Professional Documents
Culture Documents
Operation Research (Study Material)
Operation Research (Study Material)
OPERATION
RESEARCH
STUDY MATERIAL FOR MBA & PGDM
TABLE OF CONTENTS
Chapter 1: An Overview on Operation research
Page 1
Department of Business Administration, Ravenshaw University
O.R., it is generally accepted that the field originated in England during World
War II. The impetus for its origin was the development of radar defense systems
for the Royal Air Force, and the first recorded use of the term Operations
Research is attributed to a British Air Ministry official named A. P. Rowe who
constituted teams to do "operational researches" on the communication system
and the control room at a British radar station. The studies had to do with
improving the operational efficiency of systems (an objective which is still one of
the cornerstones of modern O.R.). This new approach of picking an "operational"
system and conducting "research" on how to make it run more efficiently soon
started to expand into other arenas of the war. Perhaps the most famous of the
groups involved in this effort was the one led by a physicist named P. M. S.
Blackett which included physiologists, mathematicians, astrophysicists, and even
a surveyor. This multifunctional team focus of an operations research project
group is one that has carried forward to this day. Blackett’s biggest contribution
was in convincing the authorities of the need for a scientific approach to manage
complex operations, and indeed he is regarded in many circles as the original
operations research analyst.
O.R. made its way to the United States a few years after it originated in
England. Its first presence in the U.S. was through the U.S. Navy’s Mine Warfare
Operations Research Group; this eventually expanded into the Antisubmarine
Warfare Operations Research Group that was led by Phillip Morse, which later
became known simply as the Operations Research Group. Like Blackett in
Britain, Morse is widely regarded as the "father" of O.R. in the United States, and
many of the distinguished scientists and mathematicians that he led went on after
the end of the war to become the pioneers of O.R. in the United States.
In the years immediately following the end of World War II, O.R. grew rapidly
as many scientists realized that the principles that they had applied to solve
problems for the military were equally applicable to many problems in the civilian
sector. These ranged from short-term problems such as scheduling and inventory
control to long-term problems such as strategic planning and resource allocation.
George Dantzig, who in 1947 developed the simplex algorithm for Linear
Page 2
Department of Business Administration, Ravenshaw University
Programming (LP), provided the single most important impetus for this growth.
To this day, LP remains one of the most widely used of all O.R. techniques and
despite the relatively recent development of interior point methods as an
alternative approach, the simplex algorithm (with numerous computational
refinements) continues to be widely used. The second major impetus for the
growth of O.R. was the rapid development of digital computers over the next
three decades. The simplex method was implemented on a computer for the first
time in 1950, and by 1960 such implementations could solve problems with about
1000 constraints. Today, implementations on powerful workstations can routinely
solve problems with hundreds of thousands of variables and constraints.
Moreover, the large volumes of data required for such problems can be stored and
manipulated very efficiently.
Once the simplex method had been invented and used, the development of
other methods followed at a rapid pace. The next twenty years witnessed the
development of most of the O.R. techniques that are in use today including
nonlinear, integer and dynamic programming, computer simulation, PERT/CPM,
queuing theory, inventory models, game theory, and sequencing and scheduling
algorithms. The scientists who developed these methods came from many fields,
most notably mathematics, engineering and economics. It is interesting that the
theoretical bases for many of these techniques had been known for years, e.g., the
EOQ formula used with many inventory models was developed in 1915 by Harris,
and many of the queuing formulae were developed by Erlang in 1917. However,
the period from 1950 to 1970 was when these were formally unified into what is
considered the standard toolkit for an operations research analyst and successfully
applied to problems of industrial significance. The following section describes the
approach taken by operations research in order to solve problems and explores
how all of these methodologies fit into the O.R. framework.
1.2. Definition of OR
Page 3
Department of Business Administration, Ravenshaw University
altered to something that is more indicative of the things that O.R. actually does.
Sometimes O.R. is referred to as Management Science (M.S.) in order to better
reflect its role as a scientific approach to solving management problems, but it
appears that this terminology is more popular with business professionals and
people still quibble about the differences between O.R. and M.S. Compounding
this issue is the fact that there is no clear consensus on a formal definition for
O.R. For instance, C. W. Churchman who is considered one of the pioneers of
O.R. defined it as the application of scientific methods, techniques and tools to
problems involving the operations of a system so as to provide those in control of
the system with optimum solutions to problems. This is indeed a rather
comprehensive definition, but there are many others who tend to go over to the
other extreme and define operations research to be that which operations
researchers do (a definition that seems to be most often attributed to E. Naddor)!
Regardless of the exact words used, it is probably safe to say that the moniker
"operations research" is here to stay and it is therefore important to understand
that in essence, O.R. may simply be viewed as a systematic and analytical
approach to decision-making and problem-solving. The key here is that O.R. uses
a methodology that is objective and clearly articulated, and is built around the
philosophy that such an approach is superior to one that is based purely on
subjectivity and the opinion of "experts," in that it will lead to better and more
consistent decisions. However, O.R. does not preclude the use of human
judgement or non-quantifiable reasoning; rather, the latter are viewed as being
complementary to the analytical approach. One should thus view O.R. not as an
absolute decision making process, but as an aid to making good decisions. O.R.
plays an advisory role by presenting a manager or a decision-maker with a set of
sound, scientifically derived alternatives. However, the final decision is always
left to the human being who has knowledge that cannot be exactly quantified, and
who can temper the results of the analysis to arrive at a sensible decision.
Page 4
Department of Business Administration, Ravenshaw University
(1) Orientation,
(5) Solution,
Page 5
Department of Business Administration, Ravenshaw University
the deliberations from the orientation phase to the point where there is a clear
definition of the problem in terms of its scope and the results desired. This phase
should not be confused with the previous one since it is much more focused and
goal oriented; however, a clear orientation aids immeasurably in obtaining this
focus. Most practicing industrial engineers can relate to this distinction and the
difficulty in moving from general goals such "increasing productivity" or
"reducing quality problems" to more specific, well-defined objectives that will aid
in meeting these goals.
Data Collection: In the third phase of the O.R. process data is collected with the
objective of translating the problem defined in the second phase into a model that
can then be objectively analyzed. Data typically comes from two sources –
observation and standards. The first corresponds to the case where data is actually
collected by observing the system in operation and typically, this data tends to
derive from the technology of the system. For instance, operation times might be
obtained by time studies or work methods analysis, resource usage or scrap rates
might be obtained by making sample measurements over some suitable interval of
time, and data on demands and availability might come from sales records,
purchase orders and inventory databases. Other data are obtained by using
standards; a lot of cost related information tends to fall into this category. For
instance, most companies have standard values for cost items such as hourly wage
rates, inventory holding charges, selling prices, etc.; these standards must then be
consolidated appropriately to compute costs of various activities. On occasion,
data may also be solicited expressly for the problem at hand through the use of
surveys, questionnaires or other psychometric instruments.
