Professional Documents
Culture Documents
16
104
BETWEEN
V.
TABLE OF CONTENTS
LIST OF ABBREVIATIONS............................................................................................................................................4
INDEX OF AUTHORITIES............................................................................................................................................. 5
STATUTES....................................................................................................................................................................... 5
CASES............................................................................................................................................................................... 5
BOOKS............................................................................................................................................................................. 5
WEBSITES....................................................................................................................................................................... 6
STATEMENT OF FACTS.......................................................................................................7
ISSUES RAISED.......................................................................................................................8
1. WHETHER THE RESPONDENT HAS COMMITTED A BREACH OF CONTRACT?....8
2. WHETHER THE NOTIFICATIONS AFFECT THE TIMELY COMPLETION OF
PROJECT?..............................................................................................................................................8
3. WHETHER THE CLAIMANT IS ENTITLED TO COMPENSATION?..............................8
SUMMARY OF ARGUMENTS..............................................................................................8
1. WHETHER THE RESPONDENT HAS COMMITTED A BREACH OF CONTRACT?.................8
2. WHETHER THE ORDERS/NOTIFICATIONS AFFECT THE TIMELY COMPLETION OF
PROJECT?...............................................................................................................................................8
3. WHETHER THE CLAIMANT IS ENTITLED TO COMPENSATION?..........................................8
ARGUMENTS ADVANCED...................................................................................................9
WHETHER THE RESPONDENT HAS COMMITTED A BREACH OF CONTRACT?.....................9
A. RESPONDENT HAS FAILED TO ACHIEVE SPECIFIC TIME BOUND RESULT AND THAT
TIME IS THE ESSENCE OF THE CONTRACT......................................................................................9
B. RESPONDENT failed to abide by the timelines as required by the Joint Development Agreement
(JDA).......................................................................................................................................................10
C. RESPONDENT breached the contract by flouting the timeline requirements.............................10
D. APPLICABILTY OF THE FORCE MAJEURE CLAUSE.............................................................11
E. LAWFUL TERMINATION OF THE AGREEMENT.....................................................................12
WHETHER THE NOTIFICATIONS AFFECT THE TIMELY COMPLETION OF THE PROJECT
....................................................................................................................................................................13
A. Material Breach............................................................................................................................13
B. Pertaining to temporal gap between the date of the JDA and the issuance of Govt notification. 16
WHETHER THE CLAIMANT CAN CLAIM COMPENSATION........................................................17
A. Non-transparency and Inaction....................................................................................................18
B. COMPENSATION.........................................................................................................................18
LIST OF ABBREVIATIONS
SC Supreme Court
Ors. Others
Anr. Another
V. Versus
Art. Article
Sec. Section
i.e That is
Art. Article
Govt Government
INDEX OF AUTHORITIES
STATUTES
CASES
1. Central Bank of India Ltd. v. Hartford Fire Insurance Co. Ltd., (1965) 25 Camp Cas 378, 8
2. K.K. Krishna Kutty v. Green Tree Homes Ventures Pvt. Ltd., 2019 SCC OnLine Mad
8897
3. Halliburton Offshore Service Inc. v. Vedanta Limited 2020 SCC OnLine Del 2068…
4. Standard Retail Pvt. Ltd. v. M/s G.S. Global Corp & Ors,
5. Bharat Petroleum Corpn. Ltd. & Anr. v. M/s. Jethanand Thakordas Karachiwala & Ors,
2000(1)BOMCR289
6. Strategic Outsourcing Inc. v. Continental Casualty Company
7. Dalkia Utilities services PLC v. Celtech International Limited , [2006] EWHC 63 (“Dalkia)
at 99
8. Maharashtra State Electricity Distribution Co Ltd v. DSL Enterprises Ltd, 2010 (1) RAJ 281
(BOM)
9. National Power PLC v. United Gas Company Ltd, (1998) All ER (D) 321
BOOKS
WEBSITES
1. SCC
2. Westlaw
3. Manupatra
4. Live Law
STATEMENT OF FACTS
The CLAIMANT, Mx. Krishna, a resident of Trichy owning a property of an extent of 2 acres in
Bayangammedu in Trichy was approached by the RESPONDENT, Karpanai Developers P. Ltd. to
undertake joint ventures for property development.
On 11 December 2019, after a series of negotiations, the parties signed a Joint Development
Agreement (JDA) to construct residential and commercial complex. The complex was named as
Mithila (hereinafter referred as ‘Project’). The property when developed will have 18 commercial
offices and 24 apartments consisting of 8 floors.
On 2 March 2020, the Govt of India responded to the COVID-19 situation by imposing a lockdown
for the entire country for a period of 68 days. In September 2020, the CLAIMANT requested the
RESPONDENT for updates on the Project and was informed that the pandemic and the lockdown
had affected the progress and was promised that the application for sanction of the plans would be
filed soon.
