You are on page 1of 7

ARTICLE IN PRESS

Building and Environment 42 (2007) 139–145


www.elsevier.com/locate/buildenv

Assessing the environmental performance of stabilised rammed earth


walls using a climatic simulation chamber
Matthew R. Hall
School of the Built Environment, University of Nottingham, University Park, Nottingham NG7 2RD, UK
Received 30 June 2005; accepted 16 August 2005

Abstract

The SHU climatic simulation chamber is a novel piece of apparatus that allows testing of full-sized walls with realistic inner and outer
wall climatic conditions. Four SRE test walls were successfully constructed and tested over four separate regimes to measure physical
properties such as pressure-driven moisture ingress, rate of moisture penetration, and internal/interstitial condensation. The walls far
exceeded a series of cyclic pressure-driven rainfall penetration tests based on BS 4315-2. After 5 days of exposure to static pressure-driven
moisture ingress there was no evidence of moisture penetration or erosion. The embedded sensor array detected no significant increase in
the relative humidity or liquid moisture content inside the test walls, throughout a range of temperature differentials with high levels of
humidity, indicating a negligible risk of internal or interstitial condensation.
r 2005 Elsevier Ltd. All rights reserved.

Keywords: Stabilised rammed earth; Environmental performance; Climatic simulation

1. Introduction Centre at Dubbo in south eastern Australia (see Fig. 1)


which was made using locally available soils.
Stabilised rammed earth (SRE) is an eco-friendly Dampness in buildings affects several million people
masonry wall material made from a carefully controlled throughout the UK and so the design and construction of
mix of aggregates such as graded sub-soil, quarry waste or modern masonry walls demands careful attention [3]. SRE
recycled crushed demolition waste. The aggregates are represents a new breed of environmentally friendly wall
stabilised using Portland cement and then dynamically construction that has succeeded in many developed
compacted inside removable shuttering. The walls are countries throughout the world but has yet to make a
immediately load bearing and can either be solid or significant impact in the UK despite the availability of
insulated-cavity construction. The aggregates must be experienced contractors. Under the Building Regulations
carefully graded to produce a particle-size distribution for England & Wales there are currently no recognised
that is both suitable for compaction whilst providing standards or specifications for SRE wall construction [4].
minimal linear shrinkage [1]. SRE offers a rapid rate of This factor, combined with the need for further research,
production at typically 10–15 m2 of 300-mm-thick solid has been instrumental in facilitating a conservative
wall per day and has a uniquely attractive, layered approach towards the suitability of SRE walls in the damp
appearance that closely resembles natural sandstone [2]. UK climate. Laboratory tests have shown that both
A recent SRE project is the Juvenile Justice Detention capillary and pressure-driven moisture ingress in SRE
materials has been observed to vary greatly depending
Corresponding author. Tel: +44 0 115 846 7873; upon soil type, and that the performance of the material
fax: +44 0 115 951 3159. can be greatly increased through optimisation of the soil
E-mail address: matthew.hall@nottingham.ac.uk. grading [5].

0360-1323/$ - see front matter r 2005 Elsevier Ltd. All rights reserved.
doi:10.1016/j.buildenv.2005.08.017
ARTICLE IN PRESS
140 M.R. Hall / Building and Environment 42 (2007) 139–145

Fig. 1. Juvenile Justice Detention Centre in New South Wales, Australia


(photo: Earth Structures Pty Ltd.).
Fig. 2. Schematic diagram of the SHU climatic simulation chamber
(photo: courtesy [6])

