You are on page 1of 5

.

1- ~~
~
. _~~~~~-----
~~~~~ ---
SCHEDULE OF RATES Differences between 'as built' predicted ... the nature of the work
CONTRACTS-THE quantities and those stated in bills is certain, but its extent is not ...
or other contractual estimates and variations in the levels and
ABILITY TO CLAIM FOR unit price (measured or schedule of dimensions of the work are integral
VARIATIONS FOR rates) contracts, frequently come to a schedule of rates contract ...
CHANGES IN QUANTITIES about without any alteration in the the contractor was bound to carry
work being called for by the out the works which it had agreed to
Patrick Mead
architect, engineer or owner, either carry out. The extent of the work
Carter Newell because of errors in taking off would depend on levels and
quantities from the drawings in the dimensions, but the works would
first place or because of the not change.
inherently unpredictable or
(It should by noted that the judges
provisional extent of the particular
in this case were influenced by the
work in question.
reference in the tender documents
The difference between a lump sum to the following:
contract and measured contract in
The levels and dimensions given on
this situation lies in the fact that, in
these drawings and/or in the
the former case, both parties carry
specification are intended to give
the risk of both of these types of
only a general indication of the
differences and the price will not
works. Construction drawings and/
alter, whereas in the latter the
or details issued pursuant to the
contract sum will be adjusted, up or
contract may give levels and/or
down, to take account of the
dimensions differing substantially
differences.
from those given in the
A question therefore often arises in undermentioned drawings and/or
a schedule of rates contract, specification. It is emphasised that
whether an increase or decrease in the contract covers the carrying out
the quantities of work constitutes a of the works shown on the
variation. construction drawings and details.)

In the leading Australian case on In a more recent decision-in the


the subject-Arcos Industries Pty matter of an application by
Ltd v The Electricity Commission of Queensland Electricity Commission
NewSouth Wales (1973) 2 NSWLR before Dowsett J-30 August 1991,
18b-the court held that the word His Honour determined a summons
'omissions' in the variation clause forthe construction of a schedule of
did not extend to a difference rates contract. In that case, His
between estimated and actual Honour stated:
quantities, arising from a difference
There is a fundamental difference
between the dimensions and levels
between limits ofaccuracy and
of the work as shown on the
limits ofpermissible variations.
drawings accompanying the tender
Limits ofaccuracy concern
and the dimensions and levels of
inaccuracies in estimates of the
the work shown on the actual
amount of work involved in a
construction drawings subsequently
particular, identifiable task. As
supplied, that is to say, to a shortfall
pointed out byJacobs P in Arcos
between the estimated and the
Industries, it is of the nature of a
actual quantity of any item.
schedule of rates contract that the
The variation clause in question exact amount of work to be
dealt with variations of the work of performed will not be known with
addition thereto or omission certainty until the work has been
therefrom. The court stated: completed. Nonetheless, tenders
are usually invited and made upon
The reason for having a schedule of
the basis of the range of estimated
rates contract is that the extent of
quantities. In an appropriate case,
the work cannot at the outset be

AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #79 AUGUST/SEPTEMBER 2001 11


-------~- ~~ ~~ ~ ~ _~

~~
~~~-== ~~

the principal or the contractor may damages is what is known as the


choose to stipulate the limits of 'prevention principle'. It is a rule of
accuracy for those estimates. This law that one party to a contract
will depend upon the agreement cannot complain of a breach by the
made by the parties... that is quite a other if the complainant has, by its
different situation from that with own act prevented the other from
which [the clause in question] deals. complying. It follows that a
The latter clause is intended to deal principal who delays a contractor's
with variations in the work to be progress cannot insist on strict
performed, whereas limits of compliance by the contractorwith
accuracy relate to the accuracy of the contractual date for completion.
estimates of the work agreed to be Further, if the contractual date for
performed. completion is not enforceable, then
any liquidated damages provisions
Contrast the decision of the Privy
are paralysed, because they are
Council in Mitsui v Attorney-
expressed to operate from this
General of Hong Kong (1986) 33
contractual date.
BLR 1, which decided that
quantities in excess of those The prevention principle may be
anticipated were variations; and formulated as follows:
.J Crosby and Sons v Portland UOC
• a principal will lose the right to
(1967) 5 BLR 121, inwhich an
claim liquidated damages if some
English High Court judge decided
of the delay (prior to the date for
that an increase in quantities under
completion) is due to its defaults or
ICE 4th edition amounted to a
those of its employees or agents,
variation.
unless:
LIQUIDATED DAMAGES • the extension of time clause,
~penalty
or Genuine Pre-Estimate strictly construed, allows for
of Damages?' extensions to be granted for
As a general principal, when delays caused by acts or
considering the validity of a defaults of the principal; and
liquidated damages clause, the fact
that no loss has actually been • an extension has been validly
suffered is irrelevant (8FI Group v granted;
Integration Systems Ltd [1987] • this will be the case even if the
CILL348). principal's delays are part only of
As a rule of thumb, a clause which the delay-the court will not seek to
seeks to impose liquidated apportion delay, at least when
damages will be upheld, provided it considering the enforceability of the
is a genuine pre-estimate of liquidated damages clause;
damages-the time to assess • even if the contractor would have
whetherthe provision is been unable to complete on time in
compensatory or penal is the time the absence of a delay by the
when the parties entered into the principal, the liquidated damages
transaction. In practice, successful clause will still cease to apply if the
attacks on the average liquidated principal is responsible for some of
damages clause in a contract are the delay; and
rare. It is only if the amount sought
to be imposed is so far in excess of • if the liquidated damages clause
the maximum conceivable as to be is held inoperative because of the
out of all proportion, that it may be application of this principle, the
construed as a penalty. principal will still be entitled to sue
the contractor for any general law
The Prevention Principle damages that it can prove flow from
Another basis of attack on the the contractor's default.
principal's right to liquidated

