CIP Type

SYRUP TIME TIME PREFORM& 1- Hot Water CIP Time


DILUTION UNITS Beverage (LT) LT/UNITS UNITS QTY PACK LABEL SHRINK Order 2- Caustic
Volume (L) Pet 1 Pet 2 CAPS (hrs)
3- Caustic
Perasitic
AMERICAN COLA 1+5 5 9463.25 1892.65 0 0 0.00 - 0 0.00 0.00
Via COLA 1+5 5 9463.25 1892.65 0 0 0.00 - 0 0.00 0.00
BIGOO COLA 1+5 5 9463.25 1892.65 0 0 0.00 - 0 0.00 0.00
PLANET ORANGE 1+5 6 9688.5 1614.75 0 0 0.00 - 0 0.00 0.00
BIGOO ORANGE 1+5 6 9688.5 1614.75 0 0 0.00 - 0 0.00 0.00
VIA ORANGE 1+5 6 9688.5 1614.75 0 0 0.00 - 0 0.00 0.00
PLANET PINEAPPLE 1+5 6 9692.34 1615.39 20 32307.8 46,154 25.17 - 553,848 117.42 633.23 1 3 3.00
BIGOO COCONUT 1+4 5 9630.85 1926.17 0 0 0.00 - 0 0.00 0.00
BIGOO COCKTAIL 1+5 6 9646.02 1607.67 0 0 0.00 - 0 0.00 0.00
PLANET CAFE MOKA 1+4 5 9665.45 1933.09 0 0 0.00 - 0 0.00 0.00
BIGOO CAFE MOKA 1+4 5 9665.45 1933.09 0 0 0.00 - 0 0.00 0.00
X-PLUS 12/1 1+4 4 8000 2000 0 0 0.00 - 0 0.00 0.00
X-PLUS 1+4 4 8000 2000 0 0 0.00 - 0 0.00 0.00
BIGOO APPLE JERRY RECIPE 1+4 5 10000 1000 0 0 0.00 - 0 0.00 0.00
LEMON LIME 1+5 6 9703.86 1617.31 30 48519.3 69,313 37.81 - 831,759 176.33 950.98 2 2 1.50
VIA LEMON LIME 1+5 6 9703.86 1617.31 30 48519.3 69,313 37.81 - 831,759 176.33 950.98 3 2 1.50
BUBLLE UP TONIC 1+6 6 8571.42 1428.57 0 0 0.00 - 0 0.00 0.00
TIKTOK MANGO 350 ML 16/1 1+1 2 4000 2000 0 0 0.00 - 0 0.00 0.00
TIKTOK MANGO 350 ML 1+1 2 4000 2000 0 0 0.00 - 0 0.00 0.00
TIKTOK MANGO 1 L 1+1 2 4000 2000 0 0 0.00 - 0 0.00 0.00
TIKTOK ORANGE 1+1 2 4000 2000 0 0 0.00 - 0 0.00 0.00
TIKTOK Pineapple 350 ML 1+1 2 4000 2000 0 0 0.00 - 0 0.00 0.00
Water 0.5 L 0 1 0 0 0 0 0.00 - 0 0.00 0.00
Water 1.5 L 0 1 0 0 0 0 0.00 - 0 0.00 0.00
BIGOO JERRY APPLE 1+3 4 4000 1000 0 0 0.00 - 0 0.00 0.00
Tampico 300 Ml 1+4 5 7570 1514 0 0 0.00 - 0 0.00 0.00
Tampico 1 L 1+4 5 7570 1514 0 0 0.00 - 0 0.00 0.00
Tamarind 1+3 4 4000 1000 0 0 0.00 - 0 0.00 0.00

Strating date --> 18-Jun


Strating time --> 10:00

Schedule Sidel SBO10


Order Product Name Starting Date & Time Finishing Date & Time Units
1 PLANET PINEAPPLE 6/18/2023 10:00 6/19/2023 11:10 10 After Planet
2 LEMON LIME 6/19/2023 14:10 6/21/2023 3:58 30
3 VIA LEMON LIME 6/21/2023 5:28 6/22/2023 19:17 30
4-
5-
6-
7-
8-
9-
10 -
11 -
12 -
13 -
14 -
15 -
16 -
17 -
18 -
19 -
20 -
DILUTION

