You are on page 1of 10

Fatal flaws in technical due diligences

A J H Newell1

ABSTRACT
The background and the basis for conducting a technical due diligence are discussed
as well as the source information, typical studies and potential limitations. Typical
short comings including ‘show-stoppers’ are presented for the metallurgical area,
with examples. Issues found in other areas such as geology, mining, infrastructure
and financial evaluations are briefly reviewed, highlighting the input and interaction
required by metallurgists with these disciplines. A checklist is provided as a guide
to maximise the success of a due diligence as well as a check on the quality of a
Feasibility Study.

INTRODUCTION
A due diligence is primarily required when funds are sought to develop a new
project or expand an existing operation or when there is a proposed merger or
acquisition. An investor, typically a bank and occasionally a trading house and/or
the merging or acquiring entity (usually a mining company or group of companies),
will select and appoint consultants to assist in the assessment of the project or
evaluation of the target asset.
There are two types of due diligence, namely legal/financial and technical, both
equally as important and both need to be found satisfactory before an acquisition or
merger can be progressed.
Historically, most technical due diligences conducted by RungePincockMinarco
(RPM) have been for financial institutions. Today, there are more potential operators
(ie mining companies) in the mix.

LEGAL/FINANCIAL DUE DILIGENCE


In a legal/financial due diligence, the investor conducts an investigation into both the
financial and legal status of the company, in an attempt to identify any current and
legacy issues, such as financial commitments, legal and ownership arrangements of
the company and the directors. It should be noted that the desirability for a merger
or acquisition can quickly evaporate with poor findings. This type of due diligence
should be conducted prior to undertaking a technical due diligence.
As an example, a client in the industrial minerals space planned a merger with a
Chinese producer. The technical due diligence went fairly well as one would expect
with an existing operation, except that the resources were not compliant with JORC
standards. However, the legal/financial due diligence (in this case completed in
parallel with the technical due diligence) discovered that not all of the shareholders
had been disclosed and moreover that there was money owed. Needless to say, the
merger did not go ahead.

TECHNICAL DUE DILIGENCE


A technical due diligence assesses the reasonableness of the technical and economic
aspects of a project in terms of practicality, viability and risks (Pincock, 2009). It
examines the methodologies, supporting data and underlying assumptions used
for evaluating or managing a project based on supplied information, technical and
operating data from similar projects, site visits and interviews with key project or
operating personnel.
The main purpose of a technical due diligence is to identify ‘show-stoppers’
– aspects of the project that make it impractical or unviable – and thus protect the
investor from potentially losing money by investing the project. Often the technical
due diligence uncovers a raft of assumptions or unusual methodologies – ‘devils that
you don’t know’ – that seriously undermine the project. This does not necessarily
1. MAusIMM(CP), Executive Consultant, mean that the investor would not become involved in the project, particularly when
Processing, RungePincockMinarco, Brisbane the underlying asset has significant potential (eg good orebody); it usually encourages
Qld 4000. Email: anewell@rpmglobal.com a re-development of the project by the owners.

