You are on page 1of 10

Tension Leg Platform (TLP)

Edmund Muehlner
Bechtel Oil, Gas & Chemicals, Inc., Houston, TX, USA

control valves (i.e., the Christmas trees or production trees)


1 Introduction 1 located on the deck of the platform. This “dry-tree” arrange-
2 History 1 ment makes TLPs to stand out from most other floating plat-
3 TLP Mechanics 2 forms. Spar type floaters are the only other floating platforms
able to support dry production trees.
4 TLP Functions and Configurations 5
Since the first TLP was put into service in 1984, a total of
5 TLP Design 5
26 TLPs were installed (Table 1). As of this writing (2015),
6 TLP Installation 8 one more TLP is due for installation and several more are
List of Abbreviations 9 in the planning and design stage. TLP technology is mature
Glossary 9 and robust. Only one TLP has ever been lost. That incident
Related Articles 9 happened in 2005 when the TLP installed at the Typhoon
References 9 field in the Gulf of Mexico capsized during hurricane Rita.
TLPs are niche products that mainly serve the narrow
Further Reading 10
market for dry-tree floaters. In this market, however, they
have become the dominant solution. The demand for TLPs
is on average less than one installation per year. As a result,
only a handful of contractors compete for TLP projects. An
1 INTRODUCTION even smaller number of contractors are able to provide the
specialty components for a tendon system.
Tension leg platforms (TLPs, Figure 1) are vertically moored
floating structures typically used for offshore oil and gas
production. They fall into the category of floating systems,
which are plants designed to operate in a marine environ- 2 HISTORY
ment in a buoyantly supported state (Noble, 2013). TLPs
Records of concepts for tethered buoyant structures can be
are permanent installations since they are normally intended
found in the literature from as early as the nineteenth century.
to operate at one specific location for the span of their
They were intended for various marine structures such as
design life.
bridge piers (Schofield, 1860), floating telegraph stations
The mooring system of TLPs consists of multiple near
(Dieuleveult, 1889), or marine lights (Donelly, 1890). In
vertical tension members called tendons. These tendons have
1930, an early concept of a TLP-like configuration was
sufficient axial stiffness to effectively restrain the heaving
patented by Armstrong (1930). His “Seadrom” design was to
and heeling of the platform even in large waves. This, in turn,
be used as a landing place for air ships during transoceanic
allows the use of production risers that have the main well
flight. There is no indication, however, that any of these early
Encyclopedia of Maritime and Offshore Engineering, online © 2017 John Wiley & Sons, Ltd.
concepts was ever built.
This article is © 2017 John Wiley & Sons, Ltd. The incentive to build offshore structures came in earnest
DOI: 10.1002/9781118476406.emoe400
Also published in the Encyclopedia of Maritime and Offshore Engineering (print edition)
with the advent of the oil and gas industry in the first half
ISBN: 978-1-118-47635-2 of the twentieth century. While initially relying on bottom
2 Offshore

Skidable This project was organized by the Deep Oil Technology


platform rig company and was sponsored by 17 oil companies. Additional
Facilities
tests with this model were carried out in 1978 (Mercier et al.,
1991).
Following these successful sea trials, a number of compa-
Hull
nies started their own design studies of TLPs in the late
1970s. These efforts ultimately resulted in the first full-scale
TLP in 1984. This first TLP was installed in a water depth
of 147 m at Conoco’s Hutton field in the North Sea (Mercier
et al., 1991).
Encouraged by the success of the Hutton TLP, the industry
Tendons
kept pushing ahead with the TLP development. Conoco
installed its second TLP in 1989 at their Jolliett field in the
Production Gulf of Mexico and followed up with the Heidrun platform
risers in the North Sea in 1995. Meanwhile, Saga Petroleum of
Norway installed its Snorre TLP in 1992. Shell entered the
TLP arena with its Auger TLP in 1994. Shell went on to
become an important champion for the TLP concept and has
contributed significantly to the development of TLP tech-
nology. To date, Shell has installed a total of six TLPs. The
latest of Shell’s TLPs is the Mars B Olympus TLP that started
production in 2014.
The TLP development continued rapidly throughout the
1990s and in the first half of the 2000s. Atlantia Offshore
Direct tendon/Pile
connection developed their single-column “SeaStar” design (Figure 3).
Wells This new design was first used in 1998 for a TLP at the
Morpeth field in the Gulf of Mexico. The SeaStar became
Figure 1. Tension leg platform. (Reproduced with permission from popular for small-payload applications until the Typhoon
Godfrey et al. (1997). © Society of Petroleum Engineers, 1997.) SeaStar-type TLP was lost during Hurricane Rita in 2005.
Due to this event, the SeaStar design fell out of favor with
the industry. Another step in the TLP evolution came in 2001
founded structures, the need to relocate drilling rigs between when the El Paso Corporation installed the first MOSES TLP
well sites called for floating drilling platforms (Schempf, design (Figure 4) by Modec at the Prince field in the Gulf of
2007). In addition, oil exploration had continuously moved Mexico. Similar to the SeaStar, the MOSES design is geared
further offshore and into deeper water. By the mid-1940s, toward small payloads and low cost platforms. The MOSES
the oil industry was already operating out of sight of land design later evolved into the SSIP (self-stable integrated
(Schempf, 2007). Early floating platforms had barge-like platform), which has a simpler platform installation due to its
designs. Their movements in ocean waves allowed them to improved free-floating stability. To date, there are a total of
operate only in rather calm seas. To overcome this short- five TLPs installed that use the MOSES or the SSIP design.
coming, vertically moored platform designs were proposed Another modification of the classic TLP is the extended
by different inventors. Willis and Willis (1948), Schurman pontoon TLP (ETLP, Figure 5) developed by ABB Lummus
and Kidder (1955), and Knapp (1962) are examples of such Global. The first ETLP was installed by ExxonMobil in 2004
early designs. The term tension leg platform appears to have at the Kizomba field offshore Angola. The most recent ETLP
been used for the first time in literature in 1969 in a patent is currently awaiting installation by Chevron at the Big Foot
application by the inventor Horton (1969). Horton continued field in the Gulf of Mexico. With a water depth of 1580 m,
to play an important role in the early phase of the TLP devel- the Big Foot TLP will be the deepest TLP so far.
opment. Demirbilek (1989) reports that Paulling and Horton
(1970) were the first to publish work on TLP performance
and features. Horton and Paulling were also the master minds 3 TLP MECHANICS
behind the first offshore test of a TLP. Over 3 months in 1974
and 1975, they tested a 1/3rd scale model of a three column The tendons of TLPs effectively restrain their vertical
TLP in 58 m of water off the coast of California. motions in waves. Although TLPs are not free-floating

