Professional Documents
Culture Documents
STATEMENT OF JURISDICTION
The CLAIMANT has approached this Arbitral Tribunal under Section 16 of the Arbitration
and Conciliation Act, 1996 read along with the Dispute Resolution Clause of the Joint
Development Agreement which reads as:
9.1 In the case of any dispute or differences or claims arising out of or in connection with or
relating to the Agreement or in the interpretation of any provisions of this Agreement, or the
breach, termination or in validity thereof (each, a “Dispute”), the Parties shall attempt to first
resolve such Dispute or claim through mutual discussions.
9.2 If such Dispute is not resolved through such mutual discussions within 15 (fifteen) days
after any Party has served a written notice on the other Parties requesting the commencement
of discussions, any Party may refer such Dispute to arbitration under the Arbitration and
Conciliation Act, 1996 (as amended from time to time, the “Arbitration Act”) in force at the
date of this Agreement.
9.3 The arbitration shall be conducted by 1 (one) arbitrator, to be jointly nominated by the
Developer and the Owner. The seat and venue of the arbitration shall be Tiruchirapalli.
The language of this arbitration shall be English.
9.4 Any arbitral awards made in accordance with this Agreement shall be conclusive and
binding on the Parties.
9.5 The arbitrator shall render a written and reasoned award in writing.
Page | 1
VI TNNLU NATIONAL MED_ARB COMPETITION 2024 NMAC TC 16
STATEMENT OF FACTS
On 11 December 2019, after a series of negotiations, the parties signed a Joint Development
Agreement (JDA) to construct residential and commercial complex. The complex was named
as Mithila (hereinafter referred as ‘Project’). The property when developed would have 18
commercial offices and 24 apartments consisting of 8 floors.
Soon after the JDA, the RESPONDENT began work on clearing the site and making the
detailed plans for the Project to obtain sanction. On 2 March 2020, the Government of India
responded to the COVID-19 situation by imposing a lockdown for the entire country. The
firm of M/s Batta Bhaduri was approached to design the Project, however, the partner in
charge of the Project Mr. Imroz Inderjeet passed away in August 2020, and the work was
further carried out by another partner Mr. P. Bhaduri. The effect of the pandemic, the
restrictions on accessing the office, and the death of Mr. Inderjeet had caused a cascading
effect on the work. It was only during September 2020 that the CLAIMANT requested the
RESPONDENT for updates on the Project and the RESPONDENT effectively communicated
that the pandemic and the lockdown had affected the progress of the Project. The
RESPONDENT also promised for a timely filing of the application for sanction of plans.
In response to the queries of the CLAIMANT, the RESPONDENT actively took measures to
cure the delay and prepared a detailed plans by October 2020. On 9 January 2021,
RESPONDENT filed the application for sanction of the plans for the Project. However, soon
after the application was filed, on 21 January 2021, the Government of Tamil Nadu issued a
notification increasing the fees for the applications for plan, this revision applied
retrospectively increasing the financial burden on the RESPONDENT from the earlier cost of
Rs. 15 lakhs to Rs. 135 lakhs. In February 2021, the RESPONDENT along with other
builders challenged the revision by a writ petition in the Madras High Court.
Subsequently, on 17 October 2021, the Ministry of History and Culture, Central Government
passed a ban order on the sanctions given for the construction of the multi-storeyed buildings
exceeding four storeys or beyond 45 feet in height in the ‘areas of cultural significance’ until
the next plan Master Plan for the development of those respective cities are finalised. The
ban order listed these areas, which included the Bayangammedu in Trichy.
Page | 2
VI TNNLU NATIONAL MED_ARB COMPETITION 2024 NMAC TC 16
Page | 3
VI TNNLU NATIONAL MED_ARB COMPETITION 2024 NMAC TC 16
ISSUES RAISED
Page | 4
VI TNNLU NATIONAL MED_ARB COMPETITION 2024 NMAC TC 16
SUMMARY OF ARGUMENTS
The RESPONDENT respectfully contends that the claimants' termination of the Joint
Development Agreement (JDA) lacks justification, as it allegedly disregards the underlying
reasons for the project delay. The RESPONDENT submits that the delay, which is cited as a
breach of contract by the claimants, was not a result of any misconduct on their part. The
respondents have established this in three folds:
Page | 5
VI TNNLU NATIONAL MED_ARB COMPETITION 2024 NMAC TC 16
Paragraph 3 of the Section 55 of the Indian Contract Act, 1872 provides that even where a
contract is voidable on account of the contractor's failure to perform his promise at the time
agreed (which is of the essence), the promisee cannot claim compensation for any loss
occasioned by the non-performance of the promise at the time agreed. Such a bar from
claiming compensation arises if the promisee accepts the performance of such promise at any
Page | 6
VI TNNLU NATIONAL MED_ARB COMPETITION 2024 NMAC TC 16
time other than the time previously agreed. It provides for an exception to this rule: at the
time of acceptance of performance, the promisee gives notice to the contractor of its intent to
claim compensation for the loss.
