Professional Documents
Culture Documents
2
2012
The diversity
of biomass
Coverphoto © BWSC
4 The column
Photo © BWSC
www.dbdh.dk
E N E R G Y A N D E N V I R O N M E N T
Intelligent Energy Solutions
The column
By Peter Heymann Andersen, Director, Ramboll Energy Power, and Board Member of DBDH
We cannot sustain the standard of living we have today Residual waste is often considered a renewable fuel due to
without access to a reliable generation and distribution the fact that it contains some biomass, and can substitute
of electricity and heat. Hence, we must find the talent and fossil fuels; further, if not used for energy purposes, it will
resources to develope our energy supply systems. The end up in a landfill where the biomass part will decompose
major challenge today is to convert our energy system to (rot) anyway. However, waste has some components that
a direct or indirect solar driven supply. In Europe this is reduce the possibilities for achieving a high electrical
mainly wind, biomass, photovoltaics (PV), wave energy, tidal efficiency. The combination with a DH system is therefore
and hydropower for electricity production and additionally important for WtE plants in order to increase the energy
solar thermal and geothermal heat supply. Currently, wind, efficiency and secure a low gate fee.
biomass, PV and solar heating are of a scale to be of interest
in our future energy system. Although the use of biomass has been an active business
area for more than 20 years, we have seen few technological
It is important to realize that there are limits to how much barriers. The anticipated changes in the Danish Heat Supply
the various types of energy can offer. Thus it is equally Act have started a process of converting major power
important to be aware of the efficiency on the consumption plants from fossil fuel firing to biomass firing. The process
side and to focus on the efficiency in the production side. began with the use of wood pellets on the Avedøre 2 power
Similarly, we have to realize that in particular the electricity station in Copenhagen, and with the continued focus on the
supply is Just In Time (JIT) and in our part of the world it is opportunities Denmark expects to get more than 1000 MW
demand driven; i.e. the supply must match the demand. The high efficiency biomass fired electric power as CHP within
type of power plants best suited for balancing supply with the next few years. The biomass stories in this issue of
demand are the thermal coal/oil/gas fired power plants Hot|Cool show that there is an intensive development to
either based on a steam turbine, a gas turbine or both. improve both the growing of biomass and the technologies
Therefore firing such plants with biomass instead of the to improve the efficiency of the conversion to power and
fossil fuels serves several purposes: the technological risk heat.
is low, the economic risk is low, most of the infrastructure
can be maintained, and the ability to balance supply and The high degree of PV solar and wind energy input to the
demand is also maintained. power system is expected to create large fluctuations
in our power systems. Hence, well functioning district
One of the questions that we have found an answer to in heating systems and thermal plants will continue to be the
Denmark is on the size of the biomass plant: small plants important backbone of the energy system and would need
scattered all over the country to use a local biomass to be and integrated part of a smarter grid.
resource with less electrical efficiency (maybe 30%) and
some larger plants using imported, industrialised biomass in Our energy challenges can only be solved through integrated
large quantities and generating power with a substantially solutions considering our energy system as a whole. The
larger electrical efficiency (maybe 45%); in both cases the experience from the district heating area demonstrates
energy utilization is high (85-95%) due to the coupling to a that it is possible to create system based solutions to the
district heating network. Biomass is a valuable resource and mutual benefit of environment, society, consumers and
as such conversion with the highest possible efficiency to producers.
electricity is a goal; also, in order to recover the remaining
energy, a combined power and heat production with high
energy utilization is the only option.
E N E R G Y A N D E N V I R O N M E N T
P
_
5
Hundreds of Pages
to Project Success
Background:
Cornell University is located approximately 370 km (230 miles)
northwest of metropolitan New York City in rural upstate New
York. The 302 hectare (745 acre) campus is situated on a hill
between deep gorges overlooking Cayuga Lake. It consists of
approximately 250 buildings totaling 1.3 million square meters
(14 million square feet) of facilities for teaching, research
and engagement. The campus is served by district energy
systems for heating, cooling and electricity. For decades,
Cornell’s Department of Energy and Sustainability has strived
to create a highly efficient and sustainable system. Among
the many innovative projects completed is the Lake Source
Cooling system which began operation in 2000. This deep lake
cooling system cools all of campus. Cornell University, which
has pledged to reduce its GHG emissions, ultimately to zero
over 40 years, then focused on its power and heating systems
as the next step to improved energy reliability, economy, and
sustainability.
The Project:
In 2003, Cornell engineers conceived of a new 30 MW combined
heat and power (CHP) system that would burn natural gas
and supply the campussteam for heating and electricity. This
project, now completed (operational in late 2009), included
many sustainable features, including unique dual-temperature
heat recovery steam generators that help extract additional
energy from the system while maintaining the high-pressure
steam for existing steam turbines, an ability to “island” if
needed due to local weather emergencies, and extensive
emissions controls. Once approved and funded internally, the
duration of project to completion was approximately 4 years.
There were many factors, technical and otherwise, that were
critical to the successful project.
