You are on page 1of 2

RISK

EXPLORING LIABILITY of damages arising out of the CONSEQUENTIAL LOSS


CAPS AND LIMITATIONS, performance of contracts they EXCLUSIONS IN PROCESS
enter into—particularly in
EXCLUSIONS OF ENGINEERING CONTRACTS
significant process engineering
CATEGORIES OF LOSS In a number of recent cases, a
and mining contracts where
party who has contracted for the
AND MANAGEMENT OF exposure to unlimited damages
design and installation of plant
PROCESS RISKS will be often unacceptable.
and equipment, has sought to
If the starting point is that
Patrick Mead, Partner take the benefit of exclusion
a contractor will not accept
clauses in their contracts in
Carter Newell Lawyers, liability for unlimited damages,
defence to claims arising out of
Brisbane a number of different outcomes
the performance of that plant or
can be achieved by adoption
equipment.
of appropriate exclusions,
limitations or caps. Accordingly Often these exclusions of liability
it is not uncommon to now see seek to exclude any entitlement
clauses drafted to ensure that by the principal to pursue
liability for all damages is capped recovery in relation to what has
at a percentage of the contract been generically referred to
EXCLUSION CLAUSES AND sum or an annual amount in as ‘indirect’ or ‘consequential’
LIABILITY CAPS the case of a mining or services loss. There have been some
There is a distinction between contract. recent decisions by the English
an exclusion clause, the effect of and Australian courts which
which is to either absolve a party Other than in respect of a
are likely to impact upon the
for the consequences of a breach provision for liquidated damages
interpretation of these clauses
of duty or to define substantively (which itself is likely to be capped
and suggest avenues of recovery,
the limit of the duty by negating at a percentage of the contract
notwithstanding their inclusion in
obligations that the law would sum) the contractor may insist
contracts of this nature.
otherwise impose,1 and a liability upon a complete exclusion for
damages for loss of profit, loss In British Sugar PLC v NEI
cap, the purpose of which is
of use and business interruption, Power Product Ltd & Anor,3
to limit a party’s exposure up
or alternatively seek to cap any the defendant faced a claim
to a predetermined amount or
such exposure to the limit of any for increased production costs
percentage of contract value.
applicable insurance. and loss of profits due to the
Often, these legal mechanisms breakdown of power supply
operate in tandem with provisions Process engineering and process
caused by allegedly poorly
in relation to liquidated damages design risks are of real concern
designed and badly installed
(which are not considered to be given the potential for loss to
electrical equipment. The court
exclusory, operating in theory the client over life of plant, from
held that the increased production
for the benefit of both parties) shortfalls in production in the
costs and loss of profits flowed
and insurance and indemnity event that the plant is unable to
directly and naturally from the
provisions within a contract, to meet prescribed performance
alleged breach and were therefore
create a finely balanced risk criteria. Accordingly a contractor
not consequential.
regime. will commonly seek to cap its
total liability for a shortfall in Similarly, in Deepak Fertilisers
Such clauses are construed production to the lesser of a & Petro Chemical Corporation v
‘… according to their natural percentage of the contract value Davy McKee (London) Ltd & ICI
and ordinary meaning, read in or a fixed dollar amount. Chemicals and Polymers Ltd,4 the
light of the contract as a whole, English Court of Appeal decided
thereby giving due weight to Often the principal will insist
that fixed costs and overheads
the context in which the clause upon exemptions of particular
claimed were not indirect or
appears, including the nature matters or losses when faced
consequential—they were the
and object of the contract, and with a blanket exclusion. If the
direct and natural result of the
where appropriate, construing contractor agrees to this, it will
destruction of the plant and had
the clause contra proferentum in often only do so, on the basis of a
not been excluded elsewhere in
case of ambiguity…’ 2 further cap on liability in respect
the clause.
of the matters not subject to the
Many contractors rely on such blanket exclusion. In BHP Petroleum Limited v
clauses to manage their risk British Steel & Dalmine,5 the