Where the parties have expressly provided that time is of the essence of the contract such a
provision will have to be read along with other conditions of the contract, and such other
conditions may, on construction of the contract, exclude the inference that the completion
of the work by a particular date was intended to be fundamental, for instance, if the
contract were to include clauses for extension of time in certain contingencies or for
payment of fine or penalty for every day or week the work undertaken remains unfinished
on the expiry of the time provided in the contract, such clause would be constructed as
rendering ineffective the express provision relating to the time being of the essence of the
contract.2
In this case, though the contract stipulates a time schedule for the development of the
Project, in substance it does not make time an essence of the contract. To substantiate, the
JDA provides for an automatic extension of one (1) month if the RESPONDENT fails to
obtain sanction for the plans within four (4) months from the date of the JDA 3. Essentially,
the intention of the parties can be deduced from the JDA and that the JDA has a
consideration towards reasonable delay that might be caused due to unprecedented
circumstances.
3. The Supreme Court in the case of Welspun Speciality Solution Limited v. ONGC 4, has
reiterated the principles basis which Courts are required to construe whether time is
the of essence of a contract. The Court held that a collective reading of the entire
contract and its surrounding circumstances is imperative to come to such a
2
Hind Construction Contractors v. State of Maharashtra, (1979) 2 SCC 70
3
Med-Arb Proposition Paragraph No. 06, cl. xi
4
(2022) 2 SCC 382
Page | 7
VI TNNLU NATIONAL MED_ARB COMPETITION 2024 NMAC TC 16
conclusion. Merely having an explicit clause in the contract may not be sufficient to
make time the essence of it. The Court also held that the availability of extension
procedures to fulfil obligations under a contract, is a good indicator that time is not of
the essence.
4. From the reading of the entire contract, as well as the surrounding circumstances, it
can be culled out that time is not of the essence. Essentially, the CLAIMANT was not
active in approaching the RESPONDENT for updates on the Project. It was only
during September 2020, i.e., after nearly 10 months of execution of the JDA 5, that the
CLAIMANT bothered to approach the RESPONDENT for updates on the Project.
However, the RESPONDENT was quick in responding to the needs of the
CLAIMANT and prioritised the completion of the Project. Soon after the meeting in
September 2020, the RESPONDENT prepared the detailed plans by October 2020,
validated the same by December 2020, and filed the application for sanction of the
plans for the Project.6
The RESPONDENT understands that there was a delay in the completion of the Project,
however, the RESPONDENT claims the delay was due to reasonable causes. The series of
events that hindered the completion of the Project were beyond the actual control of the
parties.
Force Majeure is wider than Vis Major since the former encompasses both natural and
artificial unforeseen events whereas the latter contemplates only natural unforeseen events. In
fact, Vis Major actually forms a sub-set of Force Majeure. Notwithstanding the differences
between the two, the effect of both the terms is to excuse non-performance of a party and
prevent a party from being liable for a breach of contract whilst also saving the non-
performing party from the consequences of something over which it has no control.
