*RESUME SHIFT MEETING PENGISIAN OP PEP #5-7/A (PAGI 2)*

✅ *Pengisian bunker #5-7 dari:*


MV.ANDHIKAPARAMESTI (BERAU)
MV.MARIA NASWAH ( MHU )

✅ *DERMAGA 2 :*
⚓ MV.ANDHIKAPARAMESTI (BERAU)
Total Pembongkaran : 9,100
📌 *Kendala :*
-

✅ *EXTENTION :*
⚓ MV.MARIA NASWAH ( MHU )
Total Pembongkaran : 3,200
📌 *Kendala :*
Batu bara lembab & besar-besar

🏭 *TOTAL KESELURUHAN PEMBONGKARAN D2 + D Ext = 12,300

✅ *KEGIATAN ST/RE02*
🚜 Stacking =
🚜 Reclaime =

*Pengisian dari Hopper ‘D* =


*Pengisian dari Emergency Chute* =

🔗 *Pengisian #1-4 :*
▪️ Via TL01 =
▪️ Via BC17 =

Tanggal : 29 Januari 2020


SP PEP #5-7/A

(SIDIK BIN SAIUN)


MT

MT

MT

08.30 s/d 10.00


-

-
-

terima tugas s/d 14.30


terima tugas s/d 14.00
⚡ *INFO LAPORAN OP PEP #5-7/A (PAGI 2)* ⚡

✅ *Pengisian bunker #5-7 dari:*


MV.ANDHIKAPARAMESTI (BERAU)
MV.MARIA NASWAH ( MHU )

✅ *DERMAGA 2 :*
⚓ MV.ANDHIKAPARAMESTI (BERAU)
HBS : 21,400

✅ *EXTENTION :*
⚓ MV.MARIA NASWAH ( MHU )
HBS : 13,400

✅ *KEGIATAN ST/RE02*
🚜 Stacking =
🚜 Reclaime =

*Pengisian dari Hopper ‘D* =


*Pengisian dari Emergency Chute* =

🔗 *Pengisian #1-4 :*
▪️ Via TL01 =
▪️ Via BC17 =

*Ship Unloader:*
▪️ U/L 1 //
▪️ U/L 2 standby
▪️ U/L 3 standby
▪️ U/L 4 standby

📌 *Peralatan:*
📍 BF/BC40 tidak stand by

📌 *Kendala :*
📍 Batu bara lembab & besar-besar

*Kegiatan :*
▪️ jam 08.00 s/d serah terima : Pengisian ke #1-4 via BC17
▪️ jam 08.25 s/d 08.45 : BC33 pek.greasing gear coupling
▪️ jam 08.25 s/d 09.50 : U/L 3 greasing
▪️ jam 10.00 s/d 11.00 : U/L 4 greasing
▪️ jam 10.15 s/d 11.00 : BC18 pek.repair chute
▪️ jam 10.15 s/d 11.30 : BC502B pek.repair chute
▪️ jam 11.00 s/d serah terima : BC02 pek.pull cord
▪️ jam 11.50 s/d : Pengisian ke 1-4 via TL01

🏭 *Beban,CF,NPHR & NK Jam 14.00*


▪️#5= 522 MW/
▪️#6= 467 MW/
▪️#7= 588 MW/

✅ *Level bunker Jam 14.00*


▪️#5= 75 96
▪️#6= 85 85
▪️#7= 80 94

🚜 *Info Stock BB Efective :*


▪️ KPC (B1) =
▪️ BERAU (B1) =
▪️ BERAU (B2) =
▪️ ADARO (C2) =
▪️ TONGKANG (C2) =

🚜 *INFO STOCK EFFECTIVE*


▪️ STOCK EFFECTIVE =
▪️ HOP =

Lain lain masih aman tks.


*#Tagline :*
*#BeraniBertindakKarenaBenar*
*PELANGI*
*Perang Melawan Heat rate Tinggi*

*Penyaluran 2.000 TPJ...SIAP…!!!*💪💪💪


*Pembongkaran 43.000 TPD...BISA…!!!*🇮🇩🇮🇩
🙏🙏 *TERIMA KASIH* 🙏🙏
MT

MT

08.30 s/d 10.00


-

-
-

terima tugas s/d 14.30


terima tugas s/d 14.00
0.72 / 2805 / 4788
0.72 / 2743 / 4852
0.73 / 4785 / 4799

70 85 93 80
80 80 80 90
80 75 88 85

9,359 MT
0 MT
0 MT
767 MT
3,314 MT

48,965 MT
1,3 HARI
*Assalamualaikum wr wb*

⚡ *Info Beban/CF/NPHR/NK* ⚡

*Jam 08.00*
▪️#5 = 514 MW/ 0.74 / 2735 / 4846
▪️#6 = 437 MW/ 0.75 / 2720 / 4879
▪️#7 = 590 MW/ 0.75 / 2759 / 4826

