EXPLORING LIABILITY of damages arising out of the CONSEQUENTIAL LOSS
CAPS AND LIMITATIONS, performance of contracts they EXCLUSIONS IN PROCESS enter into—particularly in EXCLUSIONS OF ENGINEERING CONTRACTS significant process engineering CATEGORIES OF LOSS In a number of recent cases, a and mining contracts where party who has contracted for the AND MANAGEMENT OF exposure to unlimited damages design and installation of plant PROCESS RISKS will be often unacceptable. and equipment, has sought to If the starting point is that Patrick Mead, Partner take the benefit of exclusion a contractor will not accept clauses in their contracts in Carter Newell Lawyers, liability for unlimited damages, defence to claims arising out of Brisbane a number of different outcomes the performance of that plant or can be achieved by adoption equipment. of appropriate exclusions, limitations or caps. Accordingly Often these exclusions of liability it is not uncommon to now see seek to exclude any entitlement clauses drafted to ensure that by the principal to pursue liability for all damages is capped recovery in relation to what has at a percentage of the contract been generically referred to EXCLUSION CLAUSES AND sum or an annual amount in as ‘indirect’ or ‘consequential’ LIABILITY CAPS the case of a mining or services loss. There have been some There is a distinction between contract. recent decisions by the English an exclusion clause, the effect of and Australian courts which which is to either absolve a party Other than in respect of a are likely to impact upon the for the consequences of a breach provision for liquidated damages interpretation of these clauses of duty or to define substantively (which itself is likely to be capped and suggest avenues of recovery, the limit of the duty by negating at a percentage of the contract notwithstanding their inclusion in obligations that the law would sum) the contractor may insist contracts of this nature. otherwise impose,1 and a liability upon a complete exclusion for damages for loss of profit, loss In British Sugar PLC v NEI cap, the purpose of which is of use and business interruption, Power Product Ltd & Anor,3 to limit a party’s exposure up or alternatively seek to cap any the defendant faced a claim to a predetermined amount or such exposure to the limit of any for increased production costs percentage of contract value. applicable insurance. and loss of profits due to the Often, these legal mechanisms breakdown of power supply operate in tandem with provisions Process engineering and process caused by allegedly poorly in relation to liquidated damages design risks are of real concern designed and badly installed (which are not considered to be given the potential for loss to electrical equipment. The court exclusory, operating in theory the client over life of plant, from held that the increased production for the benefit of both parties) shortfalls in production in the costs and loss of profits flowed and insurance and indemnity event that the plant is unable to directly and naturally from the provisions within a contract, to meet prescribed performance alleged breach and were therefore create a finely balanced risk criteria. Accordingly a contractor not consequential. regime. will commonly seek to cap its total liability for a shortfall in Similarly, in Deepak Fertilisers Such clauses are construed production to the lesser of a & Petro Chemical Corporation v ‘… according to their natural percentage of the contract value Davy McKee (London) Ltd & ICI and ordinary meaning, read in or a fixed dollar amount. Chemicals and Polymers Ltd,4 the light of the contract as a whole, English Court of Appeal decided thereby giving due weight to Often the principal will insist that fixed costs and overheads the context in which the clause upon exemptions of particular claimed were not indirect or appears, including the nature matters or losses when faced consequential—they were the and object of the contract, and with a blanket exclusion. If the direct and natural result of the where appropriate, construing contractor agrees to this, it will destruction of the plant and had the clause contra proferentum in often only do so, on the basis of a not been excluded elsewhere in case of ambiguity…’ 2 further cap on liability in respect the clause. of the matters not subject to the Many contractors rely on such blanket exclusion. In BHP Petroleum Limited v clauses to manage their risk British Steel & Dalmine,5 the
44 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #116 SEPTEMBER/OCTOBER 2007
claim against British Steel production or business were The most recent leading alleged that losses had been excluded. If this submission Australian authority is the case caused because the inability had been accepted, the effect of of GEC Marconi Systems Pty Ltd to use the pipeline supplied the exclusion would have been v BAP Information Technology until it was replaced had severely limited because the Pty Ltd,8 in which losses to a third serious consequences for the losses of profits, production or party such as the cost benefit of a way in which fuel operations business were likely, in the light head contract (lost future profits) were carried out, requiring of previous authorities, to have and increased project costs significant expenditure on been considered direct losses, were considered by Finn J of the installing additional facilities and not merely consequential, and Federal Court to fall within the modifying existing equipment or therefore not excluded. first limb of Hadley v Baxendale,9 necessitating flaring of gas which and thus were recoverable as It has been suggested (Rowe & would otherwise have been re directly resulting from the breach. Maw ‘Consequential and Indirect injected. It was also claimed that Loss’) that the judge adopted a As a result of the characterisation the rate of extraction of both oil somewhat charitable approach to of damages in this manner and gas was lower that it would British Steel by deciding that the and the interpretation and otherwise have been—leading best solution was to construe the efficacy of a number of so called to the postponement of the clause as though it read: ‘consequential loss’ exclusions, exploration of the field’s potential. a number of contractors are now [F]of loss of production, loss British Steel relied upon an no longer drawing a distinction of profits, loss of business or exclusion clause in the following between ‘direct loss’ and ‘indirect indirect losses or consequential terms: or consequential loss’ but damages of any other kind. are rather seeking to exclude Neither the supplier nor the These cases accordingly suggest specific types of damages. purchaser shall bear any that fixed costs and overheads, liability to the other … for loss increased production costs, and of production, loss of profits, REFERENCES sometimes even ‘loss of profits’ loss of business or any other claims will not be excluded by 1. Thomas National Transport indirect losses or consequential consequential loss exclusions (Melbourne) Pty Ltd v May & damages arising during and/or commonly found in a number Baker (Australia) Pty Ltd (1966) as a result of the performance or of the standard form contracts 115 CLR 353 non–performance of this contract and upon which contractors have regardless of the clause thereof 2. Darlington Futures Ltd v Delco traditionally relied. This would but not limited to the negligence Australia Pty Ltd (1986) 161 CLR seem to be borne out by some of the parties seeking to rely on 500 further recent decisions (albeit in this provision. a slightly different context). 3. (1997) 87 BLR 42 The court found that most of the In Hotel Services Ltd v Aitton 4. (1991) 1 Lloyd’s Rep 387 losses claimed were in fact a International Hotels (UK) Ltd,6 loss of production and therefore 5. (1999) 2 Lloyd’s Rep 583 loss of profits resulting from covered by the express wording 6. [2000] BLC 235 defective products (and their of the exclusion. However, it went removal and replacement) was 7. [2000] BLR 218 on to consider what the position held to be direct and natural would be if it was wrong in this 8. [2003] FCA consequence of the breach of conclusion and became necessary contract. 9. [1854] 9 Exch 341 to decide whether the losses were indirect or consequential. The case of Pegler Ltd v Wang (UK) Ltd (No 1),7 seemed to widen Patrick Mead’s article was As drafted, the exclusion clause previously published in the scope of losses claimable appeared to imply that ‘the loss Carter Newell’s Constructive as ‘direct and natural losses’. of production’, ‘loss of profits’ Notes—April 2007. Loss of sales, loss of opportunity and ‘loss of business’ were Reprinted with permission. to increase margins, loss of examples of indirect losses or opportunity to make staff cost consequential damages. This savings and wasted management led to the argument on behalf time were all considered to flow of BHP that only indirect and directly from the breach and were consequential losses of profits, recoverable.
AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #116 SEPTEMBER/OCTOBER 2007 45