5
Med-Arb Proposition Paragraph No. 09
6
Med-Arb Proposition Paragraph No. 10
7
Black’s Law Dictionary (11th ed . 2019)
8
Black’s Law Dictionary (11th ed. 2019)
Page | 8
VI TNNLU NATIONAL MED_ARB COMPETITION 2024 NMAC TC 16
It is the case of the RESPONDENT that there was no mens rea on part of the
2. In this case, COVID-19 impacted the commencement of the Project largely effecting
the timelines of the Project. A lockdown was imposed on 2 March 2020 for a period
of sixty-eight (68) days, and this substantially effected the trajectory of the Project. 9 If
the event that is alleged to have prevented performance under the contract, such as an
epidemic, in this case, COVD-19, is specifically mentioned in the force majeure
clause and the event occurs, then the affected parties may be relieved from
performance. Even if such event is not specifically mentioned in the force majeure
clause, many force majeure clauses contain a catch-all phrase that is addition to the
specifically mentioned events. A catch-all phrase would have similar language
to“including, but not limited to” or “any cause/event outside the reasonable control
of the parties”. Clause 11 of the JDA specifies the force majeure clause and reads as
follows – “Neither party will be liable to the other for any failure or delay or for the
consequences of any failure or delay in performance of this Agreement is it is due to
any event beyond the reasonable control or contemplation of a Party to this
Agreement….”.10 This clause specifically includes a catch-all phrase which relieves
the party from performance of the contract as a result of COVID-19 pandemic.
3. Although Indian Courts have not directly ruled on whether an epidemic/pandemic like
COVID-19 is an ‘Act of God’, an argument to that effect can derive support from the
decision of the Supreme Court in The Divisional Controller, KSRTC v. Mahadeva
Shetty11, which holds that the expression ‘Act of God’ signifies the operation of
natural forces free from human intervention with the caveat that every unexpected
natural event does not operate as an excuse from liability if there is a reasonable
possibility of anticipating their happening. Similar judgements have also been passed
by the Madras HC in P.K. Kalasami Nadar v. Ponnuswami Mudaliar12
4. The effect of COVID-19 within the ambit of force majeure clause had a direct impact
on the non-performance. The judgement of the Orissa High Court in Sri Ananda
Chandra Behera v. Chairman, Orissa State Electricity Board13 provides some
9
Med-Arb Proposition Paragraph No. 07
10
Med-Arb Annexure A Paragraph No. 11
11
(2003) 7 SCC 197; See also Province of Madras v. I.S and G Machado AIR 1955 Mad 519
12
AIR 1962 Mad 44
13
1998 85 CLT 79
Page | 9
VI TNNLU NATIONAL MED_ARB COMPETITION 2024 NMAC TC 16
guidance on the causal link between the force majeure event and the resulting
situation by citing, with approval, the decision of the House of Lords in Greenock
Corporation v. Caledonian Rly Co.,14 where it was held that “….An accident maybe
an act of God if it has resulted directly from natural causes without human
intervention. It is true that in most cases human and natural agency co-operate to
produce the result, but the immediate and direct cause is alone to be looked at in
determining whether the act is that of God or man….”.
5. On 2 March 2020, a lockdown was imposed by the authorities as a result of which
there were consequential restrictions including the quarantines, travel restrictions and
other limitations imposed by the government. Consequent to these restrictions, M/s.
Bhatta Bhaduri, the architectural firm engaged by the RESPONDENT for the detailed
plans had been irregular in their work on account of the pandemic. Furthermore, the
partner in charge of the Project Mr. Imroz Inderjeet passed away in August 2020 15,
and the work was handled by the senior partner Mr. P. Bhaduri. The effect of the
pandemic, the restrictions on accessing the office, and the death of Mr. Inderjeet had
caused a cascading effect on the work. Thus, there was a direct causal link between
the pandemic and the non-performance of the contract.
6. Clause 11 of the JDA provides for force majeure clause and clause 11.1 of the JDA
defines various force majeure events. The clause includes the term “change in policies
concerning the project”. The RESPONDENT filed an application for sanction of the
plan on 9 January 2021, however, soon after filing the same, on 21 January 2021, the
Government of Tamil Nadu issued a notification increasing the fees for the
applications for plan sanctions by 700 to 900% for all districts in Tamil Nadu and the
revision applied retrospectively, translating to a hike in the cost of the Project from
Rs. 15 lakhs to Rs. 135 lakhs. 16 This exacerbated the costs towards the Project and the
RESPONDENT was severely affected by the financial implications of such an order.
As a result, the RESPONDENT challenged the revision by writ petition in the Madras
High Court in February 2021.17 According to clause 11.1 this event essentially
satisfies the condition of “change in policy concerning the Project”.