*Jam 10.00*
▪️#5 = 515 MW/ 0.75 / 2738 / 4841
▪️#6 = 439 MW/ 0.74 / 2681 / 4908
▪️#7 = 587 MW/ 0.75 / 2760 / 4821

*Jam 12.00*
▪️#5 = 520 MW/ 0.73 / 2772 / 4812
▪️#6 = 437 MW/ 0.74 / 2725 / 4869
▪️#7 = 589 MW/ 0.73 / 2823 / 4766

✅ *Sumber pengisian bunker #5-7 dari :*


MV.ANDHIKAPARAMESTI (BERAU)
MV.MARIA NASWAH ( MHU )
*RESUME SHIFT MEETING PENGISIAN OP PEP #5-7/A ( SIANG 2 )*

✅ *Pengisian bunker #5-7 dari:*


MV. ARIMBI BARUNA (ADARO)
BG.CAMAR LAUT 3302 (BA)

✅ *DERMAGA 2 :*
⚓ MV. ARIMBI BARUNA (ADARO)
Total Pembongkaran : 8,400
📌 *Kendala :*
-

✅ *EXTENTION :*
⚓ BG.CAMAR LAUT 3302 (BA)
Total Pembongkaran : 2,100
📌 *Kendala :*

🏭 *TOTAL KESELURUHAN PEMBONGKARAN D2 + D Ext = 10,500

✅ *KEGIATAN ST/RE02*
🚜 Stacking =
🚜 Reclaime =

*Pengisian dari Hopper ‘D* =


*Pengisian dari Emergency Chute* =

🔗 *Pengisian #1-4 :*
▪️ Via TL01 =
▪️ Via BC17 =

Tanggal : 31 Januari 2021


SP PEP #5-7/A

(SIDIK BIN SAIUN)


MT

MT

MT

16.30 s/d 18.00 & 19.15 s/d 21.30


-

-
-

-
Terima tugas s/d 15.10 & 18.00 s/d Serah terima
Terima tugas s/d Serah terima
⚡ *INFO LAPORAN OP PEP #5-7/A ( SIANG 2 )* ⚡

✅ *Pengisian bunker #5-7 dari:*


MV. ARIMBI BARUNA (ADARO)
BG.CAMAR LAUT 3302 (BA)

✅ *DERMAGA 2 :*
⚓ MV. ARIMBI BARUNA (ADARO)
HBS : 34,100 MT

✅ *EXTENTION :*
⚓ BG.CAMAR LAUT 3302 (BA)
HBS : 2,100 MT

✅ *KEGIATAN ST/RE02*
🚜 Stacking = 16.30 s/d 18.00 & 19.15
🚜 Reclaime = -

*Pengisian dari Hopper ‘D* = -


*Pengisian dari Emergency Chute* = -

🔗 *Pengisian #1-4 :*
▪️ Via TL01 = Terima tugas s/d 15.10
▪️ Via BC17 = Terima tugas s/d Serah

*Ship Unloader:*
▪️ U/L 1 //
▪️ U/L 2 standby
▪️ U/L 3 //
▪️ U/L 4 standby

📌 *Peralatan:*
📍 BF/BC40 tidak stand by

📌 *Kendala :*
📍

*Kegiatan :*
▪️ Terima tugas s/d 15.10 & 18.00 s/d : Pengisian ke #1-4 via TL01
▪️ Terima tugas s/d Serah terima : Pengisian ke #1-4 BC17
▪️ jam 16.20 s/d 17.00 : BF'A pekerjaan pedestal
▪️ jam 16.30 s/d 17.30 : BC32 pekerjaan repair belt
▪️ jam 16.30 s/d 18.00 & 19.15 s/d 21.30 : Stacking 02
▪️ jam 17.40 : BG.CAMAR LAUT 3302 (BA) Sandar di D2 Ext
▪️ jam 19.40 s/d 20.40 : U/L 2 greasing
▪️ jam 19.50 s/d 20.35 : BC502B Pek pemasangan cover chain tripper

🏭 *Beban,CF,NPHR & NK Jam 21.00*


▪️#5= 600 MW/ 0.78
▪️#6= 455 MW/ 0.78
▪️#7= 575 MW/ 0.78

✅ *Level bunker Jam 21.00*


▪️#5= 85 86 75
▪️#6= 92 79 77
▪️#7= 87 82 84

🚜 *Info Stock BB Efective :*


▪️ KPC (B1) = 25,729
▪️ BERAU (B1) = 0
▪️ BERAU (B2) = 0
▪️ ADARO (C2) = 767
▪️ TONGKANG (C2) = 2,664

🚜 *INFO STOCK EFFECTIVE*


▪️ STOCK EFFECTIVE = 82,511
▪️ HOP = 2

Lain lain masih aman tks.


