Professional Documents
Culture Documents
Hariyanto.srl@starenergy.co.id
Star Energy Geothermal (Wayang Windu) Ltd.
The 2019 IERE - PLN Bali Workshop, March 2019
Abstract
This paper describes Wayang Windu team experience to manage CDM monitoring process in line with the requirement of Operational Performance
field personnel and validation purpose. Clean Development Mechanism (CDM) is one of the incentive for renewable
Generation (GWh) Availabilty Factor (%)
energy developer including geothermal energy. CDM process is strictly following standard rule starting from CDM
registration process by applicant, verification and validation process by auditor as required till process of approval as CDM 2,500
100.0
100.0
100.0
100.0
100.0
100.0
100.0
100.0
100.0
99.9
99.8
99.7
99.6
%
99.0
98.8
97.1
97.1
96.3
project. Wayang Windu (WW) Unit-1 is not registered as CDM project because WW Unit-1 was developed and
96.1
95.5
95.0
100
1,921 1,878 1,870 1,880 1,924 1,907 1,895
2,000 1,846
commissioned in 2000 before CDM program existed. With the opportunity of CDM incentive, WW Unit-2 was registered as 1,814
90
CDM project. 1,500
80
1,111
961
976
964
960
948
The process was started from WW Phase 2 Geothermal Power Construction Project which was the construction project of
891
958
953
932
910 921 937 922 938 956
3
1,000 888 856
65.4
65.0
70
117 MW geothermal power station. This project constructed and installed WW Power Plant Unit-2 as additional new unit
961
952
948
943
938
937
935
932
923
922
921
920
917
913
910
547
888
856
507
added to an existing grid started in 2007 and commissioned in 2009. This project installed steam gathering system from 500
564
60
507
various well pads which had interface connection with Unit-1 steam supply so both units are possible to be operated by
using other wells units. With this condition, selected position of metering system is really essential to verify the accurate 0
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
50
2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
data for CDM verification purpose. Total Net Gen WW1 (GWh) Total Net Gen WW2 (GWh) CombineNet (GWh) Availability Factor WW1 Availability Factor WW2
SE & SCB agreed to develop unit-2 as CDM project, 6th Nov 2008
Wayang Windu Geothermal Power Plant January 2009, PDD submitted to UNFCCC
8th May2009
Star Energy owns and operates one of the largest geothermal power plants in Indonesia, located in West Java
Star Energy has sole rights to explore and develop geothermal resources in the Wayang Windu contract area as
Pertamina Geothermal Energy’s contractor
Currently SEGWWL plant has a gross installed generation capacity of 227MW, and we have the exclusive right to sell
up to 400MW of geothermal energy generated from the contract area to PLN on a “take-or-pay” basis
We have 26 production wells and 4 injection wells Organization
Sekincau Selatan
EXPLORATION
Salak (100%)
Production data collecting, archiving, analysing
PRODUCTION
Stage: Production
Stage: Production
Capacity: 377 MW
Capacity: 271 MW
Flow measurement verification, calibration and personil certification
Unit 1: 1994 (55 MW)
Unit 1/2: 1994 (120 MW)
Unit 2: 2000 (95 MW)
Laboratory analysis
Unit 3/4/5/6: 1997 (257 MW)
Unit 3: 2007 (121 MW) 2. Verification and Re-certification
Star Energy manages and operates geothermal power plant and steam field with gross capacity of 875 MW :
Wayang Windu geothermal power plant with gross installed generation capacity of 227 MW. Monitoring Process
Salak geothermal power plant with gross installed generation capacity of 197MW and steam sales capacity of
180MW
Darajat geothermal power plant with gross installed generation capacity of 216MW and steam sales capacity of Point of Monitoring :
55MW 1. Steam Production (MSO : Main Steam Orifice), include
Steamfield Above 3
NCG (CH4 & CO2)
Star Energy has right to match the best tender offer for the license in Hamiding concession and Sekincau Selatan Ground System
concession to develop the resource area. 2. Brine Reinjection (Msb)
4
3. Steam to Turbine (Msv : Main Steam Ventury)
4. Electricity Generation Net (EGv)
5. CO2 emissions from fossil fuel Combustion (Genset diesel
5
Where Star Energy Stands Now & Fire pump)
1
Ranked 3rd as World’s Largest Geothermal Operator 2 CER = Project Emission – Baseline Emission – Leakage
Ranked 1st as the Biggest Geothermal Operator in Indonesia 1,400
Wells
1,200 1,159 Wells
1,000 Wells
875 1,031
900
1,000
800 875 Project Emission
Capacity (MW)
839
700
800
Steam Produce MSO or MSV Which is higher + Brine produce
Capacity (MW)
577 725
600
500 600
400
Baseline Emission
400
300
Project Emission * NCG content (CH4, CO2) – (Combustion fuel EDG & Fire pump * Carbon content)
200 120 110 200
100
Leakage
0 0
Star Energy Pertamina Geodipa Sarulla
Energy
Development
ENEL Green Power Star Energy Comision Federal de Calpine Corporation
Electricadad Steam leakage on system
Geothermal Consortium Corporation
Energy
Source: Pertamina & EBTKE 2017 Source: World Energy Council Publication: World Energy Resources 2016
Production Process
2,500,000
1,475,207
2,000,000
T CO2e
Power Plant
1,500,000
393,462
393,462
372,178
372,178
Ground System
323,167
323,167
Sold
2 then injected back into the reservoir through injection wells 500,000
To be issued
4
3. The steam is further cleaned in the scrubber, then goes 0
12/2/2010 - 05/23/2011 - 11/01/2011 - 06/01/2012 - 01/01/2013 - 01/01/2015 -
direct to the turbine 05/22/2011 10/31/2011 05/31/2012 12/31/2012 12/31/2014 06/30/2018
Wells • http://cdm.unfccc.int/Projects/DB/TUEV-SUED1260194062.48/view
Wells Wells
• http://en.wikipedia.org/wiki/Carbon_credit
www.postersession.com
www.postersession.com