14
1917 AC 556
15
Med-Arb Proposition Paragraph No. 09
16
Med-Proposition Paragraph No. 12
17
Med-Proposition Paragraph No. 13
Page | 10
VI TNNLU NATIONAL MED_ARB COMPETITION 2024 NMAC TC 16
Page | 11
VI TNNLU NATIONAL MED_ARB COMPETITION 2024 NMAC TC 16
four storeys or beyond 45 feet in height in the ‘areas of cultural significance’ until the
next plan Master Plan for the development of those respective cities are finalised. The
ban order listed these areas, which included the Bayangammedu in Trichy. This
notification aggravated the situation of the RESPONDENT. The order read – “With a
view to preserve and beautify the many locations in our country where historical
buildings are found, the Government has decided to stop construction of multi-
storeyed buildings in Areas of Cultural Significance with immediate effect till the
Master Plan for the cities in which the Areas of Cultural Significance are located
have been finalised. No new sanction for such construction should be issued
hereinafter.” This order put a temporary restriction on the sanction of plans for the
Project, whereby, the RESPONDENT was left with fewer options to pursue. These
circumstances were beyond the control of the parties, however, even after these
events, the RESPONDENT made diligent efforts amid unprecedented circumstances
to ensure the completion of the Project. These efforts were expressly communicated
and relayed to the CLAIMANT during the meeting on 15.02.2021. 19 The sole reason
for the forced delays, and not breaches, in the Project was due to the fact that the land
is situated in an area of cultural significance and was covered by the Ban Order.
3. Despite these orders, had the RESPONDENT pursued the Project further, then it
would be termed unlawful according to these orders leading to regulatory actions
against the parties. In order to avoid these regulatory issues, the RESPONDENT
considered it fit to take legal recourse to challenge these orders and obtain favourable
orders to commence the construction of the Project.
4. During all these events, the CLAIMANT was made aware of the situation and the
consequences of pursuing the Project despite these regulatory restrictions. However,
the CLAIMANT went on to issue a legal notice to the RESPONDENT, alleging a
breach of contract and unreasonably terminated the contract on 20 March 2022.20
5. As a result, The RESPONDENT pleads that the CLAIMANT terminated the contract
unreasonably without considering the various issues that the RESPONDENT faced
before such termination and that the RESPONDENT made highest possible efforts to
remedy the delay caused by these unprecedented circumstances, but the CLAIMANT
failed to recognise these and hence, terminated the contract unreasonably.
19
Med-Arb Annexure D Paragraph No. 05
20
Annexure F, Paragraph No. 03
Page | 12
VI TNNLU NATIONAL MED_ARB COMPETITION 2024 NMAC TC 16
Thus, the RESPONDENT pleads that there has not been a breach of contract due to delay in
performance since the delay was reasonable due to the aforementioned reasons.
The notifications and orders issued by the government significantly impacted the timely
completion of the Project, which would have otherwise seen the approval of the project plan
within the prescribed time as outlined in the Joint Development Agreement (JDA). The
unforeseen delays extended beyond the initial expectations as the RESPONDENT had to
navigate through government directives. Moreover, the initiation of legal proceedings,
including the filing of a writ petition, further contributed to the pause in Project’s progress.
This pause was a strategic measure undertaken to prevent additional scepticism and
uncertainties, considering that the ultimate outcome was contingent upon the decision of the
court. In light of these external factors and legal proceedings, it is imperative to acknowledge
the contextual challenges that have influenced the Project timeline, potentially impacting the
parties' ability to adhere strictly to the initially stipulated schedule outlined in the JDA.
A. Material Breach
1. In contract law, a "material" breach of contract is a breach (a failure to perform the
contract) that strikes so deeply at the heart of the contract that it renders the agreement
"irreparably broken" and defeats the purpose of making the contract in the first place.
The breach must go to the very root of the agreement between the parties. Only if
there is a material breach (sometimes referred to as a "total" breach), the other party
can simply end the agreement and go to court to try to collect damages caused by the
breach.21
In this case, the assertion that the contract has rendered the agreement "irreparably
broken" is effectively disproven when considering the circumstances surrounding the
delays in Project completion. The delays, which might otherwise be construed as
causing irreparable harm, are substantiated as reasonable and beyond the control of
the contracting parties. Firstly, the unprecedented and unforeseeable impact of the
COVID-19 pandemic resulted in a state-mandated lockdown, disrupting regular
operations and timelines. Secondly, the issuance of a notification by the Tamil Nadu
21
Page | 13
VI TNNLU NATIONAL MED_ARB COMPETITION 2024 NMAC TC 16
2. Lastly, a Ban Order from the Ministry of Culture, Government of India, further
impeded progress. These external factors collectively contribute to the justification of
the delays, establishing them as events beyond the parties' control. The purpose and
viability of the agreement are still intact, as the delays are clearly attributed to
extraordinary circumstances rather than any wilful or negligent actions on the part of
the contracting parties, thereby mitigating the claim of irreparable harm to the
contract.
