CONSTRUCTION DAILY REPORT

Project Information

Project Title: RESTORATION WORKS Job Order No.


PKG: AREA: LOCATION: PV FARM DISCIPLIN
DAY SHIFT 07:30 AM 05:30 PM

NIGHT SHIFT PM AM 07-Oct-23


WEATHER CHART MANPOWER WORKING EQUIPMENT

Civil-Construction Manager

Engineer/Site Supervisors
Assistant Site Manager

Admin Staff/Support

Telescopic Handler

Welding Machine
Site Manager/PIC
Project Manager

Equipt Operator

Field Technician
Service Driver
Safety Officer

Dump Truck
Truck (ELF)
Bulldozer
Foreman
Surveyor

Backhoe
Laborer

QA/QC

Grader
Loader
TOTAL

TOTAL
Roller

Roller
WBS SUBCON
1
SUMEC 1 1 0 0 2 1 2 0 0
8
2 2 0 0 29
1 1 2

- -

METHODOLOGY TOTAL 1 1 - - 2 1 2 - - 18 2 2 - - 29 - - - - - 1 - - - 2

IFC REG HRS 8 8 - - 16 8 16 - - 144 16 16 - - 232 - - - - - 8 - - - 8


WORK PERMIT OT HRS - - - - - - - - - - - - - - - - - - - - - - - -
WORK SCHEDULE TOTAL HRS 8 8 - - 16 8 16 - - 144 16 16 - - 232 - - - - - 8 - - - 8

WORK ACCOMPLISHMENT

WBS ACTIVITY TARGET Unit ACTUAL UNIT % OF TARGET REMARKS

BLOCK 8

Backfilling works 2,000.00 m2 2000.00 m2 100.00%

Slope protection works 120.00 meter 30.00 meter 25.00%

Final backfilling works 1.00 lot - lot 0.00%

Road works 120.00 meter 70.00 meter 58.33%

Fence & cctv installation 1.00 lot - lot 0.00%

Clearing works 1.00 lot 1.00 lot 100.00%

BLOCK 10

Road & TL post riprap protection 40.00 m3 40.00 m3 100.00%

Road-TL wingwall & culvert installation 4.00 m3 4.00 m3 100.00%

Box culvert base cleaning 1.00 lot 1.00 lot 100.00%

Construction of catch basin and concrete road 1.00 lot 0.80 lot 80.00%

Reinstallation of fence & CCTV 1.00 lot 0.45 lot 45.00%

Riprap protection on the east side 6.80 m3 6.80 m3 100.00%

Excavation of open ditch & cleaning of water way 1.00 lot - lot 0.00%

Clearing works 1.00 lot 1.00 lot 100.00%

BLOCK 1-5

Clearing works for road 1.00 lot 1.00 lot 100.00%

ISSUES/CONCERN ACTION/S TAKEN

MATERIALS AND CONSUMMABLES


MATERIAL STATUS
WBS ACTIVITY
CODE DESCRIPTION NOT INSTALLED PARTIAL % COMPLETE

Prepared By: Reviewed By:


Field Engineer/Supervisor Construction Manager Date

COMMENTS
CONSTRUCTION DAILY REPORT

Project Photos

X``

Gabion Wall Construction @Block 8

Reinstallation of Fence @Block 10

Clearing of Roads @Block 1-5