PRESCRIPTIA DREPTULUI THE APPLICATION OF THE

MATERIAL LA ACTIUNE AL STATUTE OF LIMITATION TO THE


ANTREPRENORULUI IN CONTRACTOR’S RIGHT OF ACTION
CONTRACTELE FIDIC ROSU IN FIDIC RED BOOK CONTRACTS

Laura Anghel | Associate Lawyer | Cobuz & Asociatii


Newsletter | September 2016

Prezentul articol isi propune sa raspunda This article aims at answering to the
urmatoarelor intrebari: following questions:
Care este termenul de prescriptie a What is the limitation period
dreptului material la actiune al applicable to the Contractor in
Antreprenorului aplicabil unui FIDIC 1999 Red Book General
Contract FIDIC 1999 Cartea Rosie? Conditions of the Contract?
De cand incepe sa curga acest When does the limitation period in
termen de prescriptie a dreptului such Contracts start to run?
material la actiune? Are the DAB proceedings likely to
CAD este de natura sa suspende sau suspend or to interrupt the limitation
sa intrerupa termenul de prescriptie a period?
dreptului material la actiune? What is it that the Contractor must
Ce trebuie sa stie Antreprenorul? know?

Baza legala Legal basis


Potrivit Sub-clauzei 20.1 din Conditiile Under the provisions of Sub-Clause 20.1 of
Generale de Contract pentru Constructii the General Conditions of Contract for
(CGC) pentru cladiri si lucrari ingineresti Construction (GCC) for buildings and
proiectate de catre Beneficiar FIDIC 1999 engineering works designed by the
Cartea Rosie - Reclamatiile/Revendicarile Employer - FIDIC 1999 Red Book –
Antreprenorului: Contractor’s Claims:

“Daca Antreprenorul se considera "If the Contractor considers himself to be


indreptatit la orice prelungire a Duratei de entitled to any extension of the Time for
Executie si/sau la orice plata suplimentara, Completion and/or any additional payment,
potrivit prevederilor oricarei Clauze ale under any Clause of these Conditions or
prezentelor Conditii sau altfel in legatura otherwise in connection with the Contract,
cu Contractul, Antreprenorul va transmite the Contractor shall give notice to the
Inginerului o instiintare in care sa descrie Engineer, describing the event or
evenimentul sau circumstanta care a circumstance giving rise to the claim. The
generat reclamatia. Instiintarea va fi notice shall be given as soon as practicable,
transmisa fara intarziere, in termen de 28 and not later than 28 days after the
de zile de la data la care Antreprenorul a Contractor became aware or should have
luat cunostinta sau ar fi trebuit sa ia
cunostinta de acest eveniment sau aceasta become aware of the event or circumstance.
circumstanta.
If the Contractor fails to give notice of a
Daca Antreprenorul nu reuseste sa claim within such period of 28 days, the
transmita o instiintare de reclamatie in Time for Completion shall not be extended,
acest termen de 28 de zile, Durata de the Contractor shall not be entitled to
Executie nu va fi extinsa, Antreprenorul nu additional payment and the Employer shall
va fi indreptatit la plata suplimentara, iar be discharged from all liability in
Beneficiarul va fi eliberat de orice connection with the claim. Otherwise, the
responsabilitate in legatura cu reclamatia. following provisions of this Sub-Clause
In celelalte cazuri, urmatoarele prevederile shall apply.
ale prezentei Sub-Clauze se vor aplica.
The Contractor shall also submit any other
Antreprenorul va transmite, de asemenea, notices which are required by the Contract,
orice alte notificari solicitate prin Contract and supporting particulars for the claim, all
si documente justificative ale reclamatiei, as relevant to such event or circumstance.
toate in functie de relevanta cu evenimentul
sau circumstanta. The Contractor shall keep such
contemporary records as may be necessary
Antreprenorul va pastra, fie pe Santier, fie to substantiate any claim, either on the Site
in alt loc acceptat de catre Inginer, toate or at another location acceptable to the
inregistrarile curente pe perioada Engineer. Without admitting the Employer’s
Contractului care pot fi necesare pentru a liability, the Engineer may, after receiving
fundamenta orice reclamatie. Fara sa any notice under this Sub-Clause, monitor
recunoasca responsabilitatea the record-keeping and/or instruct the
Beneficiarului, Inginerul poate, dupa Contractor to keep further contemporary
primirea unei instiintari potrivit records. The Contractor shall permit the
prevederilor prezentei Sub-Clauze, Engineer to inspect all these records, and
monitoriza pastrarea acestor inregistrari si shall (if instructed) submit copies to the
/ sau dispune ca Antreprenorul sa pastreze Engineer.
si inregistrari curente suplimentare.
Antreprenorul va permite Inginerului sa Within 42 days after the Contractor became
verifice toate aceste inregistrari si (daca se aware (or should have become aware) of
dispune) va transmite Inginerului copii ale the event or circumstance giving rise to the
acestora. claim, or within such other period as may
be proposed by the Contractor and
In termen de 42 de zile de la data la care approved by the Engineer, the Contractor
Antreprenorul a luat cunostinta (sau ar fi shall send to the Engineer a fully detailed
trebuit sa ia cunostinta) de acest eveniment claim which includes full supporting
sau aceasta circumstanta care a generat particulars of the basis of the claim and of
reclamatia, sau in alt termen propus de the extension of time and/or additional
catre Antreprenor si aprobat de Inginer, payment claimed.
Antreprenorul va trimite Inginerului o
reclamatie pe deplin detaliata care va If the event or circumstance giving rise to
include toate detaliile justificative the claim has a continuing effect: (a) this
referitoare la motivul reclamatiei si la fully detailed claim shall be considered as
prelungirea perioadei de executie si / sau si interim; (b) the Contractor shall send
further interim claims at monthly intervals,
/ sau platile suplimentare reclamate. giving the accumulated delay and/or
amount claimed, and such further
Daca evenimentul sau circumstanta care au particulars as the Engineer may reasonably
generat reclamatia au un efect continuu, require; and (c) the Contractor shall send a
atunci: (a) aceasta reclamatie pe deplin final claim within 28 days after the end of
detaliata va fi considerata interimara; (b) the effects resulting from the event or
Antreprenorul va trimite in continuare, circumstance, or within such other period
lunar, reclamatii interimare, care sa as may be proposed by the Contractor and
prezinte intarzierile cumulate si / sau approved by the Engineer.
valorile reclamate, impreuna cu detaliile pe
care Inginerul le poate solicita in mod Within 42 days after receiving a claim or
rezonabil; si (c) Antreprenorul va trimite o any further particulars supporting a
reclamatie finala in termen de 28 de zile de previous claim, or within such other period
la sfarsitul producerii efectelor generate de as may be proposed by the Engineer and
acest eveniment sau circumstanta, sau in alt approved by the Contractor, the Engineer
termen propus de catre Antreprenor si shall respond with approval, or with
aprobat de Inginer. disapproval and detailed comments. He may
also request any necessary further
In termen de 42 de zile de la primirea unei particulars, but shall nevertheless give his
reclamatii sau a oricaror detalii response on the principles of the claim
suplimentare de justificare a unei reclamatii within such time.
anterioare, sau in alt termen propus de
catre Inginer si aprobat de Antreprenor, Each Payment Certificate shall include such
Inginerul va raspunde printr-o aprobare, amounts for any claim as have been
sau printr-o respingere cu comentarii reasonably substantiated as due under the
detaliate. De asemenea, el poate solicita relevant provision of the Contract. Unless
orice detaliu suplimentar necesar, dar, in and until the particulars supplied are
acest termen, va transmite oricum raspunsul sufficient to substantiate the whole of the
sau referitor la principiile care au claim, the Contractor shall only be entitled
fundamentat reclamatia. to payment for such part of the claim as he
has been able to substantiate.
Fiecare Certificat de Plata va include acele
sume aferente oricarei reclamatii care, in The Engineer shall proceed in accordance
mod rezonabil, sunt confirmate ca fiind with Sub-Clause 3.5 [Determinations] to
datorate potrivit prevederilor relevante din agree or determine (i) the extension (if any)
Contract. Pana cand detaliile furnizate sunt of the Time for Completion (before or after
suficiente pentru a confirma, in cazul in its expiry) in accordance with Sub-Clause
care confirma, intreaga reclamatie, 8.4 [Extension of Time for Completion],
Antreprenorul nu va fi indreptatit decat la and/or (ii) the additional payment (if any) to
plata acelei parti a reclamatiei pe care a which the Contractor is entitled under the
reusit sa o fundamenteze. Contract.
Inginerul va actiona in conformitate cu The requirements of this Sub-Clause are in
prevederile Sub-Clauzei 3.5 [Hotarari] addition to those of any other Sub-Clause
which may apply to a claim. If the
pentru a conveni sau a hotari asupra (i) Contractor fails to comply with this or
unei prelungiri (daca este cazul) a Duratei another Sub-Clause in relation to any
de Executie (inainte sau dupa expirarea
acesteia), potrivit Sub-Clauzei 8.4 claim, any extension of time and/or
[Prelungirea Duratei de Executie], si / sau additional payment shall take account of the
(ii) unor plati suplimentare (daca este extent (if any) to which the failure has
cazul) la care Antreprenorul este indreptatit prevented or prejudiced proper
potrivit prevederilor Contractului. investigation of the claim, unless the claim
is excluded under the second paragraph of
Cerintele prezentei Sub-Clauze se adauga la this Sub-Clause.
cerintele altor Subclauze care se pot aplica
unei reclamatii. Daca Antreprenorul nu Doctrine and judicial practice have
reuseste sa respecte prevederile prezentei established that civil law principles are
Sub-Clauze sau ale altei Sub-Clauze in applicable to the contract concluded
legatura cu o reclamatie, orice prelungire between the Employer and the Contractor.
de timp si / sau plata suplimentara va tine
cont (daca este cazul) de masura in care Thus, a contract concluded in
procesul de investigare adecvata a Romania based on FIDIC Red Book is also
reclamatiei a fost impiedicat sau prejudiciat governed by legal provisions regarding
de acest esec al Antreprenorului, cu the statute of limitations (Decree-
exceptia cazului in care reclamatia este Law 167/1958 regarding the statute of
respinsa potrivit prevederilor celui de-al limitations and the 1864 Civil Code or
doilea paragraf al prezentei Sub-Clauze.” the New Civil Code).

