➡SUBPART A
GENERAL PROVISIONS.
➡SUBPART B
TYPE CERTIFICATES AND RESTRICTED TYPE- CERTIFICATES.
VALIDTY - Unlimited
TRANSFERABLE - Yes
➡SUBPART D
CHANGES TO TYPE-CERTIFICATES AND RESTRICTED TYPE CERTIFICATES.
➡SUBPART E
SUPPLEMENTAL TYPE-CERTIFICATES.
VALIDITY - Unlimited
TRANSFERABLE - Yes
➡SUBPART F
PRODUCTION WITHOUT PRODUCTION ORGANISATION APPROVAL.
VALIDITY - Not exceeding one year
TRANSFERABLE - N/A
➡SUBPART G
PRODUCTION ORGANISATION APPROVAL FOR PRODUCTS, PARTS AND
APPLIANCES.
VALIDITY - Limited duration not exceeding one year
TRANFERABLE - NO (except change in ownership)
➡SUBPART H
AIRWORTHINESS CERTIFICATES, RESTRICTED CERTIFICATES OF AIRWORTHINESS
AND EXPORT CERTIFICATES OF AIRWORTHINESS.
VALIDITY - As per F-III section-2(means validity of COA is mentioned in COA itself)
TRANFERABLE - Yes
➡SUBPART I
NOISE CERTIFICATES.
VALIDITY - Unlimited
TRANSFERABLE - Yes
➡SUBPART JA
DESIGN ORGANISATION APPROVAL- PRODUCTS OR CHANGES TO PRODUCTS.
VALIDITY - Limited period not exceeding 12 months
TRANFERABLE - NO(except change in ownership)
➡SUBPART JB
DESIGN ORGANISATION APPROVAL- PARTS & APPLIANCES.
VALIDITY - Maximum period of not exceeding 12 months
TRANFERABLE - NO(except change in ownership)
➡SUBPART K
PARTS AND APPLIANCES.
➡SUBPART M
REPAIRS.
➡SUBPART O
INDIAN TECHNICAL STANDARD ORDER AUTHORISATIONS.
VALIDITY - Unlimited
TRANSFERABLE - NO(except change in ownership)
➡SUBPART P
PERMIT TO FLY
VALIDITY - Maximum of 12 months
TRANSFERABLE - NO
CA FORMS
CA-1
Authorized Release Certificate
CA 15A
Airworthiness Review Certificate
CA 20
Permit to Fly
CA 23
Certificate of Airworthiness
CA 24
Restricted Certificate of Airworthiness
CA 25
Application for Certificate of Airworthiness
CA 30
Application for Type Certificate (TC)/ Restricted Type Certificate (RTC)
CA 31
Application for Approval of Major Change / Major Repair Design
CA 32
Application for Approval of Minor Change / Minor Repair Design
CA 33
Application for Approval of Supplemental Type Certificate (STC)
CA 34
Application for Indian Technical Standard Order Authorisation (ITSOA)
CA 35
Statement of Compliance for Indian Technical Standard Order Authorisation
CA 2006-1A
Application for Issue of Noise Certificate
CA 45A
Noise Certificate
CA 2006-1
Application for Issue of Noise Certificate
CA 45
Noise Certificate
CA 50
Application for production organisation approval under CAR 21, Subpart G
CA 51
Application for significant changes or variation of scope and terms of Production
Organization Approval under CAR 21, Subpart G
CA 52
Aircraft Statement of Conformity
CA 53
Certificate of Release to Service
CA 55
Production Organisation Approval Certificate
CA 60
Application for agreement of production under CAR 21 Subpart F
CA 65
Production without POA, Letter of Agreement
CA 80A
Application for Design Organisation Approval (DOA) / renewal of DOA under CAR 21
Subpart JA
CA 80B
Application for Design Organisation Approval (DOA) / renewal of DOA under CAR 21
Subpart JB
CA 81
Application for Alternative Procedures to Design Organisation Approval
CA 82A
Application for Significant Changes to Design Organisation Approval (DOA) under CAR 21
Subpart JA
CA 82B
Application for Design Organisation Approval (DOA) / renewal of DOA under CAR 21
Subpart JB
CA 22
Application for Permit to Fly
CA 21
Flight conditions for a Permit to Fly – Approval Form
FEES
➡ Applicants for Production Organisation Approval (POA) under CAR 21, Subpart G, will
be charged as follows for issue of POA:
● Fifty employees : Rs.25,000/-.
● More than fifty and upto two hundred employees: Rs.50,000/-.
● More than 200 employees : Rs.1,00,000/-.
The fees for renewal of POA shall be fifty percent of that of the new POA as above.
The fees for renewal of agreement shall be fifty percent of that of the new agreement
as above.
FINDINGS
SUBPART F
➡ A level one finding is-
● Any non-compliance with this Part which could lead to uncontrolled
non-compliances with applicable design data and which could affect the safety of
the aircraft.
● The holder of the letter of agreement shall demonstrate corrective action to the
satisfaction of DGCA within a period of 7 working days, extendable up to maximum
21 working days
➡ A level two finding is-
● Any non-compliance with this Part which is not classified as level one.
● The corrective action period granted by DGCA shall be within one month.
● In certain circumstances and subject to the nature of the finding, DGCA may extend
the period from one months to 45 days subject to a satisfactory corrective action
plan agreed by the DGCA.
➡ In case of level one or level two findings, the letter of agreement may be subject to a
partial or full limitation, suspension and revocation. The holder of the letter of agreement
shall provide confirmation of receipt of the notice of limitation, suspension or revocation of
the letter of agreement in a timely manner.
SUBPART G
➡ A level one finding is-
● Any non-compliance with this Part which could lead to uncontrolled
non-compliances with applicable design data and which could affect the safety of
the aircraft.
● Shall demonstrate corrective action to the satisfaction of DGCA within a period of 7
working days, extendable up to maximum 21 working days.
➡ In case of level one or level two findings, the production organization approval may be
subject to a partial or full limitation, suspension or revocation. The holder of the
production organization approval shall provide confirmation of receipt of the notice of
limitation, suspension or revocation of the production organization approval in a timely
manner.
SUBPART JA
➡ A level one finding is-
● Any non-compliance with this Part which could lead to uncontrolled
non-compliances with applicable requirements and which could lower the safety
standard and hazards seriously the safety of the aircraft.
● The holder of the design organization approval shall demonstrate/address the
corrective action immediately.
➡ Where no reasonable and justified reasons are assigned for non-implementation of the
corrective action plan within the time frame agreed upon with DGCA office, necessary
enforcement action will be initiated against the organization or the person responsible for
non-compliance as the case may be.
SUBPART JB
➡ A level one finding is-
● Any non-compliance with this Part which could lead to uncontrolled
non-compliances with applicable requirements and which could lowers the safety
standards and hazards seriously the safety of the aircraft.
● The holder of the design organization approval shall demonstrate/address the
corrective action immediately to the satisfaction of DGCA.