Professional Documents
Culture Documents
TABLE OF CONTENTS
7 HYDRAULIC DESIGN OF CULVERTS 7-1
FIGURES
Figure 7.1: Flow Profiles for Culverts under Inlet Control 7-5
Figure 7.2: Flow Profiles for Culverts under Outlet Control 7-6
Figure 7.3: Hydraulics of Culvert Flowing Full under Outlet Control 7-7
Figure 7.4: Design Flow Chart 7-11
Figure 7.5: Design Form for Culvert Calculations 7-19
Figure 7.6: Entrance Loss Coefficients 7-20
Figure 7.7: Inlet Control Nomograph – Box Culvert 7-21
Figure 7.8: Inlet Control Nomograph – Concrete Pipe Culvert 7-22
Figure 7.9: Inlet Control Nomograph – Corrugated Metal Pipe (CMP) and Structural Plate Corrugated
Steel Pipe (SPCSP) Culvert 7-23
Figure 7.10: Inlet Control Nomograph – Corrugated Steel Pipe Arch (CSPA) and Structural Plate
Corrugated Steel pipe Arch (SPCSPA) Culvert 7-24
Figure 7.11: Critical Depth in a Rectangular Section 7-25
Figure 7.12: Critical Depth in a Circular Pipe 7-26
Figure 7.13: Critical Depth in a Corrugated Steel Pipe Arch (CSPA) 7-27
Figure 7.14: Critical Depth in a Structural Plate Corrugated Steel Pipe Arch (SPCSPA) 7-28
Figure 7.15: Outlet Control Nomograph – Concrete Box Culvert Flowing Full (n=0.012) 7-29
Figure 7.16: Outlet Control Nomograph – Corrugated Metal Pipe (CMP) Flowing Full (n=0.024) 7-30
Figure 7.17: Outlet Control Nomograph – Concrete Pipe Culvert Flowing Full (n=0.012) 7-31
Figure 7.18: Outlet Control Nomograph – Structural Plate Corrugated Steel Pipe (SPCSP) Flowing Full
(n=0.0328 to 0.0302) 7-32
Figure 7.19: Outlet Control Nomograph – Corrugated Steel Pipe Arch (CSPA) Flowing Full (n=0.024)7-
33
Figure 7.20: Outlet Control Nomograph – Structural Plate Corrugated Steel Pipe Arch (SPCSPA)
Flowing Full (n=0.0327 to 0.0306) 7-34
A culvert comprises three basic components; the inlet, the section of conduit and the outlet. All three of these
components in addition to the water levels at the outlet and the elevation of the road surface will control the
hydraulic performance of a culvert.
Culverts can be installed at right angles to the road embankment or skewed across the alignment. Where
additional capacity is required, multiple culverts can be installed in parallel.
(a) Headwater
Any constriction to the natural flow in a stream or creek will result in an elevated water level upstream of the
constriction. The headwater depth of a culvert is the level difference between the upstream elevated water
depth and the invert of the inlet.
The capacity of a culvert is related to the available headwater. A smaller culvert may be installed in locations
where headwaters can be permitted to rise to cause the design flow through it. This can be easily achieved
at high road embankments.
Designers must however be fully aware of the effect of pipe selection and expected headwater levels under
design conditions as well as extreme floods. Issues to consider include:
• Properties and buildings upstream of the culvert crossing normally limit permissible headwater
depths. Elevated floodwaters in privately owned land due to substantial constrictions placed by
small culverts should be avoided.
• As headwaters rise flow velocities in culverts will also increase. Where flows under design
conditions are greater than 6 m/s scouring of the pipe material will occur over time (QUDM, 1994).
The effect of the increased flows at the outlet to the culvert also needs to be considered. An energy
dissipating structure may be necessary to return flows to a velocity that will not scour the
downstream channel.
(b) Existing Watercourse Alignment
Existing watercourses prior to the construction of a new road may cross the alignment at a variety of angles.
