You are on page 1of 12

CONTRACTS

THE TERMINATION OF INTRODUCTION The rights and wrongs of such a


BUILDING CONTRACTS: The common law of repudiation is case cannot be resolved without
complex, especially so in the delving into the full facts and
COMMON LAW circumstances surrounding the
context of building contracts. This
REPUDIATION V complexity arises in part because, alleged terminations and
CONTRACTUAL under the unitary theory of contract construing the relevant clauses in
TERMINATION law, the cases are drawn from a the context of the whole contract.
variety of commercial transactions, The victor might only emerge after
Romauld Andrew yet they are expected to have a long and protracted litigation, or
Barrister at Law general application. Most of the the court might find that neither of
Victorian Bar leading cases concern either the parties has terminated the
charter parties or contracts for the contract, either contractually or at
sale of land.1 The principles have common law, and further litigation
thus evolved in ways that try to is required.2 It is enough to make
accommodate the multitude of many of the cases settle prior to
commercial settings which may final determination.
give rise to disputes, whilst The result of termination, whether
maintaining, not always contractual or at common law, will
successfully, a coherent theory of usually be severe for the party who
general application. is ‘terminated’. Often a gross
Then there are the specific injustice may ensue. If, for instance,
provisions of building contracts a builder is in continual breach of its
which permit termination, or contract, perhaps because it under
determination, or forfeiture, or quoted for the works and will only
some other manner of bringing the make a loss on the job; and if,
contract, or the parties’ rights and through a mistake of its solicitors
obligations under the contract, to an the owner sends an invalid notice of
end. It is common in building cases termination, the builder will seize
that when a party attempts to upon this act to allege that the
terminate a contract pursuant to the owner has repudiated the contract
terms of the contract, the other and, accepting that alleged
party will counter with an allegation repudiation, purport to terminate
of repudiation and purport to the contract at common law. The
terminate the contract at common builder is then entitled to claim
law. damages on a quantum meruit.3 For
the owner, such a result, if reached,
Sometimes a party to a contract could be disastrous.
makes a mistake when attempting
to terminate under the provisions of While the leading cases are useful
the contract. The other party to the for providing general principles, few
contract might then allege if any are analogous, factually, in
repudiation and termination at the context of building contracts.
common law. When the first party Parties seeking guidance must
realizes or apprehends that it has resort, therefore, to cases of lesser
made a mistake in attempting to authority and hence less reliability
terminate under the provisions of a or certainty, especially at appellate
contract, and that its contractual level. Many of the relevant building
termination may therefore be cases are decisions of single
invalid, it may further allege that judges, often hearing appeals or
the other party alleging repudiation cases stated from arbitrators, so
is itself repudiating the contract, that the judgments are confined to
and purport to terminate the determining narrow questions,
contract at common law, as an often without the benefit of full
alternative to its contractual argument or citation of relevant
termination. authorities. These cases are seldom
reported in authorised reports—

AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #97 JULY/AUGUST 2004 11


The key question is what most are only to be found in clauses, but the actual words used
happens if a party sending specialist construction law reports. may include ‘determination’ or
‘forfeiture’ or ‘ending the
a notice of termination The general principles of
contractor’s employment’ and so
pursuant to the contract repudiation in Australian law are
on. In most cases the clause will
makes a mistake. The contained in the well known High
provide for either the employment
Court cases of Laurinda Pty Ltd v
general rule, according to Capalaba Park Shopping Centre of the builder to be ended, or for the
Carter, is that a wrongful Pty Ltd (1989) 166 CLR 623 and contract to be ended. In some cases
termination of the there is an option for either one of
Foran v Wight (1989) 168 CLR 385.
these courses.
performance of a contract The common law in this area is
will constitute a repudiation highly complex and it is not the aim Termination is a term often applied
of obligation. of this article to discuss repudiation to such clauses, but it is more
in detail. I wish merely to correct to speak of termination of
emphasise the following key points. obligations or termination of future
First, repudiation is a serious matter performance rather than
and is not to be lightly found.4 termination of the contract,
Generally speaking, repudiation because, upon termination, any
arises where a party is in breach of rights which have accrued at the
a fundamental term of the contract, time of the termination remain
or where by words or actions a enforceable, and it is only the
party evinces an intention to no parties’ future obligations which are
longer be bound by the contract. ended. Even then, in some cases,
Obvious examples in the context of after a termination, one party may
building contracts are where an be entitled to seek damages under
owner denies the builder access to the contract against the other party,
the site or engages another so that obligations under the
contract are ongoing. However,
contractor to carry out the works, or
some of the standard form
part of the works: as in Carr v J A
contracts now refer to termination
Berriman Pty Ltd (1953) 89 CLR
of the contract.5 And the
327. Or where a builder abandons
terminology is not precise or
the work and quits the site.
uniform in the cases either, the
In order to terminate the contract at terms rescission or determination
common law the innocent party being used synonymously with
must make, and communicate to termination.
the repudiating party, a clear and
The parties are generally free to
prompt election to accept the
agree to any provisions they wish
repudiation and terminate the
concerning termination, subject to
contract. Once the contract has
public policy, illegality and statute.
been thus terminated, it cannot be
It is also possible, but not common,
revived except by agreement of the
to make the contract provisions for
parties. If a contract is terminated
termination a self-standing ‘code’
pursuant to the contract
which excludes the common law. In
beforehand, then it will be too late
all cases, close examination of the
to accept the repudiation and
clause is required to ascertain the
terminate the contract—a contract
parties’ rights.
can only be terminated once. But if
the innocent party elects to affirm The key question is what happens if
the contract, then it has waived or a party sending a notice of
abandoned its rights to elect to termination pursuant to the contract
accept the repudiation and makes a mistake. The general rule,
terminate the contract. according to Carter, is that a
Building contracts usually contain wrongful termination of the
clauses dealing specifically with performance of a contract will
termination. For uniformity I shall constitute a repudiation of
refer to such clauses as termination obligation.6