1
A J H Newell

A successful and timely technical due diligence relies A Feasibility Study, when properly developed, has
on experienced personnel with a background in project progressed through the Scoping Study and Pre-Feasibility
development as well as operations and an overlap with Study stages. When a study stage has been bypassed, it
other disciplines. For example, a metallurgist, besides being is quickly revealed in a Technical Due Diligence; there is a
competent in the processing technology associated with general lack of methodology in the study approach, only a
that commodity as well as typical metallurgical responses focus on selected areas, various options remain open and
and costs, would require some knowledge of geology (the unresolved, marketing studies are not as advanced as they
geometallurgical aspects, such as ore types, as applied in should be, insufficient test work to support the study level –
the resource model etc) as well as mining (mainly mine captured in a document that is incomplete, contains gaps and
scheduling, potential for and nature of dilution etc) to assist does not flow.
in a more accurate and timely assessment. It goes without saying that studies should be conducted by
Depending upon an individuals’ experience, a metallurgist competent and experienced personnel with a proven track
is often involved in assessing site infrastructure, except that record, either within the company or outside (eg consulting
power stations, tailings storage facilities and rail are the companies or engineering, procurement, construction
management – EPCMs). As an example, a recent due diligence
domain of infrastructure specialists. In addition, a metallurgist
of an industrial operation wishing to expand revealed a very
often reviews the marketing arrangements and the nature of
poor quality Feasibility Study, conducted by a fabricator. It
the smelter/buyer contracts.
was the show stopper of all show-stoppers, fatally flawed in
Technical due diligences are typically high level and many ways, as highlighted later in this paper. Technically,
conducted over the time span of three to four weeks, depending it lacked metallurgical detail, such as mass balances, design
upon the size of the project and the number of assets. For a criteria, flow sheets, process and instrumentation drawings
major acquisition, a high level technical due diligence may (P&IDs), design criteria etc and was based on limited test
run into eight weeks or so. Occasionally a detailed technical work employing samples from another deposit. Financially,
due diligence may be requested, which would take at least six there was no breakdown of the capital and operating costs,
months or longer. while the methodology and supporting data was poor.
Two types of assets are the target of a technical due The main areas examined in a technical due diligence
diligence. Most assets that are investigated in technical due parallel those presented in a Feasibility Study, namely:
diligences are projects supported by a Feasibility Study. •• Geology – is often the most important area and has
Consequently the main technical due diligence activities are significant potential for a fatal flaw; there needs to be
based around examining the reasonableness of the study, a high level of certainty that an orebody exists and
approach/methodologies, supporting data and assumptions supports economic extraction, allowing subsequent
and thus the likelihood of the project being technically and recovery of any project expenditures. Some significant
economically feasible. In addition, attention is paid to the flaws that can be encountered include:
nature of the project’s potential/upside as well as whether •• geological interpretation and the subsequent
risks and potential mitigations have been adequately conversion of drilling core data into a model
considered.
•• basis for classification of resources (inferred and
The other asset types considered in a technical due diligence indicated).
are an existing operation or operations, often becoming
•• Mining – has potential for fatal flaws, particularly
available for either merger or acquisition at either the top or
underground mines; major shortcomings include:
the bottom of the mining cycle. These types of technical due
diligences are in some ways easier to conduct, since the asset •• mine design and schedule – output not in terms of
has passed the Feasibility Study stage and a body of industrial ore types and is ‘lumpy’; significant variations in ore
grades, ore type blends and volumes
data and actual costs is available for review. Occasionally, an
operating asset under technical due diligence is planning an •• the optimum mining rate has not been determined
expansion. The expansion, which would be generally based •• inappropriate underground mining method
on an internal study, would hopefully follow the rigour and •• proposed levels of costing accuracy not achievable
accuracy of a Feasibility Study.
•• limited supporting geotechnical and hydrogeological
As a final comment, a generally less intense variation on a studies (particularly pit slope assumptions).
technical due diligence is an independent technical review
•• Metallurgy – often has a multitude of minor flaws
(ITR) or independent engineer’s report (IER), which are
and occasionally some fatal flaws; suitable flow sheet
mainly used for an initial public offering (IPO) or stock market and equipment with reasonable costs are the main
listing. ITR/IERs have a similar content and approach to that considerations; more details are presented in the
of a due diligence, however, are conducted at a higher level following section.
(ie less depth) and often take the form of a fatal flaw analysis.
•• Environmental – is a potential show stopper, sufficient
The nature of a Feasibility Study is discussed in some detail studies need to have been conducted and permitting
in Appendix 1 since in the assessment of a project, the quality must be in place.
of a Feasibility Study has a significant bearing on the outcome
•• Infrastructure – can become a significant show stopper,
of a technical due diligence. Some typical characteristics of
particularly for larger projects in remote locations and
non-Western feasibility studies are also presented.
typically for industrial minerals; inadequate water and
When technical due diligences are conducted on non- power supply studies; inadequate tailings disposal
Western Feasibility Studies, projects need to be evaluated planning; trade-off studies have not been conducted;
within the context of the local commercial, technical and local climatic, seasonal or seismic conditions have not
political environment and not necessarily compared with the been fully considered. In addition, the lack of or limited
standard Western approach which addresses the risks raised sterilisation drilling as well as geotechnical studies for
by Western investors and developers. the locations of the processing plant and tailings storage

2 we are metallurgists, not magicians


Fatal flaws in technical due diligences

facility can introduce unexpected costs and significantly executed, then the flow sheet may be fatally compromised and,
delay a project or limit production (eg Escondida). as a consequence, the process design and associated costs.
•• Social/indigenous – has potential to be a show stopper •• Test work sample issues
(cf Garg Island); local support for the project needs to •• samples for separation test work not being representative
demonstrated.
•• limited range of samples used to conduct
•• Marketing – occasionally a show stopper (eg product comminution testing
quality and or volumes not accepted by market).
•• suitable test work sample locations for bench scale,
•• Financial evaluation – only as good as the quality and locked cycle and pilot plant test work
reliability of the inputs. Note that any project valuation
•• Limited mineralogical studies
(eg net present value (NPV)) must be based on at least
Indicated Reserves if a public document and for a •• particularly for more complex ores and subsequent
Feasibility Study financiers generally like to see at least test work
six years of reserves. •• Limited comminution test work
•• Project execution – potential for flaws, occasionally •• none – common in Russian and Chinese work
fatal flaw, generally due to optimistic construction •• only Bond Ball Mill Work Index (BBMWi) and Ai
schedules (impact of seasons and climate has not been •• poor understanding of liberation requirements
fully considered), equipment delivery schedules and
ramp-up times. •• No preconcentration test work (potential not identified)

