Professional Documents
Culture Documents
1. Normal process
a. The most common circumstances for project closure is a completed project and
then the main deliverable(s) and final report are submitted as was anticipated.
2. abnormal process
i. Premature process, The project is completed earlier than anticipated which may be due
to elimination of some activities so as to hit the deadline eg Christmas.
ii. Perpetual process Some projects never seem to end, and just drags on and are
characterized by adds on mentality which suggests a poorly conceived project scope.
Requires a review or new action plan to close this project - or to begin a new one.
iii. Failed process -Failed projects are easy to identify and easy for the project team to
institute closures
Closeout Approach
1. Termination by Integration –
It is the most common way of dealing with successful projects, and the most complex. All the
assets and resources used in a project are redistributed among the existing elements of the project
organization. The output of the project becomes a standard part of the operating systems and
procedures of the parent organization, or client. The major challenge associated with this
termination process is the ability of the project organization to blend technological differences
between the project and the project organization. When a project team is facing this type of
closeout they need to ensure that appropriate change management activities are being conducted
at the same time of performing the administrative closeout activities. In the transition from
project to integrated operation the following aspects must be considered:
3. Termination by Extinction- These are projects brought to an end (often before completion)
because they are unsuccessful, fail to meet end-user objectives, a government regulatory body
eliminated the need for the project deliverables are superseded by technical advances that make
the project obsolete, or because cost escalations destroy economic viability of the project or
product.