Cornell CHP plant from the inside
The Challenge:
While engineering brilliance, financial acumen, and astute The world of district energy is dominated by engineers who
administrative skills are necessities to a successful energy love the challenge of interconnecting equipment, piping and
project, more visceral characteristics may be equally wires to create sophisticated, ultra-efficient production
important: tenacity, patience, and perseverance. For while a and distribution facilities. But there is a realm unfamiliar to
complex energy project is full of technical challenges, some most which entails an equal amount of attention in order
of the biggest challenges lie in overcoming the myriad of to be successful. These are the contractual and regulatory
environmental and contractual hurdles. A host of parties will aspects of our projects. For Cornell’s project this resulted in
be involved, from administrators to regulatory agencies to hundreds of pages of formal permits and contract documents
utility companies – some of which may be distrustful of even – not including all of the informal or internal communication
your best intentions or, even worse, competitors who stand to documents . Unfortunately, these processes don’t follow the
lose money if you are successful. In this article, I will touch on laws of physics and often times they are not even rationally
some of the complex agreements and negotiations that helped constructed. The long term success of any project depends
Cornell become more energy efficient and, in the process, on successfully maneuvering through a myriad of permits
reduce our greenhouse gas (GHG) emissions more than 25%. and contracts to be allowed to purchase equipment, begin
J O U R N A L N 0 . 2 / 2 0 1 2 www.dbdh.dk
P
_
6
Hundreds of Pages to Project Success
Environmental Permits
Environmental permits are perhaps the most closely linked to
the technical aspects of any project. A full suite of detailed
information is needed to complete permit applications. This
means that before you can finish an application, you must
know the specific equipment you intend to purchase. You
must have exact technical and design details including a full
set of emission guarantees. These are normally the result of
View of CEP (Photo by jonreis photography)
the design effort of the equipment manufacturer, commonly
called vendor engineering. You may be asked to commit to The construction of this pipeline involved a contracting
emission limits for which the manufacturer is unwilling to give a process with the interstate pipeline company which is
guarantee. In this case, careful investigation and analysis must regulated by FERC. First, a Precedent Agreement (PA) was
be performed to assure that proposed permit limits can be developed. The PA defines the boundary conditions for the
attained. Then there’s the timing. Permits often take over a connection to the interstate pipeline such as the date the
year or more from application to receipt of a permit. Cornell’s pipeline must first deliver gas, the quantity and term of firm or
air permit took over a year to prepare and 11 months to obtain, interruptible capacity required, the supply and receipt points,
despite the fact that the plant was dramatically reducing the pressure requirements and the transportation tariff to be
both harmful emissions and GHGs compared to existing applied. Each one of these items must be carefully considered
equipment. Releasing the equipment supplier to manufacture with a long term view in mind. This agreement commits the
the equipment is risky and possibly not allowed without an air project to pay delivery costs for the transport of gas and the
emission permit in hand. Demolition and site preparation are cost of any infrastructure improvements in the interstate
normally allowed but starting the installation of foundations pipeline company’s system necessary to make the connection
is not allowed prior to receipt of the final permit to construct. and serve the new load. This agreement must be executed
All of this requires careful timing of equipment procurement far enough ahead of time for the modifications to be made.
and construction contracts to avoid extra project costs and/ In Cornell’s case this was executed 3 years prior to first the
or delays. use of gas because significant improvements were required. A
E N E R G Y A N D E N V I R O N M E N T
P
_
7
Construction and Reimbursement (C&R) agreement (executed with the senior administration were held to determine
2 years ahead of time) and a final service agreement (SA) were corporate risk tolerance and a hedge strategy was developed.
executed prior to the delivery of gas. The C&R agreement For Cornell this was a 3 year rolling purchase program with a
defines the construction cost to be paid for the connection and based hedge of 40% for year one, 30% for year two and 20%
metering point and its ownership transfer to the interstate for year 3. Cornell policy limits the maximum hedge amount to
pipeline company. The SA finally determines the transportation 80% of the expected usage.
rate to be charged for physical gas delivery based on the
actual costs of improvements the pipeline company makes to Electrical Issues
accommodate your project and the FERC tariff. The necessary agreements must be in place to provide a
connection to the local utility’s power system. Cornell owns
Once the gas pipeline and transportation are defined, work the substation which takes 115,000 volt transmission power
must begin on the procurement and delivery of the actual and transforms it to 13,200 volts for delivery to campus. It
volumes of natural gas required for the project. In Cornell’s was necessary to completely renovate this facility to accept
case, a transition from coal as a primary fuel to natural gas the relatively large quantity of new generation. In the summer
dictated that a large quantity of gas would be burned 3.12 GJ/ the connection imports power from the grid and in the winter
year (2.7 million dekatherms per year). A request for proposal power is exported to the grid. The financial implications of
was developed for gas procurement. The gas supplier’s role is the local utility’s standby electric service tariff must be fully
to assure the procurement of the transportation and physical understood. This tariff defines the cost to be paid for the
commodity on a day to day basis and to execute hedges as utility to provide power in the event that the generators are
requested. The culmination of the RFP is the industry standard not operating. A utility interconnection agreement is also
North American Energy Standards Board (NAESB) contract required by the state regulatory authority. This is a highly
which governs the activities of the supplier. technical document which dictates a myriad of requirements
to assure that the new generation cannot cause harm to the
Natural gas is traded in a well-established transparent utility’s electric grid that the system is properly monitored and
market and is a storable commodity; hence there are many that requirements for metering are met. During the design of
alternatives to hedge risk. Corporate risk tolerance is the the interconnection, very close attention must be paid to the
driver that determines the strategy to be employed. Cornell utility’s design requirements. If these are not followed carefully
developed an energy procurement policy to define the envelope there is a significant risk that the connection cannot be
within which energy procurement may occur. It includes energized. Checking and re-checking with the Utility to assure
items such as the time and financial duration of the energy the adequacy of the design is advised. This agreement often
portfolio, single transaction limits, types of instruments to be specifies that under certain extreme conditions the Utility
used, credit worthiness of counterparties, program oversight can remotely shut down the generators without notice. In the
requirements and reporting requirements. The policy also end the Utility Company’s personnel perform testing, proving
delegates the authority of fuel purchasing to the department proper system operation. Adequate time must be provided in
to allow for quick decision making in a fluid market. Discussions the schedule for this work.
J O U R N A L N 0 . 2 / 2 0 1 2 www.dbdh.dk
P
_
8
Hundreds of Pages to Project Success
The agreement also includes many legal aspects such the generator to be synchronized until the agreement is fully
as indemnification, force majeure, dispute resolution, executed. In Cornell’s case, it was just minutes between the
consequential damages, insurance requirements and terms time this contract was executed and first synchronization! The
of termination to name a few. Generally, the language in this last agreement executed by Cornell was the power purchase
document is driven by regulation so modification is possible agreement. This sets the terms by which the Utility will accept
but difficult. It is important that the draft interconnection power (kilowatt-hours) exported to the grid and compensate
agreement be obtained as early as possible in the project the generator. It does not address the value of generator
so the legal team can seek to understand and attempt to capacity (grid demand reduction). It should not be assumed
address aspects of the contract that are normally not agreed that the utility will agree to compensate for this power. State
to and are difficult to accept. It is important to note that the electric tariffs or federal regulation may dictate the value of
Utility will not allow the interconnection to be energized or the power produced and whether the Utility is obligated to
take the power. In Cornell’s case, the
Utility resisted taking power due to
its interpretation of FERC rulings.
