You are on page 1of 10

CONSTRUCTION CONTRACTS

THE SEEDS OF INTRODUCTION arrangement that involves a time


DISPUTES IN DESIGN & Construction contracts are or cost bonus.
concerned with the prediction and
CONSTRUCT CONTRACTS management of very complicated
So, why do principals put the fox
in charge of the chicken coup?
James Forrest, Partner future events.
The first reason is the availability
Mallesons Stephen Jaques In a design and construct of resources.
relationship, one party, the
principal, has an idea (such as Many principals do not have the
the appearance of a building) or a internal resources to undertake
goal (such as the production of a major construction projects.
certain profit level) and requires Their resources are generally
another party (the contractor) supplemented either by retaining
to bring that idea into reality or an external project manager to
achieve that goal. undertake the co-ordination of
design and to administer the
In order to do so thousands construction of the project; or by
of designs must be produced, entrusting all material tasks to
hundreds of people organized, a contractor as a single point of
governments managed, weather responsibility.
and geological conditions
overcome and the labour market In the latter case the contractual
pacified. In addition there are responsibility of the contractor is
many unforeseeable issues that not limited to co-ordination.
will arise and might be the bases The contractor assumes a
of disputes. contractual responsibility to carry
Into this maelstrom arrives the out the design itself. Of course
contract draftsman who, it is in practice it will discharge
hoped, will bring certainty to that responsibility by retaining
chaos. consultants, most of whom will be
novated from the principal.
The purpose of this paper is to
examine some of the difficulties The second and often more
confronted by the draftsman in dominant reason is the risk profile
preparing design and construct demanded by the principal and
contracts and some of the areas its bankers or equity investors
that are particularly susceptible to requires that the total risk of the
disputes in design and construct design and construct process be
contracting. allocated to a single party with
a substantial balance sheet and
WHY DESIGN AND insurance policies.
CONSTRUCT? If the principal remains
In its very essence the concept of responsible for the production of
a design and construct contract the design it will assume the risks
involves a conflict of interest. associated with the performance
Principals desire to have of the design consultants and
constructed a product of the best other vicissitudes such as
possible quality for the lowest complications with government
possible price. authorities and geological
conditions.
The contractor however is more
likely to make a higher profit if the It is a perceived advantage of
product is of a lower quality (and design and construct contracts
therefore, cost) and a higher price that the risk of the timely
(as opposed to cost). delivery of a quality project within
budget is seamlessly achieved
While that position is self
by allocating most risks and
evident in a lump sum contract,
responsibilities to a design and
it is actually present in any
construct contractor.
50 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #104 SEPTEMBER/OCTOBER 2005
In a legal sense, those risks The selection of the design and play in ensuring that a successful
can be reduced by allocating construct process will inevitably outcome is achieved.
responsibility for many of result in a loss of control of
the tasks in the design and decision making power in respect THE FUNDAMENTAL
construction process to the of some of the key project issues. OBLIGATION
contractor. The consultants cease to answer In broad terms, design and
to and be controlled by the construct contracts are formed in
Notwithstanding the imperatives one of two circumstances:
principal; rather, they answer to,
listed above it remains the case
are paid by and are instructed by • where no material design and
that the design and construct
the contractor. While the general construction activities have been
process involves a fundamental
nature of the project will not be undertaken by the principal; or
conflict of interest which is the
altered, under the design and
ultimate source of disputes. • where material design and
construct model, final decisions
The decision of the principal construction activities have been
relating to aesthetics and quality
should be made with that undertaken by the principal.
will be substantially influenced by
underlying risk clearly in mind. the discretion of the contractor. It will be extremely rare that the
In addition, there are a number principal has not undertaken
Indeed, many of the issues
of other inherent factors that any tasks related to the design
that are the subject of such
contribute to the susceptibility of and construction of the project.
discretions might never be known
the design and construct process Usually the principal will at least
by the principal.