*#Tagline :*
*#BeraniBertindakKarenaBenar*
*PELANGI*
*Perang Melawan Heat rate Tinggi*

*Penyaluran 2.000 TPJ...SIAP…!!!*💪💪💪


*Pembongkaran 43.000 TPD...BISA…!!!*🇮🇩🇮🇩
🙏🙏 *TERIMA KASIH* 🙏🙏
16.30 s/d 18.00 & 19.15 s/d 21.30

Terima tugas s/d 15.10 & 18.00 s/d Serah terima


Terima tugas s/d Serah terima
/ 2747 / 4850
/ 2590 / 4988
/ 2742 / 4841

79 80 95
88 81 88
77 76 85

MT
MT
MT
MT
MT

MT
HARI
*Assalamualaikum wr wb*

⚡ *Info Beban/CF/NPHR/NK* ⚡

*Jam 16.00*
▪️#5 = 480 MW/ 0.74 / 2697 / 4890
▪️#6 = 458 MW/ 0.77 / 2731 / 4861
▪️#7 = 480 MW/ 0.75 / 2759 / 4848

*Jam 18.00*
▪️#5 = 600 MW/ 0.77 / 2735 / 4855
▪️#6 = 455 MW/ 0.77 / 2683 / 4903
▪️#7 = 575 MW/ 0.77 / 2741 / 4847

*Jam 20.00*
▪️#5 = 600 MW/ 0.78 / 2648 / 4936
▪️#6 = 450 MW/ 0.77 / 2746 / 4853
▪️#7 = 577 MW/ 0.78 / 2750 / 4834

✅ *Sumber pengisian bunker #5-7 dari :*


MV. ARIMBI BARUNA (ADARO)
BG.CAMAR LAUT 3302 (BA)
*RESUME SHIFT MEETING PENGISIAN OP PEP #5-7/A ( MALAM 1 )*

✅ *Pengisian bunker #5-7 dari:*


MV. ARIMBI BARUNA ( ADARO )
BG. KAPUAS JAYA 332 (BA)
BG.KAPUAS JAYA 3117 (BA) Complet jam 01.10

✅ *DERMAGA 2 :*
⚓ MV. ARIMBI BARUNA ( ADARO )
Total Pembongkaran : 7,500
📌 *Kendala :*
Batu bara besar-besar (sering block)

✅ *EXTENTION :*
⚓ BG. KAPUAS JAYA 332 (BA)
Total Pembongkaran : 4,800
📌 *Kendala :*
BF'A speed max 35%

🏭 *TOTAL KESELURUHAN PEMBONGKARAN D2 + D Ext = 12,300

✅ *KEGIATAN ST/RE02*
🚜 Stacking =
🚜 Reclaime =

*Pengisian dari Hopper ‘D:* =


*Pengisian dari Emergency Chute:* =

🔗 *Pengisian #1-4 :*
▪️ Via TL01 =
▪️ Via BC17 =

Tanggal : 01 Februari 2021


SP PEP #5-7/A

(SIDIK BIN SAIUN)


Complet jam 01.10

MT

MT

MT

-
-

02.30 s/d 04.55


-

00.00 s/d Serah terima


Terima tugas s/d 23.00 & 06.00 s/d Serah terima
⚡ *INFO LAPORAN OP PEP #5-7/A ( MALAM 1 )* ⚡