E N E R G Y A N D E N V I R O N M E N T
P
_
9
Looking Back
As we learned at Cornell, there are significant activities that are
part of energy projects that do not involve just the pipes and
wires. I hope that by describing Cornell’s experience this article
will assist in the success of other projects. Technical expertise,
astute organization, and human and financial resources are
needed as each of these agreements is completed. In addition,
you will need a tenacity and perseverance! No two projects
are the same; therefore you will have your own set of issues
to discover. But hopefully, this explanation provides enough
of a road map to aid in determining what is required for your
particular situation. We often become consumed by the details
of the projects we build. We must remember that somehow
by aligning all of the different project components we create
systems which are part of the solution to many of the energy
and climate issues we face, both today and in the future.
Number of Ithaca Campus Buildings Over 250 buildings, 1.3 million m2 (14 million SF)
Size of Ithaca Campus 302 hectares (745 acres)
Number of customers on Over 20,000 students representing every state and 110 nations
the Ithaca campus Over 9,600 staff and faculty members
Number of Colleges on Ithaca Campus Eleven (7 undergraduate, 4 graduate and professional)
Number of Courses Available 4.000
Steam/CHP System
Year the Steam District Energy System Was Installed 1922
Gas Turbines 2 - 15 mw Solar Titan w/ 19 kg/sec
(150,000 pound per hour) HRSG and duct burners
Boilers 3 - 12.6 kg/sec (100,000 pound per hour) D-type
Annual Steam Production /Peak 500 million kg (1.1 billion pounds)/52 kg/s
(410 thousand pounds per hour)
Annual Cooling Production /Peak 46 million ton-hrs/25,000 tons
Annual Electricity Use/Peak 250 GWH/35 MW
Annual Steam/Electricity proguced by Cogen System 340 million kg (750 million pounds) / 180GWH
Cooling produced by Lake Source Cooling 98%
Steam Distribution Piping /# of Vaults 21km (13 miles) / 186
J O U R N A L N 0 . 2 / 2 0 1 2 www.dbdh.dk
P
_
10
Guldborgsund Bridge
The energy and water provider Guldborgsund Forsyning in Denmark measured by price, operational reliability, security,
Denmark installed 15,600 smart heat and water meters with environmental impact and service. The parameters are carefully
remote meter reading in six months. chosen for being of most importance for the customers in the
supply area. The strategy plan concerns both heat and water
From signing the contract with the solution provider on 18 May supply as well as waste water treatment and stretches until
2011 till installation of the last meter, just six months went by; 2014. The plan is an overall investment plan of hundreds of a
and the project was officially finalized on 15 December 2011. three-digit million amount of which the AMR project is just the
first preliminary goal that has now been reached.
The project was carried through by an extraordinary will to
cooperate which has been absolutely essential for keeping According to Flemming Bach remote reading of water and heat
up with the extremely tight schedule. From Guldborgsund is an absolute necessity to achieve efficient administration and
Forsyning CEO Flemming Bach expresses his happiness with a a high degree of customer satisfaction. ”Our plan promises
unique cooperation. But he himself deserves not least a great to reduce waste of water and heat and to inform customers
deal of credit for reaching the goal in time. about how to use water energy in a better way. This requires
a good overview of the consumption and thus many readings
Some of the most important learning points for all parties are of the meters.”
that good project management and keeping a close dialogue
are factors of great importance for a quick and hassle free Remote reading does not only relieve customers of the
implementation. Under tough conditions like a tight schedule, troubles with self-readings, it also makes it possible to offer
the values that secure a successful project are openness a range of services such as targeted energy consultancy and
about occurring problems and mutual trust in everybody leak monitoring.
taking responsibility for the common best.
In general, self-reading causes some administrative problems,
Customers in focus as it may be difficult for customers to read the meters correctly
For Guldborgsund Forsyning, the Automatic Meter Reading – and in some cases, for the utilities to make customers read
(AMR) implementation is the preliminary culmination of a the meters at all. Because Guldborgsund Forsyning can now
process which began in 2010. At that time, the utility laid out collect the correct data on time, the simplified administration
an ambitious strategy plan with the aim of moving the energy is in addition resulting in a more solidary arrangement with
provider into the league of the 25 most efficient utilities in fewer costs being divided among the customers.
E N E R G Y A N D E N V I R O N M E N T
P
_
11
Battery driven ultrasonic water meter, MULTICAL 21, with remote meter
reading for installation in outdoor meter shafts. The ultrasonic metering
principle has higher accuracy than mechanical metering and is thus a means
Worn out mechanical water meters. of securing that all consumed water is accounted for.
J O U R N A L N 0 . 2 / 2 0 1 2 www.dbdh.dk
P
_
12
Probably the world’s fastest implementation of an automatic meter reading project
Project scope:
Total number of metering points: 15,600
Heat meters MULTICAL 601
with RadioRouter module: approx. 5,500
Heat meters MULTICAL 6
with radio module: approx. 10,000
Water meters MULTICAL 21
for installation in meter wells: approx. 800
Contract signed: 18 May 2011
First delivery: 1 June 2011
Last delivery: 1 October 2011
Project closed: 15 December 2011
Termis Operation
Real-time information about your network
By using Termis Operation in your daily work, all employees can
focus on delivering the best possible service to the consumers.
is becoming
E N E R G Y A N D E N V I R O N M E N T
P
_
13
DISTRICT HUMOR
J O U R N A L N 0 . 2 / 2 0 1 2 www.dbdh.dk
P
_
14
focus
The
diversity
of biomass
The harvest ends up in the radiator
Text originally published in “Fjernvarmen” by journalist Flemming Rasmussen, the Danish District Heating Association
E N E R G Y A N D E N V I R O N M E N T
P
_
15
Breakthrough takes collaboration Only a few years ago many considered energy willow as a
Trustrup-Lyngby District Heating Plant participates in a fuel on trial stage. Today it seems as if the energy willow
project ruled by AgroTech, which is an authorized technological is here to stay, even if there still are some challenges. So
service institute which offers impartial consultancy and is the assessment for technical consultant at the Danish
provides technological services, and supported by The Danish District Heating Association Henrik Andersen, who follows
District Heating Association’s F & U account. This means the biomass area closely.
