5/22/23, 1:30 PM Aconex

Deepak Parmar Final (WF-011738) KEC For approval of Drawings/Doc… 19/05/2023


HOWE ENGINEERING PROJECTS (I) PVT LTD WORKFLOW TRANSMITTAL HEPIPL-WTRAN-021297

MAIL TYPE MAIL NUMBER REFERENCE NUMBER


Workflow Transmittal HEPIPL-WTRAN-021297 HEPIPL-WTRAN-021297

Final (WF-011738) KEC For approval of Drawings/Documents

From Mr Deepak Parmar - Howe Engineering Projects (I) Pvt Ltd

To (2) Mr Deepak Parmar - Howe Engineering Projects (I) Pvt Ltd (+1 more...)

Sent Friday, 19 May 2023 4:13:07 PM HKT (GMT +08:00)

Status N/A

DOCUMENT ATTACHMENTS (1)

(0 selected)

File Document No Revision Title Status

METHOD STATEMENT FOR CONFIRMATORY PLATE


H-W020-600-E- A2 - Approved
A LOAD TEST AT Br. No. 34 BY M/s. S M CONSULTANTS
BS-MS-008 with Comments
BHUBANESWAR

MESSAGE

Workflow Review History

The attached documents have completed the "KEC For approval of Drawings/Documents" workflow with the following results :

This transmittal was automatically generated.

Doc No Step Participant Review Outcome Comments

H-W020-600-E-BS-MS- A2 - Approved with Kindly comply the


For approval D Parmar
008 Comments comments

https://hk1.aconex.com/hub/index.html 1/1
DHAMRA PORT COMPANY LIMITED (DPCL)
PROJECT Engineering, Procurement & Construction (EPC) Contract for Dhamra
Railway Doubling – Phase 2 from Manthai River (including) to Bhatatira and
Track linking and OHE works for Phase-1B for new main line from DTY to
Manthai River with new Loop lines at Bansara & DTY and Upgradation of
existing loop line to Main Line at Gurdaspur yard on Bhadrak- Dhamra Port
Non-Government Railway System of Dhamra Port Company Ltd. at
Dhamra, Odisha.

DEVELOPER DHAMRA PORT COMPANY LIMITED (DPCL)


TITLE OF DOCUMENT METHOD STATEMENT FOR CONFIRMATORY PLATE LOAD
TEST AT Br. No. 34 BY M/s. S M CONSULTANTS,
BHUBANESWAR

CLIENT HOWE ENGINEERING PROJECTS (I) PVT LTD.

INDEPENDENT ENGINEER NA

EPC CONTRACTOR KEC INTERNATIONAL LTD.

CONTRACTOR DOC. NO. KEC/QAQC/DP-MS/CPLT-34/01 Rev-A Dt- 16.05.2023

HOWE DOCUMENT NO. H‐W020‐600‐E‐BS‐MS‐008 Rev. A

REV. NO. DATE DESCRIPTION PREPARED CHECKED APPROVED


Initial Sign Initial Sign Initial Sign

A 16.05.2023 1st Issue BM BH BBT

This Document is the property of HOWE. It should not be used, copied, or reproduced without their written permission.
HOWE ENGINEERING PROJECTS (INDIA) PVT. LTD., AHMEDABAD.
EXTERNAL DRAWING / DOCUMENT REVIEW

A1 – APPROVED A4 - ADDITIONAL INFORMATION


REQUIRED

1. Calibration certificates of jacks / dial gauges needs to be submitted A2 - APPROVED WITH COMMENTS A5 - FOR INFORMATION ONLY

prior to load test. Also include the loading chart table along with A3 - NOT APPROVED

relevant sketches (if required). This review and approval does not relieve supplier / contractor / sub-contractor from

2. Pease include the Job safety analysis (JSA) table


full compliance with purchase order / contract requirements and also from errors in
this drawing / document.

