THE TERMINATION OF INTRODUCTION The rights and wrongs of such a
BUILDING CONTRACTS: The common law of repudiation is case cannot be resolved without complex, especially so in the delving into the full facts and COMMON LAW circumstances surrounding the context of building contracts. This REPUDIATION V complexity arises in part because, alleged terminations and CONTRACTUAL under the unitary theory of contract construing the relevant clauses in TERMINATION law, the cases are drawn from a the context of the whole contract. variety of commercial transactions, The victor might only emerge after Romauld Andrew yet they are expected to have a long and protracted litigation, or Barrister at Law general application. Most of the the court might find that neither of Victorian Bar leading cases concern either the parties has terminated the charter parties or contracts for the contract, either contractually or at sale of land.1 The principles have common law, and further litigation thus evolved in ways that try to is required.2 It is enough to make accommodate the multitude of many of the cases settle prior to commercial settings which may final determination. give rise to disputes, whilst The result of termination, whether maintaining, not always contractual or at common law, will successfully, a coherent theory of usually be severe for the party who general application. is ‘terminated’. Often a gross Then there are the specific injustice may ensue. If, for instance, provisions of building contracts a builder is in continual breach of its which permit termination, or contract, perhaps because it under determination, or forfeiture, or quoted for the works and will only some other manner of bringing the make a loss on the job; and if, contract, or the parties’ rights and through a mistake of its solicitors obligations under the contract, to an the owner sends an invalid notice of end. It is common in building cases termination, the builder will seize that when a party attempts to upon this act to allege that the terminate a contract pursuant to the owner has repudiated the contract terms of the contract, the other and, accepting that alleged party will counter with an allegation repudiation, purport to terminate of repudiation and purport to the contract at common law. The terminate the contract at common builder is then entitled to claim law. damages on a quantum meruit.3 For the owner, such a result, if reached, Sometimes a party to a contract could be disastrous. makes a mistake when attempting to terminate under the provisions of While the leading cases are useful the contract. The other party to the for providing general principles, few contract might then allege if any are analogous, factually, in repudiation and termination at the context of building contracts. common law. When the first party Parties seeking guidance must realizes or apprehends that it has resort, therefore, to cases of lesser made a mistake in attempting to authority and hence less reliability terminate under the provisions of a or certainty, especially at appellate contract, and that its contractual level. Many of the relevant building termination may therefore be cases are decisions of single invalid, it may further allege that judges, often hearing appeals or the other party alleging repudiation cases stated from arbitrators, so is itself repudiating the contract, that the judgments are confined to and purport to terminate the determining narrow questions, contract at common law, as an often without the benefit of full alternative to its contractual argument or citation of relevant termination. authorities. These cases are seldom reported in authorised reports—
AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #97 JULY/AUGUST 2004 11
The key question is what most are only to be found in clauses, but the actual words used happens if a party sending specialist construction law reports. may include ‘determination’ or ‘forfeiture’ or ‘ending the a notice of termination The general principles of contractor’s employment’ and so pursuant to the contract repudiation in Australian law are on. In most cases the clause will makes a mistake. The contained in the well known High provide for either the employment Court cases of Laurinda Pty Ltd v general rule, according to Capalaba Park Shopping Centre of the builder to be ended, or for the Carter, is that a wrongful Pty Ltd (1989) 166 CLR 623 and contract to be ended. In some cases termination of the there is an option for either one of Foran v Wight (1989) 168 CLR 385. these courses. performance of a contract The common law in this area is will constitute a repudiation highly complex and it is not the aim Termination is a term often applied of obligation. of this article to discuss repudiation to such clauses, but it is more in detail. I wish merely to correct to speak of termination of emphasise the following key points. obligations or termination of future First, repudiation is a serious matter performance rather than and is not to be lightly found.4 termination of the contract, Generally speaking, repudiation because, upon termination, any arises where a party is in breach of rights which have accrued at the a fundamental term of the contract, time of the termination remain or where by words or actions a enforceable, and it is only the party evinces an intention to no parties’ future obligations which are longer be bound by the contract. ended. Even then, in some cases, Obvious examples in the context of after a termination, one party may building contracts are where an be entitled to seek damages under owner denies the builder access to the contract against the other party, the site or engages another so that obligations under the contract are ongoing. However, contractor to carry out the works, or some of the standard form part of the works: as in Carr v J A contracts now refer to termination Berriman Pty Ltd (1953) 89 CLR of the contract.5 And the 327. Or where a builder abandons terminology is not precise or the work and quits the site. uniform in the cases either, the In order to terminate the contract at terms rescission or determination common law the innocent party being used synonymously with must make, and communicate to termination. the repudiating party, a clear and The parties are generally free to prompt election to accept the agree to any provisions they wish repudiation and terminate the concerning termination, subject to contract. Once the contract has public policy, illegality and statute. been thus terminated, it cannot be