2. SHU climatic simulation chamber

Sheffield Hallam University’s climatic simulator was


originally designed and built by Alan Taylor-Firth and
David Flatt to investigate the performance of building
materials and full-sized building elements (e.g. walls) under
a wide range of simulated climatic conditions [6]. The main
advantage of the climate chamber is that it represents the
elusive ‘middle-ground’ between naturally exposed outdoor
test walls and less representative small-scale laboratory
tests. Full-sized test walls can be constructed inside the
climate chamber following normal trade practices, and
realistic climatic effects of weather and exposure can be
accurately simulated and monitored under laboratory
conditions. The simulator itself is composed of two
separate chambers called the ‘design’ side and the ‘climate’
side. The dimensions of each chamber are 4 m long, 3 m
wide and 2.6 m in height. The normal operating tempera- Fig. 3. Construction detail at the base of the SRE test walls.
ture range is +20 to 15 1C (75 1C) depending on the
internal conditions specified [7]. A schematic diagram
illustrating the basic operation of the climatic simulation of Architecture, Grenoble (CRATerre-EAG) recommend
chamber is shown in Fig. 2. parameters for a suitable rammed earth particle-size
The design side of the simulation chamber represents the distribution. These parameters have been superimposed
interior conditions of a building. It has the capacity to onto the British Standard BS1377 [9] particle-size distribu-
maintain standard indoor room conditions of 20 1C711 tion chart illustrated in Fig. 4. A standard methodology for
and 40% RH 75%. The climate side of the simulation blending graded quarry material to produce 100 mm SRE
chamber creates realistic sequences of different external cube samples has been published by the author [1]. This
weather conditions that can run in a fixed mode, sequence enables the specification and consistent production of
mode, or cyclic mode. The advantage of this is that the rammed earth mix designs of known composition (see
start and finish temperatures can be specified, as well as the Fig. 4). The mix designs are reproducible and, for the
rates of change of other weather components such as purposes of testing, allow accurate control of parameters
relative humidity and/or rainfall. such as particle-size distribution. Each of the three mix
designs was stabilised with 6% (by dry mass) ordinary
3. SRE test walls Portland cement. Prior to compaction the soils were mixed
to their optimum moisture content, previously determined
Four 300-mm-thick SRE test walls were constructed in accordance with BS 1377: 4 using the well-known
inside the SHU climatic simulation chamber on top of a ‘Proctor method’. The earth was placed in layers 150 mm
concrete plinth (see Fig. 3). Houben and Guillaud [8] of thick inside oiled proprietary formwork and compacted
The International Centre for Earth Construction—School using an Atlas Copco RAM30 pneumatic tamper.
ARTICLE IN PRESS
M.R. Hall / Building and Environment 42 (2007) 139–145 141

4. Test run 1: low-velocity rainfall simulation

The test methodologies and apparatus described in the


following section are based on the specifications provided
in BS 4315-2: 1970 Methods of test for resistance to air and
water penetration—permeable walling constructions (water
penetration) [10]. Test run 1 employed a sparge pipe
delivery system with a low-velocity constant head supply of
water. The 15 mm diameter copper sparge pipes (1 per wall)
each had an array of eight holes at 0.7 mm diameter in
order to deliver the rainfall ‘trickle’. Each sparge pipe had a
skirting attachment connecting the flow of water with the
wall in such a way that the run-off was distributed more
evenly across the face of the test wall. The water supply was
pumped from a reservoir into a separate header tank that
was positioned on the roof of the chamber. This ensured a
Fig. 4. Particle-size distribution chart showing the grading parameters for
SRE mix designs.
greater degree of accuracy in maintaining consistent water
flow rates. Between the supply of water from the header
tank and each of the four sparge pipes there was an in-line
gate valve to enable the water supply to be shut off from
within the chamber. Also fitted in-line was a 6.7 mm needle
valve to regulate flow through a range between 0.2 and
2.0 L/min. The overall configuration of this rainfall
delivery system is illustrated in Fig. 6. The rate of water
delivery specified in BS 4315-2:1970 is 0.5 L/m2 min [10].
Since the surface area of the rammed earth test walls is
0.45 m2 the required rate of water delivery equates to
0.225 L/min per wall.
The process of calibration includes covering the wall face
with a removable plastic sheet such that the total amount
of water delivery can be measured before being applied to
the porous wall face. Due to the small pressure required to
achieve this very low flow rate the delivery pattern of the
rainfall was observed to trickle down the wall in discreet
channels. The outlet for each decanting pipe was posi-
Fig. 5. Completed SRE test walls viewed from the climate side of the
simulation chamber.
tioned  6 mm above the base of the guttering. This
ensured that the guttering acted as a silt trap for any solid
particles that washed away from the wall surface. The ‘silt
The four test walls were separated from one another by a trap’ first had to be primed (prior to the test commencing)
100 mm thick timber-framed air cavity that incorporated by filling it with water until the decanting pipe overflowed
the sealed end boards from the formwork. The end boards the excess amount of water. It was intended that the total
thus became ‘sacrificial’ and were retained as a part of the
experimental design. Following their completion, the mini
test walls were allowed to cure for a minimum period of 28
days in laboratory conditions at 22 1C711 and 40%
RH75%. The wall edges were then overlapped and sealed
with phenolic resin-coated plywood and caulked around
the entire perimeter with silicone sealant. The top half of
the climate chamber (the remaining height above the test
walls) was completed with timber stud walling and ply
wood sheets. These were then covered with 1200 g damp
proof membrane and fastened around the edges with cloth
tape to pressure-seal the climate side of the chamber. The
resultant dimensions for the exposed test face of each wall
were 500 mm wide by 900 mm high (area ¼ 0.45 m2). The
result of the finishing & sealing work described here can be
seen from the picture in Fig. 5. Fig. 6. Schematic diagram of the low-velocity sparge pipe rainfall system.
ARTICLE IN PRESS
142 M.R. Hall / Building and Environment 42 (2007) 139–145

