Professional Documents
Culture Documents
6
Dewatering
6.1 Introduction
This chapter describes bulk dewatering and residual dewatering. Dewatering is
the removal of as much water as possible before the pipeline is conditioned and
the product is introduced.
6.2 Overview
The Overview will discuss the following topics useful for understanding dewa-
tering:
The terms dewatering and drying are somewhat interchangeable; however, when
used interchangeably, the terms could be confusing. For this manual, the follow-
ing definitions apply:
Different levels of drying are determined on the basis of the type of product to
be carried. For example, a pipeline for wet gas does not need to be conditioned
to the same level of dryness as one for dry gas.
Sealing gels are used in dewatering pig trains to increase the efficiency of
dewatering. These gels increase efficiency by reducing both the amount of
bypass water in the reverse direction and air or nitrogen in the forward direction.
Sealing gels also help lubricate the pig discs that will be traveling in a dry
atmosphere. The lubrication reduces the amount of wear and bypass on the pigs.
For pipelines that are filled with seawater, a batch of fresh or potable water is
often included between two of the pigs to wash out salt deposits.
The simplest pig train consists of two bidirectional pigs separated by the propel-
ling medium. Selecting the propelling medium is discussed later in this chapter.
The first pig removes the bulk of the water, while the second pig sweeps some of
the remaining pools of water through and out of the pipeline. A simple pig train
can be used in short pipelines or pipeline sections, both subsea and on land. The
simple pig train can be followed by more pig trains that incorporate foam pigs to
pick up residual water without too much additional time required for dewatering
to be completed. In long pipelines, where propelling a pig train through the
pipeline can take considerable time, the pig train is designed to complete bulk
The distance between pigs in a train is critical. If the distance is too short, a pig
may collide with the pig in front of it. A collision occurs when the propelling
medium bypasses the front pig.
There is no definite rule available for calculating the distance to allow between
pigs. As a guideline, allow 1% of the pipeline length between pigs to ensure that
the pigs will not collide. However, if the internal surface of the pipeline is
abnormally rough and could produce excessive wear on the pig discs, increase
the distance between pigs to 1.5% of pipeline length. For short pipelines, a
minimum distance of 200 m (650 ft) between pigs is recommended. Examples
of dewatering pig trains are shown in Figure 6.1.
C ~~j B ~~I
:~,
A ~
PT1 PT1
In certain cases, nitrogen must be used to dewater a pipeline. For example, when
methanol will be used as a swab in the drying operation, air may be used as the
The selection of the propelling medium depends primarily on cost. For short
pipelines, nitrogen may be less expensive because of the volumes involved. The
availability of air compressors, air dryers, and ancillary equipment may prove to
be cost-prohibitive in these situations. However, if the pressure of the dewater-
ing train is high because of accumulated heads and changes in elevation of the
terrain, compressed air might be the most economical way to dewater the
pipeline. The volume of nitrogen needed could also be prohibitive, especially on
offshore locations where space for equipment is not available. Furthermore, for
long pipelines, nitrogen may not be available in large enough quantities. Using
compressed air, or other means of inerting the pipeline must be addressed.
Therefore, designers and clients should determine the cost of all alternatives
before deciding which propellant to use.
An accumulated head can occur if a pipeline is partially filled. The pipeline can
be partially filled because (1) it is being repaired, (2) a wet buckle during
offshore construction occurred, or (3) a change in service from a liquid line to a
gas line occurs. These heads are actually gaps in the fluid column with air or gas
being moved or propelled to create differential pressures within the line (Figure
6.2). If these gaps in fluid occur, the pressure required to move the medium in
Head Pressure
With Air and Water Ph = 0.433 (h, + h2 + h3)
With Water only Ph = 0.433 h
h is expressed in feet
Ph~__~________~____________________________________________- - L
The preparatory steps required for dewatering vary depending on the client's
needs. Typical preparatory steps for Halliburton operations appear below:
• Planning
• Engineering
• Preparing procedures
• Selecting equipment and instrumentation
• Inspecting and using testing equipment
IMPORTANT Read the contract; make sure the contract covers all aspects
of the job. Pay particular attention to the scope of work and
specifications.
The dates for submitting key documents and for finishing the work are agreed
upon with the client and are available in the contract. An example of an overall
schedule is shown in Appendix B.