It is also possible, but not common, revived except by agreement of the to make the contract provisions for parties. If a contract is terminated termination a self-standing ‘code’ pursuant to the contract which excludes the common law. In beforehand, then it will be too late all cases, close examination of the to accept the repudiation and clause is required to ascertain the terminate the contract—a contract parties’ rights. can only be terminated once. But if the innocent party elects to affirm The key question is what happens if the contract, then it has waived or a party sending a notice of abandoned its rights to elect to termination pursuant to the contract accept the repudiation and makes a mistake. The general rule, terminate the contract. according to Carter, is that a Building contracts usually contain wrongful termination of the clauses dealing specifically with performance of a contract will termination. For uniformity I shall constitute a repudiation of refer to such clauses as termination obligation.6
12 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #97 JULY/AUGUST 2004
As is often the case, this general contrast is the approach adopted in Therefore, the court held that the rule, whilst capable of being stated the same year (independently, it notice was invalid even though simply, has not been found to be so would seem) in the English case of there was no dispute that the notice easily applied to the facts in Goodwin v Faucet (1965) 175 had indeed been received by the particular cases. As will be seen, Estates Gazette 27 per Stephenson builder through personal service. some of the judgments have J who construed the relevant Secondly, the court found that the produced unusual results. contract in a ‘common sense second notice had been given businessman’ way when deciding FAILURE TO COMPLY WITH whether a termination was prematurely, and hence it too was THE CONTRACTUAL invalid. On the facts of the case the effective. builder had until midnight on 14 PROVISIONS AND The strict approach was applied by May to comply with the first notice, INVALIDITY OF NOTICES Collins J in Eriksson v Whalley but the owner mailed the second Because the effects of termination (1971) 1 NSWLR 397. In that case notice on 14 May, which was will usually be severe a contractual the respondent builder challenged received by the builder on 15 May. termination clause will be strictly the applicant owner’s notice Because this was sent within the 14 construed and, generally, a failure determining the builder’s day period, Collins J found that it to comply with the provisions of the employment under the contract on was invalid, even though the contract will mean that the three grounds, two of which are contract used the word ‘give’. termination is invalid. But the relevant for present purposes: the Interestingly, His Honour found question of how strictly one should first notice had been served that: construe such clauses has met with personally on the builder’s different approaches from the It would have been quite possible foreman, rather than by registered for the builder to have effectively courts. Broadly speaking there are mail as required under the relevant two approaches, which may be discontinued his default after the clause; and the second notice notice terminating his employment described as the formalistic7 determining the builder’s approach and the common sense had been sent to him.10 employment had been sent business8 approach. prematurely. This strict approach was not The formalistic approach construes followed by English Court of Appeal The conclusions of this case are a the contract very strictly, as in the in the case of JM Hill & Sons Ltd v little difficult to understand. Collins case of Re Stewardson Stubbs & London Borough of Camden (1980) J observed that the provisions for Collett v Bankstown Municipal 18 BLR 31. The facts of this case determination in the contract gave Council (1965) NSWR 1671 per are complex, but can be the owner rights in excess of those Moffitt J. In that case the contract summarised as follows. The it would have had at common law, provided that the owners were to plaintiff contractor claimed to be and that it was reasonable to give the builder 14 days written owed moneys under certificates assume that the stringency of those notice to remedy its default before issued by the architect. When the provisions led to the formulation of they could send a notice of employer did not pay, the the principle that the power to determination. The owners sent the contractor put in place a policy of forfeit will be strictly construed. first notice giving the 14 day notice ‘go slow’ but otherwise remained on However, when applying that required. However, on the 14th day site. Both parties sent notices to the principle to facts of the case an the owners sent the second notice other party. The Court of Appeal unexpected result followed. by registered mail terminating the found that the contractor’s conduct contract ‘forthwith’. Moffit J held First, the court found that the did not in the circumstances amount that the notice was invalid because contractual requirement for service to a repudiation, so that the owner’s it was sent prematurely on the 14th of the first notice by registered mail attempt to terminate the contract day, even though it was not received was not merely ‘directory’ as came to nothing. by the builder until the 15th day. contended by the owner, but had to But the main issue was whether the be strictly complied with to the contractor’s termination pursuant to In reaching this decision Moffit J letter, in part because this method placed emphasis on the precise the contract was valid. The of service would eliminate to a employer raised a late point after words of the relevant clause, large extent disputes about service, specifically the word ‘give’ which, the appeal had been lodged, and because service by registered namely, that the second notice had when combined with the mail ‘imports a certain solemnity or requirement for registered post, led been sent prematurely because it importance to the giving of the had been sent by mail on 10 April. His Honour to believe that the time notice which a more informal ran from the time of posting. In Under the contract, the employer method of service may not convey’.9 had until 10 April to remedy its
AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #97 JULY/AUGUST 2004 13