dry mass of the trapped particles would be indicative of the drop nozzles produced a 1201 flat, fan-shaped spray
level of erosion that occurred due to rainfall. pattern. This gave an efficient distribution of water and
The test run lasted for a total of 5 days followed by a 4 subsequent run-off across the full width of the test wall
week drying period. To start the test, the protective plastic face. The spray nozzles were supplied by a high-pressure
sheets (used during the calibration phase) were removed, potable water supply delivered via a large header tank at a
and the climate side of the chamber was pressurised to pressure of  9 bar (130 PSI). The in-line gate valves
250 N/m2. This is the figure recommended by BS 4315-2: remained connected to act as an emergency shut off valve
1970; it is a static equivalent to strong wind pressure and operated from inside the climate side of the chamber. The
has the effect of exacerbating moisture penetration. The in-line needle valves were removed, however, and a single
rainfall and pressure differential was constantly maintained needle valve was used to regulate the mains water supply
for a cycle of 6 h, after which the pressure and rain are that fed a common rail connecting all four spray nozzles.
turned off for an 18 h drying cycle. This first test cycle The design for this high-pressure rainfall delivery system is
represents day 1, where the entire test programme runs for illustrated in the diagram shown in Fig. 7.
a total of 5 days. The 5-day test methodology was identical to that
The water run-off was collected at the following intervals described in test run 1. It was observed that a flow rate
after the start of each 6 h pressurised rainfall cycle: 10 min, of 0.65 L/min was the minimum rate at which a very good
20, 30, 40, 50, 60, 90, 120, 150, 180, 210, 240, 270, 300, 330, spray pattern could be achieved using this apparatus. The
and 360. That is to say, the readings are taken every 10 min average variation in the delivery rate was 70.04 L/min
for the first hour and then every 30 min for the remaining per wall. During the 6 h daily rainfall period the water run-
5 h. Since the rate of flow is known, the mass of run-off off from each test wall was collected and measured at
water collected over a 1 min period could be calculated as regular intervals.
an effective rate of absorption in ml/m2 min for each of the The water run-off collection data from each of the 5 days
four test walls. Theoretically, the initially dry test wall(s) was plotted against elapsed time on a graph. Even though
should absorb a relatively large amount of water during the the level of variation in water delivery had been much
first hour of exposure, with decreasing amounts of water improved over that of test Run 1, its effects still appeared
absorption as the remainder of the test period proceeds. It to have a significant influence. As one would expect, the
was anticipated that factors such as the total amounts of recorded mass of collected water run-off for each of the test
water absorption, rate of penetration, and the rate of walls was smaller during the early stages of the test and
decreasing absorption over time would be significantly then began to increase back towards the original delivery
affected by the soil type in each of the different rammed rate. To look at this data in isolation, however, would be
earth test walls. misleading since the delivery rates between test walls can
All four test walls ‘passed’ the test with distinction actually vary by up to 70.04 L/min. For each test wall, one
because no signs of water penetration or leakage occurred can calculate the mean absorption rate by deducting the
during the entire 5-day test run. In comparison, a similar collected amount of water run-off, at each time interval,
study was recently performed in the climate chamber on a from the set delivery rate. The mean absorption in each
series of 300 mm thick granite block walls with hydraulic SRE test wall was very low and typically less than 80 ml/
lime mortar, some with the additional application of dense min per wall. Since the typical dry mass for one of these
lime render. Most of the stone test walls began to leak 300 mm thick test walls is 280 kg, the calculated mean
during the first 6 h of exposure to these conditions, and water absorption only represents around 0.01%. It
even those protected by render began to permit water appeared that only a thin outer layer of each wall became
penetration to occur after only a couple of days. On the saturated and in doing so preventing subsequent moisture
SRE test walls, the calculated absorption rates appeared to ingress, i.e. the ‘overcoat’ effect (Fig. 8).
be masked by small, intermittent fluctuations in the rate of
water delivery. As a direct result of these issues, the
calculated data for water absorption in the test walls is
intangible. It was concluded that this particular methodol-
ogy of water delivery was perhaps only suitable for a
qualitative analysis of the time taken for full penetration/
leakage to occur, as specified in BS 4315-2, rather than
attempt to measure the rate of water absorption over time.