12 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #97 JULY/AUGUST 2004


As is often the case, this general contrast is the approach adopted in Therefore, the court held that the
rule, whilst capable of being stated the same year (independently, it notice was invalid even though
simply, has not been found to be so would seem) in the English case of there was no dispute that the notice
easily applied to the facts in Goodwin v Faucet (1965) 175 had indeed been received by the
particular cases. As will be seen, Estates Gazette 27 per Stephenson builder through personal service.
some of the judgments have J who construed the relevant
Secondly, the court found that the
produced unusual results. contract in a ‘common sense
second notice had been given
businessman’ way when deciding
FAILURE TO COMPLY WITH whether a termination was
prematurely, and hence it too was
THE CONTRACTUAL invalid. On the facts of the case the
effective.
builder had until midnight on 14
PROVISIONS AND
The strict approach was applied by May to comply with the first notice,
INVALIDITY OF NOTICES Collins J in Eriksson v Whalley but the owner mailed the second
Because the effects of termination (1971) 1 NSWLR 397. In that case notice on 14 May, which was
will usually be severe a contractual the respondent builder challenged received by the builder on 15 May.
termination clause will be strictly the applicant owner’s notice Because this was sent within the 14
construed and, generally, a failure determining the builder’s day period, Collins J found that it
to comply with the provisions of the employment under the contract on was invalid, even though the
contract will mean that the three grounds, two of which are contract used the word ‘give’.
termination is invalid. But the relevant for present purposes: the Interestingly, His Honour found
question of how strictly one should first notice had been served that:
construe such clauses has met with personally on the builder’s
different approaches from the It would have been quite possible
foreman, rather than by registered for the builder to have effectively
courts. Broadly speaking there are mail as required under the relevant
two approaches, which may be discontinued his default after the
clause; and the second notice notice terminating his employment
described as the formalistic7 determining the builder’s
approach and the common sense had been sent to him.10
employment had been sent
business8 approach. prematurely. This strict approach was not
The formalistic approach construes followed by English Court of Appeal
The conclusions of this case are a
the contract very strictly, as in the in the case of JM Hill & Sons Ltd v
little difficult to understand. Collins
case of Re Stewardson Stubbs & London Borough of Camden (1980)
J observed that the provisions for
Collett v Bankstown Municipal 18 BLR 31. The facts of this case
determination in the contract gave
Council (1965) NSWR 1671 per are complex, but can be
the owner rights in excess of those
Moffitt J. In that case the contract summarised as follows. The
it would have had at common law,
provided that the owners were to plaintiff contractor claimed to be
and that it was reasonable to
give the builder 14 days written owed moneys under certificates
assume that the stringency of those
notice to remedy its default before issued by the architect. When the
provisions led to the formulation of
they could send a notice of employer did not pay, the
the principle that the power to
determination. The owners sent the contractor put in place a policy of
forfeit will be strictly construed.
first notice giving the 14 day notice ‘go slow’ but otherwise remained on
However, when applying that
required. However, on the 14th day site. Both parties sent notices to the
principle to facts of the case an
the owners sent the second notice other party. The Court of Appeal
unexpected result followed.
by registered mail terminating the found that the contractor’s conduct
contract ‘forthwith’. Moffit J held First, the court found that the did not in the circumstances amount
that the notice was invalid because contractual requirement for service to a repudiation, so that the owner’s
it was sent prematurely on the 14th of the first notice by registered mail attempt to terminate the contract
day, even though it was not received was not merely ‘directory’ as came to nothing.
by the builder until the 15th day. contended by the owner, but had to But the main issue was whether the
be strictly complied with to the contractor’s termination pursuant to
In reaching this decision Moffit J letter, in part because this method
placed emphasis on the precise the contract was valid. The
of service would eliminate to a employer raised a late point after
words of the relevant clause, large extent disputes about service,
specifically the word ‘give’ which, the appeal had been lodged,
and because service by registered namely, that the second notice had
when combined with the mail ‘imports a certain solemnity or
requirement for registered post, led been sent prematurely because it
importance to the giving of the had been sent by mail on 10 April.
His Honour to believe that the time notice which a more informal
ran from the time of posting. In Under the contract, the employer
method of service may not convey’.9 had until 10 April to remedy its

AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #97 JULY/AUGUST 2004 13


Giles J accepted that such default so the notice of termination, Kennedy v Collings Construction
provisions are to be strictly it was argued, should not have been Company Pty Ltd (1991) 7 BCL 25.
sent until 11 April. Eriksson v In that case Giles J had to consider
construed because of their
Whalley was relied upon in support whether the plaintiff owner had
serious consequences but of this argument. validly terminated the contract with
His Honour could see no the builder after a litany of defaults
The Court of Appeal allowed the
reason to give the relevant point to be raised, even though it
by the builder. The builder
clause a construction, under had not been raised before the
challenged the owner’s notice
the name of strictness, because it had not been sent by
Master or the Judge below, but
registered mail, although there was
which would ‘lead to the such leave appears to have been
no challenge to the fact that it had
unreal result that undisputed given merely to provide an
been received. Giles J found for the
receipt of the notice would opportunity to comprehensively and
owner, and after discussing the
unceremoniously dispense with the
be ineffective because the point. Lawton LJ said that the court
relevant provisions stated:
medium of registered post was not bound by Eriksson v But this does not mean that service
had not been used’. Whalley and appeared dismissive of a notice determining
of the case and described the point employment by registered post is
raised by the employer as necessary as well as sufficient. It
‘formalistic’. His Lordship found that does not seem likely that the
the date of sending the letter was parties to a contract in the form of
not important, it was the date of BC3 should have intended that a
receipt that was important.11 notice determining employment
Ormrod LJ went further, dismissing would be invalidly given if
Eriksson v Whalley and saying that personally served, or if placed in
the point was ‘farcical’ and, if the hands of the secretary of a
applied, would make a ‘mockery’ of corporate builder at its registered
the law. office. To adopt the words of
It might have been thought that the
Wootten J (at 622) in Spectra Pty
strict or formalistic approach of Re
Ltd v Pindari Pty Ltd (above) that
Stewardson and Eriksson v Whalley would place an absurd premium on
was thus a thing of the past, except
a particular form which could be of
that these cases were followed by
no benefit to anybody. In my view
Ashley J in Wilson v Kirk
the provision for registered mail
Contractors (1991) 7 BCL 284. In should be seen as facultative,
that case, the owners’ solicitor
permitting notice of determination
made several mistakes when trying
of the builder’s employment by
to terminate the contract. One of the
registered mail rather than by the
many issues under consideration
perhaps more onerous course of
was whether the owners’ second
personal service, but not obligatory.
attempt to send a notice of
As a matter of construction of the
termination was valid. This notice
June contract, I think it sufficient if
was sent by security post on the last
the notice determining the
day of the period prescribed by the
employment of the builder be given
relevant clause. Ashley J ruled that
by any other means which is shown
the notice was invalid and applied
to have resulted in receipt of the
both Re Stewardson and Eriksson v
notice by the builder. I therefore
Whalley.12 The case of JM Hill & reject this first answer.13
Sons Ltd v London Borough of Giles J accepted that such
Camden does not appear to have provisions are to be strictly
been brought to Ashley J’s construed because of their serious
attention. consequences but His Honour could
see no reason to give the relevant
The issue of whether the
clause a construction, under the
requirement for registered mail is
name of strictness, which would
‘mandatory’ was not raised in JM
‘lead to the unreal result that
Hill & Sons but it was raised in

14 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #97 JULY/AUGUST 2004


undisputed receipt of the notice Franz (1987) 6 ACLR 33. In that WRONGFUL TERMINATION,
would be ineffective because the case the second notice was given REPUDIATION, ERRONEOUS
medium of registered post had not during the period of default allowed
CONSTRUCTION AND GOOD
been used’.14 His Honour found that for under the relevant clause of the
the reference to ‘registered post’ is contract. Carmichael J held that the FAITH
explained by another clause which notice was, accordingly, invalid. And As seen above the general rule is
made service by ordinary post in Wilson v Kirk Contractors (1991) that a wrongful termination of the
sufficient service for the purposes 7 BCL 284 Ashley J, following Cox v performance of a contract will
of other notices or documents Franz reached the same result in constitute a repudiation of
under the contract: similar circumstances. These cases obligation.17 The same rule is
differ from Re Stewardson and stated, in similar terms, in Keating18
The reference therein to registered and Hudson19. The reasoning
post is adequately explained by Eriksson v Whalley because the
notices were given to the builder 2 behind this principle is logically
cl.25; its function is to make service consistent with the principles of
or 3 days prior to the expiry of the
by ordinary post, which would repudiation. For instance if a party
relevant period. Accordingly, it
otherwise be sufficient, insufficient. such as an owner denies a builder
follows logically that the notices
That is quite understandable, and access to the site and engages
were invalid.
reflects the importance of a notice another contractor to complete the
determining employment, but as I In Central Provident Fund Board v works, doing so in purported
have said it is a different thing again Ho Bock Kee (1981) 17 BLR 21 the reliance on an invalid termination,
to say that notice served by Court of Appeal of Singapore had to then that would ordinarily amount
registered post is not only sufficient determine whether an owner’s to repudiation.
but also necessary—not only termination was valid. In that case
permissible, but also obligatory.15 the relevant termination clause However, wrongfully terminating a
provided that the superintending contract should be distinguished
This approach is eminently from merely sending an invalid
sensible, but it is in conflict with officer could send a notice of
termination. But an earlier clause notice of termination. It is often
Eriksson v Whalley, which Giles J alleged by a party receiving an
said that if an action taken under
distinguished on a rather fine point. invalid notice of termination that the
certain clauses, including the
His Honour said: sending of the notice is itself
termination clause, was to occur,
Relevant to this matter is the then the Chairman of the Board repudiation. But that will not always
decision in Eriksson v Whalley must take that action. As the be the case. On the contrary, the
[(1971) 1 NSWLR 397], although I Chairman of the Board had not sent mere sending of an invalid notice of
was not referred to it. …It was held the notice of termination, the Court termination will in most cases not
that the service of the notice was of Appeal of Singapore held the amount to repudiation. It all
invalid, on the ground that the notice to be invalid. depends, of course, upon the facts
parties had agreed that service by of each case.
In Lockland Builders v John Kim
registered post was ‘imperative’, In Cox v Franz the court had to
not merely ‘directory’. But it is Rickwood (1995) 77 BLR 38 the
English Court of Appeal (Russell, consider whether sending an invalid
necessary to consider the notice amounted to a repudiation of
Hirst and Rose LJJ) held that the
provisions of the particular contract, the contract. In that case, the
owner’s termination was invalid
and given the distinction within cl.13 builder defendant had agreed in
because, contrary to the provisions
between notice and notice by 1975 to construct a home for the
of the contract, the architect had not
registered post, and the effect of plaintiff owner. After some months
certified the contractor’s default
cl.25, I do not think that Eriksson v the builder indicated that he would
prior to serving the notice. Indeed,
Whalley [above] requires a different be unable to complete the works
the owner had completely
conclusion from that I have stated without additional payment. Then
disregarded the contractual
above. he advised the owner of his concern
requirements and had attempted to
Not all failures to comply with the summarily dismiss the contractor that sub-contractors would enter
contractual requirements may be from site. Russell LJ expressed the house and destroy work done.
dispensed with. The most obvious some sympathy for the owner but The proprietor changed the locks
failure relates to the requirement to said that the owner only had but offered keys to some parts of
provide the specified period of time himself to blame.16 the house to the builder, but this
in which the defaulting party may offer was refused. The owner then
remedy their default. A notice which sent a notice of default, followed by
is given (and received) prematurely a notice of determination. However,
is invalid, as in the case of Cox v

AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #97 JULY/AUGUST 2004 15


I cannot see that because a the second notice was sent builder’s letter. The owners’
step so taken failed to prematurely and was held to be solicitors immediately replied with
invalid. Subsequently the owner 2 further letters. The first was sent
achieve its purpose the
locked the builder out of the site to the builder attaching a schedule
builder can turn his and the builder purported to accept of defects and purporting again to
continuing breach of the owner’s repudiation. The owner determine the contract, and again
contract into the proprietor’s subsequently denied liability and in denied access to the site. The
repudiation of that contract… turn sought damages from the second letter was sent to the
What the proprietor was builder for repudiation, tacitly builder’s solicitor and asserted that
conceding that the contractual the owners had not only
purporting to do was to rely
termination had gone awry.20 determined the contract under the
upon the contract itself to relevant clause but also pursuant to
achieve certain rights: there The builder argued that because
common law.
the owner’s notice was invalid, the
was certainly no repudiation owner was repudiating the contract The builder referred the matter to
of the contract. which repudiation he had accepted. arbitration. The arbitrator found
Carmichael J rejected the builder’s that the owners had not validly
argument, finding that the owner determined the contract, rather, the
had been doing all that he could to owners had repudiated the contract,
have the contract completed and which repudiation the builder had
therefore it was not possible to accepted. The owners, appealing
impute to him a repudiation of the from the findings of the arbitrator,
contract by taking steps under the contended that their letter did not
contract to obtain its completion: seek to repudiate the contract, but
I cannot see that because a step so to enforce it. Ashley J agreed,
taken failed to achieve its purpose finding that the denial of access to
the builder can turn his continuing the site and the indication of an
intention to engage another builder
breach of contract into the
were altogether consistent with the
proprietor’s repudiation of that
course of determination available
contract… What the proprietor was
under the contract.22 It might be
purporting to do was to rely upon
noted at this point that the acts of
the contract itself to achieve certain
denying access to the site and
rights: there was certainly no
indicating an intention to engage
repudiation of the contract.21
another builder are altogether
Similar issues arose in Wilson v consistent with repudiation.
Kirk (1991) 7 BCL 284 where the
After referring in detail and with
owners’ solicitor made several
evident approval to Cox v Franz the
mistakes when sending out the
court then found that the owners’
relevant notices, with the result that
solicitors’ letter of 18 July and the
the notices were held to be invalid.
actions which it previewed, should
The first notice of termination
be considered merely as an
included an assertion that the
ineffective attempt by the owners to
contract was determined, but it also
rely upon and enforce the contract
asserted that access to the site was
and not as a repudiation. The court
denied and that the owners would
found that the arbitrator had erred
be engaging another contractor to
in finding that the sending of this
rectify and complete the works. The
letter itself amounted to
builder, who had been in default
repudiation. The arbitrator’s finding,
under the contract, alleged in a
however, was that:
letter that the owners had
themselves repudiated the contract The proprietors by their action and
and accepted the owners’ general conduct not to be bound
repudiation. by the contract amounted to a
As Ashley J observed, it must have repudiation of the contract.
come as a ‘rude shock’ to the (emphasis added)23
owners’ solicitors to receive the