Giles J accepted that such default so the notice of termination, Kennedy v Collings Construction provisions are to be strictly it was argued, should not have been Company Pty Ltd (1991) 7 BCL 25. sent until 11 April. Eriksson v In that case Giles J had to consider construed because of their Whalley was relied upon in support whether the plaintiff owner had serious consequences but of this argument. validly terminated the contract with His Honour could see no the builder after a litany of defaults The Court of Appeal allowed the reason to give the relevant point to be raised, even though it by the builder. The builder clause a construction, under had not been raised before the challenged the owner’s notice the name of strictness, because it had not been sent by Master or the Judge below, but registered mail, although there was which would ‘lead to the such leave appears to have been no challenge to the fact that it had unreal result that undisputed given merely to provide an been received. Giles J found for the receipt of the notice would opportunity to comprehensively and owner, and after discussing the unceremoniously dispense with the be ineffective because the point. Lawton LJ said that the court relevant provisions stated: medium of registered post was not bound by Eriksson v But this does not mean that service had not been used’. Whalley and appeared dismissive of a notice determining of the case and described the point employment by registered post is raised by the employer as necessary as well as sufficient. It ‘formalistic’. His Lordship found that does not seem likely that the the date of sending the letter was parties to a contract in the form of not important, it was the date of BC3 should have intended that a receipt that was important.11 notice determining employment Ormrod LJ went further, dismissing would be invalidly given if Eriksson v Whalley and saying that personally served, or if placed in the point was ‘farcical’ and, if the hands of the secretary of a applied, would make a ‘mockery’ of corporate builder at its registered the law. office. To adopt the words of It might have been thought that the Wootten J (at 622) in Spectra Pty strict or formalistic approach of Re Ltd v Pindari Pty Ltd (above) that Stewardson and Eriksson v Whalley would place an absurd premium on was thus a thing of the past, except a particular form which could be of that these cases were followed by no benefit to anybody. In my view Ashley J in Wilson v Kirk the provision for registered mail Contractors (1991) 7 BCL 284. In should be seen as facultative, that case, the owners’ solicitor permitting notice of determination made several mistakes when trying of the builder’s employment by to terminate the contract. One of the registered mail rather than by the many issues under consideration perhaps more onerous course of was whether the owners’ second personal service, but not obligatory. attempt to send a notice of As a matter of construction of the termination was valid. This notice June contract, I think it sufficient if was sent by security post on the last the notice determining the day of the period prescribed by the employment of the builder be given relevant clause. Ashley J ruled that by any other means which is shown the notice was invalid and applied to have resulted in receipt of the both Re Stewardson and Eriksson v notice by the builder. I therefore Whalley.12 The case of JM Hill & reject this first answer.13 Sons Ltd v London Borough of Giles J accepted that such Camden does not appear to have provisions are to be strictly been brought to Ashley J’s construed because of their serious attention. consequences but His Honour could see no reason to give the relevant The issue of whether the clause a construction, under the requirement for registered mail is name of strictness, which would ‘mandatory’ was not raised in JM ‘lead to the unreal result that Hill & Sons but it was raised in
14 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #97 JULY/AUGUST 2004
undisputed receipt of the notice Franz (1987) 6 ACLR 33. In that WRONGFUL TERMINATION, would be ineffective because the case the second notice was given REPUDIATION, ERRONEOUS medium of registered post had not during the period of default allowed CONSTRUCTION AND GOOD been used’.14 His Honour found that for under the relevant clause of the the reference to ‘registered post’ is contract. Carmichael J held that the FAITH explained by another clause which notice was, accordingly, invalid. And As seen above the general rule is made service by ordinary post in Wilson v Kirk Contractors (1991) that a wrongful termination of the sufficient service for the purposes 7 BCL 284 Ashley J, following Cox v performance of a contract will of other notices or documents Franz reached the same result in constitute a repudiation of under the contract: similar circumstances. These cases obligation.17 The same rule is differ from Re Stewardson and stated, in similar terms, in Keating18 The reference therein to registered and Hudson19. The reasoning post is adequately explained by Eriksson v Whalley because the notices were given to the builder 2 behind this principle is logically cl.25; its function is to make service consistent with the principles of or 3 days prior to the expiry of the by ordinary post, which would repudiation. For instance if a party relevant period. Accordingly, it otherwise be sufficient, insufficient. such as an owner denies a builder follows logically that the notices That is quite understandable, and access to the site and engages were invalid. reflects the importance of a notice another contractor to complete the determining employment, but as I In Central Provident Fund Board v works, doing so in purported have said it is a different thing again Ho Bock Kee (1981) 17 BLR 21 the reliance on an invalid termination, to say that notice served by Court of Appeal of Singapore had to then that would ordinarily amount registered post is not only sufficient determine whether an owner’s to repudiation. but also necessary—not only termination was valid. In that case permissible, but also obligatory.15 the relevant termination clause However, wrongfully terminating a provided that the superintending contract should be distinguished This approach is eminently from merely sending an invalid sensible, but it is in conflict with officer could send a notice of termination. But an earlier clause notice of termination. It is often Eriksson v Whalley, which Giles J alleged by a party receiving an said that if an action taken under distinguished on a rather fine point. invalid notice of termination that the certain