to dispute. have obtained a development
This loss of control restricts the approval from the relevant
Firstly, the passing of risk is often ability of the principal to manage authority and, in order to do that,
accompanied by the abrogation problems as they arise and can will have prepared a reasonable
of responsibility and the loss of lead to a build up of issues that amount of design.
control. are only recognized late in the
The selection of the options set
The passing of risk does not project when they cannot be
out above will be dependent on
assure an optimal project resolved in a practical way to the
the timing of the appointment
outcome. satisfaction of the principal.
of the design and construct
It does no more than give rise The loss of control also strikes contractor and the extent to which
to potential legal defences and at a key expectation of most the principal wishes to retain
claims, which are themselves principals, who, rightly, regard the control over the design of the
uncertain and unsatisfactory. project as ‘my project’. project.
While a contract might As will be discussed in more In both cases, the fundamental
contain an elaborate system detail in the section of this paper obligation is to design and
of promises, procedures and concerned with the project construct something. The
time bars, ultimate reliance brief, this mindset is at odds ‘something’ is supposed to be
on them is affected by many with the allocation of risks and particularised in the project brief.
factors, including lapses in the responsibilities to the contractor. The role of the project brief is
administration of the contract, The project will always remain in discussed in greater detail in
the performance of witnesses the ownership of the principal, section 4 of this paper, however,
in Court, the vagaries of the but what it looks like and how it for present purposes it must
judicial mind and, perhaps most works are materially within the be noted that the project brief
importantly, the will of those control of the contractor in the is the central document in the
involved to endure the trauma and design and construct process. design and construct process.
cost of the litigation process. The core obligation of the design
In advising clients in relation to and construct contractor is to
In an even more essential sense the appropriate delivery system, design and construct the project
the principal must appreciate it is important that they are aware in order to fulfil the requirements
that the right to sue a design and of all of the above factors. In of the project brief. All contractual
construct contractor is of little particular, clients must accept arrangements must be aligned to
comfort if the project has been that the selection of the design achieve that outcome.
unsuccessfully implemented. and construct model does not
Legal action can rarely result in permit them to wash their hands I want the Royal Hawaiian
the achievement of the principal’s of the delivery of the project but, The following conversation
initial commercial goals in rather, alters the role they must occurred in relation to a project
undertaking the project.
AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #104 SEPTEMBER/OCTOBER 2005 51
with which a colleague of mine described below, where the the agreement can be terminated
was involved on the Gold Coast. seamlessness of risk profile can at an appropriate time.
only be achieved by the somewhat
The design and construct • The principal must maintain a
artificial deeming of responsibility
contractor, pointing at an empty role in the selection and retention
for past acts undertaken by the
block of land, asked the Japanese of consultants.
principal.
client (in a somewhat exasperated • The design approval process
tone): In general terms, there are two should be stipulated with
disadvantages, both of which
Well what do you want your hotel considerable care, allowing
increase the likelihood of a
to be like? adequate, but not excessive,
dispute. times for the principal to assess
The Royal Hawaiian, was the only
Firstly, the clarity and specificity designs.
reply.
of the project brief will often be • As soon as possible, a cost
For those who don’t know, the diminished if it is prepared at plan should be produced, and
Royal Hawaiian is a rather famous a time when the parties do not thereafter continually refined so
hotel in Hawaii. For the Japanese have a mature understanding that design and construction are
client, that was enough for a of the project. That uncertainty driven by the economic feasibility
project brief. The fact that the can make it difficult to sensibly of the project, rather than
Royal Hawaiian is a low rise hotel stipulate the aesthetic, time, cost aesthetic extravagance.
in the northern hemisphere did and quality requirements for the
not seem to concern the client, project which, in turn, will lead to • Similarly, from an early point,
who had obtained a development the misalignment of the parties’ a design and, thereafter, design
approval for a high rise hotel in expectations. and construction program should
the southern hemisphere. be produced so that all parties
Secondly, the principal will can work to an agreed, achievable
The response of the client in that effectively cede control of the timetable.
