During the switching off of UPS A in SS5 (one circuit breaker at a time with UPS B is designed to backup automatically) as part of the Turnaround activities, Air compressor K-
Basis/ Background: 3501A tripped resulting in interruption to plant air that had the potential to affect instrument air pressure and subsequently control systems on running equipment.
To evaluate risk of switching off UPS A and potential impact it can have on other circuit breakers (total 7) and associated systems such as Demin water system, clean
Scope: condensate, raw water, and waste water.
1. Overview Checklist Response Comments Requirements
1 Are there HSE or Engineering Procedures/ Standards that apply? N/A
Does this change affect an Independent Protection Layer or UPS is considered Safety Critical Device. Turnaround scope to replace UPS A & B Include Process Control Engineer in the risk review and ensure that the Override forms have been
8 Yes
Safety/ PSM critical device? in substation # 5. completed adequately.
What If Question Response Comment Consequences Safeguards Outstanding Items Risk Action Owner