16 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #97 JULY/AUGUST 2004


This judgment raises some a valid termination under the agreement by contentious
important questions. First, if the contract, rather, it was an unlawful observations in the course of
termination was not valid, then on repudiation of the contract.25 discussions or arguments as to the
what legal basis were the owners
In Mersey Steel & Iron Co v Naylor
provisions to be inserted into the
entitled to exclude the builder from
Benzon & Co (1884) 9 App Cas 434 lease.27
site and engage another
purchasers formed an erroneous Buckley J agreed and also added
contractor? What remedy, if any,
construction as to a contract for the the element of good faith.28 This
does this leave the builder,
sale of goods, and believed that case is useful for general principles
remembering that in this case the
they could not pay for goods when a but does not assist in the case
court found that it was very doubtful
petition for winding up had been where a party, acting on an
that the builder’s defaults
served, without the sanction of the erroneous belief, conducts itself in
constituted a repudiation of the
court. They applied for an order of a manner which would otherwise
contract.24 These questions are not
the court, and this conduct was held give rise to repudiation. For
answered in the judgment probably
not to be repudiatory, the instance, if an owner misconstrues
because, having answered the
purchasers conduct being bona fide. a contract, and erroneously
narrow questions on appeal, the
In Sweet & Maxwell Ltd v Universal believes the contract has been
court remitted that matter back to
News Services Ltd (1964) 2 QB 699 validly terminated, and then acts in
the arbitrator for further hearing.
the English Court of Appeal a manner which on any objective
The answer would seem to be, rejected an allegation that an view must be repudiatory, such as
however, that merely sending an erroneous construction of a lease denying access to the site and
invalid notice of termination will not agreement gave rise to repudiation. engaging another contractor, then
in itself amount to a repudiation, Harman LJ said: there must, logically, be a
such an action being conduct repudiation.
evincing an intention (albeit …I do not think that a person who
That is what happened in Cox v
erroneously founded) to rely on the maintains his view of the
construction of what is, after all, a Franz. Because the court found that
contract. But if that party persists in the owner’s purported termination
relying on the wrongful termination, not very perspicuous document is
was invalid, then the owner was
then that conduct must, at least as a repudiating because he says ‘my
breaching fundamental terms of
matter of logic or common sense, view of it is this, and this I will do’
the contract. Was not the builder in
amount to repudiation. The leading and the other man says ‘well, my
that case entitled to accept the
authority for this principle is Lodder view is different’. Let them go to the
repudiation, and if not, why not?
v Slowey (1904) AC 441 in which the court and have the matter
Privy Council held that where a determined as they can. But to In Cox v Franz the court found that
party to a contract for execution of seize upon an attitude of that sort the owner had not repudiated the
works wrongfully re-enters and and call it repudiation in order to contract and hence the builder was
seizes the works in progress, then serve an object which was then of not entitled to accept a repudiation.
the contractor may treat the course dear to the hearts of the Carmichael J placed great reliance
contract as at an end and sue for plaintiffs, who wanted to get rid of on Sweet & Maxwell Universal
work and labour done. this deed, is not in my opinion News Services Ltd.29
justified…26 A similar approach was taken in
In Architectural Installation
Services Ltd v James Gibbons Pearson LJ agreed: Wilson v Kirk. In that case Ashley J
Windows Ltd (1989) 46 BLR 91 a cited at length and with evident
Moreover, even if they had taken an
builder sent a notice requiring a approval from the judgment in Cox
erroneous view as to the effect of
sub-contractor to work a full day as the agreement, it would not follow v Franz and His Honour also
required under the contract. Some applied the principle that ‘where a
that the expression of an erroneous
eleven months later the builder party takes action relying on the
view or the taking of an erroneous
sent a telex to the sub-contractor terms of the contract, not
objection to some clause proposed
purporting to terminate the contract manifesting by his conduct an
to be inserted in the lease would
because the sub-contractor had ulterior intention to abandon it, he
amount to a repudiation of the
withdrawn its labour. The Official should not be treated as having
agreement for a lease… In the last
Referee (Judge Bowsher QC) found repudiated it’.30 Ashley J placed
resort, if the parties cannot agree,
that there was no sensible great reliance for this principle on
the true construction will have to be
connection between the first notice the case of Woodar Investment
determined by the court. A party
and the telex, either in time or should not too readily be found to Development Ltd v Wimpey
content. Accordingly, it was held have refused to perform the Construction UK Ltd (1980) 1 WLR
that the sending of the telex was not 277: (1980) 1 All ER 571 and

AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #97 JULY/AUGUST 2004 17


accordingly that case warrants have been if Woodar had construction of a contract does not
examination. immediately treated Wimpey’s necessarily give rise to repudiation.
rescission notice as evincing an Stephen, Mason and Jacobs JJ
Woodar Investment Development
intention by Wimpey to no longer be stated the position thus:
Ltd v Wimpey Construction UK Ltd
bound by the contract, which it
concerned a contract for the sale of But there are other cases in which a
accepted, rather than seeking a
land by Woodar to Wimpey. The party, though asserting a wrong
declaration from the court, and had
contract provided that Wimpey view of a contract because he
then sold the land to another party?
could rescind the contract if any believes it to be correct, is willing to
If that were the case, Wimpey’s
public authority commenced perform the contract according to
conduct might well be seen as
compulsory acquisition prior to its tenor. He may be willing to
repudiatory because it did not
settlement. Wimpey sought to rely recognize his heresy once the true
subsequently affirm the contract.
on the fact that compulsory doctrine is enunciated or he may be
acquisition for part of the land had What makes the case interesting is willing to accept an authoritative
commenced and sent notice the fact that Woodar challenged the exposition of the correct
rescinding the contract. Woodar validity of the rescission notice and, interpretation. In either event an
challenged the notice on the basis even assuming an election were intention to repudiate the contract
that the acquisition had already available, elected to proceed with could not be attributed to him. As
commenced when the parties the contract and sought the Pearson LJ observed in Sweet &
signed the contract, and that the intervention of the court. And Maxwell Ltd v Universal News
rescission clause only related to Wimpey, rather than persisting in Services Ltd (1964) 2 QB 699, at
compulsory acquisition commenced conduct which might give rise to p.734:
after the contract was signed. repudiation (other than adhering to ‘In the last resort, if the parties
Woodar brought an action against its view of the contract) sought the cannot agree, the true construction
Wimpey seeking a declaration that intervention of the court, thus will have to be determined by the
Wimpey was not entitled to rescind affirming the contract. In these court. A party should not too readily
the contract. Wimpey in its defence circumstances, both parties can be be found to have refused to perform
seen as affirming the contract.
and counterclaim sought a the agreement by contentious
declaration that it was entitled to The facts of Woodar are clearly observations in the course of
rescind the contract. Then Woodar distinguishable from cases such as discussions or arguments...’
brought a further action alleging Cox v Franz or Wilson v Kirk where (at p.432)
that, by the notice of rescission and the erroneous party proceeded to
The important distinction, therefore,
its defence and counterclaim, take steps which would, on ordinary
which must be drawn between
Wimpey had repudiated the common law principles, give rise to
these cases is the difference
contract which was accepted and a repudiation, and which would
between asserting an erroneous
damages were claimed. actually prevent the contractor
construction on the one hand, and
from performing the contract.32 See
The House of Lords upheld an proceeding on an erroneous
also Federal Commerce Ltd v
appeal by Wimpey, finding that it construction on the other hand. This
had not repudiated the contract.
Molena Alpha Inc (1978) 1 QB 927 is no mere semantic distinction. In
in which ship owners’ instructions to
Lord Wilberforce found that in the latter case, the general rule
the masters of their vessels, based
considering whether there has been should apply, and the wrongful
on an erroneous construction of the
repudiation by a party it is termination should, in theory at
charter party, were held by the
necessary to look at his conduct as least, give rise to repudiation. As
English Court of Appeal to be so
a whole. Lord Wilberforce found Brennan J stated in Dainford Ltd v
serious in their effect on the
that both parties were asserting a Smith (1985) 155 CLR 342:
charterers that they amounted to
contrary construction of the Sometimes it is right to find that a
repudiation.33
contract, and that each party was party who adopts an erroneous
allowing the court resolve the issue, The High Court has considered the construction of a contract and who
and accordingly there was no issue in DTR Nominees Pty Ltd v intends to act in accordance with
repudiation by Wimpey.31 Lords Mona Homes Pty Ltd (1978) 138 that construction in fulfilling the
Keith and Scarman followed Lord CLR 423, another case involving a contract is not ready and willing to
Wilberforce’s reasoning, Lords contract for the sale of land. The perform the contract and has
Russell and Salmon dissenting. principle from that case, consistent evinced an intention to perform the
This is an interesting case and with Sweet & Maxwell and Woodar contract only in a manner
raises its own issues. Consider, for v Wimpey, is that an erroneous substantially inconsistent with its
example, what the result might terms.34