AMERICAN COLA 1+5


VIA COLA 1+5
PLANET ORANGE 1+5
VIA ORANGE 1+5
BIGOO ORANGE 1+5
PLANET PINEAPPLE 1+5
BIGOO PINEAPPLE 1+5
PLANET COCONUT 1+4
PLANET COCKTAIL 1+5
BIGOO COCKTAIL 1+5
PLANET CAFE MOKA 1+4
X-PLUS 1+4
PLANET APPLE 1+4
VIAL EMON LIME 1+5
BUBBLE UP LEMON LIME 1+5
BIGOO LEMON LIME 1+5
BUBLLE UP TONIC 1+6
BIGOO TONIC (Dohler) 1+6
BIGOO APPLE Dohler (Caps White) 1+3

Strating date --> 19-Jun


Strating time --> 22:00

Schedule SIDEL SBO14


Order Product Name
1 X-PLUS
2-
3-
4-
5-
6-
7-
8-
9-
10 -
11 -
12 -
13 -
14 -
15 -
16 -
17 -
18 -
19 -
20 -
SYRUP
UNITS SYRUP (LT) LT/UNITS UNITS
Volume (L)

6 9463.25 1577.2083333 0
6 9463.25 1577.2083333 0
6 9688.5 1614.75 0
6 9688.5 1614.75 0
6 9688.5 1614.75 0
6 9692.34 1615.39 0
6 9692.34 1615.39 0
5 9630.85 1926.17 0
6 9646.02 1607.67 0
6 9646.02 1607.67 0
5 9665.45 1933.09 0
4 8000 2000 80 160000
5 9607.8 1921.56 0
6 9703.86 1617.31 0
6 9703.86 1617.31 0
6 9703.86 1617.31 0
6 8571.42 1428.57 0
6 9000 1000 0
4 10000 1000 0
Starting Date & Time Finishing Date & Time Units
6/19/2023 22:00 6/22/2023 15:18 80
CIP Type
1- Hot Water
TIME TIME PREFORM&C CIP Time
QTY PACK LABEL SHRINK Order 2- Caustic
Pet 1 Pet 2 APS (hrs)
3- Caustic
Perasitic
0 - 0.00 0 0.00 0.00
0 - 0.00 0 0.00 0.00
0 - 0.00 0 0.00 0.00
0 - 0.00 0 0.00 0.00
0 - 0.00 0 0.00 0.00
0 - 0.00 0 0.00 0.00
0 - 0.00 0 0.00 0.00
0 - 0.00 0 0.00 0.00
0 - 0.00 0 0.00 0.00
0 - 0.00 0 0.00 0.00
0 - 0.00 0 0.00 0.00
142,857 - 65.31 2,285,714 484.57 1914.29 1 2 1.50
0 - 0.00 0 0.00 0.00
0 - 0.00 0 0.00 0.00
0 - 0.00 0 0.00 0.00
0 - 0.00 0 0.00 0.00
0 - 0.00 0 0.00 0.00
0 - 0.00 0 0.00 0.00
0 0.00 0.00 0 0.00 0.00
DILUTION

AMERICAN COLA 1+5


VIA COLA 1+5
BIGOO COLA 1+5
PLANET ORANGE 1+5
BIGOO ORANGE 50/50 1+5
VIA ORANGE 50/50 1+5
PLANET PINEAPPLE 1+5
PLANET COCONUT 1+4
PLANET COCKTAIL 1+5
PLANET CAFE MOKA 1+4
X-PLUS 1+4
PLANET APPLE 1+4
BUBBLE LEMON LIME 1+5
BIGOO LEMON LIME 1+5
VIA LEMON LIME 1+5
BIGOO TONIC Dohler Recipe 1+5
BIGOO AND VIA TONIC DOHLER RECIPE BLACK CAPS 1+5
BUBLLE UP TONIC 1+6
VIA TONIC Dohler Recipe 1+6
BIGOO APPLE Dohler (Caps White) 1+3

Strating date --> 19-Jun


Strating time --> 17:00
Schedule SIDEL SBO18
Order Product Name
1 BIGOO ORANGE 50/50
2 PLANET ORANGE
3 VIA ORANGE 50/50
4-
5-
6-
7-
8-
9-
10 -
11 -
12 -
13 -
14 -
15 -
16 -
17 -
18 -
19 -
20 -
SYRUP
UNITS SYRUP (LT) LT/UNITS UNITS
Volume (L)