situation, while humorous, was design process from an early
not unusual. point. The project might effectively • It must be clear that ownership
become the project of the of intellectual property vests in
It reflects the difficulty in
contractor and the principal may the principal (through legally
conveying an accurate and
be relegated to a monitoring and effective means) and that the
comprehensive understanding
verification role. principal can use the designs if
of the principal’s requirements,
the contract is terminated.
particularly at an early stage In a situation where the design
when a limited amount of concept and construct obligations are to • Consultancy agreements must
design has been completed. be assumed by the contractor at be prepared on the basis that the
an early stage, the fundamental principal can step into them if the
The decision to appoint the
role of the design and construct design and construct contract is
contractor at an early stage has a
contract is to manage the terminated.
number of advantages.
uncertainty which is inherent • The means by which the
Firstly, from a practical point of in that delivery process and contract sum is determined
view, the project can be run by a ameliorate the principal’s control must be considered with care.
sole point of control from start to of key issues. If the contractor is retained at a
finish, which will usually result
in improved co-ordination and That management can be very early stage it might not be
achieved by particularly focussing possible to sensibly agree on a
greater efficiency, particularly in
on a number of key elements in lump sum at the time of entering
the timeliness of completion.
the contract. into the contract. If that is so,
Secondly, there will be a then alternative systems must
realistic allocation of risk and • The project brief must be be considered. If it is not feasible
responsibility in a seamless way. prepared with particular care to to agree on a lump sum, then
While the contractor will bear the ensure that as much objective any proposed alternatives must
risk of the majority of activities, it guidance as possible is provided, first be approved by the project
will actually have responsibility for particularly in relation to lenders.
undertaking those activities and performance requirements.
In summary, in this situation, the
will have the contractual means • The engagement of the design design and construct contract
of obliging the consultants and and construct contractor can be must be drafted to recognise
subcontractors to perform. This is on a staged basis so that, if the
to be contrasted with the situation the evolutionary nature of the
relationship is not working out, relationship and the considerable
52 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #104 SEPTEMBER/OCTOBER 2005
degree of uncertainty that will be in this situation is all too often paper trail that can verify the
present at the time of entering ill-deserved. quality of work undertaken. The
into the contract. progress claim and payment
That approach, while legally neat,
system should also be carefully
I have a cunning plan … might attract a price premium
administered in order to minimise
At the other end of the design in tendering and must be
confusion at the point of handover
and construct spectrum is the implemented with regard to the
of contractual responsibility.
situation where the principal has following considerations.
undertaken significant design • The consultancy agreements,
• The contract must be drafted
and/or construction work prior to early works contracts and the
and administered as though
the formation of the design and design and construct contract
the prior work and existing
construct contract. should make provision for the
design were undertaken by the
novation of consultants and early
In this situation, while there is contractor. All design becomes
works contractors in an orderly
considerable detailed design the design of the contractor.
manner so that the contractor
in existence, two problems are All work must be thought of
has the contractual capacity to
encountered: the description as having been done by the
fulfil its obligations.
of the principal’s requirements, contractor.
as opposed to the design that • It is essential to always
• There should be an express
has been done to embody those understand that once the
warranty that the prior works
requirements; and the allocation design and construct contract
and existing design fulfil the
of risk and responsibility for the is formed, the responsibility for
requirements of the project brief
prior works and the existing the production of the design in
and the contract.
design. order to fulfil the requirements
• In contrast, the principal should of the project brief is vested in
The first problem is discussed in make no representations in the contractor. As a result of
detail later in this paper. relation to the quality of the prior that responsibility, the power
In relation to the second problem, work and existing design and, to produce the design and, in
usually it will be very difficult to indeed, should expressly stipulate the absence of provisions to the
define the point where existing the absence of such warranties. contrary, to amend the existing
work has ceased and new work • In order to empower the design, is also vested in the
begins. Furthermore, errors contractor to sensibly deal with contractor. It is highly likely
made in the prior work or existing the risks and responsibilities it that there will be aspects of the
design might not manifest is assuming, all contacts must existing design that the principal
themselves until later works be drafted so as to permit the will not wish to have amended.
