper and more effective to provide a series of spurs along a river bank than to provide protection
along its full length.
The noses of spurs are normally rock protected. In the event that a spur begins to fail the consequences are
not as severe as compared to erosion at an expensive structure. As the spur protrudes into the flow path
effectively shielding an embankment immediately upstream and downstream remedial works can be
undertaken on a spur whilst a structure is still effectively protected.
Spurs can also be used to protect approach embankments to bridges. In locations where considerable
overbank flow occurs, the construction of a road crossing can result in a concentrated flow path along the toe
of an embankment as runoff travels towards the main channel and bridge opening. A series of spurs at right
angles to the embankment can protect the approach from scouring.
The length of bank or road embankment protected by a spur is approximately three times the perpendicular
length of the spur as illustrated in
Figure 8.7.
At abutments and bridge piers where scour is anticipated properly designed rock riprap protection can
provide long term resistance to erosion. Riprap consists of appropriately sized stone placed on the face to be
protected. The stone is normally not secured by wire netting or mortar but resists the force of the water by
the weight of the stones and their natural interlock between the faces of the rock. This kind of protection is
generally the most economical.
Other types of rock protection can include rock filled wire mattresses, grouted stone pitching or hydraulically
filled concrete mattresses.
The California Department of Public Works developed the following relationships for minimum mass of stone
and thickness of the protection layer (AUSTROADS 1994):
where
Sgr = specific gravity of rock
ρ= 70 degrees for randomly placed rock rubble
α= face slope (degrees)
where
Wc = Class of rock protection expressed in kg
(Refer Table 8.1) (ie. Wc = ¼ tonne = 250kg)
The stones are to be graded uniformly between the specified minima for Class of rock protection with two
thirds heavier than minimum required on face. The grading of the rock is an important factor for scour
resistance.
Note that the mass by which the class of rock protection, Wc is designated does not correspond to the mass
W. The class of rock protection, Wc should be graded so that at least 2/3 of all rocks in the class have a
greater mass than W.
Rock used for riprap should be hard dense and durable stone free from laminations, fractures and otherwise
weak stone.
Stone shape is another important criterion, which will affect the interlock between the stones. Angular stones
provide numerous faces which can interact with adjacent stones. Rounded stones can be used however the
slope face will need to be limited to about 1 in 3. Generally a stones width or breadth should be no less than
1/3 of its length. Flat slab like stones should be avoided.
The placement of stones should commence from a footing trench at the base of the embankment. The base
of the trench must be lower than the level of anticipated scour. Rock should be placed to minimize voids.
In order to protect the finer particle material of the embankment a geotextile layer or gravel filter is used
underneath the rock protection.
8.4.3 Monitoring
Monitoring includes activities aimed at early identification of the developing scour problems. It can be
accomplished by instrumentation or visual inspection. Instrumentation involves fixed or portable instruments.
Fixed instruments are attached to the bridge structure to detect scour at a particular location. Typically, such
instruments are located at piers and abutments. Instruments such as sonar monitors are used to provide a
time line of scour whereas magnet sliding collars are used to monitor maximum scour depth. Data from fixed
monitors is either downloaded manually or telemetered to another location.
Portable instruments are carried manually and used along a bridge whenever required. These are
economical but lack the ability of continuous recording
Visual inspections include measurement of the bed elevation at locations of potential scour. Typically, the
bridges are inspected on a biennial schedule and channel bed elevations compared with previous records to
trace adverse developments. Channel bed elevations should also be taken during and after high flow events.
This type of monitoring, if carried out on regular basis, can help detect serious scours for a timely correction.
Many methods are available to estimate scour at bridges. The reliability and accuracy of the methods varies
greatly with most analysis based on limited available data and scarce field verification.
It is therefore recommending that calculated depths of scour be treated with caution and that sound
engineering judgement based on local field experience should always take precedence.
The method for estimating constriction and local pier scour at bridges is as follows:
• Obtain the fixed bed channel hydraulics. Flow profiles and velocities can be estimated using
backwater analysis programs such as HECRAS by the US Army Corps;
It should be noted that the normal method presented in this section assumes that the constriction and local
pier scour occur independently. With this approach the potential local scour is added to the constriction scour
without considering the effects of the constriction scour on the channel and bridge hydraulics. However, if the
constriction scour is significant, the channel and/or bridge hydraulics should be adjusted for the effects of the
constriction scour before estimating the local scour.