• Pipeline volume
• Volume per linear meter (or foot) of pipeline
• Pressures required to launch pigs and propel the pig train through
the pipeline
• Friction losses
• Elevation differentials
Formulas and examples for these calculations are available in Chapter 13.
,-------------------------------
N2 N2 N2
Tank Tank Tank
,-----------'
I
I
I
___________ I'
I I {
I
I
I
I
I
Discharge
1/4·in. Instrument Line Hose
1·in. N2 Hose
Secured
(
I--
I Spare I
I I cassion:
I
I / I
I
: Pig Launcher l
I '-
IL _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
Subsea Manifold
____________ l
I
Make sure the piping between the air compressors or nitrogen pumps and the
pipeline includes a check valve to ensure that the full pressure in the pipeline
cannot back up into the pumps. Include a double block-and-bleed system
between the air compressors or nitrogen pumps and the connection to the
pipeline. Include a pressure safety valve in the system as near as possible to the
pipeline.
If the pipeline has not been tied in to the platform, connection points will be
available on the temporary subsea head. A sample piping and instrumentation
diagram is shown in Figure 6.4.
,-------------------------------
N2 N2 N2 N2
Tank Tank Tank Tank 1------------.,
I
I
I
----------- /
: I I
Temporary
Pig Receiver
Flow Meter 0 0
Discharge
1·in. N2 Hose Hose
Secured
(
- -- A
1-- _/ I
I Spare I I
I
I
Cassion i i
I I I
I I I
I
I
IL____________________________
Subsea Manifold II
l
" ---- /'
1
"Permanent valves or other equipment, such as pig trap closure doors, will be
operated only under the supervision and control of the prime client's operation
staff. Halliburton will provide labor assistance."
Copy the operation acceptance criteria from the specification. Remember that a
quality plan showing witness and hold points is not always required. However, if
a quality plan is needed, an example is given in Table 6.1, Page 11.
Safety
Include the following points in the Safety section:
Daily Operations Report - RF.001 Leak Check and Repair Log - RF.OO? W - Witness
Pig Launch and Receive Register - RF.002 Pressurization Report - RF.008 H - Hold
Chemical and Dosing Report - RF.003 Pressure and Temperature Log - RF.009 M - Monitor
Pipeline-Pigging Report - RF.004 Hydrotest Report - RF.010 T - Halliburton Services Test Engineer
Q Gauge Plate - RF.005 Air-Inclusion Report - RF.011 C - Client
~ Instrument Calibration Check-List - RF.006 Test-Acceptance Certificate - RF.012
(b -TCR Pressure-Chart Record -PCR
..., Temperature-Chart Record
0)
'tl
......
• Inerting the pipeline with nitrogen
• Receiving the pigs into the pig trap
• Removing the pigs from the pig trap after each pigging operation
• Accepting the operation
• Recording and reporting data
In both bulk and residual dewatering operations, if there is a doubt that the pigs
have been received, continue pumping until an agreed, predetermined volume
has been pumped (e.g., 10 % of total pipeline volume). In long pipelines, it can
take a long time to depressurize the pipeline to check the number of pigs re-
ceived and repressurize the pipeline to initiate movement of the pigs; therefore,
it is important to continue pumping to a predetermined volume.
On land, disposal might be as simple as letting the fill water run across the
landscape, or it might need to be treated to remove the chemicals that were
placed in the treated water for corrosion control, oxygen scavenging, or bacteria
control. In large-volume pipelines or large sections between pipeline testing
stations, the process of making the water safe for disposal might need to be
accomplished in-situ. Instead of being held for treatment, the water might be
treated on the fly and then dumped into the approved area.
IMPORTANT Each case is different. Do not take the last disposal criteria
and apply it to the next job without checking. Each project
has its own set of specific criteria that must be met.
Receipt of pigs into the pig trap is usually verified by pig signalers fitted to the
approach pipe and to the throat of the trap. Receipt can be further verified by
careful observation of changes in the pumping and backpressures. The approach
of the pig train to the receiving facility can also be signaled by pig tracking
devices fitted to the pigs.
For pipelines requiring inerting with nitrogen, acceptance occurs when the level
of oxygen mixed with nitrogen received at the venting end is negligible, typi-
cally less than 2%.
• The data assist in tracking the progress of the pig trains and determining
the integrity of the batches of liquids in the pig train compartments.
• The data determine if a pig is bypassing or if it has become stuck and,
if so, where.
Table 6.2 lists the data collected during dewatering, which should all be included
in the final report.