Encyclopedia of Maritime and Offshore Engineering, online © 2017 John Wiley & Sons, Ltd.
This article is © 2017 John Wiley & Sons, Ltd.
DOI: 10.1002/9781118476406.emoe400
Also published in the Encyclopedia of Maritime and Offshore Engineering (print edition) ISBN: 978-1-118-47635-2
Tension Leg Platform (TLP) 3

Table 1. TLP project list.


No. Field Name Year Initial Location Water Depth (m) Hull Type Topside
Installed Operator Function
1 Hutton 1984 Conoco UK North Sea 147 Classic TLP DDP
2 Jolliett 1989 Conoco US Gulf of Mexico 536 Classic TLP DWOW
3 Snorre A 1992 Saga North Sea 335 Classic TLP DDP
4 Auger 1994 Shell US Gulf of Mexico 872 Classic TLP DDP
5 Heidrun 1995 Conoco North Sea 345 Classic TLP DDP
6 Mars 1996 Shell US Gulf of Mexico 894 Classic TLP DDP
7 Ram/Powell 1997 Shell US Gulf of Mexico 980 Classic TLP DDP
8 Morphet 1998 British Borneo US Gulf of Mexico 1699 Sea Star WP
9 Marlin 1999 BP US Gulf of Mexico 1000 Classic TLP DWOW
10 Allegheny 1999 British Borneo US Gulf of Mexico 1005 SeaStar WP
11 Ursa 1999 Shell US Gulf of Mexico 1158 Classic TLP DDP
12 Typhoon 2001 Chevron US Gulf of Mexico 639 SeaStar WP
13 Brutus 2001 Shell US Gulf of Mexico 910 Classic TLP DDP
14 Prince 2001 El Paso US Gulf of Mexico 454 MOSES DWOP
15 Matterhorn 2003 Total US Gulf of Mexico 858 SeaStar DWOP
16 West Seno 2003 Unocal Indonesia 1020 Classic TLP DTADW
17 Marco Polo 2003 Anadarko US Gulf of Mexico 1311 MOSES DWOP
18 Kizomba A 2003 ExxonMobil Angola 1177 ETLP DDW
19 Magnolia 2003 Conoco US Gulf of Mexico 1425 ETLP DWOP
20 Kizomba B 2005 ExxonMobil Angola 1010 ETLP DDW
21 Oveng 2007 Hess Equ. Guinea 271 SSIP DTADW
22 Okume/Ebano 2007 Hess Equ. Guinea 503 SSIP DTADW
23 Neptun 2008 BHP US Gulf of Mexico 1280 SeaStar WP
24 Shenzi 2009 BHP US Gulf of Mexico 1333 MOSES WP
25 Papa Terra 2014 Petrobras Brazil 1185 ETLP DTADW
26 Olympus 2014 Shell US Gulf of Mexico 914 Classic TLP DDP
27 Bigfoot To be installed Chevron US Gulf of Mexico 1580 ETLP DDP
DDP, dry tree, drilling, production; DWOW, dry tree, workover, wellhead; WP, wet tree, production; DWOP, dry tree, workover production; DTADW, dry
tree, tender assist, drilling, wellhead; DDW, dry tree, drilling, wellhead.
Reproduced with permission from D’Souza, Aggarwal, and Basu (2013). © SNAME, 2013.