clauses, including the His Honour said: sending of the notice is itself termination clause, was to occur, Relevant to this matter is the then the Chairman of the Board repudiation. But that will not always decision in Eriksson v Whalley must take that action. As the be the case. On the contrary, the [(1971) 1 NSWLR 397], although I Chairman of the Board had not sent mere sending of an invalid notice of was not referred to it. …It was held the notice of termination, the Court termination will in most cases not that the service of the notice was of Appeal of Singapore held the amount to repudiation. It all invalid, on the ground that the notice to be invalid. depends, of course, upon the facts parties had agreed that service by of each case. In Lockland Builders v John Kim registered post was ‘imperative’, In Cox v Franz the court had to not merely ‘directory’. But it is Rickwood (1995) 77 BLR 38 the English Court of Appeal (Russell, consider whether sending an invalid necessary to consider the notice amounted to a repudiation of Hirst and Rose LJJ) held that the provisions of the particular contract, the contract. In that case, the owner’s termination was invalid and given the distinction within cl.13 builder defendant had agreed in because, contrary to the provisions between notice and notice by 1975 to construct a home for the of the contract, the architect had not registered post, and the effect of plaintiff owner. After some months certified the contractor’s default cl.25, I do not think that Eriksson v the builder indicated that he would prior to serving the notice. Indeed, Whalley [above] requires a different be unable to complete the works the owner had completely conclusion from that I have stated without additional payment. Then disregarded the contractual above. he advised the owner of his concern requirements and had attempted to Not all failures to comply with the summarily dismiss the contractor that sub-contractors would enter contractual requirements may be from site. Russell LJ expressed the house and destroy work done. dispensed with. The most obvious some sympathy for the owner but The proprietor changed the locks failure relates to the requirement to said that the owner only had but offered keys to some parts of provide the specified period of time himself to blame.16 the house to the builder, but this in which the defaulting party may offer was refused. The owner then remedy their default. A notice which sent a notice of default, followed by is given (and received) prematurely a notice of determination. However, is invalid, as in the case of Cox v
AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #97 JULY/AUGUST 2004 15
I cannot see that because a the second notice was sent builder’s letter. The owners’ step so taken failed to prematurely and was held to be solicitors immediately replied with invalid. Subsequently the owner 2 further letters. The first was sent achieve its purpose the locked the builder out of the site to the builder attaching a schedule builder can turn his and the builder purported to accept of defects and purporting again to continuing breach of the owner’s repudiation. The owner determine the contract, and again contract into the proprietor’s subsequently denied liability and in denied access to the site. The repudiation of that contract… turn sought damages from the second letter was sent to the What the proprietor was builder for repudiation, tacitly builder’s solicitor and asserted that conceding that the contractual the owners had not only purporting to do was to rely termination had gone awry.20 determined the contract under the upon the contract itself to relevant clause but also pursuant to achieve certain rights: there The builder argued that because common law. the owner’s notice was invalid, the was certainly no repudiation owner was repudiating the contract The builder referred the matter to of the contract. which repudiation he had accepted. arbitration. The arbitrator found Carmichael J rejected the builder’s that the owners had not validly argument, finding that the owner determined the contract, rather, the had been doing all that he could to owners had repudiated the contract, have the contract completed and which repudiation the builder had therefore it was not possible to accepted. The owners, appealing impute to him a repudiation of the from the findings of the arbitrator, contract by taking steps under the contended that their letter did not contract to obtain its completion: seek to repudiate the contract, but I cannot see that because a step so to enforce it. Ashley J agreed, taken failed to achieve its purpose finding that the denial of access to the builder can turn his continuing the site and the indication of an intention to engage another builder breach of contract into the were altogether consistent with the proprietor’s repudiation of that course of determination available contract… What the proprietor was under the contract.22 It might be purporting to do was to rely upon noted at this point that the acts of the contract itself to achieve certain denying access to the site and rights: there was certainly no indicating an intention to engage repudiation of the contract.21 another builder are altogether Similar issues arose in Wilson v consistent with repudiation. Kirk (1991) 7 BCL 284 where the After referring in detail and with owners’ solicitor made several evident approval to Cox v Franz the mistakes when sending out the court then found that the owners’ relevant notices, with the result that solicitors’ letter of 18 July and the the notices were held to be invalid. actions which it previewed, should The first notice of termination be considered merely as an included an assertion that the ineffective attempt by the owners to contract was determined, but it also rely upon and enforce the contract asserted that access to the site was and not as a repudiation. The court denied and that the owners would found that the arbitrator had erred be engaging another contractor to in finding that the sending of this rectify and complete the works. The letter itself amounted to builder, who had been in default repudiation. The arbitrator’s finding, under the contract, alleged in a however, was that: letter that the owners had themselves repudiated the contract The proprietors by their action and and accepted the owners’ general conduct not to be bound repudiation. by the contract amounted to a As Ashley J observed, it must have repudiation of the contract. come as a ‘rude shock’ to the (emphasis added)23 owners’ solicitors to receive the