A right angle crossing will naturally provide the shortest culvert and subsequently save on construction costs.
Installing a culvert crossing which does not reflect the natural flow path however may come at a cost.
Generally culverts should be aligned with the original channel. Culverts aligned as such will require the least
amount of excavation at the inlet and outlet and also scour protection measures. Sharp changes in direction
of flows to force shorter culvert crossings are prone to scouring. Material that is eroded then has the potential
to block the culvert opening. Sharp small radius bends also reduce the hydraulic efficiency of a channel.
Whilst it is desirable to maintain the alignment of the natural flow path culvert skew should not exceed 45o.
Where large skew angles are required consideration should be given to the most appropriate road alignment
(AUSTROADS 1994).
In flat terrain existing flow paths may be difficult to define. During major storm events a very wide flow path
with no defined main channel may result. In these circumstances it is recommended that pre-development
flow paths be maintained as far as practical.
A series of culverts in parallel spread across a road embankment is more favourable than one localised high
capacity culvert. Culverts can be installed at different levels so that low flows occur at a defined location with
larger flows being conveyed by a series of culverts spread along an embankment.
7.2.3 Siltation
Depending upon the geometry of a channel immediately upstream and downstream from a culvert and also
the relative grades, siltation may be a recurrent problem at culverts. Siltation most often occurs at flows less
than the design discharge. Dependent upon factors such as the volume of material, relative compaction and
headwater depth under design flow conditions the material may be flushed out during severe storms.
Designers should consider the following factors that influence sediment transport capacity:
• Culvert area: Culverts often present a wider flow area than natural streams during low flow
conditions. The wider flow area results in lower flows and thus a reduced sediment transport
capacity;
• Direction changes: Sharp changes in direction of a channel immediately upstream of a culvert will
result in a velocity differential across the flow path. The inside of a bend will have low velocities,
which may lead to sedimentation. This occurrence may be particularly pronounced in multiple cell
culverts where the culvert closest to the inside of a bend is regularly blocked by sediments;
• Grade changes: Abrupt changes in grade between a natural channel and a culvert or formed
channel will change the sediment transport capacity. Waterborne particles will tend to be deposited
immediately downstream of a profile change to a flatter grade.
7.2.4 Safety
Any structure constructed adjacent to a travel lane, especially within the clear zone will present a potential
hazard to motorists (Main Roads 2002). An exposed culvert end projecting from a road embankment will
present an unyielding hazard with any impact against it having a high severity rating.
Road shoulders should not be narrowed at culverts to reduce their lengths. Desirably, culverts should be
extended so that structures are located outside the road clear zone Clear zone width is related to travel
speed and embankment geometry. Where site constraints do not permit locating culvert inlets and outlets at
a suitable offset to travel lanes safety barriers should be installed to protect errant vehicles.
Culverts can also present a hazard to children and pedestrians. Providing grates at culvert inlets can be
considered however this will significantly increase the possibility of blockages and also reduce the hydraulic
capacity. Where the depth, velocity or regularity of flow presents a high hazard appropriate pedestrian
fences should be installed at inlets and outlets.
To limit the risk of blockages it is considered prudent design to avoid the use of small diameter pipes. It is
recommended that the minimum pipe diameter for a culvert crossing be 600mm.
Figure 7.1 below depicts a culvert operating under inlet control with unsubmerged and submerged conditions
and also projecting and mitred entrances.
Inlet control can occur with the inlet submerged and the outlet not submerged. Under these conditions, the
flow contracts to a supercritical jet immediately downstream from the inlet. When the tail water depth
exceeds critical depth, hc and the culvert is laid on a steep grade, flow remains supercritical for the length of
the culvert with a hydraulic jump occurring at the outlet. If the culvert is laid on a slope less than critical, then
a hydraulic jump will form in the cell.