objects, they are categorized as floating structures because are typically not stable without being held by the tendons.
their working principle is based on buoyancy. Their vertical Some TLPs, but not all, can be ballasted such that they are
restraint has a significant advantage for drilling and produc- self-stable in free-floating condition.
tion platforms that are connected to subsea wells by marine The high axial tendon stiffness leads to short natural
risers. periods for the platform’s vertical modes of vibration (i.e.,
Tendons are pretensioned by excess hull buoyancy. The heave, pitch, and roll). It is important that TLPs are designed
pretension must be high enough to keep the tendons in so that these natural periods are kept below the range of
tension in all operating conditions of the platform. The significant wave energy in order to avoid a dynamic resonant
combined tendon pretension is typically 15–25% of the response of the platform in waves. Typical heave, pitch, and
hull displacement (Mercier et al., 1991). As illustrated in roll natural periods of TLPs are below 5 s (DNV, 2014).
Figure 2, the tendon tension FT also provides a horizontal In horizontal direction, the behavior of TLPs is very
restoring force FH when the platform offsets laterally. Due compliant. This results in long natural periods of the hori-
to this effect, TLPs can operate without additional lateral zontal modes of vibration (i.e., surge, sway, and yaw). With
mooring system provided the tendon pretension is large typically 100–200 s, the natural periods in surge, sway, and
enough. yaw are far greater than the longest periods of ocean waves.
Another effect of the tendon system is that a lateral offset Since all natural periods of TLPs are kept outside the
of the platform is associated with a vertical setdown as shown range of significant wave energy, the dynamic response of
in Figure 2. This vertical setdown reduces the clearance the platform to ocean waves is small.
between the deck and the water surface and needs to be taken In practice, however, TLPs do experience a certain amount
into account for selecting the column height. of resonant vibrations. Such resonant response is gener-
The tendon’s high axial stiffness also provides the platform ally undesired because it increases the stress in the tendons
with stability against capsizing. In operating condition, TLPs and the riser system. The vibration of the “stiff” modes

Encyclopedia of Maritime and Offshore Engineering, online © 2017 John Wiley & Sons, Ltd.
This article is © 2017 John Wiley & Sons, Ltd.
DOI: 10.1002/9781118476406.emoe400
Also published in the Encyclopedia of Maritime and Offshore Engineering (print edition) ISBN: 978-1-118-47635-2
4 Offshore

Offset

Set-down
π

FG

FB

FH

FT
FV

Figure 4. MOSES TLP design by Modec. (Reproduced with per-


Tendons mission from Modec. © Modec, 2015.)

Figure 2. Forces on a TLP in offset position (drawing by Edmund


Muehlner).

Figure 5. Extended pontoon TLP design by ABB Lummus Global.


(Reproduced with permission from FloaTEC © FloaTEC 2015.)

(heave, roll, and pitch) is called ringing and springing, while


the resonant response of the “compliant” modes in surge,
sway, and yaw are called slow-drift motions. Ringing and
springing are excited mainly by nonlinear wave effects, while
slow-drift motions are mainly excited by wind and to a lesser
extent by nonlinear wave effects.
Figure 3. SeaStar mini-TLP design by Atlantia Offshore. (Repro- In deeper water, it becomes increasingly difficult for TLPs
duced with permission from SBM Offshore. © SBM, 2015.)
to achieve natural periods below the wave excitation range.
That is a consequence of the tendon’s decreasing axial

Encyclopedia of Maritime and Offshore Engineering, online © 2017 John Wiley & Sons, Ltd.
This article is © 2017 John Wiley & Sons, Ltd.
DOI: 10.1002/9781118476406.emoe400
Also published in the Encyclopedia of Maritime and Offshore Engineering (print edition) ISBN: 978-1-118-47635-2
Tension Leg Platform (TLP) 5