16 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #97 JULY/AUGUST 2004
This judgment raises some a valid termination under the agreement by contentious important questions. First, if the contract, rather, it was an unlawful observations in the course of termination was not valid, then on repudiation of the contract.25 discussions or arguments as to the what legal basis were the owners In Mersey Steel & Iron Co v Naylor provisions to be inserted into the entitled to exclude the builder from Benzon & Co (1884) 9 App Cas 434 lease.27 site and engage another purchasers formed an erroneous Buckley J agreed and also added contractor? What remedy, if any, construction as to a contract for the the element of good faith.28 This does this leave the builder, sale of goods, and believed that case is useful for general principles remembering that in this case the they could not pay for goods when a but does not assist in the case court found that it was very doubtful petition for winding up had been where a party, acting on an that the builder’s defaults served, without the sanction of the erroneous belief, conducts itself in constituted a repudiation of the court. They applied for an order of a manner which would otherwise contract.24 These questions are not the court, and this conduct was held give rise to repudiation. For answered in the judgment probably not to be repudiatory, the instance, if an owner misconstrues because, having answered the purchasers conduct being bona fide. a contract, and erroneously narrow questions on appeal, the In Sweet & Maxwell Ltd v Universal believes the contract has been court remitted that matter back to News Services Ltd (1964) 2 QB 699 validly terminated, and then acts in the arbitrator for further hearing. the English Court of Appeal a manner which on any objective The answer would seem to be, rejected an allegation that an view must be repudiatory, such as however, that merely sending an erroneous construction of a lease denying access to the site and invalid notice of termination will not agreement gave rise to repudiation. engaging another contractor, then in itself amount to a repudiation, Harman LJ said: there must, logically, be a such an action being conduct repudiation. evincing an intention (albeit …I do not think that a person who That is what happened in Cox v erroneously founded) to rely on the maintains his view of the construction of what is, after all, a Franz. Because the court found that contract. But if that party persists in the owner’s purported termination relying on the wrongful termination, not very perspicuous document is was invalid, then the owner was then that conduct must, at least as a repudiating because he says ‘my breaching fundamental terms of matter of logic or common sense, view of it is this, and this I will do’ the contract. Was not the builder in amount to repudiation. The leading and the other man says ‘well, my that case entitled to accept the authority for this principle is Lodder view is different’. Let them go to the repudiation, and if not, why not? v Slowey (1904) AC 441 in which the court and have the matter Privy Council held that where a determined as they can. But to In Cox v Franz the court found that party to a contract for execution of seize upon an attitude of that sort the owner had not repudiated the works wrongfully re-enters and and call it repudiation in order to contract and hence the builder was seizes the works in progress, then serve an object which was then of not entitled to accept a repudiation. the contractor may treat the course dear to the hearts of the Carmichael J placed great reliance contract as at an end and sue for plaintiffs, who wanted to get rid of on Sweet & Maxwell Universal work and labour done. this deed, is not in my opinion News Services Ltd.29 justified…26 A similar approach was taken in In Architectural Installation Services Ltd v James Gibbons Pearson LJ agreed: Wilson v Kirk. In that case Ashley J Windows Ltd (1989) 46 BLR 91 a cited at length and with evident Moreover, even if they had taken an builder sent a notice requiring a approval from the judgment in Cox erroneous view as to the effect of sub-contractor to work a full day as the agreement, it would not follow v Franz and His Honour also required under the contract. Some applied the principle that ‘where a that the expression of an erroneous eleven months later the builder party takes action relying on the view or the taking of an erroneous sent a telex to the sub-contractor terms of the contract, not objection to some clause proposed purporting to terminate the contract manifesting by his conduct an to be inserted in the lease would because the sub-contractor had ulterior intention to abandon it, he amount to a repudiation of the withdrawn its labour. The Official should not be treated as having agreement for a lease… In the last Referee (Judge Bowsher QC) found repudiated it’.30 Ashley J placed resort, if the parties cannot agree, that there was no sensible great reliance for this principle on the true construction will have to be connection between the first notice the case of Woodar Investment determined by the court. A party and the telex, either in time or should not too readily be found to Development Ltd v Wimpey content. Accordingly, it was held have refused to perform the Construction UK Ltd (1980) 1 WLR that the sending of the telex was not 277: (1980) 1 All ER 571 and
AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #97 JULY/AUGUST 2004 17
accordingly that case warrants have been if Woodar had construction of a contract does not examination. immediately treated Wimpey’s necessarily give rise to repudiation. rescission notice as evincing an Stephen, Mason and Jacobs JJ Woodar Investment Development intention by Wimpey to no longer be stated the position thus: Ltd v Wimpey Construction UK Ltd bound by the contract, which it concerned a contract for the sale of But there are other cases in which a accepted, rather than seeking a land by Woodar to Wimpey. The party, though asserting a wrong declaration from the court, and had contract provided that Wimpey view of a contract because he then sold the land to another party? could rescind the contract if any believes it to be correct, is willing to If that were the case, Wimpey’s public authority commenced perform the contract according to conduct might well be seen as compulsory acquisition prior to its tenor. He may be willing to repudiatory because it did not