Model Formulation: This is the fourth phase of the O.R. process. It is also a
phase that deserves a lot of attention since modeling is a defining characteristic of
all operations research projects. The term "model" is misunderstood by many, and
is therefore explained in some detail here. A model may be defined formally as a
selective abstraction of reality. This definition implies that modeling is the
process of capturing selected characteristics of a system or a process and then
combining these into an abstract representation of the original. The main idea here
is that it is usually far easier to analyze a simplified model than it is to analyze the
Page 6
Department of Business Administration, Ravenshaw University
Model Solution: The fifth phase of the O.R. process is the solution of the
problem represented by the model. This is the area on which a huge amount of
research and development in O.R. has been focused, and there is a plethora of
methods for analyzing a wide range of models. It is impossible to get into details
of these various techniques in a single introductory chapter such as this; however,
an overview of some of the more important methods can be found elsewhere in
this handbook. Generally speaking, some formal training in operations research is
necessary in order to appreciate how many of these methods work and the
interested reader is urged to peruse an introductory text on O.R.; the section on
"Further Reading" at the end of the chapter lists some good books. It is also worth
mentioning that in recent years a number of software systems have emerged
which (at least in theory) are "black boxes" for solving various models. However,
some formal education in O.R. methods is still required (or at least strongly
recommended) before using such systems. From the perspective of the
practitioner, the most important thing is to be able to recognize which of the many
available techniques is appropriate for the model constructed. Usually, this is not
a hard task for someone with some rudimentary training in operations research.
The techniques themselves fall into several categories.
Validation and Analysis: Once a solution has been obtained two things need to
be done before one even considers developing a final policy or course of action
for implementation. The first is to verify that the solution itself makes sense.
Oftentimes, this is not the case and the most common reason is that the model
used was not accurate or did not capture some major issue. The process of
ensuring that the model is an accurate representation of the system is called
validation and this is something that (whenever possible) should be done before
actual solution. However, it is sometimes necessary to solve the model to discover
inaccuracies in it. A typical error that might be discovered at this stage is that
some important constraint was ignored in the model formulation - this will lead to
a solution that is clearly recognized as being infeasible and the analyst must then
Page 7
Department of Business Administration, Ravenshaw University
go back and modify the model and re-solve it. This cycle continues until one is
sure that the results are sensible and come from a valid system representation.
Physical Models: These are actual, scaled down versions of the original.
Examples include a globe, a scale-model car or a model of a flow line made with
elements from a toy construction set. In general, such models are not very
Page 8
Department of Business Administration, Ravenshaw University
Analogic Models: These are models that are a step down from the first
category in that they are physical models as well, but use a physical analog to
describe the system, as opposed to an exact scaled-down version. Perhaps the
most famous example of an analogic model was the ANTIAC model (the acronym
stood for anti-automatic-computation) which demonstrated that one could
conduct a valid operations research analysis without even resorting to the use of a
computer. In this problem the objective was to find the best way to distribute
supplies at a military depot to various demand points. Such a problem can be
solved efficiently by using techniques from network flow analysis. However the
actual procedure that was used took a different approach. An anthill on a raised
platform was chosen as an analog for the depot and little mounds of sugar on their
own platforms were chosen to represent each demand point. The network of roads
connecting the various nodes was constructed using bits of string with the length
of each being proportional to the actual distance and the width to the capacity
along that link. An army of ants was then released at the anthill and the paths that
they chose to get to the mounds of sugar were then observed. After the model
attained a steady state, it was found that the ants by virtue of their own tendencies
had found the most efficient paths to their destinations! One could even conduct
some post-optimality analysis. For instance, various transportation capacities
along each link could be analyzed by proportionately varying the width of the
link, and a scenario where certain roads were unusable could be analyzed by
simply removing the corresponding links to see what the ants would then do. This
illustrates an analogic model. More importantly, it also illustrates that while O.R.
is typically identified with mathematical analysis, the use of an innovative model
and problem-solving procedure such as the one just described is an entirely
legitimate way to conduct an O.R. study.
Page 9
Department of Business Administration, Ravenshaw University
that can help one visualize the system being simulated. Simulation models are
analyzed by running the software over some length of time that represents a
suitable period when the original system is operating under steady state. The
inputs to such models are the decision variables that are under the control of the
decision-maker. These are treated as parameters and the simulation is run for
various combinations of values for these parameters. At the end of a run statistics
are gathered on various measures of performance and these are then analyzed
using standard techniques. The decision-maker then selects the combination of
values for the decision variables that yields the most desirable performance.
Mathematical Models: This is the final category of models, and the one that
traditionally has been most commonly identified with O.R. In this type of model
one captures the characteristics of a system or process through a set of
mathematical relationships. Mathematical models can be deterministic or
probabilistic. In the former type, all parameters used to describe the model are
assumed to be known (or estimated with a high degree of certainty). With
probabilistic models, the exact values for some of the parameters may be
unknown but it is assumed that they are capable of being characterized in some
systematic fashion (e.g., through the use of a probability distribution). As an
illustration, the Critical Path Method (CPM) and the Program Evaluation and
Review Technique (PERT) are two very similar O.R. techniques used in the area
of project planning. However, CPM is based on a deterministic mathematical
model that assumes that the duration of each project activity is a known constant,
while PERT is based on a probabilistic model that assumes that each activity
duration is random but follows some specific probability distribution (typically,
the Beta distribution). Very broadly speaking, deterministic models tend to be
somewhat easier to analyze than probabilistic ones; however, this is not
universally true.
Page 10
Department of Business Administration, Ravenshaw University
Scheduling: of aircrews and the fleet for airlines, of vehicles in supply chains,
of orders in a factory and of operating theatres in a hospital.
Facility planning: computer simulations of airports for the rapid and safe
processing of travellers, improving appointments systems for medical
practice.
Yield management: setting the prices of airline seats and hotel rooms to
reflect changing demand and the risk of no shows.
Credit scoring: deciding which customers offer the best prospects for credit
companies.
2.1. Introduction
2.2. Features
Page 13
Department of Business Administration, Ravenshaw University
Objective function represents how the decision variables affect the cost or
value to be optimized (minimized or maximized)
Constraints represent how the decision variables use resources, which are
available in limited quantities
Data quantifies the relationships represented in the objective function and the
constraints
For example: If you want to decide how to supply of each kind of product in
order to minimize your costs, you have to do that within a set of constraints. For
instance you have to be able to produce enough to satisfy the demand on all your
Page 14
Department of Business Administration, Ravenshaw University
various products and you have to do it within the capacity you have, which can
produce units at a given cost.
Such that :
2.7. Example-
Page 15
Department of Business Administration, Ravenshaw University
2.7.2. Solution :
R1 R2 PROFIT
A 1 3 Rs 6
B 1 2 Rs 5
AVAILABLE 5 12
Page 16
Department of Business Administration, Ravenshaw University
a) Graphical Method
The N. Dustrious Company produces two products: I and II. The raw material
requirements, space needed for storage, production rates, and selling prices for these
products are given in Table .
Page 17
Department of Business Administration, Ravenshaw University
The total amount of raw material available per day for both products is 1575lb.
The total storage space for all products is 1500 ft2, and a maximum of 7 hours per day
can be used for production.
2.9.2. Solution
The company has decided that it wants to maximize its sale income,
which depends on the number of units of product I and II that it
produces.
Therefore, the decision variables, x1 and x2can be the number of units of
products I and II, respectively, produced per day.
The object is to maximize the equation:
Z = 13x1 + 11x2
Page 18
Department of Business Administration, Ravenshaw University
Page 19
Department of Business Administration, Ravenshaw University
An equation of the form 4x1+ 5x2= 1500 defines a straight line in the x1-
x2plane. An inequality defines an area bounded by a straight line.
Therefore, the region below and including the line 4x1+ 5x2= 1500 in the
Figure represents the region defined by 4x1+ 5x2 1500.