that the combustion of the willow that is reaped today will
be followed closer, partly by recurrent measurements. The "The energy willow has shown potential as fuel and it is so
aim is to gather more information and knowledge about how widespread that it is no longer considered an experiment
willow burns in wood chip boilers. So he urges district heating but instead real production. But, as is the case with all
plants and farms to be active co-players in order to help the new types of fuel, there is still a lot to be learnt when it
development on its way. comes to use the willow in the best possible way - and
in this case also how the willow can interact with other
types of biomass in the best possible way."
J O U R N A L N 0 . 2 / 2 0 1 2 www.dbdh.dk
P
_
16
focus
The By Anders M. Fredenslund, Post doc and
diversity Thomas Budde Christensen, Associate Professor,
of biomass Department of Environmental, Social and Spatial Change, Roskilde University
The bay of Køge Bugt is, like many other coastal waters in Solrød Biogas - key figures
Denmark, nutrient rich. This leads to a large amount of seaweed
Raw materials 154,800 tons/year (14,600 tons sand
washing up on the shores of the bay each year. A thick “blanket”
is removed from cast seaweed)
of decomposing seaweed sometimes extends 50 meters into Digester biomass input/ 140,000 tons /
the bay. Due to bad odor, and since the seaweed prohibits output pr. year 132,000 tons
recreational use of the sandy beaches, local inhabitants have Biogas production 5.4 mil. m3 CH4/year
a strong wish to have the material removed from the beach Heat produced 28.5 GWh/year
and water. This is now being done, causing several thousands Electricity produced 24.5 GWh/year
Heat use 2.2 GWh/year
of tons of organic waste, which needs to be treated each year.
E N E R G Y A N D E N V I R O N M E N T
P
_
17
The overall aim of the study was to develop a bioenergy concept From these assessments it was concluded that 154,800 tons
in a region with a relatively low amount of livestock, and thereby (wet weight) of raw materials were available for anaerobic
manure, by including “alternative” biomass fractions such as digestion, where app. half of this was pectin waste from
cast seaweed and organic waste from production of pectin CPKelco. Gas formation tests were performed of the “new”
and carrageenan. Specific aims included: types of raw materials: pectin waste and cast seaweed. From
• Determination of availability and suitability of organic measured gas production rates and amounts of available
materials for biogas production materials it was possible to predict the amount of gas
• Optimization of collection and pre-treatment of organic produced at the facility, which formed the basis for economical
materials and environmental feasibility assessments.
• Development of technological and economical optimal
incorporation of energy production in the local energy Choice of gas utilization
supply infrastructure Three biogas plant concepts were developed, which differed in
• Environmental assessment type of energy utilization:
• Evaluation of possibilities of utilization of de-gassed • Use for process energy at the pectin production facility
biomass (Concept A).
• Biogas upgrade and supply to the natural gas grid (Concept
B)
Green house gas reductions
• Production of electricity and heat in a gas engine, where
the heat energy is supplied to the VEKS district heating
45000
grid (Concept C).
40000
35000 Fertilizer substitution Various factors had to be taken into consideration when
Reduction of methane choosing between the three “concepts” and the final choice
30000
emissions
was combined heat and power (CHP), with the heat energy to
25000 Heat productions be utilized in the large VEKS district heating grid.
20000 Transport of biomass
15000 Electricity use One factor in making this choice was an evaluation of the
effects on green house gas emissions of each of the three
10000
plant concepts. A baseline method was used where positive
5000
and negative effects were quantified in case of constructing
0 a biogas plant compared to the present situation. Positive
Net reduction (t CO2 eq. year -1)
-5000 effects included in the calculations were substitution of fossil
fuel use, substitution of fertilizer with degassed biomass, and
reduction of methane emissions caused by anaerobic decay
Availability of raw materials of seaweed and other biomass fractions. Negative effects
The three main raw materials considered were: pectin waste, included electricity use at the biogas plant, and transport of
cast seaweed and manure. A local entrepreneur has collected biomass to and from the biogas plant.
cast seaweed along the entire 3.7 km coastline in Solrød
Municipality in recent years. According to the entrepreneur, Environmental benefits
the amount collected in 2009 was 4,000 tons of material Assessments of net reduction of green house gas emissions
corresponding to 1,080 tons/km. Interviewing the production suggest that production of CHP for supply to the local district
manager at the local pectin and carrageenan manufacturer heating grid would result in the highest net reduction in
provided data on amounts and compositions of pectin and greenhouse gas emissions. The least favorable plant concept
carrageenan wastes, which were available for anaerobic was found to be upgrade of biogas for injection to the natural
digestion. gas grid. This is partly due to a considerable electricity use of
the upgrade process.
The Danish Ministry of Food, Agriculture and Fisheries
maintains a database on livestock covering every farm in The assessment shows that reduction of uncontrolled
Denmark. This data is publicly available, and was used to methane emission results in app. 30% of the net reduction
determine the number of pigs and cattle within a radius of 15 of green house gas emissions. The calculations behind these
km of the proposed site of the biogas plant. Multiplying the figures are, however, based partly on rough estimates.
number of cattle and pigs retrieved from the database (online
at http://www.glr-chr.dk) with data from the same authority
on average amount of manure per animal, a potential for pig
and cattle manure for use for biogas production was found.