settlement. Wimpey sought to rely recognize his heresy once the true subsequently affirm the contract. on the fact that compulsory doctrine is enunciated or he may be acquisition for part of the land had What makes the case interesting is willing to accept an authoritative commenced and sent notice the fact that Woodar challenged the exposition of the correct rescinding the contract. Woodar validity of the rescission notice and, interpretation. In either event an challenged the notice on the basis even assuming an election were intention to repudiate the contract that the acquisition had already available, elected to proceed with could not be attributed to him. As commenced when the parties the contract and sought the Pearson LJ observed in Sweet & signed the contract, and that the intervention of the court. And Maxwell Ltd v Universal News rescission clause only related to Wimpey, rather than persisting in Services Ltd (1964) 2 QB 699, at compulsory acquisition commenced conduct which might give rise to p.734: after the contract was signed. repudiation (other than adhering to ‘In the last resort, if the parties Woodar brought an action against its view of the contract) sought the cannot agree, the true construction Wimpey seeking a declaration that intervention of the court, thus will have to be determined by the Wimpey was not entitled to rescind affirming the contract. In these court. A party should not too readily the contract. Wimpey in its defence circumstances, both parties can be be found to have refused to perform seen as affirming the contract. and counterclaim sought a the agreement by contentious declaration that it was entitled to The facts of Woodar are clearly observations in the course of rescind the contract. Then Woodar distinguishable from cases such as discussions or arguments...’ brought a further action alleging Cox v Franz or Wilson v Kirk where (at p.432) that, by the notice of rescission and the erroneous party proceeded to The important distinction, therefore, its defence and counterclaim, take steps which would, on ordinary which must be drawn between Wimpey had repudiated the common law principles, give rise to these cases is the difference contract which was accepted and a repudiation, and which would between asserting an erroneous damages were claimed. actually prevent the contractor construction on the one hand, and from performing the contract.32 See The House of Lords upheld an proceeding on an erroneous also Federal Commerce Ltd v appeal by Wimpey, finding that it construction on the other hand. This had not repudiated the contract. Molena Alpha Inc (1978) 1 QB 927 is no mere semantic distinction. In in which ship owners’ instructions to Lord Wilberforce found that in the latter case, the general rule the masters of their vessels, based considering whether there has been should apply, and the wrongful on an erroneous construction of the repudiation by a party it is termination should, in theory at charter party, were held by the necessary to look at his conduct as least, give rise to repudiation. As English Court of Appeal to be so a whole. Lord Wilberforce found Brennan J stated in Dainford Ltd v serious in their effect on the that both parties were asserting a Smith (1985) 155 CLR 342: charterers that they amounted to contrary construction of the Sometimes it is right to find that a repudiation.33 contract, and that each party was party who adopts an erroneous allowing the court resolve the issue, The High Court has considered the construction of a contract and who and accordingly there was no issue in DTR Nominees Pty Ltd v intends to act in accordance with repudiation by Wimpey.31 Lords Mona Homes Pty Ltd (1978) 138 that construction in fulfilling the Keith and Scarman followed Lord CLR 423, another case involving a contract is not ready and willing to Wilberforce’s reasoning, Lords contract for the sale of land. The perform the contract and has Russell and Salmon dissenting. principle from that case, consistent evinced an intention to perform the This is an interesting case and with Sweet & Maxwell and Woodar contract only in a manner raises its own issues. Consider, for v Wimpey, is that an erroneous substantially inconsistent with its example, what the result might terms.34
18 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #97 JULY/AUGUST 2004
And as is pointed out in Hudson, But, in most cases, one party or the And as is pointed out in differences of interpretation as to a other will be seeking to enforce Hudson, differences of party’s obligations under the their legal rights against each other interpretation as to a party’s contract, should they come to a so that they cannot be said to have head, will render a party in real abandoned the contract. obligations under the peril of a successful adverse Accordingly, if the reasoning of Cox contract, should they come rescission should his interpretation v Franz and Wilson v Kirk is to make to a head, will render a party prove to be incorrect, assuming that sense, then some explanation of in real peril of a successful he has, as a result of acting on that these open ended questions needs adverse rescission should interpretation, prejudiced the to be provided. his interpretation prove to be further performance of the contract, quite apart from the obvious cases CONCURRENT ACTION? incorrect... where he may have been led into —CONTRACTUAL prematurely rescinding or TERMINATION V COMMON terminating or abandoning the LAW TERMINATION contract himself.35 The question often arises whether a By this reasoning, the conclusions notice of termination may be given reached in Wilson v Kirk and Cox v both under the provisions of the Franz are, with respect, unhelpful. contract and pursuant to common Moreover, these judgments leave law. Usually this is alleged in order open the question, what happens to to salvage a termination because the contract in such cases? there has been some defect in the Logically, the contract must still be contractual notice. Thus, in Cox v live, as neither party has validly Franz the owner sought to rely on a terminated it. But the owner will common law termination because have denied the builder access and the notice was not valid under the engaged another contractor. Does contract. The court held that, where the contract merely expire by a contractual notice has been sent, operation of some as yet the owner was affirming the unannunciated principle? Is the contract, and could not therefore contractor entitled to sue for breach also accept repudiation.37 