You are on page 1of 44

REV01

Dominus Series
Quick Instruction for CT Installation

Dominus 64/128
REV01

Revision History
Approved Implementation
Version Revision Developed by Reviewed by
by Date

V01 New release Yoonjae Lee N/A DJ Lim Feb 29, 2024

1 /43
REV01

1. Purpose
These requirements have been developed to normalize the after-sales service process ofthe CT
products, effectively control the service process and provide timely, accurate and attentive services for
the users.

2. Scope
This procedure applies to the service and maintenance requirements for the CTproducts.

3. Responsibilities and authority


3.1 The After-Sales Service Department shall be responsible for installation and maintenance of
the products;

2 /43
REV01

4. Site inspection and preparation (Pre-installation)

4.1 Installation site inspection


Before installation, the site shall be inspected, and it is required that:
⚫ The ground shall be clean and smooth.
⚫ The lead glass and walls have been installed and the overall protection has been
provided
⚫ The slots and through-holes have been made.
⚫ The air-conditioner has been installed and can operate properly.
⚫ The service power supply is workable and the network port has been enabled.
⚫ The operating desk has been put into place.
⚫ There should be no restrictions on drilling holes in the floor.
⚫ The floor surface should be flat.
⚫ There should be no issues during the ingress of the gantry and table.

4.2 Power supply inspection and confirm


⚫ Confirm that the distribution box has been installed and it is an independently
grounded 4 wires, 3 phase 380V one. Confirm Contactor capacity not less than 125A

➢ Neutral line is not necessary to


be connected to CT System.
➢ It should not be less than 125A

3 /43
REV01

⚫ The connecting cable between the distribution box and equipment has beenprepared.
⚫ The out-site grounding resistance shall be measured and less than 2Ω.
⚫ The Neutral Line from main source should not be connected to the ground Bar

4.3 Anchor bolt installation

1. Spread out the drawing of patient table, ensure that sufficient extended positions are reserved
at both ends of the patient table, i.e. the distance from farthest end of the patient table to the
wall as shown on the drawing shall be greater than 10cm.

2. Find the tools package from accessory box

4 /43
REV01

3. Spread out the drawing of gantry on the drawing of patient table, find the rough
corresponding position and confirm it with the customer.

➢ After the task, please do not discard the case; keep it for future
use during operations

4. When the position has been confirmed by the customer, fix the drawing of patienttable
with decals.

5. Adjust the drawing of gantry so that the scanning centerline shown on it coincides with
centerline of the patient table shown on the drawing of patient table.

6. When the position has been confirmed by the customer, fix the drawing of patienttable
with decals.

7. Adjust the drawing of gantry so that the scanning centerline shown on it coincides with
centerline of the patient table shown on the drawing of patient table.

➢ cut the designated square portion and align the lines

5 /43
REV01

8. Use the positioning nails to mark central points of corresponding positions of the
anchor bolts for the patient tables (four) and Gantry (four).
Note: Gantry and Table each other have 4 back up holes

9. Remove the drawings and mark the existing positioning points with a marker pen.
10. Use a 18mm drill to make 8 mounting holes on the gantry and patient table, and depth
of the hole shall not be less than 65 mm.

M16

Tap

6 /43
REV01

5. Unpacking and installing into place


5.1 Equipment list confirmation
1. When the system is delivered to the site, confirm that the inclination indicator on
outer surface of the packing box has not become red and the outer surface of the
packing box shows no sign of damage.
2. Check the system No. indicated on the assignment list with the systems and
subsystems to ensure that all serial numbers are correct.
3. Unpack the package, take out the packing list and list of accessories, check and
confirm the goods to ensure that the packing list/list of accessories is consistent
with the material objects.
4. Inspect appearance of the machine for any sign of collision and damage.
5.2 Installation into place of gantry

1. Remove all coverings from the gantry and loosen 4 set screws of the gantry and

baseplate.

7 /43
REV01

2. Open the package of Gantry, Install the Dolly as shown in the figure below, raise
the gantry through the Dolly and push it into the equipment room.

3. Place the tooling adjusting levelness on the ground by aligning it with the
mounting hole.

8 /43
REV01

4. Move the gantry to a proper position, align it with the mounting hole, place the
gantry on the ground so that it just sits on the tooling adjusting the levelness, and
then remove the trolley of the gantry.

5. Using a level, measure the horizontal alignment both left-right and front-back,
and adjust the height accordingly

6. When proper adjustment has been made, install the fastening screws, confirm
that the torque is 90N.m, and then confirm with the gradient again.

7. Remove the fixing blocks against forward and backward inclination of the gantry
and release the rotary locking device, On the left and right side of gantry.