are undertaken and might be contractor to fulfil the obligations For example, there may be
exacerbated by other errors made which are imposed on it. In issues of aesthetics or key long
at a future time. particular, the consultancy term quality issues affecting
agreements and early works operational expenses that the
In short, the contractual
contracts must be prepared principal does not want to have
seamlessness that is desirable in
so that the obligations and changed.
all contracting is fractured and it
can be difficult to identify a chain processes contained in them are • Both the consultancy
of causation in order to allocate matched with the design and agreements and the design and
unforeseen costs to one of the construct contract. construct contract should impose
parties. • In order for the contractor to an obligation on the contractor
gain some comfort in relation not to sack consultants without at
The response of some principals
to the prior work and existing least notifying the principal and,
to this problem is to devise a
design, careful administrative in the case of key consultants,
cunning plan and oblige the
procedures, including obtaining the consent of the
design and construct contractor
consultants’ certifications, principal.
to accept responsibility for the
existing design and the prior should be instituted during the In a structural sense, the
works as though the contractor performance of the early works relationship between the relevant
had carried out those activities and the existing design. That is parties will be altered in the
itself. particularly the case for work manner described in the following
which has been covered up or diagram once the design and
As is usually the case, confidence cannot be checked for other construct contract is formed.
in the cunning plan that is devised reasons. In that way there is a

AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #104 SEPTEMBER/OCTOBER 2005 53


providing detailed objectives,
rather than general statements
Pre design and construct formation:
of motherhood, in an inclusive,
Principal rather than an exclusive, list.
Consultants Early Works Contractor • The key obligations that must
be satisfied by the principal
should be stipulated. These
Post design and construct formation: will include development
Principal approvals, environmental
approvals, agreements for lease,
Contractor
sale agreements and banking
Consultant Early works and other requirements. Fundamentally, in
subcontractors preparing the project brief, the
principal must ask itself whether
it has procured the design and
In considering the type of design The project brief will also be construct contractor to fulfil all
and construct discussed above, the fundamental document that of the principal’s own relevant
the principal must bear in mind will be the focus of lenders, obligations.
three important practical issues. purchasers and tenants. In • The performance requirements
summary, all external parties will of the building must be
Firstly, from a practical point of
have arrangements that oblige exhaustively stipulated.
view, the change in control of the
the principal to ensure that the For example, the detailed
design process can lead to a loss
project is constructed in order performance requirements for
of information and expose the
to fulfil the requirements of the air conditioning, lifts and other
project to an increased risk of
project brief. Those obligations services, car park numbers, net
failure.
must be passed on to consultants, lettable areas and apartment
Secondly, as discussed, control early works contractors and, sizes should be carefully
over the consultants and the ultimately, the design and described.
destiny of the design will be construct contractor.
shifted to the contractor. • The principal must ensure
The level of detail contained that its requirements in terms
Thirdly, while the contractor in the project brief will vary of operational expenditure are
will be contractually liable for depending on the timing of its also set out. Reduced capital
the prior works and existing preparation and the formation expenditure, which might be
design, it may well not assume of the design and construct a source of savings for the
a tortious liability because it will contract. Clearly, the later the contractor, will often only be
be difficult to establish that the brief is prepared the more detail achieved at the expense of
contractor has been negligent in that can be incorporated into it. increased operating expenses,
respect of activities over which it The preparation of the project which must be borne by the
has had no control. Accordingly, brief is an excellent litmus test to principal.
