Professional Documents
Culture Documents
Dominus Series
Quick Instruction for CT Installation
Dominus 64/128
REV01
Revision History
Approved Implementation
Version Revision Developed by Reviewed by
by Date
V01 New release Yoonjae Lee N/A DJ Lim Feb 29, 2024
1 /43
REV01
1. Purpose
These requirements have been developed to normalize the after-sales service process ofthe CT
products, effectively control the service process and provide timely, accurate and attentive services for
the users.
2. Scope
This procedure applies to the service and maintenance requirements for the CTproducts.
2 /43
REV01
3 /43
REV01
⚫ The connecting cable between the distribution box and equipment has beenprepared.
⚫ The out-site grounding resistance shall be measured and less than 2Ω.
⚫ The Neutral Line from main source should not be connected to the ground Bar
1. Spread out the drawing of patient table, ensure that sufficient extended positions are reserved
at both ends of the patient table, i.e. the distance from farthest end of the patient table to the
wall as shown on the drawing shall be greater than 10cm.
4 /43
REV01
3. Spread out the drawing of gantry on the drawing of patient table, find the rough
corresponding position and confirm it with the customer.
➢ After the task, please do not discard the case; keep it for future
use during operations
4. When the position has been confirmed by the customer, fix the drawing of patienttable
with decals.
5. Adjust the drawing of gantry so that the scanning centerline shown on it coincides with
centerline of the patient table shown on the drawing of patient table.
6. When the position has been confirmed by the customer, fix the drawing of patienttable
with decals.
7. Adjust the drawing of gantry so that the scanning centerline shown on it coincides with
centerline of the patient table shown on the drawing of patient table.
5 /43
REV01
8. Use the positioning nails to mark central points of corresponding positions of the
anchor bolts for the patient tables (four) and Gantry (four).
Note: Gantry and Table each other have 4 back up holes
9. Remove the drawings and mark the existing positioning points with a marker pen.
10. Use a 18mm drill to make 8 mounting holes on the gantry and patient table, and depth
of the hole shall not be less than 65 mm.
M16
Tap
6 /43
REV01
1. Remove all coverings from the gantry and loosen 4 set screws of the gantry and
baseplate.
7 /43
REV01
2. Open the package of Gantry, Install the Dolly as shown in the figure below, raise
the gantry through the Dolly and push it into the equipment room.
3. Place the tooling adjusting levelness on the ground by aligning it with the
mounting hole.
8 /43
REV01
4. Move the gantry to a proper position, align it with the mounting hole, place the
gantry on the ground so that it just sits on the tooling adjusting the levelness, and
then remove the trolley of the gantry.
5. Using a level, measure the horizontal alignment both left-right and front-back,
and adjust the height accordingly
6. When proper adjustment has been made, install the fastening screws, confirm
that the torque is 90N.m, and then confirm with the gradient again.
7. Remove the fixing blocks against forward and backward inclination of the gantry
and release the rotary locking device, On the left and right side of gantry.
9 /43
REV01
➢ Both of Tilting Lock and Bearing Lock should be removed before powering the machine.
➢ Please refer to the attached notice paper for Bearing Lock on the gantry cover.
➢ If not removed, it might critically damage to whole gantry system.
10 /43
REV01
1. Removing all Package box from the patient table and loosen the 4 set screws of
the gantry and baseplate.
2. Install the Dolly of the patient table and push the patient table into the scanning room
through the Dolly.
11 /43
REV01
3. Install the Dolly of the patient table and push the patient table into the
scanning room through the Dolly.
4. Place the tooling adjusting levelness on the ground by aligning it with the
mounting hole, move the patient table into place and place it on the ground by
aligning it with the mounting hole, and then remove the trolley. Then screw on
the set screws. Do not tighten the screws at this point.
5. Remove the elevation lock from at each side bottom of the patient table, which
are located at below position.
12 /43
REV01
7. Remove dolly and make the covers up with using drawing case as below.
13 /43
REV01
14 /43
REV01
1. Confirm that the installation position meets the site requirements, and the
operation desk shall be placed at such a position that during operation the
operator may see basic conditions of the scanning room to facilitate operation.
2. Push the operation desk to a proper position, and then adjust the knob below it to
make the operation desk firm (see the figure below)
3. Take out other accessories such as display, keyboard and CT BOX and place them properly
4. Remove covers of console box, and connect all cables with reference to the labels.
15 /43
REV01
3. Measure the power source on the site, and adjust jumper cable with following
the table below.