stiffness with increasing length. To compensate the stiff- with a bottom founded central production platform 10 miles
ness reduction due to increased length, tendons have to be away that receives the production streams of the Jolliett TLP
furnished with a larger cross section. As a result, the size and (Mercier et al., 1991). Other development schemes (e.g.,
cost of the tendon system increases progressively with water Kizomba A and Kizomba B) employ configurations using a
depth. For this reason, TLPs are not considered economi- TLWP together with a nearby located FPSO.
cally viable in water depths beyond about 1800 m. However, Tender-assisted drilling (TAD) is another configuration
studies indicate that TLPs are technically feasible in water used to reduce the payload of the TLP. In a TAD configu-
depths greater than 1800 m (Alves et al., 2010; Muehlner and ration, drilling equipment is stored on a tender vessel rather
McBee, 2013). than on the TLP. The tender vessel is typically a barge or a
semisubmersible. It is moored in close proximity to the TLP,
which allows the transfer of equipment and crew between
4 TLP FUNCTIONS AND the two vessels. Once drilling operations are completed, the
CONFIGURATIONS tender vessel can be removed. TAD configurations are not
unique to TLPs and have been used since the early days of
Initially conceived as drilling platforms, TLPs have been offshore field developments for drilling operations from fixed
used as production platforms and as combined production platforms, jack-ups, and floating rigs.
and drilling platforms. There were also three vertically teth- Although many TLPs were designed for rather small
ered buoys installed that are strictly speaking applications of payloads, TLPs can also have very large payloads. The
TLPs. Two of these buoys are control buoys and one is a flare largest TLP to date is the Heidrun TLP with a payload
buoy (Bone, 2012). (topside and riser load) of 637.2 MN, and an oil produc-
TLPs have also been proposed as platforms for floating tion rate of 1457 m3 /h (220,000 BOPD) (Mitcha, Morrison,
wind turbines. In 2008, a prototype of a wind turbine TLP and de Oliviera, 1986). The currently smallest TLP is the
design by Blue H was tested for 6 months off the coast of Oveng TLP with a topside weight of 22.1 MN (excluding
Southern Italy (Blue H Group, 2015). riser load) and an oil production rate of 166 m3 /h (25,000
TLPs are often selected over other types of floating system BOPD) (Wilhoit and Supan, 2010).
because of their superior motion performance and their small
seafloor footprint (Leffler, Pattarozzi, and Sterling, 2011).
Their low heave and pitch motions allow the production
trees (a.k.a. Christmas trees) to be located on the deck of 5 TLP DESIGN
the platform. Such production trees are referred to as dry
trees. Wet tree arrangements, on the other hand, have the 5.1 TLP hull
production tree located on the seabed.
Oil and gas production using dry trees has several opera- The primary function of the hull is to provide the buoyancy
tional advantages over wet tree arrangements. Currently, the to support the weight of the platform and to tension the
only other floating platform that allows offshore production tendons. The hull is subdivided into different compartments
using dry trees is the Spar platform. TLPs are also used for to mitigate potential hull damage and accidental flooding.
wet tree developments because wet tree risers, too, benefit All hull compartments are accessible for inspection. Most
from the TLP’s favorable motion behavior. Examples of pure compartments are void except the ones used as ballast tanks
wet tree TLPs are the Morpeth and Shenzi TLPs. or as pump rooms. In some cases, the hull is also used to
Early on in the evolution of TLPs, it was recognized that hold tanks containing consumables. Hydrocarbons are not
TLPs are rather sensitive to the payload and overall system normally stored in the hull to avoid hazards. In addition, TLP
costs increase significantly with increasing payloads. This hulls inherently do not lend themselves for storing significant
circumstance led to the development of the tension leg well- amounts of well products (Chakrabarti, 2005). The hull is
head platform (TLWP). The idea behind the TLWP concept also equipped with a marine system.
is to use a reduced size TLP together with a second platform. TLP hulls are constructed from steel and follow conven-
The function of the TLWP is primarily to support the dry-tree tional ship design practices using orthogonally stiffened
risers, while other heavy equipment are hosted on the second plate. One exception is the Heidrun TLP, which has a
facility. concrete hull.
The concept of the TLWP was first applied for Conoco’s The shape of TLP hulls was derived from semisub-
Jolliett TLP installed in 1989. The Jolliet platform had a mersibles with vertical water surface-piercing columns and
reduced process plant and only a completion rig rather than horizontal pontoons below the water line. This arrangement
a full-size drill rigs. It was designed to work in conjunction lends the platform good hydrodynamic behavior in waves.

Encyclopedia of Maritime and Offshore Engineering, online © 2017 John Wiley & Sons, Ltd.
This article is © 2017 John Wiley & Sons, Ltd.
DOI: 10.1002/9781118476406.emoe400
Also published in the Encyclopedia of Maritime and Offshore Engineering (print edition) ISBN: 978-1-118-47635-2
6 Offshore

The column height is selected with sufficient freeboard to Tendon top connector
keep the deck above the water elevation in the highest waves.
Flex element
A typical conventional TLP hull consists of four columns
and a four-sided ring pontoon. Circular as well as round Load cell
cross sections have been used for both the columns and
Tendon porch
the pontoons; however, most conventional TLPs have round
columns and rectangular pontoons (Yang and Ren, 2013). A Length adjustment joint
column top frame may be used to connect the top ends of the
columns. The column top frame holds the columns together Hull
during hull dry transport and will also share hydrodynamic
squeeze/pry loads on the columns due to wave action (Yang
and Ren, 2013). It can also be used to support the vertical Tendon connectors
loads of topside modules and the top-tension risers.
The installation of a TLP is greatly simplified if it can
be towed to its installation site in free-floating condition.
However, this typically dictates a larger hull size than
required for its in-place condition when the platform is
attached to the tendons. However, some TLP hulls are not
Pile receptacle
sized to be self-stable in transit condition and therefore need
special preparations for installation. During the evolution of Flex element
the TLP, different designers developed hull configurations
Foundation pile
that deviate from the classic TLP design. These designs Tendon bottom connector
aim to minimize cost by reducing the required size of the
hull and the tendons for a given payload. Atlantia Offshore Seabed
developed the SeaStar design (Figure 3). Modec developed
the MOSES and SSIP designs (Figure 4). ABB Lummus
Global developed the ETLP (Figure 5). Common to these
proprietary designs is that their column spacing is reduced
and their tendon footprint enlarged. The SeaStar design has Figure 6. Tendon assembly (drawing by Edmund Muehlner).
only one central column.