The same of contract with damages being the argument was raised in Wilson v loss of profit which would have Kirk in which case the court adopted been earned? What if the new the reasoning of Carmichael J in contractor starts work but then Cox v Franz.38 See also Bysouth v abandons the site, can the owner Shire of Blackburn and Mitcham seek to enforce the contract against (No 2) [1928] VLR 562. the original builder? These In Kennedy v Collings Construction questions are more than academic, Pty Ltd (1991) 7 BCL 25, however, they frequently arise in practice and Giles J found that it was open for the case law does not, it is the owners to ‘exercise both the submitted, adequately deal with the contractual power to determine the issues. employment of Collings and the One possibility may arise where the common law entitlement to accept builder, having purported to accept the repudiation’.39 Giles J cited the owner’s repudiation, does Summers v The Commonwealth nothing more, that is to say, does (1918) 25 CLR 144; Bysouth v Shire not issue proceedings against the of Blackburn and Mitcham (No 2) owners seeking damages. If the [1928] VLR 562; and Hudson (10th owners do not sue the builder, but ed) at 687 in support of this finding. merely complete the works using The question may not be as easily another contractor, then the parties resolved as that, however. may be said to have mutually The passage referred to by Giles J abandoned the contract.36 in Hudson (10th ed) reads as follows:
AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #97 JULY/AUGUST 2004 19
It is an open question It may, however, be noted here that However, in Lockwood Builders v whether an employer, faced a given event may be both one John Kim Rickwood (1995) 77 BLR which justifies the innocent party in 38 the English Court of Appeal with default by the treating the contract as repudiated, (Russell, Hirst and Rose LJJ) contractor which might both and also one upon the happening of rejected an owner’s argument that amount to repudiation and which an express forfeiture clause the notice, which was held to be entitle the employer to may be invoked. In such a case, invalid under the contract, was a operate a contractual unless the contract shows an common law acceptance of the determination clause, can explicit intention that the stipulated builder’s repudiation, saying that in remedy should exclude the the absence of express words to the hedge his position so as to ordinary remedies, the innocent contrary, the contractual provisions avail himself of both party may make an election. He excluded common law rights.44 The opportunities. may simply treat the contract as Court of Appeal did not follow repudiated and rely upon the Architectural Installation Services v remedies available upon James Gibbons Windows Ltd on this repudiation under the general law, point.45 Other cases which have or he may proceed under the rejected the alternative submission forfeiture clause and avail himself are: E R Dwyer v Simon Build/Peter of the rights contained therein. Lind Partnership (1982) 23 BLR 23 Indeed, there would seem to be no and Mvita Construction Co Ltd v reason why he should not enforce Tanzania Harbours Authority (1988) both sets of remedies 46 BLR 19. simultaneously and cumulatively.40 The question is addressed in The last sentence might need to be Keating as follows: reconsidered, because the rights It is an open question whether an under the contract might be employer, faced with default by the different from the rights at common contractor which might both law, the party receiving the notice is amount to repudiation and entitle entitled to know, unequivocally, the employer to operate a which remedies will be available or contractual determination clause, pursued.41 can hedge his position so as to avail In Architectural Installation himself of both opportunities. Services Ltd v James Gibbons Logically, this may not be possible, Windows Ltd (1989) 46 BLR 91 since to operate the contract is to Judge Bowsher QC, hearing a affirm it, which is inconsistent with preliminary issue, found that the accepting a repudiation.46 owner’s notice of termination, whilst This reasoning was criticised in the it did not comply with the contract commentary to Laing Management and was therefore invalid, may Ltd v Aegon (1997) 86 BLR 70: nevertheless have been a common law acceptance of the builder’s This is no conundrum at all if what repudiation, subject to the ultimate is truly happening is described findings on trial.42 And in the current without the use of the traditional edition of Hudson the following terminology. The exercise of an passage appears: express power of termination is an affirmation of the contract, but is …in the absence of express also an election to terminate the provision, contractual future employment of the determinations by either party are contractor. An election to accept a not intended as a substitute for, or repudiatory breach is also an to exclude, the common law rights election to terminate the future to rescind. While some standard employment of the contractor and form determination clauses contain all executory obligations of both express ‘without prejudice to other parties. Since it involves an rights or remedies’ wording, this is assertion that the other party is in not in fact necessary…43
20 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #97 JULY/AUGUST 2004
breach of contract it is also an letter, which specifically, relied Such a party is merely affirmation of the contract… upon the contractual clause for affirming the existence of the terminating the builders The possible dilemma posed in contract to date, which has employment, was not a common Keating on Building Contracts… is been breached, but is then law acceptance of termination.49 therefore, it is submitted, not a real immediately electing not to dilemma.47 Whilst each case must be determined upon its own particular affirm the contract any This reasoning is superficially further and instead attractive, but, upon closer analysis, facts, it is submitted that the views of Judge Humphrey Lloyd QC in terminates the contract. unsound. First, as mentioned above, the party receiving the notice is Laing Management Ltd v Aegon entitled to know which method is (1997) 86 BLR 70 correctly states being used because it may affect the principle. The question still the remedies available. But that remains open for further debate party is also entitled to know which before the courts, especially in method is being relied on so