Culverts flowing with outlet control can flow either full or part full for all the culvert length. With outlet control
and both the inlet and outlet submerged the culvert flows full under pressure. A culvert can also flow full over
part of its length, then part-full at the outlet.
Figure 7.2 presents a range of different conditions for culverts operating with outlet control.
If a culvert is laid on a flat grade, outlet control can still prevail with both the inlet and outlet unsubmerged.
The part full flow throughout the cell will be subcritical.
H = Hv + He + Hf (7.1)
Hv = V2 / 2g (7.2)
Where
V= mean velocity in the culvert cell
g= acceleration due to gravity
The mean velocity is the discharge, Q, divided by the cross-sectional area A of the cell.
He = KeV2 / 2g (7.3)
Where
Ke = loss coefficient
Ke depends on the inlet geometry primarily through the effect it has on contraction of the flow. Values of Ke
range from 0.2 for a well rounded entrance, through 0.5 for a square edged inlet in a vertical headwall to 0.9
for a sharp pipe projecting from an embankment.
Hf = 2 g n2 L V2
R1.33 2g (7.4)
Where
n= Manning’s friction factor
L= length (m) of culvert cell
V= mean velocity (m/s) of flow in culvert cell
g= acceleration due to gravity (9.807m/s2)
R= hydraulic radius (m) = A/Wp
A= area (m2) of flow for full cross-section
Wp = wetted perimeter
Figure 7.3 shows the energy line, the hydraulic grade line and the headwater depth, HW for a culvert
operating under outlet control. The energy line represents the total energy at any point along the culvert cell.
The hydraulic grade line is defined as the pressure line to which water would rise in small vertical pipes
attached to the culvert wall along its length. The difference in elevation between these two lines is the
velocity head, V2/2g.
H in Figure 7.3 is the difference between the elevation of the hydraulic grade line at the outlet and the energy
line at the inlet. Since the velocity head in the entrance pool is usually small under ponded conditions, the
water surface of the headwater pool can be assumed to be equal to the energy line.
For outlet control headwater depth HWo can be determined from the following equation:
HWo = H + ho – LS (7.5)
where
H= head determined from nomographs at the end of this chapter
ho = greater of Tw and (hc + D)/2, in which hc ≤ D
Tw = tail water depth (m)
hc = critical depth (m) refer figures at end of chapter
D= culvert height (m)
L= length (m) of culvert
S= slope (m/m) of cell
(c) Determination of ho
The determination of ho is an important factor in calculating both the headwater depth and hydraulic capacity
of a culvert flowing under outlet control.
Tailwater depth, Tw is the depth from the culvert invert at the outlet to the water surface in the outlet channel.
Designers should familiarize themselves with conditions downstream from a culvert that may influence the
tailwater depth.
Two tailwater conditions can occur with culverts operating under outlet control; the tailwater above the obvert
of the outlet pipe, and the tailwater at or below the pipe obvert.
1. Tailwater above the outlet obvert - When the tailwater in the outlet channel is above the pipe obvert
then ho = Tw
2. Tailwater at or below pipe obvert – Full flow depth at the outlet will occur only when the flow rate is
sufficient to give critical depths equal or higher than the height of the culvert opening. For all such
flows the hydraulic gradeline will pass through the top of the culvert at the outlet and the head, H can
be added to the level of the top of the culvert opening in calculating HWo.
When critical depth is less than the height of the culvert opening, the water surface drops as shown
in Fig. 7.2 C and D, depending upon the flow. For the condition shown in C, the culvert must flow full
for part of its length. Flow profile computations show that the hydraulic gradeline, if extended as a
straight line from the top of the culvert, will be at a height approximately halfway between the critical
depth and the culvert obvert (i.e. ho = (hc+D)/2)
This level should be used if it is greater than Tw. The head H can be added to this level in calculating
HWo.
As discharges decrease the flow profile will eventually reach a point where the entire length of the
pipe flows part full. For design purposes, this method is satisfactory for calculated headwater depths
above 0.75D (AUSTROADS 1994).