5.2 TLP mooring system anchored to the seabed by multiple piles. They were expen-
sive to build and install and were phased out. Gravity foun-
The mooring system of a TLP has typically 6–16 tendons dations resist the tendon uplift forces by their weight. They
arranged around the platform in three or four groups. A are typically large concrete structures. Today, gravity founda-
sketch of a single tendon is shown in Figure 6. The number tions are still considered viable design alternatives, in partic-
and size of the tendons is chosen so that the platform ular for soil conditions where driven piles are not feasible.
will survive the worst design storm even with one tendon
damaged or missing. Shell’s Auger TLP has an additional
lateral mooring system but this feature was not used on any 5.2.2 Tendon bottom connector
other platform.
The tendon bottom connector is the mechanism that connects
the tendon bottom end to the foundation. The bottom
5.2.1 Tendon foundation
connector designs in use are the bayonet-type connector, the
Tendon foundations are the structures that anchor the collet-type connector, and the side latch connector (Barl-
tendons in the seabed. All TLPs installed after 1995 used trop, 1998). Today, the bayonet-type connector is primarily
a single-driven pile for each tendon. These piles are steel used. They are stabbed into the receptacle from the top and
pipes with a tendon receptacle and a driving head at their locked by turning the entire tendon string. The collet-type
top. Typical dimensions of these piles are a diameter of connector is also stabbed from the top. It is locked by
1.5–2.5 m and a length of up to about 130 m. expanding collet fingers over a flange in the receptacle.
Prior to 1996, TLPs used gravity foundations and foun- The side latch connector is engaged by sliding it from
dation templates. Foundation templates are large structures the side into the receptacle. All tendon bottom connectors

Encyclopedia of Maritime and Offshore Engineering, online © 2017 John Wiley & Sons, Ltd.
This article is © 2017 John Wiley & Sons, Ltd.
DOI: 10.1002/9781118476406.emoe400
Also published in the Encyclopedia of Maritime and Offshore Engineering (print edition) ISBN: 978-1-118-47635-2
Tension Leg Platform (TLP) 7

This clamp resembles a segmented nut. To release the clamp,


the segments disengage from the thread of the tendon’s
LAJ. The tendon lengths are adjusted by opening the clamp,
ballasting the vessel to the desired draft, and then closing the
clamp. As for the bottom connector, the tendon top connector
incorporates a flexible element that accommodates the tilting
of the tendon relative to the tendon porch.
Two of the early TLPs had the tendon top connections
inside the columns and above the water surface. This makes
the top connectors accessible for inspection. However, these
designs require additional tendon cross load bearings at the
tendon exit locations from the columns. It also complicates
tendon installation. Today, internal tendon top connectors
are considered obsolete. Part of the tendon top connector
assembly is also the tendon tension measurement system.

Figure 7. Section view of flex element in tendon top and bottom 5.3 TLP topside
connectors (drawing by Edmund Muehlner).
The topside, also referred to as deck, sits on top of the
columns. It is designed as a separate structural component.
incorporate a flexible element (Figure 7) that allows the This allows the hull and topside to be fabricated concurrently
tendon to tilt by about 15∘ relative to the receptacle. and in different fabrication yards, which shortens the fabri-
cation schedule.
The functions and subsystems housed in the topside largely
5.2.3 Tendon body depend on the purpose of the platform. Oil and gas produc-
Tendons are made of seam welded steel pipe with forged pipe tion platforms typically have living quarters, a helicopter
sections at top and bottom. The inside of the tendons is kept landing pad (helideck), and a production plant. If the plat-
void to achieve a low submerged weight. Typical diameters form is used for drilling, completion, or work- over of wells,
of the tendons’ main sections range from 0.5 to 1.1 m; typical a drill rig is also required on the topside.
wall thicknesses range from 25 to 40 mm. The pipe cross The architecture of the topside can be either integrated or
section may vary along the length of the tendon in order modular. An integrated topside is built as a single unit. It has
to adapt to the changing axial and pressure load at different the equipment fitted into the interstitial space of the struc-
water depths. tural frame. Interconnections between different equipment
Most tendons are fabricated in segments of up to about are completed in the fabrication yard prior to load-out. The
80 m length. During installation, the segments are joined by structure of an integrated deck may be an open truss design
means of mechanical connectors. Two TLPs (Jolliett and or a plated box girder design.
Heidrun) had one-piece welded tendons. However, instal- In a modular topside architecture, components and equip-
lation of this one-piece design proved prone to accidents, ment are combined to functional subassemblies, called
which led to the current installation method of stalking modules. Each module has its own structural frame and can
the tendon section from an installation vessel (D’Souza, be loaded out separately. To integrate the topside with the
Aggarwal, and Basu, 2013). hull, individual modules are separately lifted into place.
The forged tendon top section is designed as length adjust- Once the modules are assembled, the interconnections
ment joint (LAJ). Its threaded outer surface provides the between the modules are completed.
interface for the tendon top connector clamp.
5.4 TLP well system
5.2.4 Tendon top connector
The well system encompasses the equipment used for well
Tendon top connectors attach the tendons top ends to the hull. control and for transfer of fluids between the platform and
In most cases, the tendons are attached to the outside the the seabed. Its principal components are the risers, which
hull and below the water line. The tendon load is transferred are conduits that carry the well fluids from the well to the
into the top connector by a hydraulically operated clamp. platform. The following description refers to a top-tension