J O U R N A L N 0 . 2 / 2 0 1 2 www.dbdh.dk
P
_
18
Utilizing local bio-resources in Solrød Municipality
A valuable environmental benefit is the removal of nutrients The next steps towards realization of the bioenergy concept
from the coastal area caused by removal of cast seaweed. include preparation of a final, detailed plant design, securing
From assessment of amounts and measured nutrient content contracts with biomass suppliers and energy companies,
of the collected seaweed it was found that collection of securing necessary permits and establishing a bioenergy
seaweed from Køge Bugt can remove 120 tons N/year. The company, which will be responsible for building and operating
entire input to Køge Bugt of nitrogen including both natural the biogas facility. Solrød Municipality is presently negotiating
and anthropogenic sources is estimated to be app. 1,800 tons with the EU with regards of financial support of these activities
N/year. An action plan to reduce the nutrient load to Køge under the Intelligent Energy Europe Program.
Bugt has been laid out. The action plan lists initiatives that will
reduce the nitrogen load to Køge Bugt by app. 86 tons N/year Lessons learned
at a yearly cost of 5.7 million €. The cost of collecting and pre- Several positive effects of realization of the biogas plant
treating cast seaweed for production of biogas is estimated were identified: net CO2 reduction of app. 40,000 tons CO2/
to be app.1/10 of that, and furthermore result in revenue due year, utilization of nutrients from cast seaweed and pectin
to energy production. waste, income from energy production, improving conditions
for recreational use of the local beaches and removal of
Stage of the project considerable amounts of nutrients from the local coastal
The feasibility study was finalized December 2010. Based on waters, which suffer from eutrophication.
the findings of the City Council Solrød decided to proceed in
constructing a biogas plant based on the mentioned waste Cast seaweed may not prove to be the ideal raw material from
fractions. A formal agreement between the municipality and a biogas plant operator perspective: its availability varies
CPKelco has been signed, ensuring that pectin waste will be greatly over the year (and from year to year); it may contain
supplied to the biogas plant. Economic evaluation of the large amounts of sand and may need pre-treatment. However,
concepts showed that a biogas plant using the described mix recycling of nutrients and reduction in methane emissions are
of organic material could be built and operated with a sound considerable advantages of using it for biogas production.
economic performance.
Since then, an environmental impact assessment was For further information please contact:
completed where the precise location of the construction Anders M. Fredenslund
site was specified. Gas production of the mix of materials was Thomas Budde Christensen
Roskilde University
tested in pilot scale digesters.
Universitetsvej 1 DK-4000 Roskilde
Institut for Miljø, Samfund og tbc@ruc.dk
Rumlig Forandring (ENSPAC) andersf@ruc.dk
Isoplus Denmark A/S • Korsholm Alle 20 • DK-5500 Middelfart • Tel.: +45 64 41 61 09 • iso@isoplus.dk • www.isoplus.dk
E N E R G Y A N D E N V I R O N M E N T
P
_
19
focus
The
diversity
of biomass
J O U R N A L N 0 . 2 / 2 0 1 2 www.dbdh.dk
P
_
20
Renewable energy in the District Heating system in Greater Copenhagen
Copyright BWSC
If the conversion to biomass should be credible, the biomass important to keep an eye on the biomass consumption so that
must of course be sustainable – and the CO2 accounts must it does not increase unnecessarily. As fossil fuel biomass is a
be correct. Unfortunately it has not yet been managed to limited resource and its use is not - as Concito also points out
adopt binding sustainability requirements for solid biomass in that - always CO2 neutral.
the EU but we expect - and hope - that the Danish government
will work hard for that to happen. It is therefore essential that biomass is used where it makes
most benefit to society. Using biomass in efficient CHP plants
What VEKS together with Copenhagen Energy and CTR can do is one of the most important ways to use biomass with
- as the largest buyers of DH in Denmark - is to make demands reasonable economy.
on our DH suppliers when we buy DH based on biomass:
• Biomass from forest that is original and worthy of Energy conservation, solar heating and geothermal
conservation, such as rain forest and jungle, must not be In the long term, biomass alone is not the solution to the
used. conversion of the DH system in the Greater Copenhagen from
• The origin of the biomass should be documented, so that it fossil fuels to renewable energy. It will become necessary to
is clear where the biomass is coming from. find alternatives to the use of biomass in DH system as the
• The producers of wood pellets should as far as possible demand for biomass for other purposes increases.
avoid using fossil fuels for the production of the pellets.
Regardless of how DH in the future is generated it is necessary –
The presentation of these claims has happened in a good, when it comes to resources - to focus on energy conservation.
constructive dialogue with the owners of CHP plants in And here the DH companies have a clear interest in motivating
Greater Copenhagen - DONG Energy and Vattenfall. As an customers to focus on energy savings. Why? Because if the
integral part of VEKS’ CSR policy, we will annually report on existing customers reduce the energy consumption, capacity
the used biomass quantities, types and origins. Furthermore in the existing transmission system is released, which allows
VEKS - along with CTR and Copenhagen Energy – will follow the a cheaper extension of the DH system to new customers.
ongoing sustainability debate. This means that there will be more customers to share the
fixed costs, which will either reduce the heating cost for all
It is VEKS’ opinion that if the shift from primarily coal to – or create better earnings for the DH companies. There is
biomass takes place in a responsible manner, the use of thus no contradiction between doing business in selling DH
biomass is the best solution here and now when we want to do and simultaneously motivate customers to reduce the heat
something for the climate in the coming years. However, it is consumption.
E N E R G Y A N D E N V I R O N M E N T
P
_
21
Summary
The DH system in Greater Copenhagen
will in the next few years be
characterized by a production system
where most of the used fuel will be
biomass - and a little later in the
future also a significant proportion
geothermal heat. It is therefore quite
feasible that the DH system in Greater
Copenhagen will have a significant
stake in Copenhagen as one of the
first capitals of the world - possibly
the first - being CO2 neutral in 2025.
sustaining
gREEn HEat
converting the energy sector to green energy requires
knowledge and insight. ramboll is the owner’s engineer
for a new large district heating network south of
copenhagen where cHP based on biomass supplies
green power and heat to the local community.
www.ramboll.com/re
J O U R N A L N 0 . 2 / 2 0 1 2 www.dbdh.dk
P
_
22
focus
The
Biomass - a renewable and flexible
diversity
of biomass
energy source for heating towns
By Mr. Jens Dall Bentzen, Managing Director, Dall Energy
More than 100 towns in Denmark are daily supplied with energy Low emission heat only biomass plant in Bogense
from the local biomass heating plant. The town Bogense on the north coast of the Island Funen
in the center of Denmark is an example of a town that has
More and more of the fossil-fuelled heating plants are recently switched from natural gas to biomass.
converting to biomass as prices of fossil fuel and awareness
of CO2 emissions increase. Until 2010 the heat for Bogense was produced by natural gas.