There are four predominant constriction conditions as illustrated in Figure 8.8. The method used to calculate
constriction scour shall depend upon the prevailing condition.
Case 1- This condition involves a channel with overbank flow which is forced back into the main channel by
the bridge and associated embankment. There are three different situations which can occur:
(a) The river channel width becomes narrower, either due to the bridge abutments projecting into the
channel or the bridge being located at a narrowing reach of the river;
(b) No constriction of the main channel but the overbank flow area is completely obstructed by the
embankment;
(c) Abutments are set back from the main channel permitting some overbank flow.
Case 2 – Flow is confined to the main channel and there is no overbank flow. The normal river channel
becomes narrower due to the bridge itself or the bridge site being located at a narrower reach of the river.
Case 3 – A relief bridge in the overbank area with little or no bed material transport in the overbank area (ie.
clear water scour)
Two methods are presented for the calculation of constriction scour; Laursen’s Method and the Mean
Velocity Method. Generally an estimate of constriction scour should be made by both methods as a
comparison and guide to the reliability of the calculated scour depth.
The modified version of Laursen’s Equation (AUSTROADS 1994) for live bed scour at a long contraction can
be used to estimate the depth of live bed constriction scour. Clear water constriction scour can also be
calculated using the same equation but with the removal of the last term involving the ratio of W1 to W2.
Figure 8.9 defines y1, y2, W1 and W2 for Case 1(a). From Figure 8.8 it can be seen that these parameters will
be similar for Cases 1(b), 2(a), 2(b) and 2(c).
Note: For Case 1(b) where W1 and W2 are of similar magnitude and the width of the piers is not significant,
the last part of Equation 8.4 can be ignored.
Figure 8.9: Definition Sketch for Scour Depths for Case 1(a)
Source: AUSTROADS, 1994
Cases 1(c), 3 and 4 are more complicated and can be treated in two ways:
(1) The main channel can be treated as for Case 1(b) and the overbank flow, between the stream bank
and the bridge abutment, can be treated separately. This approach requires an estimate of the flow
in the main channel and the area of overbank flow, both upstream of the bridge and in the bridge
opening. Estimation of the distribution of flow in the bridge opening poses a difficult problem. Given
the problem of estimating the flow distribution and the limitations of the method for estimating
constriction scour, the complexity involved in this approach cannot be justified.
(2) The alternative approach is to consider the total flow in the bridge opening, when the last term of
Equation 8.4 becomes 1 and the other parameters are as follows:
y1 = average depth (m) of flow in the area of stream channel and floodplain occupied by the
bridge (at normal stage without scour)
y2 = average depth (m) of flow in the bridge opening (including scour)
Q1 = flow (m3/s) in area of stream channel and floodplain occupied by the bridge (at normal stage
and without backwater)
Q2 = total flow (m3/s) through bridge opening
Figure 8.11 defines y1 and y2 for Case 1(c). From Figure 8.8 it can be seen that these parameters will be
similar for Cases 3 and 4
Figure 8.11: Definition Sketch for Scour Depths for Case 1(c)
Source: AUSTROADS 1994
(iv) Calculate mean velocity of flow in the unrestricted main channel for the discharge at which
constriction scour will just commence;
(v) Determine average constriction scour level that will make the mean velocity through the bridge
opening equal to the estimated mean velocity calculated in (i) above.
It is assumed that the discharge at which constriction scour will just commence is that of the total waterway
design flood. The experience has shown that it gives realistic estimates of constriction scour. The total
waterway design flood can be either the 50 or 100 year ARI design flood depending upon the standard
adopted. It is not anticipated that estimates of constriction scour will vary greatly with the use of either flood,
as velocities in the main channel of a stream should be of a similar magnitude for both floods.