Same thing applies to other equations as well.
The shaded area of the figure comprises the area common to all the
regions defined by the constraints and contains all pairs of x1 and x2 that
are feasible solutions to the problem.
This area is known as the feasible region or feasible solution space. The
optimal solution must lie within this region.
There are various pairs of x1and x2that satisfy the constraints such as:
X1 = 270
X2 = 75
Page 20
Department of Business Administration, Ravenshaw University
Page 21
Department of Business Administration, Ravenshaw University
The N. Dustrious Company produces two products: I and II. The raw material
requirements, space needed for storage, production rates, and selling prices for these
products are given below:
The total amount of raw material available per day for both products is 1575lb.
The total storage space for all products is 1500 ft2, and a maximum of 7 hours per day
can be used for production. The company wants to determine how many units of each
product to produce per day to maximize its total income.
2.10.3. Solution
Step 1: Convert all the inequality constraints into equalities by the use of slack
variables. Let:
Page 22
Department of Business Administration, Ravenshaw University
Introducing these slack variables into the inequality constraints and rewriting
the objective function such that all variables are on the left-hand side of the
equation. Equation can be expressed as:
…..Eq (5)
Since the coefficients of x1 and x2in Eq. (A1) are both negative, the value of Z
can be increased by giving either x1 or x2some positive value in the solution.
In Eq. (B1), if x2 = S1 = 0, then x1= 1500/4 = 375. That is, there is only
sufficient storage space to produce 375 units at product I.
From Eq. (C1), there is only sufficient raw materials to produce 1575/5 = 315
units of product I.
From Eq. (D1), there is only sufficient time to produce 420/1 = 420 units of
product I.
Step 2: From Equation CI, which limits the maximum value of x1.
…..Eq (6)
Substituting this equation into Eq. (5) yields the following new formulation of the
model.
Page 23
Department of Business Administration, Ravenshaw University
…..Eq (7)
It is now obvious from these equations that the new feasible solution is:
It is also obvious from Eq.(A2) that it is also not the optimum solution. The
coefficient of x1in the objective function represented by A2 is negative ( -16/5),
which means that the value of Z can be further increased by giving x2some
positive value.
From Eq. (C2), x2can take on the value (5/3 )(315) = 525 if x1= S2 = 0
Page 24
Department of Business Administration, Ravenshaw University
From these equations, the new feasible solution is readily found to be: x1 = 270, x2 =
75, S1 = 45, S2 = 0, S3 = 0, Z = 4335.
Because the coefficients in the objective function represented by Eq. (A3) are all
positive, this new solution is also the optimum solution.
3.1. Introduction
Page 25
Department of Business Administration, Ravenshaw University
3.2.1. Characteristics
Each source is able to supply a fixed number of units of the product, and each
destination has a fixed demand for the product.
The linear programming model has constraints for supply at each source and
demand at each destination.
Origin Points (or sources) can be factories, warehouses, car rental agencies
like AVIS or any other points from which goods are shipped.
The origin points and the capacity or supply per period at each
The cost of shipping one unit from each origin to each destination
Page 26
Department of Business Administration, Ravenshaw University
We are given the m.n costs associated with shipping one item from any origin
to any destination, and are asked to empty the origins and fill the destinations in
such a way that the total cost is minimized.
Page 27
Department of Business Administration, Ravenshaw University
This initial feasible solution may or may not be optimal. The only way you can
find it out is to test it.
If the solution is not optimal, it is revised and the test is repeated. Each iteration
should bring you closer to the optimal solution.
The format followed in the above table will be used throughout the unit.
Plant supplies are shown to the right of the table and warehouse requirements
are shown below the table.
Page 28
Department of Business Administration, Ravenshaw University
The larger box (also known as cells) at the intersection of a specific row and
column will contain both quantity to be transported and per unit transportation
cost.
The quantity to be transported will be shown in the centre of the box and will
be encircled and the per unit transportation cost is shown in the smaller
rectangular box at the left hand side corner.
There are a number of methods for generating an initial feasible solution for a
transportation problem.
Step 1: Select the North West (upper left-hand) corner cell of the transportation
table and allocate as many units as possible equal to the minimum between available
supply and demand requirement i.e., min (S1, D1).
Step 2: Adjust the supply and demand numbers in the respective rows and
columns allocation.
Step 3:
a) If the supply for the first row is exhausted, then move down to the first
cell in the second row and first column and go to step 2.
b) If the demand for the first column is satisfied, then move horizontally to
the next cell in the second column and first row and go to step 2.
Page 29
Department of Business Administration, Ravenshaw University
Step 4: If for any cell, supply equals demand, then the next allocation can be
made in cell either in the next row or column.
Step 5: Continue the procedure until the total available quantity id fully
allocated to the cells as required.
Remark 1: The quantities so allocated are circled to indicated, the value of the
corresponding variable.
As stated in this method, we start with the cell (P1, W1) and Allocate the min
(S1, D1) = min (20,21)=20. Therefore we allocate 20 Units this cell which completely
exhausts the supply of Plant P1 and leaves a balance of (21-20) =1 unit of demand at
warehouse W1
Now, we move vertically downward to cell (P2, W1) At this stage the largest
allocation possible is the (S2, D1 –20) =min (28, 1)= 1. This allocation of 1 unit to the
cell (P1 W2). Since the demand of warehouse W2 is 25 units while supply available at
plant P2 is 27 units, therefore, the min (27-5) = 25 units are located to the cell (P1,
W2). The demand of warehouse W2 is now satisfied and a balance of (27-225) = 2
units of supply remain at plant P2. Moving again horizontally, we allocated two units
to the cell (P2, W3) Which Completely exhaust the supply at plant P2 and leaves a
balance of 17 units to this cell (P3, W3).. At this, 17 Units areavailable at plant P3 and
17 units are required at warehouse W3. So we allocate 17 units to this cell (P3, W3).
Hence we have made all the allocation. The initial feasible solution is shown below.
The Total transportation cost for this initial solution is
Page 30
Department of Business Administration, Ravenshaw University
Step 1:
a) Select the cell with the lowest transportation cost among all the rows or
columns of the transportation table.
b) If the minimum cost is not unique, then select arbitrarily any cell with
this minimum cost.
Step 2:
Repeat Steps 1 and 2 for the reduced table until the entire supply at different
plants is exhausted to satisfied the demand at different warehouses.
Page 31
Department of Business Administration, Ravenshaw University
This method is preferred over the other two methods because the initial feasible
solution obtained is either optimal or very close to the optimal solution.
Step 1:
Compute a penalty for each row and column in the transportation table.
Step 2:
Step 3:
Repeat steps 1 and 2 for the reduced table until entire supply at plants are
exhausted to satisfy the demand as different warehouses.
Page 32
Department of Business Administration, Ravenshaw University
We need a method, like the simplex method, to check and obtain the optimal
solution
Two methods:
Stepping-stone method
Modified distributed method (MODI)
Let consider the following initial tableau from the Least Cost algorithm
Page 33
Department of Business Administration, Ravenshaw University
Here, we can select any non-basic variable as an entry and then using the
“+ and –” steps to form a closed loop as follows:
Page 34
Department of Business Administration, Ravenshaw University
The above saying that, we add min value of all –ve cells into cell that has “+”
sign, and subtractsthe same value to the “-ve” cells.