A design form which can be used to record calculations along with relevant nomographs are presented in
Section 7.8.
Methods to determine peak flows are described in Chapter 3. Whilst culverts on minor roads for instance
may be designed for less severe storms like 10-year ARI or 20-year ARI. The designers must also assess
the effect of a culvert for major storms such as 100-year ARI. Where the consequences of overtopping or
backwater effects will cause considerable damage culverts should be designed to convey the full major
event storm flow.
After selecting an appropriate culvert material, shape, and entrance type, a trial culvert size is selected and
analysed. The initial culvert size can be arbitrarily selected or be based on desired flow velocity within the
culvert.
A=Q/V (7.6)
Where
A = cross section area of culvert (m2)
Q = design flow rate (m3/s)
V = flow velocity (m/s)
In locations where the approach flow velocity is considerable the velocity head can be subtracted from the
headwater depth obtained by the nomographs to determine the actual physical head required.
Where
hc = critical depth (m)
D = culvert height (m)
If hc exceeds D then take hc as D.
2. Determine tailwater depth Tw from known flood levels, downstream flood levels or through Manning’s
equation for the known cross section geometry and channel roughness.
The larger of the two depths determined above is then adopted as ho.
where
L1 = adjusted culvert length (m)
L = actual culvert length (m)
n1 = actual Manning’s n value of culvert
n = Manning’s n value presented in nomographs
HWo = H + ho – LS (7.9)
where
L = culvert length (m)
S = culvert slope (m/m)
As with the calculation for inlet control if the culvert approach velocity is considerable, the velocity
head can be subtracted from the headwater depth calculated above to give the actual physical head
required.
5. If HWo is less than 0.75D and the culvert is under outlet control, then the culvert may be only part full
and using (hc + D)/2 may not be applicable. If required, more accurate results can be obtained by
flow profile calculations.
When HWi is the larger of the two values the culvert is said to operate under inlet control and conversely
where HWo is larger, outlet control prevails.
If it is determined that the headwater depth required to convey the design flow is greater than the maximum
permissible for the site then a larger culvert size is trialled and the process repeated. If the calculated
headwater depth at the inlet is near to that of the culvert obvert a smaller more economical culvert could be
considered.
The average outlet velocity can be calculated from the design flow and the cross-sectional area at the outlet.
An estimate of the depth of flow at the outlet will be necessary to determine the flow area.
Vo = Q / A
It should be noted that the normal depth yn will usually be high as this depth is seldom reached in the
relatively short length of an average culvert.
For culverts operating under outlet control the flow depth at the culvert outlet can be either:
• the critical depth yc;
• the tailwater depth Tw; or
• or the depth of the culvert D.
The following criteria should be used in selecting the appropriate outlet flow depth.
If hc > Tw use hc
If hc < Tw < D use Tw
If D < Tw use D
The outlet flow area is calculated from the depth above and from hence the outlet velocity.
Vo = Q / A
Cutoffs in the form of a vertical wall constructed below the end or apron of a culvert should always be
provided at culvert inlets to prevent undermining and piping.
Mitred Ends – These are generally limited to corrugated metal pipe culverts, where the end of the pipe is cut
parallel to the slope of the embankment. The area of embankment around the ends of the culvert is usually
protected with concrete or rock.
Projecting Ends – occur where the end of a culvert projects from an embankment. These types of end
treatments, although the cheapest, should generally be avoided as they tend not to meet safety
requirements and are unsightly.
Upstream wing walls, aprons and cut-off walls and embankment paving assist in protecting the embankment
and stream bed against scouring.
If it is deemed necessary to include additional measures the following treatments could be considered:
An important parameter in the selection of a suitable energy dissipater is the Froude number, Fr of the outlet
flow. Where an outlet has Fr < 1.7, a simple apron structure, riprap, or a flow expansion structure will suffice.