the contractor’s professional ascertain whether the principal is
indemnity insurance might not • Where appropriate, industry
in a position to sensibly articulate
respond to claims made on the standards, such as those for
its requirements for the project.
basis of errors contained in the commercial buildings stipulated
If the principal cannot describe
prior works or the existing design. by the Property Council of
its requirements with certainty in
Australia, can be helpfully
the project brief, then it must be
THE PROJECT BRIEF employed. Considerable care
questioned whether the project
The project brief is fundamental should be taken before stipulating
has reached a point where it can
to identifying precisely what a benchmark building since
be put to tender.
it is that must be designed it will be rare that any other
and thereafter constructed. It is useful to use the following building will encapsulate all of the
The project brief is the central checklist in assessing the content requirements of the principal in a
point from which all obligations of the project brief. perfect manner.
emanate. If it is flawed, then all • The detailed objectives of the • Other practical matters such
of the obligations assumed by the principal should be listed. The as the standard of finishes, floor
design and construct contractor emphasis in this regard is on coverings and sound proofing
will be imperfect.
should be described, as should
54 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #104 SEPTEMBER/OCTOBER 2005
the telecommunications and PROFESSIONAL Fundamentally, the
security requirements. INDEMNITY INSURANCE contractor must seek to
• If there are special staging AND SECURITY contain the expectations
requirements for the construction These issues have been grouped of the principal and to
process, particularly where the together because they are relied curb the enthusiasm of
development is to occur adjacent on by the principal for a similar
to other operating buildings,
the consultants in order to
purpose. Both measures provide
those requirements should also a fund of money in the event ensure that the project brief
be set out. that the contractor either does can be fulfilled within the
• The project brief should not not have the money or refuses scope of the assumptions
contain the design that has been to honour its obligations under made in compiling the
undertaken by the Principal prior the contract or arising out of tender.
to the formation of the contract. a breach. In effect, they are a
That design is work which has source of financial comfort.
been undertaken in order to fulfil Frequently, these issues are not
the principal’s requirements, assessed in a co-ordinated way
responsibility for which will often as part of an overall risk analysis.
be assumed by the contractor. Principals have tended to have
a knee jerk reaction to their
• It is not a statement of the requirements for professional
requirements themselves. indemnity insurance without
The contractor also has an assessing the genuine risk
interest in ensuring that the elements in the project. In the
project brief is not ambiguous and current insurance environment
cannot be construed to impose the cost and availability of
higher standards than those professional indemnity insurance
which are the basis of the tender. and bank securities will require
principals to scrutinise these
The contractor must remember matters with greater care and
that throughout the process the sophistication.
principal will hold its securities
and its progress payments. In the Professional indemnity
event of a dispute arising out of an insurance
ambiguity in the project brief, the At the outset, it must be
principal will generally have the appreciated that, unless the policy
upper hand simply because it has which is effected covers general
the money. From a tactical point legal liability risks, a professional
of view the contractor should indemnity insurance policy will
seek to tie down the principal only respond to the negligence
to accept a specific product as of the contractor in undertaking
soon as possible. It will often be professional duties. Many of
in the interests of both parties the activities undertaken by
to construct a prototype so that contractors are not ‘professional’
issues of finishes and design in nature; and many of the risks
functionality can be worked assumed by contractors in
through at an early point in the design and construct contracts,
design and construction process. while imposed contractually,
Fundamentally, the contractor will not manifest themselves as
must seek to contain the negligence actions. As discussed
expectations of the principal and previously, the contractor’s
to curb the enthusiasm of the ‘deemed responsibility’ for
consultants in order to ensure existing design and prior works
that the project brief can be might well fall into that category.
fulfilled within the scope of the Generally, the proceeds of
assumptions made in compiling professional indemnity insurance
the tender. will only become available to a

AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #104 SEPTEMBER/OCTOBER 2005 55


The amount of the security principal after years of expensive or whether the security is to be
is influenced by the nature and difficult litigation against a available to the principal while its
well funded professional litigant entitlement is being determined.
