Professional Documents
Culture Documents
0.25
Feb-22 Project Projected LTI F/R 0.40 Mar-22
Fatalities
7
Severity (S) F/R
Serious Injuries No. of days lost x 100,000 / Total Man-hours
4 4 0.55
3 0.545 0.544847
Minor Injuries 2 0.54
0 0 0 0 0 0 0 0.535
0.53
Near Misses 0.525
0.518691345
0.52
0.515
Unsafe Act /
Unsafe Condition 0.51
0.505
Feb-22 Mar-22
Page 1 to 12
Date: Mar 2022 HSE Monthly Performance
Activity Involves in Accident / BODY PARTS AFFECTED BY WORKS
Incident
Accident Incident Location INJURIES
HEAD
4 4 2
SHOULDER
2 FACIAL
2 2 0
1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Crane Backfilling Shuttering Shifting of Pedestrian Coring MEP Block Works Haulling
HAND NECK
Icon B-900 P-500 B-300 B-801 B-102 B-200 T-400 P-300 P-700 QIN Road
Lifting Doka Concrete Tower
4 0
WRIST
0
LEG
3 5
1 KNEE
Falling Objects 0
Riad Traffic 3
QIN PROJECT No. 285 Prepared by RCA H&S Manager RBD. Page 2 to 12
Date: Mar 2022 HSE Monthly Performance
RCA Safety Officers Internal Safety Observation Raised: 153
26
15
8 9 8
7 7 7 7 6 6 6 6
4 4 4 5
2 3 2 3 2 3 2
0 1 0 0 0 0
AMMOS ATTIBA DAVID JOHNSON JUSTIN PETER SAMUEL SHAKAWAT SREEJIT VIVEK
Good Closed Open
DHAMIKA ENG. ABDEL RAOF ENG. ABDUL ENG. FRANCIS ENG. IHAB ENG. JAWAD ENG. JOE ENG. KAMAL ENG. MAHDY ENG. MOATH ENG. ROBBI ENG. RYAN
KHADER Good Closed Open
QIN PROJECT No. 285 Prepared by RCA H&S Manager RBD. Page 3 to 12
Date: Mar 2022 HSE Monthly Performance
IOR Site Engineer Close-out and Good Practices Performance
15
11
10
9
8
6 6 6
5 5 5 5
4 4 4
3 3 3 3 3 3
2 2 2 2 2 2 2 2 2
1 1 1 1 1 1 1 1 1 1 1 1 1
1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
ABBAR ABDUL RASAK ADEL BIJU BILAL CHANAKA HAMDI IBRAHIM JABELL JABER JASIM MAHMOUD KHALID MANOJ OMAR RAJESH RAM PATHAK RUSSEL SAMAWI SHERIFF SANDU VIJAY
Good Closed Open
ISOR Engineer Foreman and Site Safety Officers Good Practices / Reactive Observation %
No. of Observation Raised Contributed to
1 1
Internal Safety Internal Safety number of
Observation Observation Reactive Observation Internal
Raised Raised observation
safety
1 Internal Safety
Observation
Closed
1 Internal Safety
Observation
Open
observation
QIN PROJECT No. 285 Prepared by RCA H&S Manager RBD. Page 4 to 12
Date: Mar 2022 HSE Monthly Performance
Opportunities / Threat Analysis Strength / Weakness Analysis
Activity / Risk Activity / Behavior ISOR Amplifier
Damage Good
Housekeeping
Scaffolding Material Housekeeping
Standard
Work at Height Imposing Scaffolding 9 22
Fire Controls of Working at Height
Housekeeping
Housekeeping Access and Egress
Hit by Protruding Up right to
Plant & Equipment Object Resolve issues
Electrical Working from Height 14 14
Excavation Planning Work Plant and Equipment
Slip Trip and Fall
Access
Hot work Scaffolding
Incomplete Good Housekeeping 22 11
Void Spaces Scaffolding Supervision
3% 9%
1%
Improper Organized work
2% 2% 1% Erecting Areas
Plant & Equipment 2 9
16%
Missing Fall
10% 8% 1% Arrest FBH 27%
10% No Safe Excavation 1 9
17% 24% 1% Access 35%
27% 42% CORE
13% Unsecured
10% 1% Material
STRENGTH
6% Electrical 2 5
Page 5 to 12
Date: Mar 2022 HSE Monthly Performance
Engineer Close-out Consultant Report Ext. Report
Ext. Report Closed Out %
Closed Out %
120%
HSE-IR-0137, 100%
100% HSE-IR-0140, 75%
80% HSE-IR-0141, 75%
HSE-IR-0139, 75%
60%
HSE-IR-0142, 50% HSE-IR-0143, 50%
40%
-1
0%
0 1 2 3 4 5 6 7 8 9
20%
Open Observation
80%
277
241
Closed Observation
147
136
16 15 13 23 15
8
NCN HSE LEADERSHIP SITE WALK HSE INSPECTION REPORT NON HSE OBSERVATION SEE AND ACT OBSERVATION
REPORT REPORT
ISSUED REPORT CLOSED REPORT
Page 6 to 12
Date: Mar 2022 HSE Monthly Performance
CONFINED SPACE 35
TOTAL NO. SAFETY INDUCTED 7248
SCAFFOLDING ERECTION 197
FIRST AID 11
MARCH SAFETY INDUCTED 204
DEFENSIVE DRIVING 28
Page 7 to 12
Date: Mar 2022 HSE Monthly Performance
MAHMOUD 66
MUHAMMUD
KHALID 26
28
STARRT CARD RCA / Subcontractor
VIJAY 44
JABER 28
MADAN 68
ABDUL RAZAK 16
RASSEL 4
SUBCONTRACTORS 1510
RAMPATAK 24
MANOJ 136
Page 8 to 12
Date: Mar 2022 HSE Monthly Performance
4
4
11 1 1
APPROVED AS NOTED RESUBMITTED FOR INFORMATION ACCUMULATIVE PRESENT MONTH ACCUMULATIVE PRESENT MONTH
2
39
25
1 1 21
12
Page 9 to 12
Date: Mar 2022
HSE Monthly Performance
NUMBER OF REPORT RAISED RCA HSE & CONSULTANT HSE REPORT CONSTELLATION
2,622
1%
ATKINS NCN 73%
ATKINS
REPORT HSE Inspection
Report /Audits Report
5%
Leadership
Site Walk
293
15 9%
RCA Safety
Observation Report
2 10 40%
5 1 1 2 1 1 20%
0 0%
HSE MANAGER SAFETY OFFICERS SITE DOCTOR NURSE ENVIRONMENTAL ENVIRONMENTAL
0 MANAGER ENGINEER
INTERNAL OBSERVATION INT/EXT MEETINGS CONSULTANT REPORT - CLOSED RAMS REVIEW WEEKLY TBT HSE STAFF
Page 11 to 12
Date: Mar 2022 HSE Monthly Performance
PLANT /
FBH INSPECTION EQUIPMENT
INSPECTION
Sharing food to
HOUSEKEEPING STARRT MEETING Workers
Page 12 to 12