5. Test run 2: high-velocity rainfall simulation

Test run #2 utilised high-pressure water supplying high-


velocity raindrop spray nozzles. The purpose of this testing
was to quantify moisture absorption, erosion and rate of Fig. 7. Schematic diagram of the high-velocity spray nozzle rainfall
pressure-driven moisture ingress. The high-pressure rain- system.
ARTICLE IN PRESS
M.R. Hall / Building and Environment 42 (2007) 139–145 143

The test methodology provides the effects of static


pressure differential combined with a known quantity of
surface absorption; therefore attempts were made to
calculate the rate of water absorption per unit inflow
surface area, i.e. the initial surface absorption (ISA). The
findings were compared with the results of previous
experimental work published by the author [11] involving
100 mm SRE cube samples made from the same soil mix
recipes (433, 613, and 703). The samples had the same
material dry density and were stabilised with the same
percentage of cement (6% by mass). The graphs in Figs. 9, Fig. 9. A comparison between the ISA values for SRE test cubes and the
SRE test wall using the 433 mix design.
10 and 11 show the comparison between the ISA of
rammed earth cube samples for a given mix recipe, with the
ISA observed in the corresponding climate chamber test
wall. All of the test walls appear to have similar ISA values
to one another regardless of the type of soil mix recipe or
the day on which it was tested. However, the differences in
ISA values for the cube samples vary greatly according to
the type of soil mix recipe. There is virtually no disparity
between the cube sample and test wall ISA values for the
433-mix recipe. The test wall ISA values for the 613-mix
recipe are significantly lower than the cube sample values,
whilst the test wall ISA values for the 703-mix recipe are
Fig. 10. A comparison between the ISA values for SRE test cubes and the
considerably lower than their equivalent cube sample
SRE test walls using the 613 mix design.
values. It was hypothesised that the insignificant level of
moisture ingress that occurred in the climate chamber test

Fig. 11. A comparison between the ISA values for SRE test cubes and the
SRE test wall using the 703 mix design.

walls may result from the moisture source being dynamic


and not static (as in the standard ISA test). The forces of
capillarity and applied pressure differential, which are
working to incise absorption of the surface run-off, are
perhaps working against the kinetic energy of the moving
water.
The clayey-silt content of each test wall was kept
constant, and yet the granular particle-size distribution
was varied considerably by using different mix recipes. We
can conclude that, for full-scale test walls under simulated
rainfall conditions, the initial surface absorption of
pressure-driven water run-off appears to be independent
of the granular particle-size distribution in a soil. In
addition, it would appear that at this scale the level of clay
Fig. 8. Saturated fac- ade of an SRE test wall during high-velocity rainfall content in a soil might be the principal factor controlling
simulation. the level of moisture ingress and migration. Summarily, an
ARTICLE IN PRESS
144 M.R. Hall / Building and Environment 42 (2007) 139–145

approximate clay content (CC) of 0.1 and a silt content of


0.2 [5] can be used to produce stabilised rammed earth
walls (with 6% cement) that have a very low absorption
when exposed to pressure-driven water run-off.