of the project and the
- the insurance company. This is essentially a cash flow
financial capacity of the issue. Must the principal wait or
contractor. It would be rare It is also important to understand
can it use the security while the
the nature of the policy and the
for security to be provided limit of cover. The insurance cover legal position is being sorted out?
in excess of 10% and, effected by the contractor will Of course, from the point of view
more frequently, security generally only be effective from of the principal it is desirable
in the amount of 5% of the year to year, so that the crucial for the security to be available
contract sum is provided. time is not when the contract is pending the final determination of
formed, but when the claim is its rights and, just as clearly, the
made; and the cover might well contrary position is favourable to
be in respect of all claims made the contractor.
in a particular year, rather than in Whatever is agreed by the parties,
respect of the specific project. it must be clearly documented
If the principal identifies that in the contract. If acting for a
professional indemnity insurance principal, the terms dealing with
is an essential part of its risk security should make it plain
management strategy, then it that the principal may access the
should investigate the taking out security on the basis of a claim
of project specific insurance and which is asserted, rather than a
it must familiarise itself with the claim which is finally established.
terms of the insurance policy and The contractor, even if it
the financial status of the insurer. concedes on this issue, will
Both the principal and the argue that it should be entitled
contractor should ensure to notice before the security can
that the consultants take out be accessed. Such a request
professional indemnity insurance is not unreasonable, although
on appropriate terms and for a it does provide the contractor
sensible level of cover. In reality, with the opportunity to obtain an
in the current insurance climate injunction restraining the calling
most consultants will restrict up of the security. Nevertheless,
their insurance requirements to if the security clause is properly
$5 million - $10 million or even drafted, commercial common
less. sense indicates that it is not
inappropriate for notice to be
In any event once the novation
given to the contractor.
of consultants is effected and
the contractor is responsible for The amount of the security is
their performance, the dispersion influenced by the nature of the
of insurance cover for modest project and the financial capacity
amounts among a number of of the contractor. It would be
consultants places the contractor rare for security to be provided
in a position where it has a in excess of 10% and, more
considerable exposure and will frequently, security in the amount
not be able to adequately back to of 5% of the contract sum is
back its liability to the principal. provided.
Security Security will normally be provided
The threshold issue to be in one or a combination of the
considered by the parties is following five forms:
whether the purpose of the 1. an unconditional undertaking
security is to provide a fund in given by an Australian bank;
the event that an entitlement
of the principal is established; 2. an unconditional undertaking
given by a foreign bank;
56 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #104 SEPTEMBER/OCTOBER 2005
3. an unconditional undertaking delivery of as built drawings does not provide clear guidance
given by an Australian non- and maintenance and operation as to these requirements.
banking institution; manuals; and the resolution From the principal’s perspective,
of any outstanding disputes,
4. an unconditional undertaking it will be important to ensure
including the payment of costs
given by a foreign non-banking that it is permitted enough time
incurred by the principal.
institution; and to review designs and can make
VARIATIONS comments on them.
5. a conditional undertaking given
by a non-banking institution. ‘We paid you for a casino. That Ideally, those comments should
looks like a casino.’ not detract or derogate from the
The first point of difference
So said the project manager of a obligations of the contractor.
between those securities is
that the fifth security will be casino project that went wrong. Conversely, and again ideally, the
payable only when the conditions It was in response to a claim contractor should ensure that it
precedent to payment have been made by the design and construct is not delayed by the principal’s
fulfilled. It is not an unconditional contractor based on hundreds of delays in reviewing proposals
promise to pay money on variations. It was a simple, but and is not exposed to the
demand, which is the essential compelling, message and in the consequences of the principal’s
form of the other securities. end we couldn’t escape its logic. fickle whims.