Encyclopedia of Maritime and Offshore Engineering, online © 2017 John Wiley & Sons, Ltd.
This article is © 2017 John Wiley & Sons, Ltd.
DOI: 10.1002/9781118476406.emoe400
Also published in the Encyclopedia of Maritime and Offshore Engineering (print edition) ISBN: 978-1-118-47635-2
8 Offshore

riser system as it is used on TLPs. Catenary risers are also can be lifted in one piece due to crane capacity limitation.
sometimes used on TLPs but are not described here. (The Larger topsides require multiple lifts thus dictating a modular
reader is referred to Risers Introduction; Steel Catenary topside design.
Riser SCR’s; Top Tension Risers TTR’s; Drilling Risers For some TLPs, the topsides were joined with the hull by
& Well Intervention for a more complete treatise on the the float-over method. For float-over, the topside is loaded
subject of marine risers.) onto a transportation barge and floated over the ballasted TLP
Dry-tree risers carry the full well pressure up to the plat- hull. The weight of the topside is then transferred from the
form where the production tree is located. During normal barge to the hull by deballasting the hull. Topside float-over
operation of a TLP, the riser system remains connected to is less restrictive to the topside weight but it is depending on
the wells in all weather conditions. Should the risers fail, a a suitable near-shore site with sufficient water depth.
subsurface safety valve located below the mudline will close
the well.
6.2 Foundation installation
A typical stack-up of a dry-tree riser includes a wellhead
connector, a riser midsegment, and a top section (Mercier
Foundation piles are lowered to the seabed and driven into the
et al., 1991). The wellhead connector is a releasable mech-
soil by means of a subsea hammer. For designs incorporating
anism that ties the riser to the wellhead. It transitions into
a foundation template, the template is lowered into place first
a tapered riser stress joint that accommodates angular riser
and then the piles are driven through the template sleeves.
movements.
Piles and template are then connected by grouting.
The riser midsegment extends from the tapered stress joint
Gravity foundations are lowered into place and become
to the TLP. It comprises of production tubing inside an
embedded into the seabed under their own weight. The
outer casing. The well fluids are carried in the production
seabed penetration may be assisted by pumps that create a
tubing while the casing is a redundant pressure barrier. Some
suction pressure underneath the foundation. In that way, the
designs use two concentric casings for added safety.
horizontal alignments of the foundation can be controlled. In
The riser top section includes a hydro-pneumatic riser
some designs, solid ballast is added on top of the foundation,
tensioner that keeps the riser under tension while allowing
once its target embedment is achieved.
it to move vertically relative to the deck. In some designs,
the risers are routed through guide tubes at the keel elevation
of the hull. On top of each riser is the assembly of main 6.3 Tendon installation
well control valves, called production tree or Christmas tree.
It is connected by flexible jumper lines to a deck-mounted Tendons can be installed prior to the hull or together with the
manifold. hull. The former method is called preinstallation, while the
Drilling risers are very similar to production risers except latter is called coinstallation. Tendon preinstallation aims to
that the inner most pipe is a drill pipe instead of production minimize the time for making the TLP storm safe.
tubing. On top of the riser stack is a blow-out preventer For preinstallation, all tendons are installed some weeks
(BOP) instead of a Christmas tree. The BOP is a safety device before the TLP arrives at the site. The tendons are assem-
that rapidly seals the well should the release of well fluids bled one by one by sequentially stacking one tendon segment
become imminent during drilling or well maintenance. In on the next and making up their connection. This operation
some designs, the BOP is located on the seabed and not on is normally performed by means of a dedicated installation
deck of the TLP. vessel. Once assembled, each tendon is fixed to its foun-
dation. Then a temporary buoyancy module is attached to
the upper portion of the tendon just below the LAJ. The
6 TLP INSTALLATION purpose of the temporary buoyancy module is to keep the
tendon upright and tensioned until the TLP is hooked-up to
6.1 Hull-to-topside integration the tendons.
For coinstallation, four tendons are assembled in the same
It is preferred to join the topside with the hull quay-side of way as for preinstallation. Each of the tendons is then hung
a fabrication yard. This may not always be possible due to off from a different corner of the TLP, while the TLP is held
limitation in water depth or in crane lifting capacity or due laterally in place by tugs. Then, the four tendons are stabbed
to the lack of hull stability. In such cases, the operation has into their pile receptacles and locked in place. At this stage,
to be performed near shore of offshore. the TLP is storm safe and the remaining tendons are added.
Joining the topside with the hull is normally done by When all tendons are installed, the TLP is deballasted to
crane lift. Currently, only topsides up to about 13,000 tonnes achieve the desired tendon pretension.