Most of the heat was produced CHP mode - gas engines -, and
The use of forest chips at district heating (DH) plants has peak load heat was produced in a gas boiler.
increased significantly since the first systems came into
operation at the beginning of the 1980s. While there were In 2010 the board of the DH Company decided to build a
only three wood chip-fired DH plants in 1984, the number has biomass plant.
increased to approx. 100 plants today.
Wood chip-fired DH plants are established either in order to At that time Dall Energy was testing a 2 MW prototype of the
replace gas-fired DH plants connected to old DH systems, or as Dall Energy furnace close by. The plant manager of Bogense DH
new plants and systems. Currently there is a trend in Denmark Company, Peter Lind, found the furnace very interesting as the
where domestic boilers in individual households supplied by combustion appeared to be very clean compared to state-of-
the natural gas grid are replaced by DH. Often these new DH the-art technologies.
systems are fuelled with heat from biomass plants.
Supported with a grant from the Research and Development
Typically the heat-only biomass plants at Danish DH plants are programme EUDP, an agreement was made between a turnkey
designed for the generation of heat in the range of 1 MW and contractor, Dall Energy and Bogense DH Company. Now the
10 MW. plant is supplying the town of Bogense with renewable heat.
Most biomass plants in Denmark are based on grate The performance of the new biomass furnace has been verified
combustion technologies. However, new biomass heating by an external institute:
and biomass heat and power (CHP) technologies are being • Dust emissions from the furnace are reduced by 90-95%.
developed and implemented in new demonstration projects. • CO emissions are reduced by 95%.
This article describes some of these new technologies and the Due to these very low emissions the plant in Bogense is
demonstration projects. simpler than other biomass plants. For instance: There is no
multicyclone, ESP (electrostatic precipitator) or bag filter, but
emissions are still way below emission limits.
E N E R G Y A N D E N V I R O N M E N T
P
_
23
Combination of biomass & solar The Marstal project aims at supplying the town of Marstal
A new trend in Denmark is the combination of heating from with 50% of solar energy and 50% of energy from biomass.
biomass & solar: In the winter period the biomass plant is The Marstal plant comprises a 15,000 m2 solar system, a CHP
the prime producer of heating, but in the summer period biomass system with a 4.0 MW wood chip thermal oil boiler and
the heating is provided by solar panels from solar collector a 750 kWel ORC (Organic Rankine Cycle) and 75,000 m3 pit heat
fields that are placed in the outskirts of the town. In this way storage.
considerable amount of fuel can be saved.
The Marstal project is supported by the EU 7. Framework
In some cases large heating storages are built, and hereby hot programme. Read more at http://www.solarmarstal.dk/
water produced in the summer can be stored and used in the SUNSTORE%20.html.
fall, thus saving even more fuel.
Next generation medium-scale biomass CHP plant
The solar collector projects are especially feasible in countries As in other countries Denmark focuses on CHP. For medium-
where there is considerable taxation on fuels for DH (such as scale biomass plants the focus has been on gasification
Denmark). systems (as in Hillerød) or ORC systems (as in Marstal). The
ORC systems have proven to be very reliable, which is very
Examples of such projects are the projects in Hillerød and in important for plant operators.
Marstal:
A new demonstration project is now being prepared by Dall
The Hillerød project aims at supplying a new development Energy, where the low emission Dall Energy furnace is combined
of the city Hillerød with CO2-neutral heat and power. This is with an ORC installation. This project will demonstrate a low
done via a two-stage biomass gasification system and a large emission, reliable, medium-scale biomass CHP plant. The plant
solar collector system. The two stage gasification system was is planned to be in operation in 2013. The host of the project is
originally developed at the Technical University of Denmark, the utility company SEAS-NVE in Denmark. The demonstration
but now the technology is to be commercialized by the Danish project is supported by EUDP.
boiler manufacturer Weiss A/S.
The Hillerød project is supported by the EU programme For further information please contact:
J O U R N A L N 0 . 2 / 2 0 1 2 www.dbdh.dk
P
_
24
By V.S. Gusev, General Director of Scientific and Research Center ENIT and
Kasanzev Nicolay Nicolaevich, Director of Golovenkovsky District Heating
Results of the
project
TACIS ERUS 9404 in Tula
Part of the water treatment (part stream filter and additives to stabilize pH and reduce corrosion)
The demonstration project TACIS ERUS 9404 on modernisation The project included:
of existing district heating network in the Golovenkovsky village • improvement of water treatment
of the Tula region was implemented from October 1995 to April • leak detection
1998. Since 2000 ENIT has been responsible for maintenance • production of hot tap water (as an alternative to
services of the equipment. unauthorized tapping of the district heating water)
• internal draining of ducts
The TACIS project included several components. One of them
had the objective to improve the efficiency and lifetime of Almost 14 years have already passed after the official
the district heating system in the village Golovenkovsky. This completion of the project. Now it is possible to state that
component of the project was implemented successfully the installed equipment, introduced technologies and
by Ramboll in co-operation with Tula Energy Centre and the recommended methods for monitoring over district heating
district heating company. system not only allowed the district heating company LLC
”Teploservis” to reduce energy costs but also had a positive
influence on social factors of the village.
E N E R G Y A N D E N V I R O N M E N T
P
_
25
Conclusion Vejle
Based on this project we demonstrate a real possibility of how
to increase the efficiency of existing district heating systems
in small towns and villages of Russia by implementation of
low cost activities which is a very acute topic due to existing
financial deficit.
Fredericia
Introduction of the project results in other towns
Th results of the described project were fully used in Sosensky
town of the Kaluga region, where 4 boiler houses supply heat
and hot water to the town.