3. Load test to be carried out only after submitting the aforesaid. Reviewed By: Durgaprasad Pattanaik Signature :

Date: 19-5-2023 Discipline: QUALITY


METHOD STATEMENT FOR Page 1 of 9

CONFIRMATORY PLATE LOAD


TEST AT Br. No. 34 BY M/s. S M Doc. No. ‐
CONSULTANTS, BHUBANESWAR

Change Authorization History

Overall Process Owner Quality Manager (QM)


Process Change Authorization Head Quality (HQ)
To be Reviewed By Head Quality (HQ)
Periodicity of Review of this Document: 6 Months

Version Control
Version No. Prepared by Reviewed by Date Location
Rev-A Biranchi Mohanty Bikash Halder 16-05-2023 Dhamra

Version Control History

Version No. Reasons for change


Rev-A NA

Bir Bijoyanta Talukdar


Bikash Halder Biranchi Mohanty
Project Manager (PM)
Date 16-May-2023 Head Quality (HQ) Project Quality Manager (QM)
Date 16-May-2023 Date 16-May-2023
METHOD STATEMENT FOR Page 2 of 9

CONFIRMATORY PLATE LOAD


TEST AT Br. No. 34 BY M/s. S M Doc. No. ‐
CONSULTANTS, BHUBANESWAR

TABLE OF CONTENTS

Sl. DESCRIPTION PAGE NO.


No.
1 General 3
2 Responsibility 4
3 Purpose 5
4 Methodology 5-7
5 Load Chart 8
6 Reference Documents (Calibration Certificates)
METHOD STATEMENT FOR Page 3 of 9

CONFIRMATORY PLATE LOAD


TEST AT Br. No. 34 BY M/s. S M Doc. No. ‐
CONSULTANTS, BHUBANESWAR

1. GENERAL
1.1 Objective
The objective of the proposed testing is to determine the confirmatory Bearing Capacity on the
improved ground layer of Minor Bridges will be conducted by approved Third-party laboratory M/s.
S M Consultants, Bhubaneswar

1.2 Distribution list


The documents shall be distributed to the following stake holders for reference and
implementation as applicable:

 Director Projects (DP)


 Project Director (PD)
 Head Quality (HQ)
 Project Engineering Manager (PEM)
 Project Procurement Manager (PPM)
 Construction Manager (CM)
 Project Control Manager (PCM)
 Project Safety Manager (HSM)
 Equipment Manager (EM)

1.3 Method and stages of revision


The document shall be reviewed by HQ once in 6 months with respect to its effectiveness
and applicability for the project. He will assess the fulfillment of all the Quality objectives and
requirements in the execution stage through various inputs like:

 Changes in Corporate Quality Policy and objectives (if any)


 Quality MIS
 Contractors’ scorecard
 Audit reports
 Customer Feedback
 Technological change

Based on the review feedback from HQ, QM decides whether to revise the document to meet
the new requirements for the project or not. If yes, he shall revise the document as per the
requirements. If not, the process document remains unchanged and the same document
continues to be followed.
METHOD STATEMENT FOR Page 4 of 9

CONFIRMATORY PLATE LOAD


TEST AT Br. No. 34 BY M/s. S M Doc. No. ‐
CONSULTANTS, BHUBANESWAR

2. Responsibility

Project Manager/ Shall report to management.


Project Director
Construction -Shall report to the Project Manager/Project Director.
Manager -Shall be responsible for control, supervision & direction for
implementation & execution of construction plans.
-Shall also be responsible for supervision of construction activities
and preparation of construction records.
-Develop construction schedules, construction method statements &
prepare progress & accomplishment reports.

Engineers -Shall report to Construction Manager.


-Shall be responsible for day-to-day planning at site.
-Activity related documentation and preparation of construction
records.
-Shall raise RFI
Survey Engineer/ -Shall report to Project Manager.
Surveyor -Shall give location of work at site as per approved scheme.
QA/QC Engineer -Shall report to Project Manager.
-Shall be responsible for overall control of QC activities and sub-
contractor’s QC activities, implementation of Project Quality
Assurance Plan.
-Shall be responsible for carrying out inspection as per the Field
Quality Assurance Plan (Inspection and Testing Plan) and/or this
approved construction methodology.
Geologist of third- -Shall report to Project Manager.
party agency -Shall take & preserve samples
-Shall analyze the strata and prepared report.
Safety Officer -Shall report to Project Manager.
-Shall observe all safety aspects in all the activities
-Shall analyze the strata.
METHOD STATEMENT FOR Page 5 of 9

CONFIRMATORY PLATE LOAD


TEST AT Br. No. 34 BY M/s. S M Doc. No. ‐
CONSULTANTS, BHUBANESWAR

3. PURPOSE:

The object of this method Statement is to lay down a procedure for carrying out the
confirmatory plate load test on PCC bottom level at Box Culverts to check the SBC after
ground improvement at Br. 34 as per the approved drawing and IS 1888.

