You are on page 1of 184

Continuous Improvement












저서명
프로젝트 관리자와 공정관리자를 위한 Primavera P6 성안당 - 2012
프로젝트 관리자와 리스크 관리자를 위한 PRA 성안당 - 2013
PMI-SP(Scheduling Professional) 성안당 - 2015
PMI-RMP(Risk Management Professional) 성안당 - 2016
Time & Risk Management 기반의 Project Management 렛츠북 - 2017
Primavera P6 정복하기 성안당 - 2019
Project Risk Manager를 위한 PRA - 2021
PMP Certification ECO 문제집 - 2023


Course Identifier
: Sample








Using Schedule and Cost Integrated Risk Management can help
to:

• Provide a more realistic budget and timeline for the
project.

• Allow for better resource planning.

• Provide a system for decision-making.

• Reduce surprises during project execution.

• Improve project performance and delivery.
It is important to note that risk management is an ongoing
process throughout the project lifecycle. All stakeholders should
be involved in the process to ensure that all potential risks are
identified and appropriately managed.
• –









Unknown
Unknown-Known Unknown-Unknown
(Hidden Fact) (Emergent risk)

Known-Known Known-Unknown
Known (Fact & Requirement) (Classic risk)

Known Unknown
• Unknown Known / Known Unknown Risk

Delay
Extension Of Time

“ Trust ”
• Schedule Cost

656.9 24

USD 6 9
USA 2024
• Schedule Cost


• Schedule Cost
• Schedule Cost

• (FIDIC) 2017
(International Federation of Consulting Engineers)
(Fédération Internationale Des Ingénieurs-Conseils)

✓ 8.3 Programme (Schedule)

• (KEPCO) 2021


• Schedule Cost

• (FIDIC) 2017
(International Federation of Consulting Engineers)
(Fédération Internationale Des Ingénieurs-Conseils)

✓ 8.3 Programme (Schedule)

• (KEPCO) 2021


• Schedule Cost
• Schedule Cost
• PMI PMBOK

✓ Labor : $/h
4. Integration
13. Stakeholder ✓ Non-labor : $/h
✓ Material : $ /Measure

PMB(Performance Measurement Baseline)


✓ QM
Scope-BL Schedule-BL Cost-BL ✓ ITP

6. 7. 8.
5.
Schedule
Scope (Time)
Cost Quality

10. 12.
9. 11. Procurem
Communi
Resource Risk ent
cation

✓ Event Risk
✓ Variance
✓ Labor : $/h ✓ Labor : $/h
✓ Non-labor : $/h ✓ Non-labor : $/h
✓ Material : $ /Measure ✓ Material : $ /Measure
• PMI PMBOK

Data Gathering

Data Analysis
Iteration Knowledge
Decision Making

Data
Representation
WPD(Work Performance Data)

Variance

Monitoring
Initiating Planning Executing & Closing
Controlling

WPI(Work Performance Information)


Change(Revision)
WPR(Work Performance Report)

Lessons Learned (OPA)


• PMI PMBOK
• PMI PMBOK
• PMI PMBOK
• PMI PMBOK

✓ Schedule network analysis


✓ Resource Optimization
✓ Critical Path Method Activity
✓ Data Analysis
- What if Scenario
- Simulation
• Monte-Carlo(중복허용)
• Latin-Hypercube
• PMI PMBOK

✓ Schedule network analysis


✓ Resource Optimization
✓ Critical Path Method
✓ Data Analysis
- What if Scenario
- Simulation
• Monte-Carlo(중복허용)
• Latin-Hypercube
• PMI PMBOK

✓ Schedule network analysis


✓ Resource Optimization
✓ Critical Path Method
✓ Data Analysis
- What if Scenario
- Simulation
• Monte-Carlo(중복허용)
• Latin-Hypercube
• PMI PMBOK
• PMI PMBOK

✓ Schedule network analysis


✓ Resource Optimization
✓ Critical Path Method
✓ Data Analysis

- What if Scenario
- Simulation
• Monte-Carlo(중복허용)
• Latin-Hypercube
• PMI PMBOK
• PMI PMBOK
• PMI PMBOK
• PMI PMBOK
• PMI PMBOK

Tornado Graph Sample


• PMI PMBOK

Scope Management Process Cost Management Process


Schedule Management Process ✓ Plan Cost Management
✓ Plan Schedule ✓ Estimate Cost
Stakeholder Management Process
Management ✓ Determine Budget
✓ Define Activities Risk Management Process Communication Management
✓ Sequence Activities Process
✓ Estimate Activity Duration ✓ Plan Risk Management
✓ Develop Schedule ✓ Identify Risk Integration Management Process
✓ Perform Qualitative Risk
Analysis
✓ Perform Quantitative Risk
Quality Management Process Analysis
✓ Plan Risk Response
Resource Management Process

Procurement Management
Process
• EVMS
• EVMS
• EVMS
• EVMS
• EVMS
• EVMS















– –






























































































– – –
– – –


Activity Predecessor Optimistic Most Likely Pessimistic Average Variance
A - 4 6 8
B - 1 4.5 5
C A 3 3 3
D A 4 5 6
E A 0.5 1 1.5
F B,C 3 4 5
G B,C 1 1.5 5
H E,F 5 6 7
I E,F 2 5 8
J D,H 2.5 2.75 4.5
K G,I 3 5 7
































































You might also like