12 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #79 AUGUST/SEPTEMBER 2001


The two key features required of support that the following would
extension of time provisions so as t6 need to be established by the
maintain the efficacy of a liquidated contractor.
damages clause are:
(i) An implied term requiring
• extensions of time must be co-operation between the parties in
available for delays which are order for them to enjoy the benefits
caused by preventative acts; of the contract. The implication of
such a term was thought to be well
• the superintendent must have the
established on the authorities,
right to extend time of his or her
although recent decisions have
own motion. Otherwise, the
called this into question,
contractor, simply by not applying
particularlywhere the contract
for an extension, could cause the
contains express provisions to the
prevention principle to be activated.
contrary.
To summarise:
(ii) In breach of this implied term,
• the fact that the principal has not the principal failed to direct or
in fact suffered any loss as a result coordinate the work of other
of a delay in completion will not, of subcontractors on the site causing
itself, have the effect of rendering the contractor disruption and delay
void a provision in relation to in carrying out its obligations under
liquidated damages; the contract within the time
specified in the contract.
• the contractor should examine
the circumstances giving rise to the In J & J Fee Ltd v Express Lift Co Ltd
figure which was inserted into the (1993) 34 Con LR 147, it was held
contract as liquidated damages to that in the absence of contrary
satisfy itself that it does qualify as a express terms, there would be
'genuine pre-estimate' at the time implied not only the 'Perini' implied
at which the contract was entered terms not to hinder and to co-
into; operate, but also the implied term
to provide correct information
• if the reason that the contractor
concerning the works in such a
has been delayed is as a result of
manner and at such times as was
an act of 'prevention' by the
reasonably necessary in orderfor
principal or its agents then,
the contractor to fulfil any
notwithstanding that the contractor
obligations under the contract.
may not have sought an extension
of time under the contract, it is However, in Martin Grant & Co Ltd v
arguable that the principal has lost Sir Lindsay Parkinson & Co Ltd
its right to levy liquidated damages (1984) 29 BLR 31, the court
if there is no mechanism provided in rejected an implied term that work
the contract for it to grant an and operations would be available
extension of time of its own volition. so as to enable them to be carried
out in a mannerwhich was not
THE CONTRACTOR'S
piecemeal nor uneconomic as that
ABILITY TO CLAIM implied term was contrary to the
ADDITIONAL COSTS DUE TO express term to carry out the works
INEFFICIENCIES IN underthe contract at times and in
ADMINISTERING THE manners as directed or required.
CONTRACT In the Australian case of B G
To succeed in establishing a claim Gregory Pty Ltd v Shire of
for disruption and delay for breach Greenough-Butterworths
of contract (as opposed to a claim Unreported Judgments, BC 870
underthe contract) arising from 0718, the appellant claimed that
poor coordination and planning by when it was preparing the tender it
the principal, the authorities relied upon a document described

AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #79 AUGUST/SEPTEMBER 2001 13