PLATE LOAD TEST METHODOLOGY

Base Pressure
Ultimate Kent ledge Load
Bridge Requirement Plate Size Converted
Bearing Test Level (Hyundai 210
No. at Box (mm) Load on Plate
Capacity Excavator)
Structure

27.25
34 109 KN/Sqm 600x600 9.81 Ton PCC Bottom 21.2 Ton
Ton/Sqm

4. Reaction
The reaction shall be obtained as under –
4.1 - Kent ledge load shall be used as the dead weight of Excavator of 21.2 MT.
4.2 - The maximum ultimate load is to confirm 27.25tons/sqm (Br.34). The corresponding
ultimate load required on a plate size of 60 x 60 cm. is 9.81 tons. The thickness of plate shall
be 25mm.
4.3 - The maximum reaction to be made available for the test shall be 9.81 tons (Br.34) i.e.,
1.25 times the required loading. In our case we use 21.2 Ton. Hence it is ok.
4.4 - A typical arrangement for the test setup is shown below. The main purpose is to check
the required load and meeting the testing requirements within the allowable settlements
METHOD STATEMENT FOR Page 6 of 9

CONFIRMATORY PLATE LOAD


TEST AT Br. No. 34 BY M/s. S M Doc. No. ‐
CONSULTANTS, BHUBANESWAR

BY USING EXCAVATOR AS A KENTELAGE

5. Loading of Test Plate


5.1 - A bearing plate – 600 x 600 mm. shall be placed on the founding layer. It shall be
ensured that the plate is leveled on a horizontal plane and centered in the line of approx. CG
of the kentledge.
5.2 - Smooth loading hydraulic jack shall be placed on the plate and a load measuring
proving shall be fixed between the jack and kentledge Centre (refer figure). The pumping unit
of the jack shall be kept away from the testing plate through extending pressure pipes.
METHOD STATEMENT FOR Page 7 of 9

CONFIRMATORY PLATE LOAD


TEST AT Br. No. 34 BY M/s. S M Doc. No. ‐
CONSULTANTS, BHUBANESWAR
5.3 - For measuring settlement of plate under loading, four dial gauges shall be placed on the
plate with magnetic base attached – one at each corner of plate. The tip of gauges shall be
resting on an independent datum bar.
5.4 - The pressure gauge for load measuring and settlement measuring gauges used shall be
calibrated with traceability to National Standards through unbroken chain of NABL accredited
laboratories. The calibration certificates shall be verified and provided during time of testing.
5.5 - A seating load of 0.07 kg/sq.cm. shall be applied using jack. The measurement applied
load shall be recorded in proving ring. Once the seating load is steady, the initial reading in
dial gauges shall be recorded.
5.6 - The test shall be carried out by applying a series of vertical downward incremental load
with each increment being of 1 kg/cm2 or 20 percent of ultimate load whichever is less. With
load 27.25tons/sqm, required allowable capacity and allowing for water table and factor of
safety, 20 % of ultimate load will be 2.18tons on plate size 600 x 600 mm. The Load
increment shall be as per the Load Chart.
5.7 - The load shall be applied without impact, fluctuation or eccentricity and the load in of
hydraulic jack shall be measured on the proving ring.

6. Settlement
6.1 - Settlement shall be recorded with 4 dial gauges of 0.01 mm sensitivity, each positioned
at diametrically opposite corner of plate piles and shall be held by datum bars.
6.2 - For each load increment, settlements shall be recorded at 1 min. 2.25 min, 4 min, 6.25
min, 9 min, 16 min, 25 min and 1hr to the nearest 0.02 mm. Then next increment shall be
applied, and it will be continued till the required ultimate bearing capacity is reached.

7. Unloading
After the criteria as per settlement is reached, unloading shall be done in same decrements
and recovery in settlements shall be recorded after the readings become stable.

8. Report
Safe bearing capacity shall be estimated as per IS 1888.
METHOD STATEMENT FOR Page 8 of 9

CONFIRMATORY PLATE LOAD


TEST AT Br. No. 34 BY M/s. S M Doc. No. ‐
CONSULTANTS, BHUBANESWAR

9. Load Chart

Dial Gauge Reading (mm) Average Dial Average Cumulative


Increament
Time Gauge Settlement settlement in
loads in Tons
Reading in mm in mm mm
D1 D2 D3 D4
METHOD STATEMENT FOR Page 9 of 9

CONFIRMATORY PLATE LOAD


TEST AT Br. No. 34 BY M/s. S M Doc. No. ‐
CONSULTANTS, BHUBANESWAR