44 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #116 SEPTEMBER/OCTOBER 2007


claim against British Steel production or business were The most recent leading
alleged that losses had been excluded. If this submission Australian authority is the case
caused because the inability had been accepted, the effect of of GEC Marconi Systems Pty Ltd
to use the pipeline supplied the exclusion would have been v BAP Information Technology
until it was replaced had severely limited because the Pty Ltd,8 in which losses to a third
serious consequences for the losses of profits, production or party such as the cost benefit of a
way in which fuel operations business were likely, in the light head contract (lost future profits)
were carried out, requiring of previous authorities, to have and increased project costs
significant expenditure on been considered direct losses, were considered by Finn J of the
installing additional facilities and not merely consequential, and Federal Court to fall within the
modifying existing equipment or therefore not excluded. first limb of Hadley v Baxendale,9
necessitating flaring of gas which and thus were recoverable as
It has been suggested (Rowe &
would otherwise have been re directly resulting from the breach.
Maw ‘Consequential and Indirect
injected. It was also claimed that Loss’) that the judge adopted a As a result of the characterisation
the rate of extraction of both oil somewhat charitable approach to of damages in this manner
and gas was lower that it would British Steel by deciding that the and the interpretation and
otherwise have been—leading best solution was to construe the efficacy of a number of so called
to the postponement of the clause as though it read: ‘consequential loss’ exclusions,
exploration of the field’s potential. a number of contractors are now
[F]of loss of production, loss
British Steel relied upon an no longer drawing a distinction
of profits, loss of business or
exclusion clause in the following between ‘direct loss’ and ‘indirect
indirect losses or consequential
terms: or consequential loss’ but
damages of any other kind.
are rather seeking to exclude
Neither the supplier nor the These cases accordingly suggest specific types of damages.
purchaser shall bear any that fixed costs and overheads,
liability to the other … for loss increased production costs, and
of production, loss of profits, REFERENCES
sometimes even ‘loss of profits’
loss of business or any other claims will not be excluded by 1. Thomas National Transport
indirect losses or consequential consequential loss exclusions (Melbourne) Pty Ltd v May &
damages arising during and/or commonly found in a number Baker (Australia) Pty Ltd (1966)
as a result of the performance or of the standard form contracts 115 CLR 353
non–performance of this contract and upon which contractors have
regardless of the clause thereof 2. Darlington Futures Ltd v Delco
traditionally relied. This would
but not limited to the negligence Australia Pty Ltd (1986) 161 CLR
seem to be borne out by some
of the parties seeking to rely on 500
further recent decisions (albeit in
this provision. a slightly different context). 3. (1997) 87 BLR 42
The court found that most of the In Hotel Services Ltd v Aitton 4. (1991) 1 Lloyd’s Rep 387
losses claimed were in fact a International Hotels (UK) Ltd,6
loss of production and therefore 5. (1999) 2 Lloyd’s Rep 583
loss of profits resulting from
covered by the express wording 6. [2000] BLC 235
defective products (and their
of the exclusion. However, it went removal and replacement) was 7. [2000] BLR 218
on to consider what the position held to be direct and natural
would be if it was wrong in this 8. [2003] FCA
consequence of the breach of
conclusion and became necessary contract. 9. [1854] 9 Exch 341
to decide whether the losses were
indirect or consequential. The case of Pegler Ltd v Wang
(UK) Ltd (No 1),7 seemed to widen Patrick Mead’s article was
As drafted, the exclusion clause previously published in
the scope of losses claimable
appeared to imply that ‘the loss Carter Newell’s Constructive
as ‘direct and natural losses’.
of production’, ‘loss of profits’ Notes—April 2007.
Loss of sales, loss of opportunity
and ‘loss of business’ were Reprinted with permission.
to increase margins, loss of
examples of indirect losses or opportunity to make staff cost
consequential damages. This savings and wasted management
led to the argument on behalf time were all considered to flow
of BHP that only indirect and directly from the breach and were
consequential losses of profits, recoverable.

AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #116 SEPTEMBER/OCTOBER 2007 45

You might also like