6 9463.25 1577.20833333333 0
6 9463.25 1577.20833333333 0
6 9463.25 1577.20833333333 0
6 9688.5 1614.75 48 77508
6 9688.5 1614.75 72 116262
6 9688.5 1614.75 48 77508
6 9692.34 1615.39 0
5 9630.85 1926.17 0
6 9646.02 1607.67 0
5 9665.45 1933.09 0
4 8000 2000 0
5 9607.8 1921.56 0
6 9703.86 1617.31 0
6 9703.86 1617.31 0
6 9703.86 1617.31 0
6 9703.86 1617.31 0
6 6000 1000 0
6 8571.42 1428.57 0
6 9000 1000 0
4 10000 2500 0
Starting Date & Time Finishing Date & Time Units
6/19/2023 17:00 6/21/2023 13:17 72
6/21/2023 14:27 6/22/2023 19:59 48
6/22/2023 21:09 6/24/2023 2:40 48
CIP Type
1- Hot Water
TIME TIME PREFORM&C CIP Time
QTY PACK LABEL SHRINK Order 2- Caustic
Pet 1 Pet 2 APS (hrs)
3- Caustic
Perasitic
0 - 0.00 0 0.00 0.00
0 - 0.00 0 0.00 0.00
0 - 0.00 0 0.00 0.00
110,726 - 29.53 1,328,709 281.69 1483.72 2 1 1.17
166,089 - 44.29 1,993,063 422.53 2225.59 1 1 1.17
110,726 - 29.53 1,328,709 281.69 1483.72 3 1 1.17
0 - 0.00 0 0.00 0.00
0 - 0.00 0 0.00 0.00
0 - 0.00 0 0.00 0.00
0 - 0.00 0 0.00 0.00
0 - 0.00 0 0.00 0.00
0 - 0.00 0 0.00 0.00
0 - 0.00 0 0.00 0.00
0 - 0.00 0 0.00 0.00
0 - 0.00 0 0.00 0.00
0 - 0.00 0 0.00 0.00
0 0.00 0.00 0 0.00 0.00
0 - 0.00 0 0.00 0.00
0 - 0.00 0 0.00 0.00
0 0.00 0.00 0 0.00 0.00
0.00
DILUTION UNITS

PIPPO MANGO 1+1 1


PIPPO ORANGE 1+1 1
PIPPO PINEAPPLE 1+1 1
PIPPO COCKTAIL 1+1 1
PIPPO STRAWBERRY 125 ml 1+1 1
PIPPO APPLE 1+1 1
PIPPO MILK MANGO 1+1 1
PIPPO MILK ORANGE 1+1 1
PIPPO MILK PINEAPPLE 1+1 1
PIPPO MILK CHOCLATE 1+1 1
PIPPO CHOCLATE MALT 1+1 1
PIPPO MILK COCKTAIL 1+1 1
PIPPO STRAWBERRY MILK 1+1 1
PIPPO SOYA MILK 1+1 1
PIPPO GRAPE 125 ml 1+1 1
Tampico Citrus 250 ml 1+1 1
Tampico Mango 250 ml 1+1 1
Tampico Multifruit 250 ml 1+1 1

Strating date --> 16-Jun-23


Strating time --> 10:00

Schedule TETRA PAK


Order Product Name Starting Date & Time
1 PIPPO MANGO 6/16/2023 10:00
2 PIPPO PINEAPPLE 6/17/2023 7:27
3 PIPPO COCKTAIL 6/18/2023 4:54
4-
5-
6-
7-
8-
9-
10 -
11 -
12 -
13 -
14 -
15 -
16 -
17 -
18 -
19 -
20 -
TETRA TETRA SYRUP TETRA TETRA TIME
SYRUP (LT) LT/UNITS UNITS
125 250 Volume (L) 125 ML 250 ML Pet 2

1000 1000 80 47.2 32.8 80000 15,733 5,467 19.95


1000 1000 0 0 0 0 0 0.00
1000 1000 80 47.2 32.8 80000 15,733 5,467 19.95
1000 1000 80 47.2 32.8 80000 15,733 5,467 19.95
1000 1000 0 0 0 0 0 0.00
1000 1000 0 0 0 0 0 0.00
1000 1000 0 0 0 0 0 0.00
1000 1000 0 0 0 0 0 0.00
1000 1000 0 0 0 0 0 0.00
1000 1000 0 0 0 0 0 0.00
1000 1000 0 0 0 0 0 0.00
1000 1000 0 0 0 0 0 0.00
1000 1000 0 0 0 0 0 0.00
1000 1000 0 0 0 0 0 0.00
1000 1000 0 0 0 0 0 0.00
1514.2 1514.2 0 0 0 0 0 0.00
1514.2 1514.2 0 0 0 0 0 0.00
1909.66 1909.66 0 0 0 0 0 0.00

