Professional Documents
Culture Documents
Achieves standardisation at component level while allowing design freedom at asset level; Requires a potentially deeper engagement with the supply chain; Superstructure including
Less material (with associated cost, carbon, transport etc.); May be perceived as a riskier solution since it is not traditional construction; cores;
Fewer components, enabling: May require traditional contractors to take on a different role (acting more as Envelope including façade
Manufactured Platforms
Economies of scale (with the benefit amplified by procuring across much larger portfolio an integrator). and roof;
than any one client has access to); MEP distribution including
High levels of optimisation and manufacturing levels of quality; ceiling cassettes and risers;
Distributed, resilient supply chain (from major manufacturers to local SME’s) Interior fit out including bed
Greater control of logistics, training, on site activities, etc. head services.
Standardised processes (in manufacture and assembly) enabling:
Diversification of the sector (new jobs and skills, potential to upskill non-construction
operatives);
Improved health + safety;
Increased productivity (and speed of assembly);
Reduced reliance on trades and workmanship (more consistent whole life performance);
Potential to automate (in design, manufacture + assembly).
Fewer operatives on site; Carbon intensive (duplication of horizontal vertical structure to achieve Plant + equipment skids;
High levels of site safety + productivity; stiffness needed for lifting and shifting, combined with material miles material Prefabricated plant rooms;
Ability to pre-test and commission. miles); Generators and sub
Vibration characteristics may not suit healthcare applications; stations;
Shifts labour off site but may still not address productivity i.e. includes
Volumetric
‘construction in a shed’;
Ideally requires a high degree of repeatability (inflexible design);
May preclude ease of later refurbishment / future flexibility;
Potential for long lead time;
Logistically inefficient unless modules are highly optimised;
May require specialist lifting equipment for heavy modules;
Requires large capital investment to set up manufacturing facility or may limit
supply chain to specialist providers;
Generally, over engineered (to be stiff enough for lifting + transport).
Reduced design time (standard elements re-used); Remains relatively labour intense with relatively low safety and productivity; Utilities trenches / duct
Components
Fewer documents + other information to manage; Adopted where the value proposition for some ‘higher order’ of MMC is not banks;
Easier submissions + approvals; justified (initially). Bedhead services;
Interfaces better resolved + pre-approved for regulatory / buildability / warranties etc; Prefabricated hygienic
Over time, some repeatable items may be productised or delivered using some other form of walling systems;
MMC. MEP ceiling cassettes;
Toilet pods
Must always be planned in as part of the overall MMC approach in terms of timing, interfaces Most unpredictable and labour intensive, least safe, precise and productive; Bulk excavation;
Trad.
etc. - can be planned to take place while other activities are taking place off site; Minimise these elements as far as possible. Cut + fill;
Consider where automation may be applied e.g. cut + fill levels using data enabled site Access roads
equipment.
What are
construction
platforms?
https://www.youtube.com/watch?v=hVQnE35CRvo
A mandated approach:
in the next two years the
government will set out a
requirement for platform
approaches to be
adopted for social
infrastructure
Case study
The Forge, London
https://vimeo.com/394805860
Links to key documents
Delivery Platforms for Government The Construction Playbook Platform Design Programme: Transforming Infrastructure
Assets: Creating a marketplace for Defining the Need Performance: Roadmap to 2030
manufactured spaces UK Government
2020 Construction Innovation Hub Infrastructure and Projects Authority
Bryden Wood 2020 2021
2017 (Second edition 2021) https://assets.publishing.service.gov.u
k/government/uploads/system/upload https://the- https://assets.publishing.service.gov.u
https://www.brydenwood.co.uk/filedo s/attachment_data/file/941536/The_C mtc.worldsecuresystems.com/Constru k/government/uploads/system/upload
wnload.php?a=17725-613f434f0f64c onstruction_Playbook.pdf ction%20Innovation%20Hub/Construc s/attachment_data/file/1016726/IPA_TI
tion%20Innovation%20Hub%20- P_Roadmap_to_2030_v6__1_.pdf
%20Defining%20the%20Need%20202
1.pdf
Thank you.
@Jaimie_BW
@BrydenWood
Bryden Wood
@brydenwoodtech
@brydenwoodtech