Encyclopedia of Maritime and Offshore Engineering, online © 2017 John Wiley & Sons, Ltd.
This article is © 2017 John Wiley & Sons, Ltd.
DOI: 10.1002/9781118476406.emoe400
Also published in the Encyclopedia of Maritime and Offshore Engineering (print edition) ISBN: 978-1-118-47635-2
Tension Leg Platform (TLP) 9

6.4 TLP hook-up REFERENCES


This step is only required if the tendons were preinstalled. Alves, L., Goulart, R., Mourelle, M., and Poll, P. (2010) TLP—A
To connect the TLP with the preinstalled tendons, the TLP Dry Tree Solution for Pre-salt in Santos Basin. Proceedings of the
is brought over the tendons and ballasted down until the top ASME 2010 29th International Conference on Ocean, Offshore
of the tendons reach through the tendon porches. Then, the and Arctic Engineering, OMAE2010, June 6–11, Shanghai, China,
tendon top connectors are locked and the TLP is deballasted OMAE2010-20656.
to achieve the desired tendon pretension. Armstrong, E. (1930) Seadrome. US Patent No. 1,892,125, granted
December 27, 1932.
Hull stability is an important consideration for TLP instal-
Barltrop, N. (1998) Floating Structures: A Guide for Design and
lation. If the integrated vessel is not stable without tendons,
Analysis, Oilfield Publications Limited, pp. 11-4–11-6.
the TLP cannot free-float to the integration site. In such case,
Bone, D. (2012) The Use of Unmanned Production Buoys to
the installation procedure needs to be engineered for the Develop Marginal or Submarginal Stranded Fields or End of Life
specific situation. A common solution is to use temporary Hydrocarbon Resources. Proceedings of the Offshore Technology
stability tanks attached to the hull prior to the hook-up to the Conference, Houston, Texas, April 30–May 3, 2012, OTC 23494.
tendons. Chakrabarti, S. (2005) Handbook of Offshore Engineering, vol. 1,
Elsevier, Amsterdam.
Demirbilek, Z. (1989) Tension Leg Platform: An Overview of the
LIST OF ABBREVIATIONS Concept, Analysis, and Design, American Society of Civil Engi-
neers, New York, NY.
Dieuleveult, U. (1889) Floating Telegraph Station. US Patent No.
BOPD barrels of oil per day
398,035, granted February 19, 1889.
TLP tension leg platform
DNV (2014) DNV Recommended Practice. DNV-RP-C205, Environ-
TTR top tension riser mental Conditions and Environmental Loads, April 2014.
Donelly, A. (1890) Marine Electric Light. US Patent No. 424,544,
granted April 1, 1890.
GLOSSARY D’Souza, R., Aggarwal, R., and Basu, S. (2013) The Tension Leg
Platform—A Retrospective. Proceedings of the 18th Offshore
Dry-tree Oil or gas well master control valve Symposium, Texas Section of the Society of Navel Architects and
assembly situated above the water Marine Engineers, Houston, February 7, 2013.
surface. Godfrey, D., Haney, J., Pippin, A., Stuart, C., Johnston, D., and
Floating system A plant designed to operate in a marine Orlean, R. (1997) The Mars Project Overview. Proceedings of the
Offshore Technology Conference. Houston, Texas, May 5–8, 1997,
environment in a buoyantly supported OTC 8368.
state. Horton, E. (1969) Tension Leg Offshore Marine Apparatus. US
Offshore A facility located in the ocean, typically Patent Application Ser. No. 821,275, May 2, 1969.
platform used for oil and gas exploration and Knapp, R. (1962) Stable Floating Foundation. US Patent No.
production. 3,154,039, granted October 27, 1964.
Tendon Vertical tension member, used to anchor Leffler, W., Pattarozzi, R., and Sterling, G. (2011) Deepwater
a tension leg platform to the seabed. Petroleum Exploration & Production, PennWell Corp, Tulsa, OK.
TLWP Acronym for tension leg wellhead Mercier, J., Birell, N., Chivvis, J., and Hunter, A. (1991) Tension Leg
platform, a TLP with the primary Platform—Progress and Prospects. SNAME Transactions, Vol. 99,
purpose to support wellheads. 1991, pp. 249–279.
Top tension Tensioned vertical conduit for Mitcha Jr. J., Morrison, C., and de Oliviera, J. (1996) The Heidrun
Field—Development Overview. Proceedings of the Offshore Tech-
riser transporting fluids between the seabed
nology Conference, Houston, Texas, May 6–9, 1996, OTC8084.
and a floating offshore platform.
Muehlner, E. and McBee, H. (2013) Taking TLPs to new depths. E&P
Magazine, November 1, 2013,
RELATED ARTICLES Noble, P. (2013) Floating Systems in the Offshore Oil and Gas
Industry. Presentation to UK Collegium, SNAME Western Euro-
pean Section, October 14, 2013, London, UK.
Floater Introduction
Blue H Group (2015) Floating Platform Technology for Offshore
Spar Wind Energy, http://www.bluehgroup.com (accessed 24 March
FPSO 2015).
Semisubmersibles Schempf, J. (2007) Pioneering Offshore: The Early Years, PennWell
Top Tension Risers TTR’s Custom Publishing, Tulsa, OK.

