Professional Documents
Culture Documents
1.Define Activities
T=5 1.Gather Re 2.Sequence Activities 1.Plan Risk Mngt
R=5 2.Define Scope 3.Estimate Resource 1.Estimate Cost Plan Quality Plan Hr Plan Communication 2.Identify Risk Plan Procurement
2.Determine
Planning Project Plan 3.Create WBS 4.Estimate Duration Budget 3.Quantative Risk
5.Develop Schedule 4.Qualative Risk
5.Plan Risk Response
Control
Monitoring Integrated Monitor Scope Control Schedule Control Cost Monitor Quality Contro Stakeholder Monitor & Control Ri Procurement
& Control Change Control Control Scope
As you taught us, the numbers 756334466 are helpful to remember how many processes are in each knowledge
area. In addition, it is helpful to know that Time and Risk have the most planning processes (5 each), and that H.R.
and Procurement have the most executing processes (2 each, and you can remember that because there are the
two things you can execute: people and contracts!). Then each of the other knowledge areas with more than 3
processes have an unusually large number of monitor and controlling processes (2 each). If you circle these boxes
in the brain dump -- one in each knowledge area with more than 3 processes -- then you can fill in these processes
knowing exactly how many go in each circle. Then, most of the other boxes have just one process, and so it's not
hard to remember all 46 of them.
addition there are "S" words for three of them: Time=Schedule, H.R.=Staffing, and Communication=Stakeholder. The reason this
is helpful to know is that some of the processes and some of the management plans are named after the alternate "S" word, so
writing those three aliases at the very top of the brain dump is helpful. In addition, the project management plan has two
subordinate plans -- one in Quality (Process Improvement Plan) and the other in Procurement (Contract Management Plan),
which can be indicated above the respective columns.
Integr. Scope (sched)
7 5 Time
6
Init DPC
DPPSS
Planning DPMP SP AD
SDf AS
CWBS ARE
ADE
SDv
Exec- DMPE
ution
Mon & MCPW SV SC
Ctrl ICC SC
Closing CP
P+4M+O McGregor=X,Y AC - actual cost
Pert = 6 (X is bad, Y is good) EV - earned value
P-O Maslow's Hierarchy PV - planned value
SD = 6 Self-act, Esteem, Social, Safety, Psych BAC - bud @ compl