The Colorado State University (CSU) Equation can be used to determine depth of local pier scour for both
live-bed and clear water scour conditions. Whilst this equation predicts equilibrium scour depths, maximum
scour depths may be 10% greater.
where
yps = scour depth (m) below constriction scour level (Figure 8.9)
K1 = correction factor for pier nose shape from Figure 8.12 and Table 8.3
Shape of Nose K1
(a) Square Nose 1.1
(b) Round Nose 1.0
(c) Circular Cylinder 1.0
(d) Sharp Nose 0.9
(e) Group of Cylinders 1.0
Source: AUSTROADS 1994
Note: The correction factor K1 should be determined using Table 8.4 for flow angle of attack up to 5 degrees.
For greater angles, K2 dominates and K1 should be considered as 1.0. If L/a is larger than 12, use the values
of L/a = 12 as a maximum.
The top width of scour at a pier in cohesionless bed material can be estimated as 2.8 ys (2.8 times the
constriction scour depth) from one side of the pier.
Section – 8 Design of Scour Protection FINAL – November 2004
Page 8-20
GUIDELINE 6
AACRA DRAINAGE DESIGN MANUAL
For multiple columns skewed to the direction of flow, the scour depends upon the spacing between the
columns. The correction factor K2 for angle of attack would be smaller than for a solid pier. The pier width, a
in Equation 8.5 would be the total projected width of all the columns in a single bent, normal to the flow angle
of attack. The correction factor K1, for the multiple columns would be 1.0 regardless of column shape. If
debris is likely to pile up against the multiple columns, it would be logical to consider the multiple columns as
a solid elongated pier. In this instance the appropriate L/a value and flow angle of attack would then be used
to determine K2 from Table 8.4.
Pressure flow occurs when the water level beneath a structure rises to an extent where the bridge soffit
affects the flow conditions by being partially or completed submerged. Under these circumstances
constriction scour and local scour can be expected to increase considerably. The depth of scour will depend
on the velocity of the approach flow and the clearance between the superstructure and the stream bed. For
the same approach velocity, constriction and local scour can be expected to increase with decreasing
clearance between superstructure and the stream bed.
Where the footing extends above the stream bed a second calculation should be made and the larger of the
two adopted. The second computation should use the width of the footing or pile cap for the value of a, and
the depth and average velocity in the flow zone obstructed by the footing for the y1 and V1 values
respectively in the scour equation.
The average velocity of flow at the exposed footing, Vf, should be determined using the following equation
(Jones, 1989):
where
The values of Vf and yf should be used in Eq 8.5 for V1 and y1 respectively.
Pile groups protruding above the stream bed, as a result of constriction scour or long term degradation, can
be conservatively analysed by assuming that the area of the pile group represents a single pier of equal
width ignoring the clear spaces between. Engineering judgment is needed to assess the likelihood of floating
debris being trapped by the pile group and increasing the effective waterway obstruction.
If a pile group is exposed to the flow as a result of local scour then it is unnecessary to consider the piles in
calculating pier scour.
The correction factor K1 in Equation 8.4 should be considered to be 1.0 regardless of the layout of the piles.
If the pile group is square then K2 would be 1.0. However, if the pile group is a rectangle then the dimensions
used would be based on the assumption that they are a single pier and the appropriate L/a value used for
determining K2.
3/ 7
⎡ Q2 ⎤
y=⎢ 2/3 2 ⎥
(8.7)
⎣ 40 Dm W ⎦
Average scour depth, ys = y-yo
Where,
Q = discharge through contraction (m3/s)
Dm = effective mean bed material size = 1.25 d50, (m)
W = bottom width in contraction (m)
yo = existing depth in the contracted section before scour (m)
Due to its implication on scour, the designers are invariably interested in the impact of the flow velocity on
mobility of a given bed material size. Critical velocity, Vc, for beginning of motion a given sediment size is
given by the following relation (HEC 18 1995):
K s1 / 2 ( S s − 1)1 / 2 D1 / 2 y 1 / 6
Vc = (8.8)
n
Where,
Vc = critical velocity to move bed material size D or smaller (m/s)
Ks = Shields parameter (0.039 – HEC 18 1995, for this equation)
Ss = Specific gravity of the bed material (2.65)
D = size of the bed material (m)
y = depth of flow (m)
n = Manning’s roughness coefficient.