that, if Australia. it wishes to challenge the REFERENCES termination, it knows what grounds 1. For example, Hong Kong Fir might be successful. Finally, it Shipping Co Ltd v Kawasaki Kisen simply does not follow, as a matter Kaisha Ltd (1962) 2 QB 26 and of logic, that in accepting a Foran v Wight (1989) 168 CLR 385. repudiation a party is thereby also A building contract is the subject of ‘affirming’ the contract. Such a Carr v J A Berriman Pty Ltd (1953) party is merely affirming the 89 CLR 327. existence of the contract to date, which has been breached, but is 2. As for instance in Cox v Franz then immediately electing not to (1987) 6 ACLR 33 and Wilson v Kirk affirm the contract any further and Contractors Pty Ltd (1991) 7 BCL 284, both of which are discussed in instead terminates the contract. In greater detail below. the case of contractual termination, that party is not terminating the 3. Lodder v Slowey (1904) AC 442; contract at all, rather, the contract Bolwell v Foley (1984) VR 97 per may well live on and the remedies Brooking J;Wilson v Kirk available are often pursuant to the Contractors Pty Ltd (1991) 7 BCL contract. The principles of common 284 per Ashley J; Renard law repudiation and contractual Constructions (1992) 26 NSWLR termination are, unfortunately, not 234 Meagher JA. But more recently so easily reconcilable.48 in GEC Marconi Systems Pty In the actual judgment of Laing Limited v BHP Information Management Ltd v Aegon (1997) 86 Technology Pty Limited (2003) FCA 50 Finn J observed in obiter at para BLR 70 Judge Humphrey Lloyd QC 666 that there is ‘an obvious lack of said that it is difficult to see how the coherence between the modern exercise of the power to terminate rationale of quantum meruit (i.e. could be anything other than an unjust enrichment) and the implementation of the contractual principles presently employed in terms and as such an affirmation in giving effect to it’ but his Honour legal terms. His Honour then cited was not required to rule on the from the judgment of Lord Goff in matter. The Kachenjunga (1990) 1 Lloyd’s Rep 391 at 398, where his Lordship 4. Laurinda Pty Ltd v Capalaba stressed the point that in cases of Park Shopping Centre Pty Ltd repudiation, an election must be (1989) 166 CLR 623 at 657 citing made, and if an election to affirm is Lord Wright in Ross T Smyth & Co made, then the right to elect to Ltd v T D Bailey, Son & Co (1940) terminate is waived or abandoned. 3 All ER 60 at p71. His Honour thus found that the
AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #97 JULY/AUGUST 2004 21
5. See for example AS2124 clause 1 WLR 277: (1980) 1 All ER 571, 39. (1991) 7 BCL 25 at 39. 44.4(b) ‘terminate the contract’ and discussed further below. 40. IN Duncan Wallace, Hudson’s HIA Plain English Contract clause 18. S Furst and V Ramsey, Keating Building and Engineering Contracts, 42 ‘bring contract to an end’. on Building Contracts, Sweet & (10th ed), London, Sweet & Despite the use of this language, it Maxwell, London 2001 at 189. Maxwell, 1970. is generally accepted that such termination is not ab initio but 19. IN Duncan Wallace, Hudson’s 41. This passage does not appear to merely in futuro—see McDonald v Building and Engineering Contracts, have been included in the 11th Dennys Lascelles Ltd (1933) 48 Sweet & Maxwell, London 1995. edition. CLR 457 at 476–477. 20. Of course, the owner would not 42. Architectural Installation 6. JW Carter, Breach of Contract, have been able to claim damages Services Ltd v James Gibbons (2nd ed, 1991) at 282. This general for repudiation if the contract had Windows Ltd (1989) 46 BLR 91 at rule is discussed in greater detail been validly terminated under the 100. below. provisions of the contract. 43. Hudson, page 1246. 7. As described in JM Hill & Sons 21. (1987) 6 ACLR 33 at 38. 44. The commentary in the Building Ltd v London Borough of Camden 22. (1991) 7 BCL 284 at 290. Law Reports seems critical of this (1980) 18 BLR 31, discussed below. case and suggests that the 23. (1991) 7 BCL 284 at 289. 8. As described in Goodwin v approach of the House of Lords in Faucet (1965) 175 Estates Gazette 24. (1991) 7 BCL 284 at 294. Gilbert-Ash is a better authority 27. 25. (1989) 46 BLR 91 at 100. (albeit in a different context) for the principle that express reservation of 9. (1971) 1 NSWLR 397 at 26. Sweet & Maxwell Ltd v common law rights was not 400–401. Universal News Services Ltd (1964) necessary. 10. (1971) 1 NSWLR 397 at 401. 2 QB 699 at 730. 45. See Lockwood Builders v John 11. JM Hill & Sons Ltd v London 27. (1964) 2 QB 699 at 734. Kim Rickwood (1995) 77 BLR 38 at Borough of Camden (1980) 18 BLR 28. (1964) 2 QB 699 at 737. 45–46 per Russell LJ. 31 at 44. 46. Keating, page 190. 29. See Cox v Franz (1987) 6 ACLR 12. Wilson v Kirk Contractors (1991) 33 at 38–39. 47. Laing Management Ltd v Aegon 7 BCL 284 at 296. 30. See Wilson v Kirk (1991) 7 BCL (1997) 86 BLR 70 at 76–77. 13. Kennedy v Collings Construction 284 at 291. 48. It is to be noted that the authors Company Pty Ltd (1991) 7 BCL 25 of Keating have not changed this 31. (1980) 1 All ER 571 at 574–575. at 37. passage from the previous edition 32. Carter observes that the Woodar 14. (1991) 7 BCL 25 at 37. the subject of the commentary. principle is a narrow one: Breach of 15. (1991) 7 BCL 25 at 37. Contract at 282. And Hudson states 49. Laing Management Ltd v Aegon that the case is a difficult one: see (1997) 86 BLR 70 at 108–110. 16. Lockland Builders v John Kim Rickwood (1995) 77 BLR 38 at 48. the note at the end of the summary of Woodar v Wimpey at page 620. 17. JW Carter, Breach of Contract Law Book Company, Sydney, 1991 33. Upheld on appeal by the House at 282. Carter cites a number of of Lords: Federal Commerce Ltd v authorities, including two High Molena Alpha Inc (1979) 1 ALL ER Court cases (Ogle v Comboyuro 307 and cited with approval by Lord Investments Pty Ltd [1976] 136 CLR Wilberforce in Woodar v Wimpey. 444 at 453 and Sibbles v Highfern 34. Dainford Ltd v Smith (1985) 155 Pty Ltd [1987] 164 CLR 214), both CLR 342 at 365. of which relate to contracts for the 35. Hudson, page 621. sale of land but he also notes that a wrongful but bona fide termination 36. See DTR Nominees Pty Ltd v may not necessarily give rise to Mona Homes Pty Ltd (1978) 138 repudiation, citing Woodar CLR 423 and Summers v Investment Development Ltd v Commonwealth (1919) 26 CLR 180. Wimpey Construction UK Ltd (1980) 37. (1987) 6 ACLR 33 at 38. 38. (1991) 7 BCL 284. 22 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #97 JULY/AUGUST 2004