Finishing Date & Time Units


6/17/2023 5:57 80 Already Started
6/18/2023 3:24 80
6/19/2023 0:51 60
Packs/STRAW Packs/STRAW Cartons Cartons SHRINK SHRINK
Order
125 ml 250 ml 125 ml 250 ml 125 ml 250 ml

377,600 131,200 15,733 5,467 183 86.87 1


0 0 0 0 0 0.00
377,600 131,200 15,733 5,467 183 86.87 2
377,600 131,200 15,733 5,467 183 86.87 3
0 0 0 0 0 0.00
0 0 0 0 0 0.00
0 0 0 0 0 0.00
0 0 0 0 0 0.00
0 0 0 0 0 0.00
0 0 0 0 0 0.00
0 0 0 0 0 0.00
0 0 0 0 0 0.00
0 0 0 0 0 0.00
0 0 0 0 0 0.00
0 0 0 0 0 0.00
0 0 0 0 0 0.00
0 0 0 0 0 0.00
0 0 0 0 0 0.00
CIP Type
1- Hot Water
CIP Time
2- Caustic
(hrs)
3- Caustic
Perasitic
2 1.50
2 1.50
2 1.50
2 1.50
DILUTION UNITS SYRUP (LT) LT/UNITS

Tikto Mango 1+1 1 1000 1000


Tiktok Orange 1+1 1 1000 1000
Tiktok Pineapple 1+1 1 1000 1000
Tiktok Cocktail 1+1 1 1000 1000
Hero 1+1 1 1000 1000
Tiktok Milk Mango 1+1 1 1000 1000

Strating date --> 12-Jun-23


Strating time --> 12:00

Schedule CUP Machine


Order Product Name Starting Date & Time Finishing Date & Time Units
1 Tikto Mango 6/12/2023 12:00 6/15/2023 10:50 170
2-
3-
4-
5-
6-
7-
8-
9-
10 -
11 -
12 -
13 -
14 -
15 -
16 -
17 -
18 -
19 -
20 -
SYRUP Cup Pack TIME Packs/STRAW Cartons Cup Film
Units Order
Volume (L) 250 ml Cup 250 ml 250 ml 250 ml

170 170000 30,357 70.83 850,000 30,357 354 1


0 0 0.00 0 0 0
0 0 0.00 0 0 0
0 0 0.00 0 0 0
0 0 0.00 0 0 0
0 0 0.00 0 0 0
CIP Type
1- Hot Water
CIP Time
2- Caustic
(hrs)
3- Caustic
Perasitic
2 1.50
DILUTION UNITS SYRUP (LT)

Tikto Mango Pouch 1+1 1 1000


Tiktok Pineapple Pouch 1+1 1 1000
Tiktok Cocktail Pouch 1+1 1 1000
Tiktok Orange Pouch 1+1 1 1000

Strating date --> 16-Jun-23


Strating time --> 10:00

Schedule Pouch Machine


Order Product Name Starting Date & Time Finishing Date & Time
1 Tikto Mango Pouch 6/16/2023 10:00 6/18/2023 12:55
2 Tiktok Orange Pouch 6/18/2023 14:25 6/19/2023 7:05
3 Tiktok Pineapple Pouc 6/19/2023 8:35 6/19/2023 19:42
4 Tiktok Cocktail Pouch 6/19/2023 21:12 6/20/2023 13:52
5-
6-
7-
8-
9-
10 -
11 -
12 -
13 -
14 -
15 -
16 -
17 -
18 -
19 -
20 -
SYRUP Cup Pack TIME Carton
LT/UNITS Units Pouch 180Ml Spout
Volume (L) 250 ml Cup 180 ml

1000 55 55000 12,731 50.93 305,556 12,731 12,731


1000 20 20000 4,630 11.11 111,111 4,630 4,630
1000 30 30000 6,944 16.67 166,667 6,944 6,944
1000 30 30000 6,944 16.67 166,667 6,944 6,944

Units
55 Already Started
30
20
30
CIP Type
1- Hot Water
CIP Time
Order 2- Caustic
(hrs)
3- Caustic
Perasitic
1 2 1.50
3 2 1.50
4 2
2 2 1.50