6. Test run 3: embedded sensor arrays

After the first and second test runs had been completed,
an array of electronic sensors was retrofitted to each of the
four rammed earth test walls. Three different types of
sensors were installed such that the properties of tempera-
ture, relative humidity (RH), and liquid moisture content
could be monitored throughout subsequent test regimes. Fig. 12. A typical temperature depth profile analysis of an SRE test wall
The sensors were embedded by drilling a small hole from during a cyclic pressure-driven rainfall/drying regime.
the inside of the wall to the required depth and then
carefully inserting the sensor using a metal rod marked at
different depths. Once in place the sensor hole was capped Fig. 12, the cooling effects of the rainwater run-off were
and sealed using silicone caulking. In each wall, six type-T cumulative resulting in a gradual reduction in wall core
copper/constantan thermocouples (protected by hollow temperature over the 5-day period. The implications are
plastic tubing) were installed to depths of 25, 50, 75, 100, that potential may arise for interior surface condensation
125, and 150 mm. In addition, armoured thermocouples or the accumulation of interstitial condensation within an
were mounted onto both the internal and external wall SRE wall. This would strongly depend upon the vapour
faces. A single Rotronic RH sensor (encased in a protective permeability of the material, the determination of which
PTFE membrane) was embedded to a depth of 150 mm, would require further research at this stage.
whilst six gold-plated resistance probes (for moisture
content) were embedded to the same depths as the 7. Test run 4: static climate differentials
thermocouples. The sensors were energised, where appro-
priate, using a 5 V DC stabilised supply and logged The effect of temperature differential has been explored
readings every 10 min for the entire 5-day period of test further by creating various fixed temperature and humidity
run 3. gradients across the test walls. This was achieved by
The same methodology for pressure-driven rainfall that maintaining a difference in temperature/humidity between
was used in run 2 was also applied in run 3 using high- the design side and the climate side of the chamber for a
velocity spray nozzles. The target rainfall delivery rate 24 h period. All of this testing was performed in the absence
remained at 0.65 L/min per wall and the applied static of any rainfall or pressure differential. The indoor (design
pressure differential had a force equivalent to 250 N/m2. side) conditions were maintained at 20 1C71 1 and 40%
No changes in liquid moisture content or relative humidity RH 75% to represent a comfortable indoor living
were detected between the depths of 150 and 300 mm environment. The outdoor conditions (climate side) were
(inside face) from the exposed external face. From this we kept at a constantly high level of relative humidity: 75%
may deduce that, under these conditions, the test walls did 75%. This represents a damp outdoor environment that is
not appear to allow the pressure-driven moisture to typical of the inclement British weather.
penetrate as far as 150 mm into the wall. The relative Test run 4 was performed in order to provide additional
humidity recorded at the centre point of each test wall data on the interesting effect of temperature depth profile
typically remained constant with the values observed prior analysis. The test run lasted for a total period of 4 days and
to testing, and ranged between 93% and 94%. included three different outdoor temperature levels.
The observed cooling effect of the surface run-off water On days 1 and 2 the ‘outdoor’ conditions were continu-
(approx. 15 1C) upon the wall surface was significant, and it ously maintained at 8 1C 75% RH, on day 3 they were
affected the wall temperature all the way to the interior maintained at 0 1C 75% RH, and on day 4 they were
surface. The thermal behaviour for each of the test walls maintained at 8 1C 75% RH, during which time snowfall
was observed to be very similar with no significant began to occur. During all 4 days of test run 4 the sensor
differences occurring between soil mix recipes. The initial array was used for recording the performance of the test
temperature of both the internal and external wall faces walls.
was approximately 22 1C, and the temperature of the The temperature depth profiles appeared to be remark-
exposed faces were lowered by the cooling effect of the ably similar to one another and independent of soil type.
water to around 18 1C. The core temperature of each test The typical thermal performance of a test wall can be
wall gradually dropped by up to 1.5 1 (approx. 20.5 1C) represented by the example shown in Fig. 13. No
below the interior wall face temperature during the 6 h significant changes were observed in the relative humidity
period of exposure to rainfall. We can observe from or moisture content resistance probes during run 4. This
ARTICLE IN PRESS
M.R. Hall / Building and Environment 42 (2007) 139–145 145