9 /43
REV01

<Gantry Tilting Lock; each side of the gantry>

<Gantry Bearing Lock; 4 Locked screws>

➢ Both of Tilting Lock and Bearing Lock should be removed before powering the machine.
➢ Please refer to the attached notice paper for Bearing Lock on the gantry cover.
➢ If not removed, it might critically damage to whole gantry system.

10 /43
REV01

5.3 Installation into place of patient table

1. Removing all Package box from the patient table and loosen the 4 set screws of
the gantry and baseplate.

2. Install the Dolly of the patient table and push the patient table into the scanning room
through the Dolly.

11 /43
REV01

3. Install the Dolly of the patient table and push the patient table into the
scanning room through the Dolly.

4. Place the tooling adjusting levelness on the ground by aligning it with the
mounting hole, move the patient table into place and place it on the ground by
aligning it with the mounting hole, and then remove the trolley. Then screw on
the set screws. Do not tighten the screws at this point.

5. Remove the elevation lock from at each side bottom of the patient table, which
are located at below position.

12 /43
REV01

6. After removing elevation lock, adjust supporter for leveling.

7. Remove dolly and make the covers up with using drawing case as below.

8. After checking levels, fasten the fixing bolt as below.

13 /43
REV01

9. Remove cover holders as below.

for Front and Rear side, remove just


holder and keep the supporter
frame as above

14 /43
REV01

9.1 Installation into place of console

1. Confirm that the installation position meets the site requirements, and the
operation desk shall be placed at such a position that during operation the
operator may see basic conditions of the scanning room to facilitate operation.

2. Push the operation desk to a proper position, and then adjust the knob below it to
make the operation desk firm (see the figure below)

3. Take out other accessories such as display, keyboard and CT BOX and place them properly

4. Remove covers of console box, and connect all cables with reference to the labels.

15 /43
REV01

9.2 Installation into place of power adapter

1. Confirm that the installation position meets the site requirements.


2. Place the power adapter as close to the distribution box as
possible.

3. Measure the power source on the site, and adjust jumper cable with following
the table below.

<Default set for 380VAC 3Phase in three fields>

16 /43
REV01

<Table for selecting tabs in each primary voltage>

# If the main power source was measured to 400VAC, it’s necessary to make changes from A6, B6 and C6
to A5, B5 and C5 with following the table

4. Connect 3 Phase 380VAC Cable(Y labeled) and 220VAC (W labeled) with the reference
to its labels.

17 /43
REV01

A. Physical connection and power-up

i. Physical connection of system

3. Confirm that the power supply on the site is a 380VAC one and its primary output is
“OFF”, without voltage at the outgoing port, and the master switch of the power
adapter is OFF.

4. Find the system connecting lines among the accessories and connect the system
including table lines according to the figure below.

Connection diagram of
Dominus
CT system

Interface panel of console


Exposure indicator
Gating switch System power-up indicator
Power interface
Console

Power adaptor
System power supply input
Power interface

N line
Ground line Gantry
Ground line

Scanning table

PA

18 /43
REV01

Gantry rear
bottom for Y

Gantry rear bottom


for W,GND

19 /43
REV01

Interface/Con.

Spare port

X-ray light

<X-ray Light output port, not standard configured>

Interface/Con. For table

Gantry side Table side

20 /43
REV01

ii. Power inspection and power-up of system

1. Confirm again that the input voltage on the power adapter is set to the correct
position, make jumper according to the figure below based on the power supply on
site.
2. Close the input voltage of the power measuring power adapter on the distribution
board and confirm that the voltage of the three-phase line is within the normal range
380VAC±10%; *for the case that 380VAC was set to operation.
Close the master power switch of the system on the power adapter, measure two
groups of output voltage of the power adapter and confirm that voltage of the
three-phase line in Group 1 is within the normal range of 380V±10% and thevoltage
of the three-phase line in Group 2 is within the normal range of 220V±10%.

3. Close the right lower circuit breaker on back of the gantry and turn on the master
switch on the console. The system will start, and then the home page of the system
will appear on screw of the console.

4. Turn on the PDX switches as below (Default set)

21 /43
REV01
5. Check SCU switch setting as below(only S1,S2 and S3 should be up)

6. Press the emergency stop switches at both sides of the gantry to confirm that the
system may be emergency powered off.
7. Press the emergency stop switches at both sides of the gantry to confirm that the
system may be emergency powered off.

➢ Before pressing the green button above, please check whether all locks such as tilting, bearing and table
elevation were removed normally in previous step.
➢ Before pressing the green button above, please check all the connection is normally cleared and Power
source is in normal status.

22 /43
REV01

8. Get the machine code with login service account (service2/FOUR) and click
“machine code”. if the machine code appears, ask SGH CS team to issue 7 days
service key with sharing it (the valid date is fixed to 7days)

9. After login to service2, perform simplified checking for operation of table and display
status. Touch the buttons on both of the CT box and gantry.

