9 8 7 3 2 1
KICKER WALL
1,70
1,20 1,70 1,20
10
62 5 35 25 1,45 25 24 3 45 8 62 5
24 3 35 8 10
12
+10.50 +10.50
8
STAINLESS STEEL L PROFILE
POWDER COATED STEEL
30
RAL 9002
+10.20 +10.20
WATERPROOF MEMBRANE
80 - 40 MM , 15% CONCRETE SLAB
250 MM CONCRETE SLAB
120 MM ISOLATION
30 MM WOOD CEILING FINISH
2,65
CONCRETE COLUMN
DIAMETER 235 MM
20 MM WOODEN PARQUET
80 MM ISOLATION
250 MM CONCRETE SLAB ,
POLISHED WHEN VIEWED
180 MM ISOLATION
30 MM COATED WOODEN CEILING
13 82 23 5 72 3 10
+7.55 +7.55
4
STAINLESS STEEL L PROFILE
POWDER COATED STEEL
RAL 9002
26
+7.25 +7.25
2,65
11,00
20 MM WOODEN PARQUET
80 MM ISOLATION
250 MM CONCRETE SLAB ,
POLISHED WHEN VIEWED
180 MM ISOLATION
30 MM COATED WOODEN CEILING
82 23 5 1,08 3 15
+4.60 +4.60
4
RAL 9002
+4.30 +4.30
18 18
3,90
20 MM WOODEN PARQUET
80 MM ISOLATION
10 MM CONCRETE SLOPE (1 .5%)
POLISHED CONCRETE (WHEN VIEWED)
CONCRETE POURED3IN SITE
13 82 23 5 1,08 18
250 MM CONCRETE SLAB
STAINLESS STEEL L PROFILE WATERPROOF MEMBRANE
POWDER COATED STEEL STABILIZED SAND
+40 RAL 9002 +40
4
26
+0 +0
10
30
-30 -30
18 1,08 25 12 4 9 43 43 9 4 21 25 1,00 70 18
1,26 25 12 1,11 21 25
Dar Al Jinaa
Office 126 / Centres for Traditional Music Detailed section 0 5 50 cm
Scale 1/80