Where 1.7<Fr<3 a riprap basin or horizontal roughness elements basin is appropriate. Where Fr>3 a
hydraulic jump basin will be required.
Stream bed protection can be achieved with a concrete apron, rock riprap, or rock mattresses, or concrete
filled mattresses. It is important that mattresses are anchored to the cut-off wall or apron at the culvert outlet,
to stop them moving downstream. A geotextile filter should be provided under the mattresses and also under
rock riprap.
A range of controls can be considered where local experience reveals a high likelihood of water borne
debris. Debris damage to the culvert can be controlled by three methods (HEC 9, 1971): 1- intercepting the
debris at or above the inlet; 2- deflecting the debris for detention near the inlet; or 3- passing the debris
through the structure.
In designing relief culverts the option of providing a single larger culvert should be weighed against providing
additional high-level culverts.
The effectiveness of debris control relies on regular monitoring and cleaning of the structure. This approach
is particularly effective in Addis Ababa city environment. Structural measures of debris control constitute a
subject in itself, hardly justified as a section of this chapter. The information is readily available at the web
site of Federal Highway Administration, US Department of Transportation: www.fhwa.dot.gov. Hydraulic
Engineering Circular No. 9 “Debris Control Structures”, available at the web site describes various types of
debris control structures in sufficient details.
Figure 7.9: Inlet Control Nomograph – Corrugated Metal Pipe (CMP) and Structural Plate Corrugated
Steel Pipe (SPCSP) Culvert
Source: AUSTROADS (1994)
Figure 7.10: Inlet Control Nomograph – Corrugated Steel Pipe Arch (CSPA) and Structural Plate
Corrugated Steel pipe Arch (SPCSPA) Culvert
Source: AUSTROADS (1994)
Figure 7.14: Critical Depth in a Structural Plate Corrugated Steel Pipe Arch (SPCSPA)
Source: AUSTROADS (1994)
Figure 7.15: Outlet Control Nomograph – Concrete Box Culvert Flowing Full (n=0.012)
Source: AUSTROADS (1994)
Figure 7.16: Outlet Control Nomograph – Corrugated Metal Pipe (CMP) Flowing Full (n=0.024)
Source: AUSTROADS (1994)
Figure 7.17: Outlet Control Nomograph – Concrete Pipe Culvert Flowing Full (n=0.012)
Source: AUSTROADS (1994)
Figure 7.18: Outlet Control Nomograph – Structural Plate Corrugated Steel Pipe (SPCSP) Flowing
Full (n=0.0328 to 0.0302)
Source: AUSTROADS (1994)
Figure 7.19: Outlet Control Nomograph – Corrugated Steel Pipe Arch (CSPA) Flowing Full (n=0.024)
Source: AUSTROADS (1994)
Figure 7.20: Outlet Control Nomograph – Structural Plate Corrugated Steel Pipe Arch (SPCSPA)
Flowing Full (n=0.0327 to 0.0306)
Source: AUSTROADS (1994)
7.9 References
ACT Government (1994), “Urban Stormwater – Edition 1: Standard Engineering Practices”.
AUSTROADS (1994), “Waterway Design –A Guide to the Hydraulic Design of Bridges, Culverts and
Floodways”, AUSTROADS National Office, Sydney.
Institute of Engineers, Australia (2001), “Australian Rainfall and Runoff – A Guide to Flood Estimation
Volume 1”.
Department of Main Roads (Main Roads - 1987), Queensland Australia, “Road Drainage Design Manual”.
HDS 5 (2001)– Federal Highway Administration, “Hydraulic Design of Highway Culverts”, US Department of
Transportation.
NAASRA (1986), “Guide to the Design of Road Surface Drainage”, National Association of Australian State
Roads Working Group.
QUDM (1994), Department of Primary Industries - Water Resources, “Queensland Urban Drainage Manual
– Volume 1: Text”, Institute of Municipal Engineering Australia, Queensland Division, Brisbane City Council.