Doctrina si practica judiciara au stabilit ca According to both the old and the new
principiile dreptului civil sunt aplicabile regulation, the limitation period is 3 years.
Contractului incheiat intre Beneficiar si The New Civil Code mentions, however,
Antreprenor. that the parties may establish another
limitation period.
Astfel, unui contract FIDIC Rosu incheiat in
Romania i se vor aplica dispozitiile legale According to Sub-clause 20.1 of the GCC
privitoare la prescriptia dreptului material la Red FIDIC, we conclude that the
actiune (Decretul-Lege 167/1958 privind Contractor’s right to act starts as follows:
prescriptia extinctiva si ale Codului Civil
The statute of limitations starts to run when
din 1864 sau ale Noului Cod Civil).
the Contractor submits to the Engineer its
Atat potrivit vechii, cat si potrivit noii notification of intention to claim describing
reglementari, termenul de prescriptie a the event or circumstance giving rise to the
dreptului material la actiune al claim.
Antreprenorului este de 3 ani. Noul Cod
The suspension or interruption of the statute
Civil prevede insa si faptul ca partile pot of limitations cases are clearly and
stabili un alt termen de prescriptie.
limitative established by the law. The DAB
Nasterea dreptului la actiune potrivit Sub- proceedings are not provided by the same as
clauzei 20.1 FIDIC CGC: being able to suspend or interrupt the statute
of limitations period. Our conclusion is,
Opinam ca termenul de prescriptie incepe sa hence, that the DAB proceedings are not
curga in momentul in care Antreprenorul likely to suspend or discontinue any
transmite Inginerului instiintarea in care limitation period, the latter being interrupted
descrie evenimentul sau circumstanta care a only by submitting a request for arbitration.
generat reclamatia. Therefore, the Contractor must submit its
request for arbitration within three years
Cazurile de suspendare si de intrerupere a since it submitted the notification of
cursului termenului prescriptiei sunt clar si intention to claim. If the Contractor fails to
limitativ prevazute de lege. Procedura in do so, its claim and/or any additional
fata CAD nu este prevazuta ca fiind un caz payment can be dismissed subsequently to
de suspendare sau intrerupere a cursului the fact that the Statute of limitations
prescriptiei extinctive. Concluzionam, occurred.
asadar, ca procedura in fata CAD nu este de
natura nici sa suspende si nici sa intrerupa
termenul prescriptiei extinctive, aceasta din
urma fiind intrerupta doar prin introducerea
unei cereri de arbitrare.
Astfel, Antreprenorul trebuie sa depuna
cererea de arbitraj in decursul a 3 ani din
momentul transmiterii revendicarii sale. In
sens contrar, revendicarea si costurile
aferente acesteia pot fi respinse de catre
Tribunalul Arbitral ca fiind prescrise.