✅ *Pengisian bunker #5-7 dari:*


MV. ARIMBI BARUNA ( ADARO )
BG. KAPUAS JAYA 332 (BA)
BG.KAPUAS JAYA 3117 (BA) Complet jam 01.10

✅ *DERMAGA 2 :*
⚓ MV. ARIMBI BARUNA ( ADARO )
HBS : Complet

✅ *EXTENTION :*
⚓ BG. KAPUAS JAYA 332 (BA)
HBS : 1,500

✅ *KEGIATAN ST/RE02*
🚜 Stacking =
🚜 Reclaime =

*Pengisian dari Hopper ‘D* =


*Pengisian dari Emergency Chute* =

🔗 *Pengisian #1-4 :*
▪️ Via TL01 =
▪️ Via BC17 =

*Ship Unloader:*
▪️ U/L 1 stand by
▪️ U/L 2 Stand by
▪️ U/L 3 //
▪️ U/L 4 //

📌 *Peralatan:*
📍 BF/BC40 tidak stand by

📌 *Kendala :*
📍 BF'A speed max 35%

*Kegiatan :*
▪️ Terima tugas s/d 23.00 : Pengisisan ke #1-4 via BC17
▪️ jam 00.00 s/d serah terima : Pengisian ke #104 via TL01
▪️ jam 01.10 : BG.KAPUAS JAYA 3117 complet
▪️ jam 02.30 s/d 04.55 : Pengisian dari Hopper'D
▪️ jam 03.50 : BG.KAPUAS JAYA 332 (BA) sandar di D2 Ext
▪️ jam 05.10 : MV.ARIMBI BARUNA selesai bongkar

🏭 *Beban,CF,NPHR & NK Jam 06.007


▪️#5= 550 MW /
▪️#6= 594 MW /
▪️#7= 600 MW /

✅ *Level bunker Jam 06.00*


▪️#5= 90 97
▪️#6= 96 95
▪️#7= 90 100

🚜 *Info Stock BB Efective :*


▪️ KPC (B1) =
▪️ BERAU (B1) =
▪️ BERAU (B2) =
▪️ ADARO (C2) =
▪️ TONGKANG (C2) =

🚜 *INFO STOCK EFFECTIVE*


▪️ STOCK EFFECTIVE =
▪️ HOP =

Lain lain masih aman tks.


*#Tagline :*
*#BeraniBertindakKarenaBenar*
*PELANGI*
*Perang Melawan Heat rate Tinggi*

*Penyaluran 2.000 TPJ...SIAP…!!!*💪💪💪


*Pembongkaran 43.000 TPD...BISA…!!!*🇮🇩🇮🇩
🙏🙏 *TERIMA KASIH* 🙏🙏
omplet jam 01.10

MT

MT

-
-

02.30 s/d 04.55


-

00.00 s/d Serah terima


Terima tugas s/d 23.00 & 06.00 s/d Serah terima
0.78 / 2690 / 4895
0.78 / 2694 / 4882
0.77 / 2758 / 4824

99 95 85 90
90 85 91 90
90 85 90 85

31,225 MT
0 MT
0 MT
767 MT
2,664 MT

100,827 MT
2,8 HARI
*Assalamualaikum wr wb*

⚡ *Info Beban/CF/NPHR/NK* ⚡

*Jam 00.00*
▪️#5 = 600 MW/ 0.78 / 2711 /
▪️#6 = 547 MW/ 0.78 / 2654 /
▪️#7 = 586 MW/ 0.77 / 2722 /

*Jam 02.00*
▪️#5 = 600 MW/ 0.78 / 2689 /
▪️#6 = 554 MW/ 0.79 / 2665 /
▪️#7 = 590 MW/ 0.77 / 2723 /

*Jam 04.00*
▪️#5 = 600 MW/ 0.77 / 2728 /
▪️#6 = 550 MW/ 0.77 / 2736 /
▪️#7 = 592 MW/ 0.76 / 2692 /

✅ *Sumber pengisian bunker #5-7 dari :*


MV. ARIMBI BARUNA ( ADARO )
BG. KAPUAS JAYA 332 (BA)
4878
4918
4854

4896
4908
4853

4861
4846 (Belum diinput)
4888 (Belum diinput)
NOVEMBER DESEMBER
AREA 21 22 23 24 25 26 27 28 29 30 1 2 3 4
am pm am pm am pm am pm am pm am pm am pm am pm am pm am pm am pm am pm am pm am pm
PLN BB/KPC Adaro
Dermaga 2
Berau coal ADC/MHU Maria Naswah
PLN BB/BT BA
Dermaga 2 EXT
PLN BB/MHU

Tanggal 26-27 menggunakan ADC/MHU


Jika tanggal 27 sudah diperoleh setting terbaik, maka dilanjutkan dengan MHU + MIX s/d tanggal 29 sampai adaro masuk
Jika tanggal 27 belum diperoleh setting terbaik untuk MHU maka tetap menggunakan MHU s/d tanggal 29 (adaro masuk)
Tanggal 30 Nov - 1 Des menggunakan adaro
Setelah sampai di Indonesia TKA melakukan swab ulang