23 /43
REV01

24 /43
REV01

i. Position correction of gantry and patient table


1. Turn on the laser lamp, raise the table to its highest position and push it to the position
where the laser lamp is located.

2. Measure width of the table plate with a tape and observe whether the laser rays in Z
direction are located in the middle part of the table plate. the distance from the
middle to both sides is 209mm plus or minus 1mm, If not, fine tune position of the
patient table.

25 /43
REV01

3. Push the table plate in and confirm again that the laser rays are located in the
middle part of the table plate.

4. After proper adjustment, install the fastening screws, confirm that the torque is
90N.m, and then confirm again with a level

26 /43
REV01

ii. Cover installation


1. Install front and bottom covers of the
gantry.
2. Install left and right bottom covers

3. Install left and right bottom covers of the patient table.

27 /43
REV01

4. Make side covers down slowly

28 /43
REV01

5. Install the pedal

6. Install all rubber hole covers.

29 /43
REV01

B. System test
i. Safety test
1. Press the emergency switch on the console and gantries (four) respectively and
confirm that the system can be emergency powered off.

2. Create a new scanning, press the stop and pause keys for CTbox during exposure,
and the scanning will stop.

3. Press latch of the patient table, and the table plate may be moved by manually
pushing it.

30 /43
REV01

4. If there is door-motor interlocking, confirm that the rays cannot be transmitted


when the gate is open.
5. If the exposure indicator lamp is connected, confirm that the exposure indicator
lamp is steady on when the rays are transmitted.

ii. Motor function test


1. Lower the patient table to its lowest position and control forward and backward
inclination of the gantry through control panel of the gantry and to ensure that the
gantry may be inclined to ±30°.
2. Return the gantry to 0°and control rise and fall and push-in and pull-out of the patient
table through control panel of the gantry and CTBox respectively to ensure that each
function is effective.
3.
iii. Sound function test
1. Press the speaking key on the console, and the sound can be heard in the scanning
room.
2. The sound made in the scanning room can be heard at the console.
3. Play the scanning voice at the console and confirm that it can be clearly heard in the
scanning room.

iv. Scanning function test


1. Confirm that no objects in the scan center,close the door of scan room
2. Confirm that the DAS temperature between 3600-3700

31 /43
REV01

3. Do fast cal ,confirm can be done


4.

➢ Before starting fast calibration, please check whether there is not any object in scan field again. Fast
calibration is for air scan

32 /43
REV01

v. Image quality confirmation


✓ 20 Water Noise: ≤0.35 20 water CT value: -4≤ Tested value ≤4
✓ 20 water Homogeneity: -4≤ Tested value ≤4 ;air CT value: -1000±10

1. Select optimal protocols for testing as below,

Air Water

2. Install the phantom holder and attach the phantom to it, and then make it positioned on the
center of scan field as below.

Inner line, not outer

33 /43
REV01

3. Press the zero-position button and progress further for scan

4. After finishing scan, according below to get the value

34 /43
REV01

35 /43
REV01

5. Measure the MTF curve of the high-resolution images obtained by scanning the
water phantom.

Make Inner laser alignment


on this line

MTF
(Only Max_Head)

6. Values of the MTF curve shall meet the following requirements:

50%: ≥10 (applicable to Dominus 64) or ≥11


10%: ≥17
0%: ≥20
36 /43
REV01

Load file (.pd) > Measure > Select the point to the center as marked > Analysis > Check values

7. Air Artifact images confirm


Protocol for Artifact :330Air

Air Artifact

37 /43
REV01

Load file > Measure > Select the circle point > Analysis > Check the values

38 /43
REV01

8. Field parameter setting


A. Equipment information setting
i. Click Daily Kit→System Config→Others.
ii. Click to enter “Hospital Info”, and modify information such as
hospital name and department.

B. Network system setting(for connecting PACS, worklist or IVW Workstation)


Daily Kit→System Config→Server→Add

39 /43
REV01

C. IVW setting for connecting with OP console PC


i. Connect LAN cable between Console and Workstation.
ii. Configure the network adapter setting is as below in both of Op and IVW

<an example of setting>

* 192.168.0.11(IVW) <-> 192.168.0.10(Op console PC)

iii. Make sure that the following settings exist

➢ For starting this steps, it’s necessary to use 2 kinds of service key. The one is for Op console
service(service2/FOUR), the other is for IVW AUZ Code(login info. 001/123)
➢ AUZ code can be inserted In setting > system lock (at gear icon in IVW after login)
➢ For getting 2 of them, please contact SGH CS Team
40 /43
REV01

iv. In Op console SW, add the information for IVW as below,

v. In workstation, set for retrieving information as below,


Dicom service at Right top banner > Setting as below > Save > Stop >Start

41 /43
REV01

vi. Testing in Op console SW for connection

42 /43
REV01

43 /43

You might also like