The plans were completed by October 2020. Subsequently, on 9 January 2021, the
RESPONDENT filed an application for the sanction of the plans for the project. However, on 21
January 2021, the Govt of Tamil Nadu issued a notification increasing the fees for the applications
for plan sanctions by 700 to 900% for all districts in Tamil Nadu and the revision applied
retrospectively, translating to a hike in the cost of the Project from Rs. 15 lakhs to Rs. 135 lakhs.
The RESPONDENT challenged the revision by writ petition in the Madras High Court in February
2021. Subsequently, on 17 October 2021, the Ministry of History and Culture, Central Govt passed
a ban order on the sanctions given for the construction of the multi-storeyed buildings exceeding
four storeys or beyond 45 feet in height in the ‘areas of cultural significance’ until the next plan
Master Plan for the development of those respective cities are finalised. The ban order listed these
areas, which included the Bayangammedu in Trichy.
The CLAIMANT issued a lawyer’s notice on 17 December 2021 stating their intention to terminate
the JDA and the Power of Attorney, following which a detailed reply was issued by the
RESPONDENT. After further communications, on 20 March 2022, the CLAIMANT issued a letter
of termination to the RESPONDENT. The CLAIMANT filed a petition in the District Court U/s 9
of the Arbitration and Conciliation Act, 1996 for interim measures. The court directed the parties to
maintain status quo and directed them to mediation.
SUMMARY OF ARGUMENTS
The claimant humbly submits that the respondent has breached the terms of the contract, particularly the
Joint Development Agreement (JDA). The JDA meticulously outlined specific timelines for crucial phases
of the project. Regrettably, the respondent consistently failed to meet these established deadlines, thereby
violating the contractual obligations. The argument is three fold:
a. Time is the essence of the contract
b. Applicability of the force majeure clause
c. Lawful termination of agreement
The counsel on behalf of the claimants submits that the orders/notifications cited by the
respondents serve as mere excuses for their failure to adhere to the terms of the contract, resulting in
a material breach. The claim contends that the time gap, for which no justifiable explanation has
been provided by the respondents, represents a significant and unjustified delay in fulfilling
contractual obligations. This unexplained delay has contributed to a material breach of the contract,
raising concerns about the respondents' commitment to the agreed-upon timelines and the overall
project schedule.
3. WHETHER THE CLAIMANT IS ENTITLED TO COMPENSATION?
The claimant contends that the respondent's breach of contract, marked by non-compliance with the Joint
Development Agreement (JDA) timelines, entitles the claimant to seek compensation. The lack of
transparency and effective communication from the respondent throughout the project, especially regarding
delays, is highlighted. Sec. 73 is invoked, emphasizing the duty of the party suffering from a breach to take
remedial steps. The claimant submits that, as per the valid and binding contract, compensation is warranted
for the sustained losses due to the respondent's inefficiencies, which led to the rightful termination of the
contract. The claimant pleads for compensation to restore them to the position they would have been in had
the breach not occurred.
1. RESPONDENT breached the contract and shall be liable for the ensuing damages, because
(a) Time is the essence of the contract and (b) RESPONDENT failed to abide by the
timelines as required by the Joint Development Agreement (JDA) and (c) RESPONDENT
breached the contract by flouting the timeline requirements.
1
Central Bank of India Ltd. v. Hartford Fire Insurance Co. Ltd., (1965) 25 Camp Cas 378, 8
2
Med-Arb Proposition, Paragraph No. 6
5. The Joint Development Agreement (JDA) set out the time schedule for the development of
the property. The timelines were agreed as below:
i. Firstly, detailed plans for the project to be prepared by the RESPONDENT within a
period of two (2) months from the date of the JDA, i.e., the JDA was executed on
11.12.2019 and two (2) months from then would mean latest by 11.2.2020. However,
the RESPONDENT failed to meet the said deadline.
ii. Secondly, the sanction for the plans had to be obtained within a period of four (4)
months from the date of the JDA, with an automatic extension of one (1) month in
case of delay. This translates to sanctions being obtained latest by May 2020.
However, the RESPONDENT failed to meet the said deadline.
iii. Furthermore, the deadline for the completion of the whole project was within a
period of two years from the approval of the plan sanction. However, the
RESPONDENT failed to meet the said deadline as well.
Essentially, the RESPONDENT failed to meet the deadlines set forth at every stage of the
contract and also failed to communicate the delay to the CLAIMANT at every stage.
6. Time being the essence of the contract, RESPONDENT breached the contract by flouting
the timeline requirements. There was a delay of over nine (9) months in preparing the
detailed plan as against the timeline provided i.e., two (2) months from the date of the JDA.