Thus, max –veis min (200,25) = 25, and we add 25 to cell A1 and A3, and
subtract it from B1 and A3
We can repeat this process to all possible non-basic cells in that above
Page 35
Department of Business Administration, Ravenshaw University
Step 0: let ui,vj, cij variables represent rows, columns, and cost in the
transportation tableau, respectively
Step 1: (a) form a set of equations that uses to represent all basic variables
ui + vj= cij
cij – ui – vj = kij
Step 3: Select the cell that has the most –ve value in 2(b).
Step 5:Repeat the above steps until all cells in 2(a) has no negative value
Page 36
Department of Business Administration, Ravenshaw University
Step 0: let ui, vj, cij variables represent rows, columns, and cost in the
transportation tableau, respectively
C3A
Step 1: (a) form a set of equations that uses to represent all basic variables
ui + vj = cij
Page 37
Department of Business Administration, Ravenshaw University
Page 38
Department of Business Administration, Ravenshaw University
Step2: (a & b)
Page 39
Department of Business Administration, Ravenshaw University
Note this may look difficult and complicated, however, we can add these
Page 40
Department of Business Administration, Ravenshaw University
2
6-0-7
Step 3: Select the cell that has the most –ve value in 2b
Page 41
Department of Business Administration, Ravenshaw University
These cells mean, introduce it will reduce the min z to -1 cost unit
Page 42
Department of Business Administration, Ravenshaw University
Step 5: we repeat steps 1-4 again for the above tableau, we have
Page 43
Department of Business Administration, Ravenshaw University
Page 44
Department of Business Administration, Ravenshaw University
4.1. Introduction
Let m be the number of jobs as well as the operators, and tij be the processing
time of the job i if it is assigned to the operator j. Here the objective is to assign
the jobs to the operators such that the total processing time is minimized.
Page 45
Department of Business Administration, Ravenshaw University
m m
Min Z Cij X ij
i 1 j 1
X
j 1
ij 1 for i 1,....m
X
i 1
ij 1 for j 1,....m
4.5. Example : Assign the 5 operators to the 5 jobs such that the total processing
time is minimized.
Operator 1 2 3 4 5
job
1 10 12 15 12 8
2 7 16 14 14 11
3 13 14 7 9 9
4 12 10 11 13 10
5 8 13 15 11 15
Page 46
Department of Business Administration, Ravenshaw University
First phase: Row reductions and column reductions are carried out.
Second phase: The solution is optimized in iterative basis.
o Phase 1: Row and column reductions
Step 0: Consider the given cost matrix
Step 1: Subtract the minimum value of each row from the entries of
that row, to obtain the next matrix.
Step 2: Subtract the minimum value of each column from the entries
of that column, to obtain the next matrix.
Treat the resulting matrix as the input for phase 2.
o Phase 2: Optimization
Step3: Draw a minimum number of lines to cover all the zeros of the
matrix.
Row scanning
– Starting from the first row ,if there’s only one zero in a row mark a square
round the zero entry and draw a vertical line passing through that zero.
Otherwise skip the row.
– After scanning the last row, check whether all the zeros are covered with
lines. If yes go to step 4. Otherwise do column scanning.
Column scanning.
– Starting from the first column: if there’s only one zero in a column mark a
square round the zero entry and draw a horizontal line passing through that
zero. Otherwise skip the column.
– After scanning the last column, check whether all the zeros are covered with
lines. If yes go to step 4. Otherwise do row scanning.
– Step 4: check whether the number of squares marked is equal to the number of
rows/columns of the matrix.
– If yes go to step 7. Otherwise go to step 5.
Page 47
Department of Business Administration, Ravenshaw University
– Step 5: Identify the minimum value of the undeleted cell values ,say ‘x’.
Obtain the next matrix by the following steps.
5.1 Copy the entries covered by the lines ,but not on the intersection
points.
5.2 Add x to the intersection points
5.3 Subtract x from the undeleted cell values.
– Step 6: go to step 3.
– Step 7: optimal solution is obtained as marked by the squares
4.6.2. Maximization problem
– If the problem is a maximization problem ,convert the problem into a
minimization problem by multiplying by -1.
– Then apply the usual procedure of an assignment problem.
– Example : Assign 4 sales persons to four different sales regions such that the
total sales is maximized.
Salesregion 1 2 3 4
Sales person
1 10 22 12 14
2 16 18 22 10
3 24 20 12 18
4 16 14 24 20
Sales region 1 2 3 4
Sales person
Page 48
Department of Business Administration, Ravenshaw University
After step 1
Sales region 1 2 3 4
Sales person
1 12 0 10 8
2 6 4 0 12
3 0 4 12 6
4 8 10 0 4
After step 2
Sales region 1 2 3 4
Sales person
1 12 0 10 4
2 6 4 0 8
3 0 4 12 2
4 8 10 0 0
Phase 2
Sales region 1 2 3 4
Sales person
1 12 0 10 4
2 6 4 0 8
3 0 4 12 2
Page 49
Department of Business Administration, Ravenshaw University
4 8 10 0 0
Note that the number of squares is equal to the number of rows of the
matrix. solution is feasible and optimal.
Result:
Salesman Sales Sales
1 2 22
2 3 22
3 1 24
4 4 20
Page 50
Department of Business Administration, Ravenshaw University
5.1. Introduction
One of the most challenging jobs that any manager can take on is the
management of alarge-scale project that requires coordinating numerous activities
throughout the organization. A myriad of details must be considered in planning how
to coordinate all theseactivities, in developing a realistic schedule, and then in
monitoring the progress of the project.
PERT and CPM have been used for a variety of projects, including the
followingtypes.
4. Movie productions
5. Building a ship
Page 51
Department of Business Administration, Ravenshaw University
PERT and CPM were independently developed in the late 1950s. Ever since,
theyhave been among the most widely used OR techniques.
The original versions of PERT and CPM had some important differences, as we
willpoint out later in the chapter. However, they also had a great deal in common, and
the twotechniques have gradually merged further over the years. In fact, today’s
software packages often include all the important options from both original versions.
5.2. NETWORK
Page 52
Department of Business Administration, Ravenshaw University
Common error – build network on the basis of time logic (a feeling for proper
sequence )
Immediate predecessors for a particular activity are the activities that, when
completed, enable the start of the activity in question.
Sequence of activities
Can start work on activities A and B anytime, since neither of these activities
depends upon the completion of prior activities.
Activity D cannot be started until both activities A and C have been completed.
Page 53
Department of Business Administration, Ravenshaw University
Example 2
Develop the network for a project with following activities and immediate
predecessors:
Page 54
Department of Business Administration, Ravenshaw University
This information indicates that the total time required to complete activities is 51
weeks. However, we can see from the network that several of the activities can be
conducted simultaneously (A and B, for example).
We are interested in the longest path through the network, i.e., the critical path.
Page 55
Department of Business Administration, Ravenshaw University
The expression EF = ES + t can be used to find the earliest finish time for a
given activity.
For example, for activity A, ES = 0 and t = 5; thus the earliest finish time for
activity A is
EF = 0 + 5 = 5
Page 56
Department of Business Administration, Ravenshaw University
The earliest start time for an activity leaving a particular node is equal to the largest
of the earliest finish times for all activities entering the node.
LS = 26 – 2 = 24
Page 57
Department of Business Administration, Ravenshaw University
The latest finish time for an activity entering a particular node is equal to the smallest
of the latest start times for all activities leaving the node.