-
~ -- =~

-~
~ =~~=
~--=

The arbitrator in his award as 'construction managers quantum meruit in that the
said that the works had so construction program', from which obligation to pay is grounded in the
the times at which the appellant principal's promise to do so, rather
dramatically changed under
was to commence and complete than the duty to make restitution.
the terms of the subcontract various aspects of its work could be
that the pricing formula The decision of Atlantic Civil Pty Ltd
established. It argued for an
v Water Administrations Ministerial
accepted by the parties implied term that the respondent
Corporation [unreported decision of
could no longer apply. It would manage the project to
Giles J, NSW Supreme Court, 16
followed that the only way enable the appellant to start its
October 1992) raised the existence
work on a fixed date and thereafter
to price the work under the of a valid contract as a defence to a
work progressively in an orderly
contract was as a total re- manner.
claim on quantum meruit. The
measurement of the works. decision of the referee, who ruled
On appeal from a case stated for that a quantum meruit was
the opinion of the Supreme Court of available even though there was a
Western Australia, the majority of valid contract was challenged. The
the Full Court concluded it was not court held that the referee in
possible to imply a term to that making his determination
effect as: considered that the schedule of
rates were inapplicable, and
[Ilt was not necessary to give
referred to 'a quantum meruit
business efficacy to the contract
underthe contract'. The court
and more importantly it would be
interpreted this as meaning a
inconsistent with the express terms
reasonable sum forthe additional
of the contract.
work, and was not an assessment
Quantum Meruit/Restitution outside the contract.
Confusion abounds as to the
Similarly in the matter of Concrete
circumstances in which contractors
Constructions Group Ltd v OVP
are entitled to formulate claims for
Engineering PtyLtd (1998) 14BLCL
extra payment outside of the
168 a fabricator subcontractor had
contract on the basis of the legal
entered into a lump sum contract
notions above.
with a builder, whereby the
(a) Quantum Meruit fabricator had agreed to supply and
An action on a quantum meruit install the structural steel
generally rests not on implied component of works under the
contract but on a claim to restitution head contract. A dispute arose
or a claim based on unjust between the parties as to the
enrichment, arising from the fabricator's entitlement to the price
acceptance of benefits accruing to of the works performed by it. The
one party as a result.of the work dispute was referred to arbitration.
done by the other. The obligation to The arbitrator in his award said that
pay fair and just compensation for a the works had so dramatically
benefit which has been accepted changed under the terms of the
will only arise in a case where there subcontract that the pricing formula
is no applicable genuine agreement accepted by the parties could no
orwhere such an agreement is longer apply. It followed that the
frustrated, avoided or only way to price the work under
unenforceable. the contract was as a total re-
measurement of the works.
On the other hand, where a
variation has not been valued prior The builder appealed to the
to execution, and the valuation is Supreme Court of Victoria for
determined after the event on orders settling aside the award.
principles of reasonableness, The Court in refusing the builders
recovery is on the basis of a appeal held that the arbitrator had
contractual quantum meruit. This decided the matterwithin the
differs from a restitutionary contract and not on restitutionary

14 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #79 AUGUST/SEPTEMBER 2001


~ ~= ~c~c. __ ~ ~ ~ ~ · · ~ -

~~ ~ ~~~~~.~.. ~ ~

- ~ ~~~ -~~~ ~

principles. He had approached the WET WEATHER DELAYS such events. It should be noted that
issue on the basis of the contractor As a general principle, a contractor a number of the standard forms
receiving a sum which was to be who undertakes to complete works provide such a mechanism. While
calculated at a fairvalue. by a specified date (time being of this protects the contractor from the
the essence) for a fixed lump sum, imposition of liquidated damages it
These later cases raise the
will bearthe risk in both a time and will not, in the absence of a
possibility of an arbitratorvaluing
money sense, in the absence of generous delay costs provision,
the works undertaken by a
specific provisions which pass some assist recovery of the contractors
contractor on are-measurement
or all of this risk to the principal or additional costs caused by the extra
basis, notwithstanding the existence
other parties. Under an evenly time spent on site.
of the contract. The likelihood of
any similar decision would be balanced contractual regime, there
is often provision for a contractor to Patrick Mead's article first
dependant upon a contractor
be awarded an extension of time for appeared in Carter Newell's
demonstrating to an arbitratorthat
events beyond its control not Constructive Notes newsletter
the works had so dramatically
reasonably anticipated at the time (July 2001). It appears here with
changed under the subcontract that
of contract, e.g. inclement weather. permission.
the pricing formula accepted by the
parties should no longer apply. The ability to gain an extension of
time in these circumstances is
(b) Restitution however a quite separate issue
Provided the additional works from the ability of the contractor to
performed are extra-contractual recover extra costs as a resu lt of it
obligations, the court may impose being delayed by these events.
an obligation on the principal to pay Normally such a right, if it is given
for work done by operation of the at all, will only arise in
principle that it has taken the circumstances where the contractor
benefit of the work done and had has been delayed by the principal
actually or constructively accepted or, in certain circumstances, parties
this benefit. Because the principal forwhom the principal is
would be unjustly enriched if it were responsible, e.g. superintendent,
allowed to accept this benefit acts of other contractors etc.
without paying for it, the law
imposes an obligation to make The relevance to the contractor of
restitution. It is on this restitutionary receiving an extension of time in the
basis that a contractor is entitled to absence of any entitlement to claim
recover a quantum meruit for his damages or extra costs for delay, is
work. that it may avoid being placed in a
position where it is forced to
The decision of Update accelerate the works (at its cost] in
Constructions Pty Ltd v Rozelle order to achieve completion by the
Childcare Centre (1990) 20 NSWLR due date. The sanction for failing to
251 is instructive on this point. This achieve completion by the due date
case involved a claim for variation is often a daily orweekly sum of
work in the absence of a written liquidated damages. Even in the
order. The court ultimately decided absence of a provision for
that the principal was estopped liquidated damages, failure to
from relying on the requirement for achieve completion by the due date,
a variation order to bein writing. will, in the absence of any
Where a condition precedent to disentitling factors by the principal,
enforceability of payment under a give the principal a right to sue the
variation clause is not fulfilled, a contractor for breach of contract.
contractor may be able to recover
on a quantum meruit, the obligation Generally, in the absence of an
being imposed by operation of law express provision giving the
where it can be shown that the contractor the ability to claim an
principal has actually or EOT in respect of neutral events of
constructively accepted the benefit delay, the obligation to complete by
of the work. the due date will not be altered by

AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #79 AUGUST/SEPTEMBER 2001 15

You might also like