3
K.K. Krishna Kutty v. Green Tree Homes Ventures Pvt. Ltd., 2019 SCC OnLine Mad 8897
4
Med-Arb Proposition, Clause 3.2.5, Annexure A
1. ‘Force Majeure’5 means an “event or effect that can be neither anticipated nor controlled….
[and] includes both acts of nature (e.g., floods and hurricanes) and acts of people (e.g., riots,
strikes, and wars).”6 The general categorisation of an event/occurrence, like the mass
lockdown due to COVID-19, as force majeure event per se is meaningless, unless the event
actually impacts the obligations under the contract.
The Bombay High Court, in the case of Standard Retail Pvt. Ltd. v. M/s G.S. Global Corp &
Ors. 8 held that one of the grounds for refusing to grant an injunction was the absence of a direct
causal link between the pandemic and the non-performance of the contract.
5
Med-Arb Proposition, Clause 11, Annexure A
6
Blacks Law Dictionary (11th Edition, 2019)
7
Halliburton Offshore Service Inc. v. Vedanta Limited 2020 SCC OnLine Del 2068
8
Standard Retail Pvt. Ltd. v. M/s G.S. Global Corp & Ors,
1. After the CLAIMANT’s attempts to seek clarifications regarding the project’s status and
the measures taken by the RESPONDENT to fulfil the obligations, the CLAIMANT was
met with no substantive response. Instead, the interactions were concluded with
protracted arguments. Consequently, the CLAIMANT sent a legal notice to the
RESPONDENT on 17.12.2021 in light of the delays and repeated breaches of contract,
thereby invoking Clause 3.2.5 of the JDA. Through this legal notice, the CLAIMANT
called upon the RESPONDENT to remedy the breaches and begin the procurement
process for the construction within 90 of the notice. 10 The notice also demanded prompt
response within fifteen (15) days from the receipt of this communication on the plan of
action and the steps taken by the RESPONDENT to meet the requirements of clause
3.2.5 of the JDA. Subsequently, the CLAIMANT sent a rejoinder to reply notice dated
23.12.2021 on 30.01.2022 addressing the issues relating to the delay in the project.
Furthermore, the notice also sought precise details outlining the specific actions or
omissions considered as breach by the RESPONDENT. However, due to the inaction
and ineffective communication from the RESPONDENT, the CLAIMANT was
compelled to issue a notice of termination. 11
2. Clause 3.2.5 of the JDA states “In the event any of these timelines are not met, either
party may issue a notice of 90 days, to enable curing of the default. If after the period of
90 days the default remains, the party may issue a notice of termination upon which the
agreement will terminate”.12 Accordingly, the CLAIMANT has acted in consonance
with the provisions of the contract and at every stage of the contract has maintained
effective communication as required by the contract. Furthermore, there no procedural
9
Med-Arb Proposition, Clause 11.2, Annexure A
10
Med-Arb Proposition, Paragraph No. 7, Annexure C
11
Med-Arb Proposition Page 26
12
Med-Arb Proposition Page 10
A. Material Breach
1. A “material breach” of contract is a breach (a failure to perform the contract) that strikes so
deeply at the heart of the contract that it renders the agreement “irreparably broken” and
defeats the purpose of making the contract in the first place. The breach must go to the very
root of the agreement between the parties. If there is a material breach (sometimes referred
to as “total” breach), the other party can essentially end the agreement and claim damages
caused by the breach.
13
Bharat Petroleum Corpn. Ltd. & Anr. v. M/s. Jethanand Thakordas Karachiwala & Ors, 2000(1)BOMCR289
14
Christopher Clarke J laid down the following factors in assessing the materiality of breach
i. The nature of the contract and the specific obligations involved.
15
Dalkia Utilities services PLC v. Celtech International Limited , [2006] EWHC 63 (“Dalkia) at 99
Two principles which emerge from the rule of law laid down in cases relating to fundamental breach
of contract can be said to be16:
i. A fundamental breach is a breach of the most basic and essential term of the
contract, which goes to the root of the contract; and
ii. A breach of fundamental term enables the aggrieved party to repudiate the
contract and sue for damages17
5. In the present case, both principles have surfaced, thereby solidifying the establishment of a
breach.
6. The essence of the contractual agreement lay within the framework of a Joint Development
Agreement (JDA), outlining the obligations and responsibilities of the involved parties. The
crux of this contractual commitment mandated the completion of the designated project
within a stipulated timeframe of two years from the sanction of the plan. However, the
breach in this contractual relationship extended beyond mere material infractions,
encompassing the critical aspect of communication. The culpability of the party in breach
was not confined solely to the failure in delivering the project within the specified timeline
but also extended to the non-disclosure or inadequate communication to the CLAIMANT
regarding the delays that transpired. The breach of contract, therefore, assumed a dual nature
—both in terms of the tangible failure to meet the project completion deadline and the
intangible breach of the duty to communicate effectively and transparently about the delays
incurred. This compounded breach not only jeopardized the timely execution of the project
by the RESPONDENT but also undermined the fundamental principles of trust and
cooperation inherent in contractual agreements, emphasizing the complex nature of the
challenges faced in contractual relationships.