Slack is the length of time an activity can be delayed without affecting the completion
date for the entire project.
Page 58
Department of Business Administration, Ravenshaw University
IMPORTANT QUESTIONS
What are the scheduled start and completion times for each activity?
Page 59
Department of Business Administration, Ravenshaw University
1. Slack or Float shows how much allowance each activity has, i.e how long it can
be delayed without affecting completion date of project
2. Critical path is a sequence of activities from start to finish with zero slack.
Critical activities are activities on the critical path.
4. If any activity on the critical path is shortened or extended, project time will be
shortened or extended accordingly
5. So, a lot of effort should be put in trying to control activities along this path, so
that project can meet due date. If any activity is lengthened, be aware that
project will not meet deadline and some action needs to be taken.
7. Don’t waste resources on non-critical activity, it will not shorten the project
time.
For many situations this is not possible, e.g Research, development, new
products and projects etc.
Variance (V) = ( ( b – a) / 6 ) 2
Page 61
Department of Business Administration, Ravenshaw University
Page 62
Department of Business Administration, Ravenshaw University
Page 63
Department of Business Administration, Ravenshaw University
Calculate Z, where
Z = (D-S) / V
Example,
D = S + 5.745 (1.645)
Page 64
Department of Business Administration, Ravenshaw University
= 43 + 9.45
= 52.45 days
Page 65
Department of Business Administration, Ravenshaw University
• Identified activities with slacks that can be delayed for specified periods
without penalty, or from which resources may be temporarily borrowed
• Shows which tasks may run in parallel to meet project completion date
• Project managers may have the option or requirement to crash the project, or
accelerate the completion of the project.
• The length of the critical path is reduced by reducing the duration of the
activities on the critical path.
• When there is more than one critical path, each of the critical paths must be
reduced.
• If the length of the project needs to be reduced further, the process is repeated.
Page 66
Department of Business Administration, Ravenshaw University
• Crashing
• Crash time
• Crash cost
• Goal
Reduce project length as long as crashing costs are less than indirect costs
Page 67
Department of Business Administration, Ravenshaw University
Time-Cost Tradeoff
Page 68
Department of Business Administration, Ravenshaw University
Page 69
Department of Business Administration, Ravenshaw University
• PERT assumes a beta distribution for these time estimates, but the actual
distribution may be different
Page 70
Department of Business Administration, Ravenshaw University
6.1. INTRODUCTION
However, the focus in this chapter ison the simplest case, called two-person, zero-
sum games. As the name implies, thesegames involve only two adversaries or players
(who may be armies, teams, firms, and soon). They are called zero-sum games
because one player wins whatever the other oneloses, so that the sum of their net
winnings is zero.
The resulting payoff to player 1 in dollars is shown in the payoff table given in
Table.
Page 71
Department of Business Administration, Ravenshaw University
Before the game begins, each player knows the strategies she or he has available,
the onesthe opponent has available, and the payoff table. The actual play of the game
consists ofeach player simultaneously choosing a strategy without knowing the
opponent’s choice.
A strategy may involve only a simple action, such as showing a certain number
offingers in the odds and evens game. On the other hand, in more complicated games
involvinga series of moves, a strategy is a predetermined rule that specifies
completelyhow one intends to respond to each possible circumstance at each stage of
the game. Forexample, a strategy for one side in chess would indicate how to make
the next move forevery possible position on the board, so the total number of possible
strategies would beastronomical. Applications of game theory normally involve far
less complicated competitivesituations than chess does, but the strategies involved can
be fairly complex.
The payoff table shows the gain (positive or negative) for player 1 that would
resultfrom each combination of strategies for the two players. It is given only for
player 1 becausethe table for player 2 is just the negative of this one, due to the zero-
sum nature ofthe game.
The entries in the payoff table may be in any units desired, such as dollars,
providedthat they accurately represent the utility to player 1 of the corresponding
outcome. However,utility is not necessarily proportional to the amount of money (or
any other commodity)when large quantities are involved. For example, $2 million
(after taxes) is probablyworth much less than twice as much as $1 million to a poor
Page 72
Department of Business Administration, Ravenshaw University
person. In other words,given the choice between (1) a 50 percent chance of receiving
$2 million rather than nothingand (2) being sure of getting $1 million, a poor person
probably would much preferthe latter. On the other hand, the outcome corresponding
to an entry of 2 in a payoff tableshould be “worth twice as much” to player 1 as the
outcome corresponding to an entryof 1. Thus, given the choice, he or she should be
indifferent between a 50 percent chanceof receiving the former outcome (rather than
nothing) and definitely receiving the latter outcome instead 1.
2. Both players choose their strategies solely to promote their own welfare (no
compassionfor the opponent).
Two politicians are running against each other for the U.S. Senate. Campaign
plans mustnow be made for the final 2 days, which are expected to be crucial because
of the closenessof the race. Therefore, both politicians want to spend these days
campaigning in twokey cities, Bigtown and Megalopolis. To avoid wasting campaign
time, they plan to travelat night and spend either 1 full day in each city or 2 full days
in just one of the cities.
Therefore, each politician has asked his campaign manager in each of these cities
to assesswhat the impact would be (in terms of votes won or lost) from the various
possiblecombinations of days spent there by himself and by his opponent. He then
wishes to usethis information to choose his best strategy on how to use these 2 days.
Page 73
Department of Business Administration, Ravenshaw University
As the problem has been stated, each player has the following three strategies:
Each entry in the payoff table for player 1 represents the utility to player 1 (or
thenegative utility to player 2) of the outcome resulting from the corresponding
strategiesused by the two players. From the politician’s viewpoint, the objective is to
win votes, and each additional vote (before he learns the outcome of the election) is of
equal valueto him. Therefore, the appropriate entries for the payoff table for politician
1 are the totalnet votes won from the opponent (i.e., the sum of the net vote changes in
the two cities)resulting from these 2 days of campaigning. Using units of 1,000 votes,
this formulationis summarized in Table 14.2. Game theory assumes that both players
are using the sameformulation (including the same payoffs for player 1) for choosing
their strategies.
However, we should also point out that this payoff table would not be appropriate
ifadditional information were available to the politicians. In particular, assume that
theyknow exactly how the populace is planning to vote 2 days before the election, so
that eachpolitician knows exactly how many net votes (positive or negative) he needs
to switch inhis favor during the last 2 days of campaigning to win the election.
Page 74
Department of Business Administration, Ravenshaw University
This situation is a rather special one, where the answer can be obtained just by
applyingthe concept of dominated strategies to rule out a succession of inferior
strategiesuntil only one choice remains.
Page 75
Department of Business Administration, Ravenshaw University
Because both players are assumed to be rational, player 2 also can deduce that
player1 has only these two strategies remaining under consideration. Therefore, player
2 nowdoes have a dominated strategy—strategy 3, which is dominated by both
strategies 1 and2 because they always have smaller losses for player 2 (payoffs to
player 1) in this reducedpayoff table (for strategy 1: 1 ˂ 4, 1 ˂ 5; for strategy 2: 2 ˂ 4,
0 ˂ 5). Eliminatingthis strategy yields
Page 76
Department of Business Administration, Ravenshaw University
Consequently, both players should select their strategy 1. Player 1 then will
receivea payoff of 1 from player 2 (that is, politician 1 will gain 1,000 votes from
politician 2).