independently of particle-size distribution. The embedded


sensor array detected no significant increase in the relative
humidity or liquid moisture content inside the test walls
from a minimum depth of 150 mm away from the exposed
face. This observation applied throughout a range of
temperature differentials and high levels of humidity
indicating a negligible risk of internal or interstitial
condensation.

Acknowledgements

Fig. 13. A typical temperature depth profile analysis of an SRE test wall The author wishes to acknowledge the advice and
during different static temperature and humidity gradients. assistance of laboratory technician Stephen Hetherington
(Sheffield Hallam University) for the experimental work
detailed in this paper.
suggests that no interstitial condensation could be gener-
ated within the confines of this test regime. References

8. Summary [1] Hall M, Djerbib Y. Rammed earth sample production: context,


recommendations and consistency. Construction and Building
The SHU climatic simulation chamber is a unique and Materials 2004;18(4):281–6.
[2] asEg. New earth structures, [brochure] available, Affiliated Stabilised
well-established base for experimental work involving full- Earth Group, North Fremantle, Australia, 2003.
scale building elements. A series of stabilised rammed earth [3] Hall M, Djerbib Y. Moisture ingress in rammed earth: part 1—the
test walls have successfully been constructed inside the effect of particle-size distribution on the rate of capillary suction,
climate chamber in a manner that conforms to established Construction and Building Materials 2004;18(4):269–80.
[4] Hall M, Damms P, Djerbib Y. Stabilised rammed earth (SRE) and
procedures and parameters for this apparatus. Test
the building regulations (2000): part A—structural stability, Building
methodologies for investigating rainfall penetration with Engineer 2004;79(6):18–21.
static pressure-differential, based upon BS 4315-2: 1970, [5] Hall M, The mechanics of moisture ingress & migration in rammed
are suitable for assessing the environmental performance of earth walls. PhD. Thesis, Sheffield Hallam University, UK, 2004.
SRE walls. [6] Taylor-Firth A, Flatt DE. Climatic simulation and environmental
All of the cement-stabilised rammed earth test walls monitoring—a facility for realistic assessment of construction
materials in-service performance. Construction and Building Materi-
exceeded the SHU climatic simulation chamber rainfall als 2001;5(1):3–7.
penetration tests based upon BS4315-2: 1970. After 5 days [7] Laycock EA, Hetherington S, Hall M. Damp towers—understanding
of exposure to static pressure-driven moisture ingress there and controlling the ingress of driven rain through exposed solid
was no evidence of moisture penetration or erosion. Under masonry wall structures. London: Confidential report for English
these test conditions, the ISA is a comparatively low value Heritage; 2002.
[8] Houben H, Guillaud H. Earth construction: a comprehensive guide.
that is similar for each test wall and appears to be 2nd ed. London: Intermediate Technology Publications; 1996.
independent of differences in the particle-size distribution [9] BSI. BS 1377-2: 1990—soils for civil engineering purposes—part 2:
between mix recipes. This indicates that the kinetic energy classification tests. London: British Standards Institute; 1990.
of the dynamic moisture source (i.e. run-off water) is [10] BSI. BS 4315-2: 1970—methods of test for resistance to air and water
penetration: part 2—permeable walling constructions (water penetra-
sufficient to exceed the capillary potential of the wall face.
tion). London: British Standards Institute; 1970.
However, since the clayey-silt content of each mix recipe [11] Hall M, Djerbib Y. Moisture ingress in rammed earth: part 2—the
was constant it may also indicate that the proportion of effect of particle-size distribution on the absorption of static pressure-
cohesive fines in the mix determines the ISA of a wall driven water. Construction and Building Materials 2005, in press.

You might also like