General description of problem – A 54 m long bridge with 1.5:1 spillthrough abutments (see Figure 8.13) is
to be constructed over an ephemeral stream in the Kimberley Region of Western Australia. The bridge will
have a deck level of 210.55 m and a 1.0 m deep superstructure, which will be continuous over the piers.
The three piers, which will be aligned with the flow and evenly spaced, will comprise three 0.6 m diameter
columns founded on spread footings.
The bridge will be overtopped with a flood with a ARI less than 500 years. This overtopping ultimate limit
state flood will be used to evaluate the foundations and the 100 year average recurrence interval flood will be
used to design the abutment protection. The overtopping flood has a discharge of 510 m3/s at a stage height
of 208.80 m and the 100 year design flood discharge is 405m3/s at a stage height of 208.60 m.
The stream has a catchment area of 30 km2 and has a well defined channel with floodplains on either side.
The bridge crossing is located on a slight bend, with a moderately uniform channel upstream and
downstream of the bridge site. The main channel contains a very shallow depth of coarse and overlying
weathered granite. On the floodplains there is a shallow depth of loam over weathered granite. The granite
is distinctly weathered at the surface and readily breaks down into a quartz gravel. Weathering decreases
with depth until fresh granite is reached at a depth of about 12m below bed level. D50 is about 3 to 5 mm for
the quartz gravel of the completely weathered granite.
Hydraulic Characteristics – the distribution of flow in the natural channel (without the bridge) and bridge
hydraulics were determined for the overtopping flood and 10 year design flood using the computer program
AFFLUX. The details are as follows:
l
Distribution of Flow Flow Mean Average
(m3/s) Velocity Depth of Flow
(m/s) (m)
Q overtopping
Q100
The bridge slightly constricts the main channel (Case 1a on Figure 8.8). Because there is very little sand in
the bed of the main channel, it is anticipated that scour will be predominately clear-water in the bridge
opening.
Q1 = 325 m3/s
Q2 = 510 m3/s
For clear-water scour, the last part of Equation 8.3 can be ignored, and
0.86
y2 ⎡ 510 ⎤
=⎢ = 1.67
2.52 ⎣ 280 ⎥⎦
*Without Scour
Source: AUSTROADS 1994
Try Mean Velocity Method utilizing the average velocity of 2.78 m/s in the main channel for the 100 year
design flood. From Table 8.6 it can be seen that a scour depth of about 1.8 m is required to reduce the
velocity to 2.78 m/s. Accept 1.8 m as depth of constriction scour.
(b) For the 100 year flood for the design of protection works
y1 = 2.31 m
Q 1 = 280 m3/s
Q 2 = 405 m3/s
0.86
y2 ⎡ 405 ⎤
=⎢ = 1.37
2.31 ⎣ 280 ⎥⎦
With the Mean Velocity Method the scour required to reduce velocity to 2.78 m/s is about 1.1 m.
Step 4 – Plot and evaluate total scour depths, and evaluate foundation design
The depths of constriction scour and local pier scour are plotted on Figure 8.13. From this plot it can be
seen that the top of the footings need to be 3.50 m (1.8 + 1.7 m) below the stream bed level. This appears
to be excessive given that the weathering of the granite decreases with depth and this will tend to limit the
scour that can occur.
Given the uncertainties in estimating the scour depths, the top of the footings will be placed 3.12 m below the
lowest point in the stream bed at a level of 203.00 m. The footings will be cast against the sides of the
excavation in the weathered rock and the excavation above the footing backfilled with rock riprap. The top of
the abutment footings will be placed at a level of 205.00 m.
Rock protected guide banks will be provided at both abutments. Sufficient rock will be provided at the toe of
the spillthrough abutment and guide bank to protect against a depth scour of 1.5 m, which is slightly greater
that the depth required to achieve a velocity of 2.78 m/s (see Table 8.6) through the bridge opening.
8.7 References
AUSTROADS (1994), “Waterway Design –A Guide to the Hydraulic Design of Bridges, Culverts and
Floodways”, AUSTROADS National Office, Sydney.
HEC 23 (1997) - Federal Highway Administration, ”Bridge Scour and Stream Instability Countermeasures”,
US Department of Transportation.
Institute of Engineers, Australia (2001) ‘Australian Rainfall and Runoff – A Guide to Flood Estimation Volume
1’