In general, the payoff to player 1 when both players play optimally is referred
to asthe value of the game. A game that has a value of 0 is said to be a fair game.
Since thisparticular game has a value of 1, it is not a fair game.
The concept of a dominated strategy is a very useful one for reducing the size of
thepayoff table that needs to be considered and, in unusual cases like this one, actually
identifyingthe optimal solution for the game. However, most games require another
approachto at least finish solving, as illustrated by the next two variations of the
example.
Page 77
Department of Business Administration, Ravenshaw University
If both players choose their strategy 2, the result is that both break even. Thus, in
thiscase, neither player improves upon his best guarantee, but both also are forcing the
opponentinto the same position. Even when the opponent deduces a player’s strategy,
theopponent cannot exploit this information to improve his position.
The end product of this line of reasoning is that each player should play in such
away as to minimize his maximum losses whenever the resulting choice of
strategycannotbe exploited by the opponent to then improve his position. This so-
called minimax criterionis a standard criterion proposed by game theory for selecting
a strategy. In effect,this criterion says to select a strategy that would be best even if
the selection were beingannounced to the opponent before the opponent chooses a
strategy. In terms of the payofftable, it implies that player 1 should select the strategy
whose minimum payoff islargest, whereas player 2 should choose the one whose
maximum payoff to player 1 is thesmallest. This criterion is illustrated in Table ,
where strategy 2 is identified as themaximin strategy for player 1 and strategy 2 is the
minimax strategy for player 2. The resultingpayoff of 0 is the value of the game, so
this is a fair game.
Notice the interesting fact that the same entry in this payoff table yields both the
maximinand minimax values. The reason is that this entry is both the minimum in its
rowand the maximum of its column. The position of any such entry is called a saddle
point.
Page 78
Department of Business Administration, Ravenshaw University
The fact that this game possesses a saddle point was actually crucial in
determininghow it should be played. Because of the saddle point, neither player can
take advantageof the opponent’s strategy to improve his own position. In particular,
when player 2 predictsor learns that player 1 is using strategy 2, player 2 would incur
a loss instead ofbreaking even if he were to change from his original plan of using his
strategy 2. Similarly,player 1 would only worsen his position if he were to change his
plan. Thus, neitherplayer has any motive to consider changing strategies, either to take
advantage of hisopponent or to prevent the opponent from taking advantage of him.
Therefore, since thisis a stable solution (also called an equilibrium solution), players 1
and 2 should exclusivelyuse their maximin and minimax strategies, respectively.
As the next variation illustrates, some games do not possess a saddle point, in
whichcase a more complicated analysis is required.
Suppose that both players attempt to apply the minimax criterion in the same way
asin variation 2. Player 1 can guarantee that he will lose no more than 2 by playing
strategy1. Similarly, player 2 can guarantee that he will lose no more than 2 by
playing strategy 3.
However, notice that the maximin value (-2) and the minimax value (2) do not
coincidein this case. The result is that there is no saddle point.
What are the resulting consequences if both players plan to use the strategies just
derived?
Page 79
Department of Business Administration, Ravenshaw University
It can be seen that player 1 would win 2 from player 2, which would make player2
unhappy. Because player 2 is rational and can therefore foresee this outcome, he
wouldthen conclude that he can do much better, actually winning 2 rather than losing
2, by playingstrategy 2 instead. Because player 1 is also rational, he would anticipate
this switchand conclude that he can improve considerably, from _2 to 4, by changing
to strategy 2.
In short, the originally suggested solution (player 1 to play strategy 1 and player 2
toplay strategy 3) is an unstable solution, so it is necessary to develop a more
satisfactorysolution. But what kind of solution should it be?
The key fact seems to be that whenever one player’s strategy is predictable, the
opponentcan take advantage of this information to improve his position. Therefore, an
essentialfeature of a rational plan for playing a game such as this one is that neither
playershould be able to deduce which strategy the other will use. Hence, in this case,
rather thanapplying some known criterion for determining a single strategy that will
definitely beused, it is necessary to choose among alternative acceptable strategies on
some kind ofrandom basis. By doing this, neither player knows in advance which of
his own strategieswill be used, let alone what his opponent will do.
This suggests, in very general terms, the kind of approach that is required for
gameslacking a saddle point. In the next section we discuss the approach more fully.
Given thisfoundation, the following two sections will develop procedures for finding
an optimal wayof playing such games. This particular variation of the political
campaign problem willcontinue to be used to illustrate these ideas as they are
developed.
Page 80
Department of Business Administration, Ravenshaw University
CHAPTER 2:
Rob Richman, president of AmeriBank, takes off his glasses, rubs his eyes in
exhaustion,and squints at the clock in his study. It reads 3 A.M. For the last several
hours,Rob has been poring over AmeriBank’s financial statements from the last three
quartersof operation. AmeriBank, a medium-sized bank with branches throughout
theUnited States, is headed for dire economic straits. The bank, which provides
transaction,savings, and investment and loan services, has been experiencing a steady
declinein its net income over the past year, and trends show that the decline will
continue.
Page 81
Department of Business Administration, Ravenshaw University
potential customersunderstand and use the World Wide Web. He therefore feels that if
AmeriBank offersWeb banking (as the practice of Internet banking is commonly
called), the bank willattract many new customers.
Before Rob undertakes the project to make Web banking possible, however,
heneeds to understand the market for Web banking and the services AmeriBank
shouldprovide over the Internet. For example, should the bank only allow customers
toaccessaccount balances and historical transaction information over the Internet, or
shouldthe bank develop a strategy to allow customers to make deposits and
withdrawals overthe Internet? Should the bank try to recapture a portion of the
investment market bycontinuously running stock prices and allowing customers to
make stock transactionsover the Internet for a minimal fee? Because AmeriBank is
not in the business of performing surveys, Rob has decidedto outsource the survey
project to a professional survey company. He has opened theproject up for bidding by
several survey companies and will award the project to thecompany which is willing
to perform the survey for the least cost.
Page 82
Department of Business Administration, Ravenshaw University
group for the future. AmeriBank wants to interview 2,000customers with at least 20
percent from the first age group, at least 27.5 percent fromthe second age group, at
least 15 percent from the third age group, and at least 15 percentfrom the fourth
agegroup.
Rob understands that the Internet is a recent phenomenon and that some
customersmay not have heard of the World Wide Web. He therefore wants to
ensurethat the sur-vey includes a mix of customers who know the Internet well and
thosethat have lessexposure to the Internet. To ensure that AmeriBank obtains the
correct mix, he wantsto interview at least 15 percent of customers from the Silicon
Valley where Internet useis high, at least 35 percent of customers from big cities
where Internet use is medium,and at least 20 percent of customers from small towns
where Internet use is low.
(a) Formulate a linear programming model to minimize costs while meeting all
surveyconstraintsimposed by AmeriBank.
(b) If the profit margin for Sophisticated Surveys is 15 percent of cost, what bid
willtheysubmit?
(c) After submitting its bid, Sophisticated Surveys is informed that it has the
lowestcost butthat AmeriBank does not like the solution. Specifically, Rob feels that
the selected surveypopulation is not representative enough of the banking customer
Page 83
Department of Business Administration, Ravenshaw University
population. Rob wants atleast 50 people of each age group surveyed in each region.
What is the new bid made bySophisticated Surveys?