18 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #97 JULY/AUGUST 2004


And as is pointed out in Hudson, But, in most cases, one party or the And as is pointed out in
differences of interpretation as to a other will be seeking to enforce Hudson, differences of
party’s obligations under the their legal rights against each other
interpretation as to a party’s
contract, should they come to a so that they cannot be said to have
head, will render a party in real abandoned the contract. obligations under the
peril of a successful adverse Accordingly, if the reasoning of Cox contract, should they come
rescission should his interpretation v Franz and Wilson v Kirk is to make to a head, will render a party
prove to be incorrect, assuming that sense, then some explanation of in real peril of a successful
he has, as a result of acting on that these open ended questions needs adverse rescission should
interpretation, prejudiced the to be provided.
his interpretation prove to be
further performance of the contract,
quite apart from the obvious cases
CONCURRENT ACTION? incorrect...
where he may have been led into —CONTRACTUAL
prematurely rescinding or TERMINATION V COMMON
terminating or abandoning the LAW TERMINATION
contract himself.35 The question often arises whether a
By this reasoning, the conclusions notice of termination may be given
reached in Wilson v Kirk and Cox v both under the provisions of the
Franz are, with respect, unhelpful. contract and pursuant to common
Moreover, these judgments leave law. Usually this is alleged in order
open the question, what happens to to salvage a termination because
the contract in such cases? there has been some defect in the
Logically, the contract must still be contractual notice. Thus, in Cox v
live, as neither party has validly Franz the owner sought to rely on a
terminated it. But the owner will common law termination because
have denied the builder access and the notice was not valid under the
engaged another contractor. Does contract. The court held that, where
the contract merely expire by a contractual notice has been sent,
operation of some as yet the owner was affirming the
unannunciated principle? Is the contract, and could not therefore
contractor entitled to sue for breach also accept repudiation.37 The same
of contract with damages being the argument was raised in Wilson v
loss of profit which would have Kirk in which case the court adopted
been earned? What if the new the reasoning of Carmichael J in
contractor starts work but then Cox v Franz.38 See also Bysouth v
abandons the site, can the owner Shire of Blackburn and Mitcham
seek to enforce the contract against (No 2) [1928] VLR 562.
the original builder? These In Kennedy v Collings Construction
questions are more than academic, Pty Ltd (1991) 7 BCL 25, however,
they frequently arise in practice and Giles J found that it was open for
the case law does not, it is the owners to ‘exercise both the
submitted, adequately deal with the contractual power to determine the
issues. employment of Collings and the
One possibility may arise where the common law entitlement to accept
builder, having purported to accept the repudiation’.39 Giles J cited
the owner’s repudiation, does Summers v The Commonwealth
nothing more, that is to say, does (1918) 25 CLR 144; Bysouth v Shire
not issue proceedings against the of Blackburn and Mitcham (No 2)
owners seeking damages. If the [1928] VLR 562; and Hudson (10th
owners do not sue the builder, but ed) at 687 in support of this finding.
merely complete the works using The question may not be as easily
another contractor, then the parties resolved as that, however.
may be said to have mutually The passage referred to by Giles J
abandoned the contract.36 in Hudson (10th ed) reads as
follows:

AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #97 JULY/AUGUST 2004 19


It is an open question It may, however, be noted here that However, in Lockwood Builders v
whether an employer, faced a given event may be both one John Kim Rickwood (1995) 77 BLR
which justifies the innocent party in 38 the English Court of Appeal
with default by the
treating the contract as repudiated, (Russell, Hirst and Rose LJJ)
contractor which might both and also one upon the happening of rejected an owner’s argument that
amount to repudiation and which an express forfeiture clause the notice, which was held to be
entitle the employer to may be invoked. In such a case, invalid under the contract, was a
operate a contractual unless the contract shows an common law acceptance of the
determination clause, can explicit intention that the stipulated builder’s repudiation, saying that in
remedy should exclude the the absence of express words to the
hedge his position so as to
ordinary remedies, the innocent contrary, the contractual provisions
avail himself of both party may make an election. He excluded common law rights.44 The
opportunities. may simply treat the contract as Court of Appeal did not follow
repudiated and rely upon the Architectural Installation Services v
remedies available upon James Gibbons Windows Ltd on this
repudiation under the general law, point.45 Other cases which have
or he may proceed under the rejected the alternative submission
forfeiture clause and avail himself are: E R Dwyer v Simon Build/Peter
of the rights contained therein. Lind Partnership (1982) 23 BLR 23
Indeed, there would seem to be no and Mvita Construction Co Ltd v
reason why he should not enforce Tanzania Harbours Authority (1988)
both sets of remedies 46 BLR 19.
simultaneously and cumulatively.40 The question is addressed in
The last sentence might need to be Keating as follows:
reconsidered, because the rights It is an open question whether an
under the contract might be employer, faced with default by the
different from the rights at common
contractor which might both
law, the party receiving the notice is
amount to repudiation and entitle
entitled to know, unequivocally,
the employer to operate a
which remedies will be available or
contractual determination clause,
pursued.41
can hedge his position so as to avail
In Architectural Installation himself of both opportunities.
Services Ltd v James Gibbons Logically, this may not be possible,
Windows Ltd (1989) 46 BLR 91 since to operate the contract is to
Judge Bowsher QC, hearing a affirm it, which is inconsistent with
preliminary issue, found that the accepting a repudiation.46
owner’s notice of termination, whilst
This reasoning was criticised in the
it did not comply with the contract
commentary to Laing Management
and was therefore invalid, may
Ltd v Aegon (1997) 86 BLR 70:
nevertheless have been a common
law acceptance of the builder’s This is no conundrum at all if what
repudiation, subject to the ultimate is truly happening is described
findings on trial.42 And in the current without the use of the traditional
edition of Hudson the following terminology. The exercise of an
passage appears: express power of termination is an
affirmation of the contract, but is
…in the absence of express also an election to terminate the
provision, contractual future employment of the
determinations by either party are contractor. An election to accept a
not intended as a substitute for, or repudiatory breach is also an
to exclude, the common law rights election to terminate the future
to rescind. While some standard employment of the contractor and
form determination clauses contain all executory obligations of both
express ‘without prejudice to other parties. Since it involves an
rights or remedies’ wording, this is assertion that the other party is in
not in fact necessary…43

20 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #97 JULY/AUGUST 2004


breach of contract it is also an letter, which specifically, relied Such a party is merely
affirmation of the contract… upon the contractual clause for affirming the existence of the
terminating the builders
The possible dilemma posed in contract to date, which has
employment, was not a common
Keating on Building Contracts… is been breached, but is then
law acceptance of termination.49
therefore, it is submitted, not a real immediately electing not to
dilemma.47 Whilst each case must be
determined upon its own particular
affirm the contract any
This reasoning is superficially further and instead
attractive, but, upon closer analysis, facts, it is submitted that the views
of Judge Humphrey Lloyd QC in terminates the contract.
unsound. First, as mentioned above,
the party receiving the notice is Laing Management Ltd v Aegon
entitled to know which method is (1997) 86 BLR 70 correctly states
being used because it may affect the principle. The question still
the remedies available. But that remains open for further debate
party is also entitled to know which before the courts, especially in
method is being relied on so that, if Australia.
it wishes to challenge the REFERENCES
termination, it knows what grounds 1. For example, Hong Kong Fir
might be successful. Finally, it Shipping Co Ltd v Kawasaki Kisen
simply does not follow, as a matter Kaisha Ltd (1962) 2 QB 26 and
of logic, that in accepting a Foran v Wight (1989) 168 CLR 385.
repudiation a party is thereby also A building contract is the subject of
‘affirming’ the contract. Such a Carr v J A Berriman Pty Ltd (1953)
party is merely affirming the 89 CLR 327.
existence of the contract to date,
which has been breached, but is 2. As for instance in Cox v Franz
then immediately electing not to (1987) 6 ACLR 33 and Wilson v Kirk
affirm the contract any further and
Contractors Pty Ltd (1991) 7 BCL
284, both of which are discussed in
instead terminates the contract. In
greater detail below.
the case of contractual termination,
that party is not terminating the 3. Lodder v Slowey (1904) AC 442;
contract at all, rather, the contract Bolwell v Foley (1984) VR 97 per
may well live on and the remedies Brooking J;Wilson v Kirk
available are often pursuant to the Contractors Pty Ltd (1991) 7 BCL
contract. The principles of common 284 per Ashley J; Renard
law repudiation and contractual Constructions (1992) 26 NSWLR
termination are, unfortunately, not 234 Meagher JA. But more recently
so easily reconcilable.48 in GEC Marconi Systems Pty
In the actual judgment of Laing
Limited v BHP Information
Management Ltd v Aegon (1997) 86 Technology Pty Limited (2003) FCA
50 Finn J observed in obiter at para
BLR 70 Judge Humphrey Lloyd QC
666 that there is ‘an obvious lack of
said that it is difficult to see how the
coherence between the modern
exercise of the power to terminate
rationale of quantum meruit (i.e.
could be anything other than an
unjust enrichment) and the
implementation of the contractual
principles presently employed in
terms and as such an affirmation in
giving effect to it’ but his Honour
legal terms. His Honour then cited
was not required to rule on the
from the judgment of Lord Goff in
matter.
The Kachenjunga (1990) 1 Lloyd’s
Rep 391 at 398, where his Lordship 4. Laurinda Pty Ltd v Capalaba
stressed the point that in cases of Park Shopping Centre Pty Ltd
repudiation, an election must be (1989) 166 CLR 623 at 657 citing
made, and if an election to affirm is Lord Wright in Ross T Smyth & Co
made, then the right to elect to Ltd v T D Bailey, Son & Co (1940)
terminate is waived or abandoned. 3 All ER 60 at p71.
His Honour thus found that the

AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #97 JULY/AUGUST 2004 21


5. See for example AS2124 clause 1 WLR 277: (1980) 1 All ER 571, 39. (1991) 7 BCL 25 at 39.
44.4(b) ‘terminate the contract’ and discussed further below.
40. IN Duncan Wallace, Hudson’s
HIA Plain English Contract clause 18. S Furst and V Ramsey, Keating Building and Engineering Contracts,
42 ‘bring contract to an end’.
on Building Contracts, Sweet & (10th ed), London, Sweet &
Despite the use of this language, it
Maxwell, London 2001 at 189. Maxwell, 1970.
is generally accepted that such
termination is not ab initio but 19. IN Duncan Wallace, Hudson’s 41. This passage does not appear to
merely in futuro—see McDonald v Building and Engineering Contracts, have been included in the 11th
Dennys Lascelles Ltd (1933) 48 Sweet & Maxwell, London 1995. edition.
CLR 457 at 476–477. 20. Of course, the owner would not 42. Architectural Installation
6. JW Carter, Breach of Contract, have been able to claim damages Services Ltd v James Gibbons
(2nd ed, 1991) at 282. This general for repudiation if the contract had Windows Ltd (1989) 46 BLR 91 at
rule is discussed in greater detail been validly terminated under the 100.
below. provisions of the contract.
43. Hudson, page 1246.
7. As described in JM Hill & Sons 21. (1987) 6 ACLR 33 at 38. 44. The commentary in the Building
Ltd v London Borough of Camden 22. (1991) 7 BCL 284 at 290. Law Reports seems critical of this
(1980) 18 BLR 31, discussed below. case and suggests that the
23. (1991) 7 BCL 284 at 289.
8. As described in Goodwin v approach of the House of Lords in
Faucet (1965) 175 Estates Gazette 24. (1991) 7 BCL 284 at 294. Gilbert-Ash is a better authority
27. 25. (1989) 46 BLR 91 at 100. (albeit in a different context) for the
principle that express reservation of
9. (1971) 1 NSWLR 397 at 26. Sweet & Maxwell Ltd v common law rights was not
400–401. Universal News Services Ltd (1964) necessary.
10. (1971) 1 NSWLR 397 at 401. 2 QB 699 at 730.
45. See Lockwood Builders v John
11. JM Hill & Sons Ltd v London 27. (1964) 2 QB 699 at 734. Kim Rickwood (1995) 77 BLR 38 at
Borough of Camden (1980) 18 BLR 28. (1964) 2 QB 699 at 737. 45–46 per Russell LJ.
31 at 44. 46. Keating, page 190.
29. See Cox v Franz (1987) 6 ACLR
12. Wilson v Kirk Contractors (1991) 33 at 38–39. 47. Laing Management Ltd v Aegon
7 BCL 284 at 296.
30. See Wilson v Kirk (1991) 7 BCL (1997) 86 BLR 70 at 76–77.
13. Kennedy v Collings Construction 284 at 291. 48. It is to be noted that the authors
Company Pty Ltd (1991) 7 BCL 25 of Keating have not changed this
31. (1980) 1 All ER 571 at 574–575.
at 37.
passage from the previous edition
32. Carter observes that the Woodar
14. (1991) 7 BCL 25 at 37. the subject of the commentary.
principle is a narrow one: Breach of
15. (1991) 7 BCL 25 at 37. Contract at 282. And Hudson states 49. Laing Management Ltd v Aegon
that the case is a difficult one: see (1997) 86 BLR 70 at 108–110.
16. Lockland Builders v John Kim
Rickwood (1995) 77 BLR 38 at 48. the note at the end of the summary
of Woodar v Wimpey at page 620.
17. JW Carter, Breach of Contract
Law Book Company, Sydney, 1991 33. Upheld on appeal by the House
at 282. Carter cites a number of of Lords: Federal Commerce Ltd v
authorities, including two High Molena Alpha Inc (1979) 1 ALL ER
Court cases (Ogle v Comboyuro 307 and cited with approval by Lord
Investments Pty Ltd [1976] 136 CLR Wilberforce in Woodar v Wimpey.
444 at 453 and Sibbles v Highfern 34. Dainford Ltd v Smith (1985) 155
Pty Ltd [1987] 164 CLR 214), both CLR 342 at 365.
of which relate to contracts for the
35. Hudson, page 621.
sale of land but he also notes that a
wrongful but bona fide termination 36. See DTR Nominees Pty Ltd v
may not necessarily give rise to Mona Homes Pty Ltd (1978) 138
repudiation, citing Woodar CLR 423 and Summers v
Investment Development Ltd v Commonwealth (1919) 26 CLR 180.
Wimpey Construction UK Ltd (1980) 37. (1987) 6 ACLR 33 at 38.
38. (1991) 7 BCL 284.
22 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #97 JULY/AUGUST 2004

You might also like