Middelfart
Kolding
Similar equipment (water treatment, plate heat exchangers,
Hydro-X and Grundfos pumping equipment) is used at all boiler
houses. The search of leakages is carried out with application
of colouring addictive ”URANIN”. The mentioned activities and
constant monitoring over heating networks have allowed heat
supplying company LLC ”KalugaEnergoInvest” to become a
leader in supplying heat to the town.
J O U R N A L N 0 . 2 / 2 0 1 2 www.dbdh.dk
Annonce til tvis nov 2009 60x200 med Diagram.indd 1 05-01-2010 11:58:32
P
_
26
latest news
DANISH ENERGY EVENT IN KYIV
On 26 & 27 April, a large group of Danish companies participated The Eastern Europe Energy Efficiency and Environment
in an Energy Event arranged by the Danish Embassy in Kyiv, Partnershif (E5P) is a newly established multi-donor fund
Consulate General in St. Petersburg and DBDH on the occasion with the following key objectives: 1. Improvement of energy
of a Danish EU-Presidency celebration in Kyiv on 27 April. efficiency and 2. Significant reductions of CO2 and other green
house gas emissions.
E N E R G Y A N D E N V I R O N M E N T
P
_
27
J O U R N A L N 0 . 2 / 2 0 1 2 www.dbdh.dk
P
_
28
AEROVIT
M E M B E R C O M P A NY P R O F IL E
By Kathrine Windahl, Information and Marketing Manager, DBDH
Soot blowing specialist company Aerovit is based in the Aerovit operates with very high power in the shock waves. The
outskirts of Horsens, Mid-Jutland, Denmark, and here I meet product is delivered with efficient soundproofing of the system
with managing director of the company Mr. Søren Amby who and, finally, the product is delivered with a patented cooling
offers a short guided tour of the premises and the factory system that ensures functionality at high temperatures and at
where the Aerovit products are produced. a corrosive environment.
The products What makes the company unique is the fact that they have
Aerovit is a system for soot blowing with shock waves. taken out a patent on the cooling of the valves as well as
The system operates on pure compressed air ensuring a the soundproofing system so that the valves can be placed
continuous cleaning of all kind of boiler systems. In a fraction in all kinds of areas, and according to Søren Amby potential
of a second 400-600 liters of air are under high pressure blown customers are often referred to a plant close by the factory
through a special valve, the process of which generates a very as reference plant. This Aerovit system dates back to 1992,
powerful pressure blow that is led into the boiler construction. proving that the product really is a durable one. However, the
The blow eliminates sediments in boiler pipes and boiler company has also just developed a brand new valve unit. Up
compartments in the area in front of the system. The system until now they have been using a basic type valve which was
has an internationally patent. modified and patented. But now the company has its own valve
where everything is integrated.
A continuous cleaning of the boiler results in a proven higher
efficiency and numerous stoppages for boiler cleaning can Aerovit is supplying primarily to boiler producers all over
be avoided. Thus oil consumption on supplementary energy Europe, but in the recent years they have also supplied to the
supply will be reduced due to less cleaning stops. Since the marine market and installations with catalyst technology. Last
manual boiler cleanings will be less the working environment year the company witnessed its largest turnover ever, and
will improve as the manual cleaning task is a hard and health the company has expectations of an even better result this
threatening task. The fuel consumption is smaller per produced year. (At present they are counting on an order corresponding
MW and thus CO2 emissions will be lower. And the investment is to half a year’s revenue.) So things are looking very good for
expected to yield interest in 3-24 months’ time. Aerovit indeed.
E N E R G Y A N D E N V I R O N M E N T
P
_
29
The case of the oil refinery Orlén Lietuva The situation after the Aerovit installation
Last year the company was contacted by the Latvian oil refinery Aerovit was installed in April 2011 on both boilers with immediate
Orlén Lietuva, who sent Aerovit an unsolicited email in which results. The steam production of each boiler remains stable
they asked if Aerovit would carry about the task for them. around 17t/h, which means 34t/h for both boilers. The refinery
therefore gained 19t/h for both boilers. In order to produce
The situation before the Aerovit installation these 19t/h of steam on an oil boiler, Orlén Lietuva should use
Orlén Lietuva Refinery has two boilers which were losing a around 11.6 mio. liters of oil/year. The payback time for this
considerable amount of heat due to catalyst dust build- project was only 3 months.
up in the tubes. After two months of operation the boilers
tubes were fully covered by catalyst dust, but the refinery’s The numerous Aerovit installations worldwide have proven
own technicians were not able to stop the boilers for manual considerable energy and fuel savings for the customers, and
cleaning as this would mean that the whole refinery would have thus considerably reduced emission of soot particles and CO2
to shut down. to the environment.
t/h
20
18
16
14
12
10
6
With Aerovit
4
Without Aerovit
2
0
days
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
The task of developing these countries is enormous and the challenges can be seen as insurmountable, but Director Erik
Rasmussen has with over 8 years of experience in Russia created a good base in collaboration with DBDH through joint export
promotion, and has thus achieved a good impact towards the Russian authorities and created awareness about the technology
behind Aerovit.
The expectations for these markets are high due to the need for efficient energy utilization. The Russian Government has
through legislation created a pressure on the individual regions to effectively improve energy efficiency. Furthermore, it
has been decided to attempt to exploit the resources available in addition to gas, namely mazut (heating oil), coal, bio fuels,
and combustible waste. These boilers therefore have the company’s attention and Era-Power LLC hopes to contribute to a,
compared to today, significant improvement of the utilization of the calorific value of these fuels and benefit the environment
as well as the Russian population. The large economic savings that are achieved by using the Aerovit system will be used directly
for the reduction of the tariffs that the district heating consumers currently pay for the heat.
In addition to Russia Era-Power LLC works at present to establish subsidiaries in both Ukraine and Belarus which are also
largely deselecting expensive gas for other fossil fuels, wood chips and waste, all of which fit the Aerovit system perfectly.