The fundamental distinction In construct only contracts, it is In preparing D&C contracts
between the other securities lies comparatively easy to identify it is important to ensure
in the identity of the promisor. instructions which are variations. that a carefully considered
From the point of view of a The principal will have produced administrative structure is
principal, it is desirable to require the design and changes to that established. From the point of
the security to be in the form of design will be variations. Of view of the principal, it will be
an unconditional undertaking course, these variations will not important to ensure that no
given by an Australian bank. If a necessarily have time or cost approval derogates from the
Mallesons client wishes to depart ramifications. fundamental obligation to fulfil
from that formula, then it must Obviously, the situation is more the requirements of the project
satisfy itself as to: complex in design and construct brief.
• the financial capacity of the contracts where the contractor If acting for the contractor, we
actual promisor (as opposed to a has carriage of the design. would look to institute a system
parent); An instruction by, or on behalf of, that adjusts the requirements
the principal to amend a design as designs and concepts are
• the place of incorporation of the
will generally only amount to a approved. The contractor will not
promisor;
variation if it: want the principal to make design
• how a demand is to be made on work redundant, once it has been
the promisor; and • amends the project brief; or approved, on the basis that the
• the ability to enforce a judgment • it amends a design or principal subsequently forms
in the jurisdiction where the work which has already been a view that the work does not
promisor’s assets are located. undertaken and which complied comply with the brief.
with the contract.
All of the above matters will RELATED AGREEMENTS
require a considerable amount of If the project brief has been poorly The D&C contract will not stand
due diligence. prepared, that assessment can be alone in the suite of agreements
contentious. that will be entered into by the
Contractors should be prepared
Changing principal requirements principal. Depending on the type
to provide that information
can be particularly irritating as of project, it will be closely linked
to assuage the concerns of
well as time consuming during to a number of the principal’s
conservative principals.
the design development phase. other agreements. Many of those
Finally, most securities are The contractor might simply other agreements must be taken
returned, in part, at practical not produce designs that satisfy into account when preparing the
completion and, in full, on the the aesthetic taste or subjective D&C contract. This is particularly
issue of the final certificate. In functional requirements of the critical in respect of project
considering the timing of the principal. What we’ve found is financed or limited recourse
return of the security, regard that the situation will usually be projects.
should also be had to the exacerbated if the project brief
AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #104 SEPTEMBER/OCTOBER 2005 57
A building development because the principal prefers to • defects liability period; and
documentation flow is as follows: retain its financial knowledge. • final certification.
• Government approvals It is important to remember that, • In particular, the ‘services’
from the point of novation, the
• Agreements for Lease (as the term is defined in the
consultant: consultancy agreement) should
• Sale Contracts
• will owe its contractual stipulate the monthly design
• Lender Agreements obligations to the contractor; certifications and sign-offs
• Principal’s objectives required for progress payments,
• will be directed by the
requirements are set out in the the certifications required at
contractor; and
project brief and draft D&C practical completion and the
• will be paid by the contractor. certifications required for the
• Project brief is prepared issue of the final certificate. It
The relationship between the
together with a draft D&C. Brief is usually pointless requiring
principal and the consultant will
forms basis of the consultants’ the contractor to produce
change in a fundamental way
services. these certificates if it cannot
from the date of novation.
• Consultants’ agreements are procure them from the relevant
It is essential that the consultancy consultants.
formed – to embody the brief and
agreements are negotiated and
be consistent with the D&C. • Administrative issues such
drafted in the knowledge that
• D&C is finalised on the basis they will ultimately be novated as reporting and attendance at
of the brief and the principal’s and that the D&C contractor meetings should be documented
other [anticipated] contractual is likely to scrutinize them to in a manner consistent with the
requirements. ensure consistency with, ensure D&C contract.