3. In the case of T Amuthavalli v. Secretary to the Government and others 22, the Madras
High Court rendered a significant decision by acknowledging and considering the
impact of the COVID-19 pandemic on the period of delay. The court held that the
duration of the delay in the proceedings appeared to be reasonable, considering the
extraordinary circumstances imposed by the global health crisis. The unprecedented
challenges posed by the pandemic, such as lockdowns, disruptions in court operations,
and the overall strain on the judicial system, were deemed valid reasons contributing
to the extended time frame. By recognizing the exceptional nature of the
circumstances brought about by COVID-19, the Madras High Court demonstrated a
pragmatic approach in its decision, ensuring fairness and understanding in light of the
challenges posed by the pandemic on legal processes.
4. The alleged breach in this case has failed to address the fundamental aspects of the
issue at its core, and the termination of the Joint Development Agreement (JDA) is
deemed entirely wrongful based on the aforementioned reasons. Specifically, the
impact of three significant conditions—namely, the COVID-19 pandemic, the
issuance of notifications/orders by the Tamil Nadu authorities, and the imposition of a
ban order—have substantially hindered the progress of the contractual procedure. The
respondent was compelled to halt the proceedings due to these external factors beyond
their control. Notably, the claimant is cognizant of the fact that a writ petition filed in
the Madras High Court further contributed to delays, as the respondent’s pursued
relief through the writ and argued for a reduction in fees for plan sanction. In light of
these circumstances, the RESPONDENT pleads that the termination of the JDA is
unjust and unreasonable.
22
(2021) SCC OnLine Mad 2315
Page | 14
VI TNNLU NATIONAL MED_ARB COMPETITION 2024 NMAC TC 16
Government Notifications/Orders:
Page | 15
VI TNNLU NATIONAL MED_ARB COMPETITION 2024 NMAC TC 16
8. The respondents in response to the allegations replied that the delay in the sanction
was clearly due to the revision in the fees which:
i. The notification announcing a staggering increase in the plan sanction fee,
ranging from 700% to 900% above the customary rates, has engendered
significant disruption and turmoil within the offices of the Trichy Municipal
Corporation. This abrupt and exorbitant rise in fees has had profound
implications, causing a substantial upheaval in the routine operations of the
municipal offices. The sudden financial burden imposed by such a drastic fee
hike has created an environment of uncertainty and complexity, leading to an
immense churn in the administrative processes. The increased fees have not
only strained the financial resources of applicants but have also resulted in a
considerable delay in the approval and processing of plans. The Trichy
Municipal Corporation, grappling with these unforeseen challenges, is
navigating through a period of heightened difficulty and disruption, attempting
to adapt to the unprecedented circumstances brought about by the substantial
increase in plan sanction fees.
ii. The meticulous planning undertaken over months to establish a comprehensive
and viable financial framework for the Project now faces upheaval due to the
unforeseen hike in fees. This sudden and substantial deviation from the
anticipated costs has created a ripple effect, impacting the financial projections
and overall feasibility of the project. RESPONDENT, in charge of overseeing
the Project, is actively engaged in efforts to resolve these newfound issues in
the costing structure. The unexpected financial burden resulting from the
escalated plan sanction fees requires a reassessment of the Project's financial
landscape and poses a considerable hurdle in adhering to the initially outlined
business plan. RESPONDENT is currently navigating through the complexities
arising from these unforeseen challenges, seeking solutions to ensure the
Project's financial viability and successful realization despite the unexpected
hurdles introduced by the increased plan sanction fees.
The onerous financial burden arising from unforeseen circumstances, such as the
substantial increase in plan sanction fees, was shouldered entirely by the respondents,
demonstrating their resilience in the face of adversity.
Ban Order
Page | 16
VI TNNLU NATIONAL MED_ARB COMPETITION 2024 NMAC TC 16
9. The state of Tamil Nadu was already grappling with considerable confusion
surrounding the fees for plan sanction, a situation the respondents adeptly managed.