16 /43
REV01
# If the main power source was measured to 400VAC, it’s necessary to make changes from A6, B6 and C6
to A5, B5 and C5 with following the table
4. Connect 3 Phase 380VAC Cable(Y labeled) and 220VAC (W labeled) with the reference
to its labels.
17 /43
REV01
3. Confirm that the power supply on the site is a 380VAC one and its primary output is
“OFF”, without voltage at the outgoing port, and the master switch of the power
adapter is OFF.
4. Find the system connecting lines among the accessories and connect the system
including table lines according to the figure below.
Connection diagram of
Dominus
CT system
Power adaptor
System power supply input
Power interface
N line
Ground line Gantry
Ground line
Scanning table
PA
18 /43
REV01
Gantry rear
bottom for Y
19 /43
REV01
Interface/Con.
Spare port
X-ray light
20 /43
REV01
1. Confirm again that the input voltage on the power adapter is set to the correct
position, make jumper according to the figure below based on the power supply on
site.
2. Close the input voltage of the power measuring power adapter on the distribution
board and confirm that the voltage of the three-phase line is within the normal range
380VAC±10%; *for the case that 380VAC was set to operation.
Close the master power switch of the system on the power adapter, measure two
groups of output voltage of the power adapter and confirm that voltage of the
three-phase line in Group 1 is within the normal range of 380V±10% and thevoltage
of the three-phase line in Group 2 is within the normal range of 220V±10%.
3. Close the right lower circuit breaker on back of the gantry and turn on the master
switch on the console. The system will start, and then the home page of the system
will appear on screw of the console.
21 /43
REV01
5. Check SCU switch setting as below(only S1,S2 and S3 should be up)
6. Press the emergency stop switches at both sides of the gantry to confirm that the
system may be emergency powered off.
7. Press the emergency stop switches at both sides of the gantry to confirm that the
system may be emergency powered off.
➢ Before pressing the green button above, please check whether all locks such as tilting, bearing and table
elevation were removed normally in previous step.
➢ Before pressing the green button above, please check all the connection is normally cleared and Power
source is in normal status.
22 /43
REV01
8. Get the machine code with login service account (service2/FOUR) and click
“machine code”. if the machine code appears, ask SGH CS team to issue 7 days
service key with sharing it (the valid date is fixed to 7days)
9. After login to service2, perform simplified checking for operation of table and display
status. Touch the buttons on both of the CT box and gantry.
23 /43
REV01
24 /43
REV01
2. Measure width of the table plate with a tape and observe whether the laser rays in Z
direction are located in the middle part of the table plate. the distance from the
middle to both sides is 209mm plus or minus 1mm, If not, fine tune position of the
patient table.
25 /43
REV01
3. Push the table plate in and confirm again that the laser rays are located in the
middle part of the table plate.
4. After proper adjustment, install the fastening screws, confirm that the torque is
90N.m, and then confirm again with a level
26 /43
REV01
27 /43
REV01
28 /43
REV01
29 /43
REV01
B. System test
i. Safety test
1. Press the emergency switch on the console and gantries (four) respectively and
confirm that the system can be emergency powered off.
2. Create a new scanning, press the stop and pause keys for CTbox during exposure,
and the scanning will stop.
3. Press latch of the patient table, and the table plate may be moved by manually
pushing it.
30 /43
REV01
31 /43
REV01
➢ Before starting fast calibration, please check whether there is not any object in scan field again. Fast
calibration is for air scan
32 /43
REV01
Air Water
2. Install the phantom holder and attach the phantom to it, and then make it positioned on the
center of scan field as below.
33 /43
REV01
34 /43
REV01
35 /43
REV01
5. Measure the MTF curve of the high-resolution images obtained by scanning the
water phantom.
MTF
(Only Max_Head)
Load file (.pd) > Measure > Select the point to the center as marked > Analysis > Check values
Air Artifact
37 /43
REV01
Load file > Measure > Select the circle point > Analysis > Check the values
38 /43
REV01
39 /43
REV01
➢ For starting this steps, it’s necessary to use 2 kinds of service key. The one is for Op console
service(service2/FOUR), the other is for IVW AUZ Code(login info. 001/123)
➢ AUZ code can be inserted In setting > system lock (at gear icon in IVW after login)
➢ For getting 2 of them, please contact SGH CS Team
40 /43
REV01
41 /43
REV01
42 /43
REV01
43 /43