Encyclopedia of Maritime and Offshore Engineering, online © 2017 John Wiley & Sons, Ltd.
This article is © 2017 John Wiley & Sons, Ltd.
DOI: 10.1002/9781118476406.emoe400
Also published in the Encyclopedia of Maritime and Offshore Engineering (print edition) ISBN: 978-1-118-47635-2
10 Offshore

Schofield, T. (1860) Bridge Pier. US Patent No. 27,571, granted Features. Proceedings of the Offshore Technology Conference,
March 20, 1860. Houston, Texas, May 3–6, 1982, OTC 4427.
Schurman, G. and Kidder, R. (1955) Anchoring System for Floating Enze, C., Brasted, L., Arnold, P., Smith, J., Breaux, J., and Luyties, W.
Drill Structure. US Patent No. 2,939,291, granted June 7, 1960. (1994) Auger TLP Design, Fabrication and Installation Overview.
Wilhoit, L. and Supan, C. (2010) 2010 Worldwide Survey of Proceedings of the Offshore Technology Conference, Houston,
TLPs, TLWPs. Offshore Magazine, February 10, 2010, Avail- Texas, May 2–5, 1994, OTC 7615.
able at:, www.offshore-mag/maps-posters.html/0219OS-TLP- Kibbee, S. and Snell, D. (2002) New Directions in TLP Technology.
Poster012510Ads.pdf. Proceedings of the Offshore Technology Conference, Houston,
Willis, C. and Willis, D. (1948) Marine Well Drilling Apparatus. US Texas, May 6–9, 2002, OTC 14175.
Patent No. 2,777,669, granted January 15, 1957. Koon, J. and Langewis, C. (1990) Jolliet: The Project. Proceedings of
Yang, C. and Ren, M. (2013) TLP hull structural design and analysis, the Offshore Technology Conference, Houston, Texas, May 7–10,
Journal of Engineering Sciences and Technology, 11(4), 2013, 1990, OTC 6359.
35–40. Koon, J., Heijermans, B., and Wybro, P. (2002) Development of the
Prince Field. Proceedings of the Offshore Technology Conference,
Houston, Texas, May 6–9, 2002, OTC 14173.
Ølen, L. and Sandnes, J. (1988) Deepwater North Sea Development:
Snorre Field Concept. Proceedings of the Offshore Technology
FURTHER READING Conference, Houston, Texas. May 2–5, 1988, OTC 5830.
Paulling, J.R. and Horton, E.E. (1970) Analysis of the Tension Leg
American Petroleum Institute (2010) Planning, Design, and Stable Platform. Proceedings of the Offshore Technology Confer-
Constructing Tension Leg Platforms. API Recommended Practice ence, Houston, Texas, April 22–24, 1970, OTC 1263.
2T, 3rd edn, American Petroleum Institute.
Rainey, R. (2002) Brutus Project Overview. Proceedings of the
Boles, B. and Mayhall, G. (2006) Kizomba A and B: Project Offshore Technology Conference, Houston, Texas, May 6–9, 2002,
Overview. Proceedings of the Offshore Technology Conference, OTC 13990.
Houston, Texas, May 1–4, 2006, OTC 17915.
Scott, S. (2002) Typhoon Development Project Overview. Proceed-
Curtis, L. (2013) How conoco developed the tension leg platform. ings of the Offshore Technology Conference, Houston, Texas, May
Ocean Industry, 19, 35–46. 6–9, 2002, OTC 14122.
Davies, K., Leverette, S., and Spillane, M. (1994) Ringing Response Wetch, S. and Wybro, P. (2004) West Seno: Facilities Approach,
of TLP and GBS Platforms. Proceedings of the 7th International Innovation, and Benchmarking. Proceedings of the Offshore Tech-
Conference on Behavior of Offshore Structures (BOSS), vol. 2, nology Conference, Houston, Texas, May 3–6, 2004, OTC 16521.
pp. 569–585.
Ellis, N., Tetlow, J., Anderson, F., Lithgow, S., and Woodhead, A.
(1982) Hutton TLP Vessel—Structural Configuration and Design

Encyclopedia of Maritime and Offshore Engineering, online © 2017 John Wiley & Sons, Ltd.
This article is © 2017 John Wiley & Sons, Ltd.
DOI: 10.1002/9781118476406.emoe400
Also published in the Encyclopedia of Maritime and Offshore Engineering (print edition) ISBN: 978-1-118-47635-2

You might also like