J O U R N A L N 0 . 2 / 2 0 1 2 www.dbdh.dk
P
_
30
list of members
Aalborg Engineering Phone +45 9631 3950 Danfoss Phone +45 7488 2222
Supplier of boilers and boiler systems Fax +45 9631 3951 Heating controls, metering Fax +45 7449 0949
ae@aalborg-engineering.dk and pump speed control danfoss@danfoss.com
www.aalborg-engineering.com www.danfoss.com
ABB Phone +45 4450 4450 DESMI Phone +45 9632 8111
Monitoring and control for Fax +45 4450 4311 Pumps, pump systems and equipment Fax +45 9817 5499
district heating networks abb@dk.abb.com desmi@desmi.com
www.abb.com www.desmi.com
Aerovit Phone +45 8692 4422 E.ON Danmark A/S Phone: +45 4485 4100
Boiler cleaning Fax +45 8692 2919 Tore.Harritshoj@eon.dk
sales@aerovit.dk www.eon.dk
www. aerovit.dk
AffaldVarme Aarhus Phone +45 8940 1500 Envotherm Phone +45 7365 0900
jawi@akv.aarhus.dk Waste water solutions Fax: +45 7442 4770
www.aarhuskommune.dk info@envotherm.dk
www.envotherm.dk
Albertslund Fjernvarme Phone +45 4364 8692 Fjernvarme Fyn Phone +45 6547 3000
District heating company Fax +45 4364 3888 Municipal district heating supply Fax +45 6547 3001
albertslund@albertslund.dk kontakt@fjernvarmefyn.dk
www.fjernvarmefyn.dk
Amagerforbrænding Phone +45 3268 9300 Focus Energy Phone +45 9714 2022
Waste and energy company Fax +45 3268 9393 Biomass-based boiler systems Fax +45 9714 2686
amfor@amfor.dk post@focusenergy.dk
www.amfor.dk www.focusenergy.dk
ARCON Solar A/S Phone +45 9839 1477 Forsyning Helsingør Phone +45 4840 5050
Large-scale thermal solar systems Fax +45 9839 2005 Muncipal district heating supply sag@fh.dk
www.arcon.dk www.fh.dk
Broen Phone +45 6471 2095 Frederiksberg Forsyning Phone +45 3818 5100
Ballomax valves Fax +45 6471 2195 Municipal district heating supply Fax +45 3818 5199
broen@broen.dk ff@frb-forsyning.dk
www.broen.com www.frb-forsyning.dk
Brunata Phone +45 7777 7000 Grontmij Phone +45 4348 6060
Heat cost allocators, heat meters, Fax +45 7777 7001 Consulting engineers and planners Fax +45 4348 6660
water meters and heat and water brunata@brunata.dk info@grontmij.dk
accounting service www.brunata.com www.grontmij.com
BWSC Phone +45 4814 0022 Grundfos Phone +45 8750 1400
Heat & power plant developer, turnkey Fax +45 4814 0150 Pumps, controls and Fax +45 8750 1490
and operation contractor sales@bwsc.dk related equipment grundfos@grundfos.com
www.bwsc.dk www.grundfos.com
Cowi Phone +45 5640 0000 HentechSolution ApS Phone +45 4390 4720
Consulting engineers and planners Fax +45 5640 9999 Mechanical seals Fax +45 4390 4775
cowi@cowi.dk huhnseal@huhnseal.dk
www.cowi.dk www.huhnseal.dk
CTR Phone +45 3818 5777 Hydro-X Phone +45 9828 2111
Metropolitan Copenhagen Fax +45 3818 5799 Boiler water treatment Fax +45 9828 3021
Heating Transmission Company ctr@ctr.dk info@hydro-x.dk
www.ctr.dk www.hydro-x.dk
Dall Energy Phone +45 2987 2222 Iron Pump Phone +45 4491 6788
New Biomass Technologies info@dallenergy.com Manufacturer of pumps Fax +45 4454 7119
www.dallenergy.com bts@ironpump.dk
www.ironpump.com
E N E R G Y A N D E N V I R O N M E N T
P
_
31
Isoplus Fjernvarmeteknik Phone +45 6441 6109 SK Forsyning Phone +45 5836 2500
Preinsulated piping systems Fax +45 6441 6159 Municipal district heating supply Fax +45 5836 2501
for district heating and cooling iso@isoplus.dk info@skforsyning.dk
www.isoplus.dk www.skforsyning.dk
Kamstrup Phone +45 8993 1000 SPX Flow Technology Phone +45 7027 8444
Supplier of energy meters & automatic Fax +45 8993 1001 Supplier of plate heat exchangers, Fax +45 7632 4110
meter reading systems for heat, cooling, energi@kamstrup.dk hybrid heat exchangers and solutions apv.emea.heat@spx.com
water and gas www.kamstrup.com for district energy www.apv.com
Københavns Energi Phone +45 2795 2750 TVIS Phone +45 7594 0711
Copenhagen Energy Fax +45 2795 2012 Heat transmission company tvis@tvis.net
ke@ke.dk of Denmark’s ”triangle area”. www.tvis.net
www.ke.dk
Logstor Phone +45 9966 1000 VEKS Phone +45 4366 0366
Preinsulated transmission Fax +45 9966 1180 West Copenhagen Heating Fax +45 4366 0369
and distribution pipes logstor@logstor.com Transmission Company veks@veks.dk
www.logstor.com www.veks.dk
Niras Phone +45 6312 1581 Vestforbrænding Phone +45 4485 7000
Consulting engineers and planners Fax +45 4014 2784 Power and heat supply based on Fax +45 4485 7001
niras@niras.dk waste incineration vestfor@vestfor.dk
www.niras.dk www.vestfor.dk
Rambøll Phone +45 5161 1000 DBDH Phone +45 3818 5440
Consulting engineers and planners Fax +45 5161 1001 Secretariat dbdh@dbdh.dk
ramboll@ramboll.dk www.dbdh.dk
www.ramboll.com
CHP
a benefit for the environment
J O U R N A L N 0 . 2 / 2 0 1 2 www.dbdh.dk
The bar is getting higher ...
before:
during:
P i n d P r o m o t o r . d k 19831
after:
LOGSTOR A/S
Danmarksvej 11 · DK-9670 Løgstør
Tel. +45 9966 1000 · Fax +45 9966 1180
logstor@logstor.com · www.logstor.com