Professional Documents
Culture Documents
visualizing progress
- once data about project progress is collected, the collected data should be
presented by the project manager. the progress is views in 2 ways
Cost Monitoring
- This is also called ad “Expenditure monitoring”
- - it gives an indication about the amount of effort which is required to develop a project.
- One of the charts used for this pupose is “Cumulative expentiture chart”.
- This provides a simple method of comparing the planned and actual expenditure.
- The fighure below shows the expenditure chart
- This chart shows the deviation between planned cost and the actual cost.
- The current status of the project should also be considered before monitoring the
expenditure.
- Project costs augmented by project monitoring can be used to generate forecast of future
costs.
- The following diagram show the additional information available once the revised cost
schedule is included – in this case it is apparent that the project is behind schedule nd
over budget.
Prioritizing Monitoring
Here list prorities we must apply in deciding levels of monitoring
Critical path activities Any delay in an activity on the critical path will cause a delay in the
completion date for the project. Critical path activities are therefore likely to have a very high
priority for close monitoring.
Activities with no free float A delay in any activity with no float will delay atleast some
subsequent activities eventhough, if the delay is less than the float, no delay the project
completion date.These subsequent delays can have serious effects on our resource
schedule(resources unavailable before that activity is completed).
Activity with less than a specified float If any activity has very little float it might use up this float
before the reqular activity monitoring brings the problem to the project manager’s attention. It is
to monitor closely.
Hight risk activities A set of high risk activities should have been indentified as part of the initial
risk profilling exercise. We will designate as high risk those activities that have duration variance.
These activities will be give close attention.
Activities using critical resources Activites can be critical because they are expensive( as contact
programmers). Staff or other resources avail only for liited period. In any event, an acitivity that
demands a critical resource requires high level monitoring.