• Consultants’ agreements to compliance with the D&C • The services should be
are [usually] novated to the contract. delivered in accordance with a
contractor; bank side deed In certain respects the program that is consistent with
and other related agreements consultancy agreements will the D&C contract.
executed. also have to take account of • The fees to be paid to the
An important consideration is that the requirements of lenders, consultant should consistent with
some of the related agreements particularly in connection with the payments to be made under
will not be in existence until certification obligations. the D&C contract, both in relation
after the D&C contract is signed. I’ll mention briefly some of the to amount and payment cycle.
That’s where our job becomes issues that must be taken into • The consultancy agreement
more complex and planning and consideration when preparing must be made subject to novation.
awareness of what input these consultancy agreements in the And…
future documents will have on the light of their eventual novation to
D&C contract, and vice-versa, is • Restrictions on the termination
the D&C contractor.
particularly important. of the consultancy agreement
• Firstly, and not surprisingly, should be built in so that a valued
Consultancy agreements it must compel the consultant consultant cannot be replaced by
The consultants will actually carry to undertake its services in a a less expensive one in the post
out most of the design. manner that permits it to comply novation phase. Certainly not
with the requirements of the without very good reason or the
The principal will usually
project brief. approval of the Principal.
have entered into many of the
consultancy agreements prior • The description of the services Lenders
to the formation of the D&C should be consistent with the There is considerable variation
contract and might have strong requirements of the D&C contract between banks in relation to the
preferences in relation to the throughout the various phases: extent they will intrude into the
other consultants to be appointed. relationship between the principal
• concept design;
The existing consultancy and the D&C contractor.
• design development;
agreements, with the exclusion of Clearly, banks will require the
the quantity surveyor, will usually • detail design;
parties to enter into a bank side
be novated to the contractor. • contract administration; deed or tripartite agreement. It
The QS will often not be novated is desirable for that deed to be
• practical completion;
annexed to the tender documents
58 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #104 SEPTEMBER/OCTOBER 2005
or, preferably, the D&C contract. This can often be a complex
If that isn’t possible, the contract undertaking. In particular,
should at least contain an agreements for lease will
agreement by the contractor to sometimes contain concessions
enter into a bank side deed and which have been made by the
list the terms which are likely to principal that directly affect
be found in that document. The matters such as:
identity and requirements of the • the timing of construction;
bank are essential in drafting
D&C contracts. • responsibility for separate
contractors;
The bank’s requirements extend
beyond entry into a tripartite • the pricing of variations; and
agreement, particularly in • the requirements for
relation to monthly sign-offs completion.
or certifications prior to the
drawdown of funds. These are all matters which must
be built into the D&C contract.
On PPPs and project financed
deals, the banks go a lot CONCLUSION
further and will want to re-open The purpose of this seminar has
previously hard fought issues been to briefly discuss some of
in a D&C contract if they don’t the complexities of design and
meet their very extensive set of construct contracting that can
‘bankability’ requirements. If lead to disputes.
acting for the principal, our role is The issues mentioned are by no
very much to prepare the contract means complete.
so as to anticipate the banks
internal ‘bankability’ checklist. As most of you are aware,
the process of design and
In the tripartite agreement, they construction is really concerned
usually want to ensure that they with managing the unforeseen
have access to information, and dealing with problems.
restrictions on termination rights
(certainly on timing) and an ability Contracts must be negotiated
to step-in if the principal defaults with that understanding in mind.
under the financing agreements.
James Forrest’s paper was
Some of these requirements must previously presented at the
also be built into the consultancy Chartered Institute of Building
agreements. Australia seminars in Brisbane
Agreements for lease and on 17 March, Melbourne on 22
March, and Sydney on 23 March.
sale contracts
Reprinted with permission.
Development projects, which are
projects designed to be sold or
leased, will generally not obtain
finance and proceed unless
tenants or presales have been
achieved.
Accordingly, agreements for lease
and sale contracts will usually
predate the D&C contract.
It is essential to build into the
project brief obligations that deal
with fulfilling the requirements of
those leases and sale contracts.

AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #104 SEPTEMBER/OCTOBER 2005 59

You might also like