In the case of National Power PLC v. United Gas Company Ltd.18, Justice Colman conducted a
comprehensive analysis of the term "material breach." His interpretation elucidated that a material
breach referred to a substantial violation of the party's obligations, deemed serious enough to
warrant contract termination if the remedy for such a breach was not initiated within seven days.
The court, in its wisdom, established a crucial distinction between material and repudiatory
16
P.C. Markanda, The Law of Contract 1495 (5th ed. 2022).
17
Maharashtra State Electricity Distribution Co Ltd v. DSL Enterprises Ltd, 2010 (1) RAJ 281 (BOM)
18
National Power PLC v. United Gas Company Ltd, (1998) All ER (D) 321
B. Pertaining to temporal gap between the date of the JDA and the issuance of Govt
notification
1. The Joint Development Agreement (JDA) between the involved parties was formally
executed on 11th December 2019, following an extensive series of negotiations. However, a
significant development unfolded when the Govt of Tamil Nadu issued a notification on 21st
January 2021, announcing a substantial increase in fees for plan sanction applications across
all districts of Tamil Nadu. This fee hike ranged from 700% to 900%, marking a
considerable adjustment in the financial landscape for such applications. Intriguingly, the
temporal gap between the signing of the JDA on 11th December 2019 and the Govt's
notification on 21st January 2021 amounted to thirteen months and ten days. This timeline
appeared notably disproportionate, especially when considering the typical duration required
for plan sanctions. The elongated period raised questions about the reasonable expectations
and assumptions made during the negotiation and execution of the JDA, potentially
impacting the financial projections and feasibility of the agreed-upon terms within the
agreement.
2. The absence of any information or explanatory details from the RESPONDENT regarding
the significant delay during the elapsed time gap has emerged as a pivotal concern for the
CLAIMANT. Despite the CLAIMANT's anticipation and subsequent legal notice, has yet to
provide a justifiable explanation for the prolonged period in question. This lack of
communication and transparency has created an atmosphere of uncertainty, prompting the
claimant to take the decisive step of terminating the Joint Development Agreement (JDA).
RESPONDENT, in defense, asserts that the delay is attributed to an order from the Ministry
of Culture, Govt of India, which mandated the cessation of multi-storeyed building projects
in areas of cultural significance until the respective plans were re-worked, finalized, and
approved. However, the CLAIMANT contends that this notification would not have
adversely affected the project's development if the plan sanction had been obtained and
When there is a breach of contract, the innocent party is entitled to receive compensation from the
breaching party for any loss or damage caused to him thereby. In the present case, the claimant
further states the claimant has suffered breach on various grounds mentioned below that potentially
entitles the claimant to receive compensation from the respondent.
19
Med-Arb Proposition, Order, Clause 3, Page 4
1. After the execution of the JDA, it was the duty of the parties to maintain effective
communication with each other. While the RESPONDENT failed to adhere to the timelines
of the JDA, it was their duty to communicate effectively regarding the delay at each stage of
the Project. It was only upon the request of the CLAIMANT for the updates on the project in
September 2020, the CLAIMANT learned that plans were yet to be prepared. Essentially,
the RESPONDENT did not communicate about the status of the project to the CLAIMANT
right from the date of the execution of the Project. This failure to effectively communicate
shows the lackadaisical attitude of the RESPONDENT towards the Project. The
RESPONDENT
B. COMPENSATION
1. Sec. 73 The party who suffers from the breach of the contract cannot sit with folded hands in
the good expectation of recovering the compensation; it must take steps for remedying the
inconvenience caused by the non-performance of the contract. In this case there is a valid
and binding contract between the parties. It is provided that where a party sustains a loss on
account of breach of contract, he is entitled to receive from the party who has broken the
contract, compensation for such loss or damages.20
2. The theory of damages is such that they are a compensation and satisfaction for the injury
sustained, i.e. that the sum of money to be given for reparation of the damages suffered
should be as nearly as possible, be the sum which will put the injured party in the same
position as he would have been if he had not sustained the wrong for which he is getting
damages.21
In this case, the CLAIMANT has rightfully terminated the contract due to the inefficiencies on part
of the RESPONDENT, hence CLAIMANT pleads that the CLAIMANT is entitled to compensation.
20
Tarsem Singh v. Sukhminder Singh, 1998 (3) SCC 471
21
B.R. Herman & Mohatta v. Asiatic Steam Navigation Co. Ltd., AIR 1941 Sind 146