However, another order, issued subsequently, posed a more substantial disruption to
the Project. Recognizing the importance of preserving the nation's history and culture,
the Ministry of History and Culture, Central Government, issued an office
memorandum on 17 October 2021. This directive specified that, until the next Master
Plan for the development of respective cities is finalized, no new sanctions would be
granted for the construction of multi-storeyed buildings exceeding four storeys or
beyond 45 feet in height in Areas of Cultural Significance. The Bayangammedu area
in Trichy, included in the Areas of Cultural Significance, was affected by this Ban
Order, causing a complete standstill in all project-related activities.
10. The order clarified that a 'multi-storeyed' building is one exceeding 45 feet or
extending beyond four storeys, requiring lift services. In response to this significant
hurdle, the respondents, demonstrating flexibility and commitment, expresses their
willingness to fulfil contractual obligations through novation or alteration of the Joint
Development Agreement (JDA) to construct half of the project, adhering to the
permissible limits outlined in the Ban Order. Despite these unforeseen challenges, the
respondents remained proactive, actively exploring measures to commence the Project
within the constraints imposed by the regulatory environment.
11. The termination of the contract is asserted to be unreasonable based on two key
issues, namely the invocation of Force Majeure and the absence of any material
breach. Firstly, the application of Force Majeure is emphasized as a valid ground for
the purported termination. It is contended that unforeseen and uncontrollable
circumstances, such as government notifications and orders, fall under the purview of
Force Majeure events. These events, beyond the control of the respondent, have
significantly impeded the smooth progress of the Project. Secondly, the assertion is
made that no material breach has occurred on the part of the respondents. The
circumstances leading to the termination were allegedly beyond their control, and they
had actively sought to navigate challenges imposed by external factors, including
government directives. By highlighting these factors, the argument aims to establish
that the termination was unjust and unreasonable, given the context of Force Majeure
events and the absence of any substantial breach on the part of the respondents, hence
it is pleaded to revoke the termination.
III. WHETHER THE CLAIMANT IS ENTITLED TO COMPENSATION
Page | 17
VI TNNLU NATIONAL MED_ARB COMPETITION 2024 NMAC TC 16
1. It is pertinent to note that clause 11.1 of the JDA dealing with force majeure clause
states that neither party will be liable to the other for any failure or delay if it is due to
an event beyond the reasonable control or contemplation of a party to this agreement
including, the acts of god. The respondent had no control over the drastic spread of
the pandemic and consequences that followed. In M/s Halliburton Offshore Services
Inc v. Vedanta Ltd & Anr23, the petitioner Halliburton was obliged under a contract to
develop three blocks in Rajasthan for Vedanta Ltd. Due to the lockdown, Halliburton
was not in a position to complete the work in the given time frame. Thus, the
company decided to invoke the force majeure clause, but Vedanta Ltd objected to this.
As a result, Vedanta threatened to terminate the contract, forcing Halliburton Offshore
Services Inc to move to the Delhi High Court. The Delhi High Court tended towards
granting an ad-interim injunction to the invocation of bank guarantees given by
Halliburton to Vedanta. The court held that the lockdown caused due to COVID-19
was prima facie a force majeure event.
23
(2020) SCC OnLine Del 542
Page | 18
VI TNNLU NATIONAL MED_ARB COMPETITION 2024 NMAC TC 16
24
Med-Arb Proposition, Paragraph No. 12
25
Med-Arb Proposition, Paragraph No. 15
Page | 19
VI TNNLU NATIONAL MED_ARB COMPETITION 2024 NMAC TC 16
Project as it had been planned, unlawful. Hence the respondent pleads that the drastic
spread of COVID-19, imposition of restrictions in the COVID-19 affected areas,
lockdown, unexpected and sudden revision in fees for plan sanctions and lastly the
Ban Order all of which get covered under the clause 11.1 of the JDA and can be stated
as Force Majeure. Therefore, the respondent under the umbrella of the clause 11.1
pleads that any claim, compensation of the claimant should be rejected.
PRAYER
Wherefore in view of the above, the RESPONDENT respectfully prays the Tribunal to
find that:
Page | 20
VI TNNLU NATIONAL MED_ARB COMPETITION 2024 NMAC TC 16
The RESPONDENT reserves the right to amend its request for relief as may be required.
Page | 21