(d) Rob feels that Sophisticated Survey oversampled the 18- to 25-year-old
populationand theSilicon Valley population. He imposes a new constraint that no
more than 600 individualscan be surveyed from the 18- to 25-year-old population and
no more than 650 individualscan be surveyed from the Silicon Valley population.
What is the new bid?
Page 84
Department of Business Administration, Ravenshaw University
By how much would these new requirements increase the cost of surveying
forSophisticatedSurveys? Given the 15 percent profit margin, what would
SophisticatedSurveys bid?
NEWS ANALYSIS
The sales department indicates that the sales potential forproducts 1 and 2
exceeds the maximum production rate and thatthe sales potential for product 3 is 20
units per week. The unitprofit would be $50, $20, and $25, respectively, on products
1, 2,and 3. The objective is to determine how much of each productOmega should
produce to maximize profit.
Page 85
Department of Business Administration, Ravenshaw University
CHAPTER 3:
NEWS ANALYSIS
Assume that any plant having the capability and capacityto produce them can
produce any combination of the products inany quantity.
Management wishes to know how to allocate the new productsto the plants to
minimize total manufacturing cost.
Page 86
Department of Business Administration, Ravenshaw University
CASE STUDY
Alabama Atlantic is a lumber company that has three sources of wood and
fivemarketsto be supplied. The annual availability of wood at sources 1, 2, and 3 is
15, 20,and 15 million board feet, respectively. The amount that can be sold annually at
markets1, 2, 3, 4, and 5 is 11, 12, 9, 10, and 8 million board feet, respectively.
In the past the company has shipped the wood by train. However,
becauseshippingcosts have been increasing, the alternative of using ships to make
some of the deliveriesis being investigated. This alternative would require the
company to invest insome ships. Except for these investment costs, the shipping costs
in thousands of dollarsper million board feet by rail and by water (when feasible)
would be the followingfor each route:
Page 87
Department of Business Administration, Ravenshaw University
Considering the expected useful life of the ships and the time value of
money,theequivalent uniform annual cost of these investments is one-tenth the
amount giveninthe table. The objective is to determine the overall shipping plan that
minimizes the totalequivalent uniform annual cost (including shipping costs).
You are the head of the OR team that has been assigned the task of
determiningthis shipping plan for each of the following three options.
Present your results for each option. Compare. Finally, consider the fact
thatthese results are based on current shipping and investmentcosts, so that the
decision on the option to adopt now should take into accountmanagement’s projection
of how these costs are likely to change in the future.
For each option, describe a scenario of future cost changes that would justify
adoptingthat option now.
Page 88
Department of Business Administration, Ravenshaw University
CHAPTER 4:
NEWS ANALYSIS
A contractor, Susan Meyer, has to haul gravel to threebuilding sites. She can
purchase as much as 18 tons at a gravel pitin the north of the city and 14 tons at one in
the south. She needs10, 5, and 10 tons at sites 1, 2, and 3, respectively. The
purchaseprice per ton at each gravel pit and the hauling cost per ton aregiven in the
table below.
Now suppose that trucks (and theirdrivers) need to be hired to do the hauling,
where each truck canonly be used to haul gravel from a single pit to a single site.
Eachtruck can haul 5 tons, and the cost per truck is five times the haulingcost per ton
given earlier. Only full trucks would be used tosupply each site.
(d) Obtain an optimal solution for the problem as formulated inpart (c).
Page 89
Department of Business Administration, Ravenshaw University
During the past 12 years, Tazer continued a moderate amount of research and
development,but it never stumbled upon a drug as successful as the hypertension drug.
One reason is that the company never had the motivation to invest heavily in
innovativeresearch and development. The company was riding the profit wave
generated byits hypertension drug and did not feel the need to commit significant
resources to findingnew drug breakthroughs.
Now Tazer is beginning to fear the pressure of competition. The patent for the
hypertensiondrug expires in 5 years,1 and Tazer knows that once the patent
expires,generic drug manufacturing companies will swarm into the market like
vultures. Historicaltrends show that generic drugs decreased sales of branded drugs by
75 percent.Tazer is therefore looking to invest significant amounts of money in
research anddevelopment this year to begin the search for a new breakthrough drug
that will offerthe company the same success as the hypertension drug. Tazer believes
that if the companybegins extensive research and development now, the probability of
finding a successfuldrug shortly after the expiration of the hypertension patent will be
high.
Page 90
Department of Business Administration, Ravenshaw University
research,you have decided that your department will pursue five separate projects,
which arelisted below:
Project Choice Develop a less intrusive birth control method for women.
For each of the five projects, you are only able to specify the medical ailment
the researchshould address, since you do not know what compounds will exist and be
effectivewithout research.
You also have five senior scientists to lead the five projects. You know
thatscientistsare very temperamental people and will work well only if they are
challenged andmotivated by the project. To ensure that the senior scientists are
assigned to projects theyfind motivating, you have established a bidding system for
the projects. You have giveneach of the five scientists 1000 bid points. They assign
bids to each project, giving ahigher number of bid points to projects they most prefer
to lead. The following table providesthe bids from the five individual senior scientists
for the five individual projects:
Page 91
Department of Business Administration, Ravenshaw University
(a) Given the bids, you need to assign one senior scientist to each of the
fiveprojects to maximizethe preferences of the scientists. What are the assignments?
(b) Dr. Rollins is being courted by Harvard Medical School to accept a teaching
position. Youare fighting desperately to keep her at Tazer, but the prestige of Harvard
may lure her away.If this were to happen, the company would give up the project with
the least enthusiasm.
(c) You do not want to sacrifice any project, since researching only four
projects decreases theprobability of finding a breakthrough new drug. You decide that
either Dr. Zuner or Dr.Mickey could lead two projects. Under these new conditions
with just four senior scientists,which scientists will lead which projects to maximize
preferences?
(d) After Dr. Zuner was informed that she and Dr. Mickey are being considered
for two projects,she decided to change her bids. The following table shows Dr.
Zuner’s new bids foreach of the projects:
Under these new conditions with just four scientists, which scientists will lead
which projectsto maximize preferences?
(e) Do you support the assignment found in part (d)? Why or why not?
(f ) Now you again consider all five scientists. You decide, however, that
several scientists cannotlead certain projects. In particular, Dr. Mickey does not have
experience with researchon the immune system, so he cannot lead Project Hope. His
family also has a history ofmanic-depression, and you feel that he would be too
personally involved in Project Stableto serve as an effective project leader. Dr.
Mickey therefore cannot lead Project Stable. Dr.Kvaal also does not have experience
Page 92
Department of Business Administration, Ravenshaw University
with research on the immune systems and cannot leadProject Hope. In addition, Dr.
Kvaal cannot lead Project Release because he does not haveexperience with research
on the cardiovascular system. Finally, Dr. Rollins cannot lead ProjectUp because her
family has a history of depression and you feel she would be too personallyinvolved
in the project to serve as an effective leader. Because Dr. Mickey and Dr.Kvaal cannot
lead two of the five projects, they each have only 600 bid points. Dr. Rollinshas only
800 bid points because she cannot lead one of the five projects. The following
tableprovides the new bids of Dr. Mickey, Dr. Kvaal, and Dr. Rollins:
(g) You decide that Project Hope and Project Release are too complex to be led
by only onescientist. Therefore, each of these projects will be assigned two scientists
as project leaders.You decide to hire two more scientists in order to staff all projects:
Dr. Arriaga and Dr. Santos.Because of religious reasons, the two doctors both do not
want to lead Project Choice.
