Q 1: Draw a simple Work Breakdown Structure for the manufacture of a Motor bike.
Ans
manufacture of a Motor bike.
The project time management process that involves identifying and documenting
dependencies between schedule activities is option 3 i.e Sequence activities because
Sequence Activities is that the method of distinguishing and documenting relationships
among the project activities.
Answer 2.
The project calendar is a calendar of working days or shifts that establishes those dates on
which schedule activities are worked.
Answer 3.
The sequence of activities that depicts the activities before beginning preparing the project
schedule is option 1 i.e. Sequence Activities, Estimate activity resources, Estimate activity
durations.
Answer 4.
In this question the answer is option 4 i.e Start to finish with a 15 days lead because in this
situation the successor activity will begin 15 days prior the precursor activity has finished.
Q 3: What are the inputs of the Collect Requirements Process? Provide brief description.
Ans.
The project charter is one of two defined inputs for the collect requirements process. (The other input is
the stakeholder register.
“Collect Requirements is the process of determining, documenting, and managing stakeholder needs &
requirements to meet project objectives." Hence, in Collection requirement process, the first step is to
identify stakeholders' needs. Second, Document these needs & requirements
All of the tools and techniques in Collect Requirements
Group Creativity Techniques.
Brainstorming.
Idea/mind mapping.
Affinity diagram.