The following table lists all projects, scientists, and their bids.
Page 93
Department of Business Administration, Ravenshaw University
(h) Do you think it is wise to base your decision in part (g) only on an optimal
solution for anassignment problem?
CHAPTER 5:
You and several friends are about to prepare a lasagna dinner.The tasks to be
performed, their immediate predecessors, andtheir estimated durations are as follows:
(b) Find all the paths and path lengths through this project network.Which of
these paths is a critical path?
(c) Find the earliest start time and earliest finish time for eachactivity.
(d) Find the latest start time and latest finish time for each activity.
(e) Find the slack for each activity? Which of the paths is a criticalpath?
(f) Because of a phone call, you were interrupted for 6 minuteswhen you should
have been cutting the onions and mushrooms.By how much will the dinner be
Page 94
Department of Business Administration, Ravenshaw University
delayed? If you use your foodprocessor, which reduces the cutting time from 7 to 2
minutes,will the dinner still be delayed?
Sharon Lowe, vice president for marketing for the ElectronicToys Company, is
about to begin a project to design an advertisingcampaign for a new line of toys. She
wants the projectcompleted within 57 days in time to launch the advertising
campaignat the beginning of the Christmas season.Sharon has identified the six
activities (labeled A, B, . . . , F)needed to execute this project. Considering the order
in which theseactivities need to occur, she also has constructed the following
projectnetwork.
(a)Find the estimate of the mean and variance of the durationof each activity.
Page 95
Department of Business Administration, Ravenshaw University
(c) Use the mean critical path to find the approximate probabilitythat the
advertising campaign will be ready to launchwithin 57 days.
(d) Now consider the other path through the project network. Find the
approximate probability that this path will be completedwithin 57 days.
(e) Since these paths do not overlap, a better estimate of the probabilitythat
theproject will finish within 57 days can be obtainedas follows. The project will finish
within 57 days if bothpaths are completed within 57 days. Therefore, the
approximateprobability that the project will finish within 57 days isthe product of the
probabilities found in parts (c) and (d). Performthis calculation. What does this answer
say about the accuracyof the standard procedure used in part (c)?
CASE STUDY:
Brent Bonnin begins his senior year of college filled with excitement and a
twinge offear. The excitement stems from his anticipation of being done with it all—
professors,exams, problem sets, grades, group meetings, all-nighters. . . . The list
could go on andon. The fear stems from the fact that he is graduating in December
and has only 4months to find a job.
Brent is a little unsure about how he should approach the job search. During
hissophomore and junior years, he had certainly heard seniors talking about
theirstrategiesfor finding the perfect job, and he knows that he should first visit the
Campus CareerPlanning Center to devise a search plan.
On Sept. 1, the fist day of school, he walks through the doors of the
CampusCareerPlanning Center and meets Elizabeth Merryweather, a recent graduate
overflowingwith energy and comforting smiles. Brent explains to Elizabeth that since
he isgraduating in December and plans to begin work in January, he wants to leave all
ofNovember and December open for interviews. Such a plan means that he has to
haveall his preliminary materials, such as cover letters and résumés, submitted to the
companieswhere he wants to work by Oct. 31. Elizabeth recognizes that Brent has to
follow a very tight schedule, if he wants tomeet his goal within the next 60 days. She
suggests that the two of them sit down togetherand decide the major milestones that
Page 96
Department of Business Administration, Ravenshaw University
need to be completed in the job searchprocess. Elizabeth and Brent list the 19 major
milestones. For each of the 19 milestones,they identify the other milestones that must
be accomplished directly beforeBrent can begin this next milestone. They also
estimate the time needed to completeeach milestone. The list is shown below.
Page 97
Department of Business Administration, Ravenshaw University
Page 98
Department of Business Administration, Ravenshaw University
*An open interview schedule occurs when the company does not select the
candidates that it wants to interview.Any candidate may interview, but since the
company has only a limited number of interview slots, interestedcandidates must bid
points (out of their total allocation of points) for the interviews. The candidates
withthe highest bids win the interview slots.
Page 99
Department of Business Administration, Ravenshaw University
organized. One of his friends reminds himof the cool OR class they all took together
in the first semester of Brent’s junior year,and how they had learned about some
techniques to organize large projects. Brent re members this class fondly, since he was
able to use a number of the methods he studiedin that class in his last summer job.
(a) Draw the project network for completing all milestones before the interview
process. If everythingstays on schedule, how long will it take Brent until he can start
with the interviews?
(b) Brent realizes that there is a lot of uncertainty in the times it will take him to
complete someof the milestones. He expects to get really busy during his senior year,
in particular since heis taking a demanding course load. Also, students sometimes
have to wait quite a while beforethey get appointments with the counselors at the
career center. In addition to the list estimatingthe most likely times that he and
Elizabeth wrote down, he makes a list of optimisticand pessimistic estimates of how
long the various milestones might take.
Page 100
Department of Business Administration, Ravenshaw University
How long will it take Brent to get done under the worst-case scenario? How
long will ittake if all his optimistic estimates are correct?
(c) Determine the mean critical path for Brent’s job search process. What is the
variance of theproject duration?
(d) Give a rough estimate of the probability that Brent will be done within 60
days.
(e) Brent realizes that he has made a serious mistake in his calculations so far.
He cannot schedulethe career fair to fit his schedule. Brent read in the campus
newspaper that the fair hasbeen set 24 days from today on Sept. 25. Draw a revised
project network that takes into accountthis complicating fact.
Page 101
Department of Business Administration, Ravenshaw University
(f ) What is the mean critical path for the new network? What is the probability
that Brent willcomplete his project within 60 days?
Page 102
Department of Business Administration, Ravenshaw University
CHAPTER 6:
NEWS ANALYSIS
To begin, each player selects one of her chips and places iton the table,
concealed. Both players then uncover the chips anddetermine the payoff to the
winning player. In particular, if bothplayers play the same kind of chip, it is a draw;
otherwise, the followingtable indicates the winner and how much she receives fromthe
other player. Next, each player selects one of her two remainingchips and repeats the
procedure, resulting in another payoff accordingto the following table. Finally, each
player plays her oneremaining chip, resulting in the third and final payoff.
CASE STUDY:
Two politicians soon will be starting their campaignsagainst each other for a
certain political office. Each must now selectthe main issue she will emphasize as the
theme of her campaign.Each has three advantageous issues from which to choose,but
the relative effectiveness of each one would depend upon theissue chosen by the
opponent. In particular, the estimated increasein the vote for politician 1 (expressed as
a percentage of the totalvote) resulting from each combination of issues is as follows:
Page 103
Department of Business Administration, Ravenshaw University
For each of the situations described here, formulate this problemas a two-
person, zero-sum game, and then determine whichissue should be chosen by each
politician according to the specifiedcriterion.
(a) The current preferences of the voters are very uncertain, soeach additional
percent of votes won by one of the politicianshas the same value to her. Use the
minimax criterion.
(b) A reliable poll has found that the percentage of the voters
currentlypreferring politician 1 (before the issues have beenraised) lies between 45
and 50 percent. (Assume a uniform distributionover this range.) Use the concept of
dominated strategies,beginning with the strategies for politician 1.
(c) Suppose that the percentage described in part (b) actually were45 percent.
Should politician 1 use the minimax criterion? Explain.
Page 104