An issue that can initially arise when conducting a technical •• Poor understanding of metallurgical losses
due diligence is getting access to documentation and data in •• Limited amount of separation test work
a timely fashion. This information is typically provided via •• insufficient amount of test work to convincingly support
an online data room through a series of access protocols. The flow sheet interpretation and metallurgical response
quality of data can vary greatly and be in unusual places; for •• bench scale flotation test work – no locked cycle test
example, in a recent technical due diligence of a large nickel work (LCT)
operation, some metallurgical studies were in geological
•• no reproducibility studies, particularly when results
reports – which is not a place that a metallurgist would
are variable – test work and thus flow sheet decisions
naturally search.
being made based on one result
Another strategy employed by target companies is the
•• no establishment of feed grade-recovery relationships
provision of copious quantities of data, of variable relevance
(important for financial model)
and often out of date. Often the site visit produces the critical
data sought, however due to bureaucratic protocols, there may •• Limited amount of dewatering test work
be delays, some of which can be a strategy employed by the •• insufficient body of data to convincingly size and
target company. Both of these approaches were experienced select dewatering equipment
in a previously mentioned technical due diligence. •• where concentrates are produced, no transportable
While site personnel tend to be knowledgeable, helpful and moisture limit (TML) studies
communicative, this is not always the case. A relatively recent •• where ‘dry stacking’ is selected for the tailings, a range
technical due diligence site visit to a moderately large eastern of tailings samples reflecting the likely range in the
Australian copper operation revealed that a complete turnover quantity of fines needs to be tested.
of technical staff had occurred within the previous nine months
•• Flow sheet
or so and that site personnel had limited detailed knowledge.
•• not finalised
Generic flaws, which often prove fatal, result from:
•• unresolved technical issues
•• insufficient or unavailability of supporting data
(eg geological data, metallurgical samples etc) •• insufficient test work to support flow sheet selection
•• optimistic, incorrect or poorly based interpretations •• not suitable for all ore types/blends that would be
of data (eg geological data, future metal prices, metal presented to the plant
recoveries etc) •• insufficient flexibility
•• proposed levels of accuracy not achieved (eg capital and •• ‘novel’ flow sheets
operating costs). •• not been proven on a demonstration scale (cf. pilot
A processing technical due diligence checklist has been plant and bench scale tests).
provided in Appendix 2 highlighting the many elements that Other areas that are often flawed include:
need to be considered. For a project, it is also a guide to what •• Metallurgical recoveries
a successful Feasibility Study should be addressing.
•• limited understanding of sample or test work error
(reproducibility)
PROCESSING FLAWS •• no establishment of feed grade-recovery relationships
The most commonly encountered processing flaws are related
•• no allowance for scale-up
to the flow sheet. The flow sheet attracts much attention
because it is the basis for the processing plant design through •• Plant design
the mass and water balance, design criteria, equipment sizing •• design criteria does not allow for the full range of
and selection as well as the determination of consumable and processing requirements over the life-of-mine (LOM)
labour requirements and finally operating and capital costs. and may require a later expansion
A flow sheet is based on test work samples, mineralogy •• equipment selection and sizing unsatisfactory and not
and the test work program. If any of these tasks are poorly well supported

we are metallurgists, not magicians 3


A J H Newell

•• limited or lack of modelling particularly for milling •• could not be easily upgraded
circuits; eg transfer sizing (SAB/ball mill circuits) •• had poor gold recovery downstream (low gold
•• Operating costs recoveries found with intensive leaching).
•• consumable estimates not based on first principles
(eg test work or simulation results), however not Case study 3
always an issue, benchmarking may be acceptable The project assessed was a multibase metal deposit (Cu-Pb-
•• no current consumable unit cost quotations including Zn-Ag-Au) in Peru. The gravity concentration vendor had
power taken over the test work program and not surprisingly, the
proposed flow sheet had eight stages of gravity separation,
•• proposed levels of costing accuracy not achieved
some differential flotation and no tailings stream. Needless
•• no personnel list (employees and on-site contractors). to say, this flow sheet was fatally flawed and completely
undermined the Feasibility Study.
‘SHOW STOPPER’ PROCESSING CASE STUDIES
Three case studies are presented based on process development CONCLUSIONS
issues concerning flow sheet design and equipment selection. Technical due diligences are often challenging experiences
Each technical due diligences found a ‘show stopper’ that that generally reveal flaws, sometimes fatal, that justify the
was caused by the equipment vendor being involved in test expense of conducting such investigations. ‘Forearmed is
work and the flow sheet selection. Notably, the test work was forewarned’ and identifying fatal flaws or ‘show-stoppers’
designed around the equipment proposed to be supplied. As a provides the investor or potential owner with the opportunity
result of the due diligence findings, the interest of the investor to either walk away from the project or become involved
waned and in two cases, the projects were not developed. by applying a new approach to the project development or
The key issues found were: operation.
•• some misrepresentation about the capability of the While it is difficult to predict general fatal flaws or ‘show-
equipment stoppers’ for specific projects, they typically arise from:
•• some misinterpretation of the test work results •• insufficient or lack of supporting data
•• metallurgical ignorance by the project owners (no •• optimistic, incorrect or poorly based interpretations of
technical competency). data
•• poor costing methodologies
Case study 1 •• proposed levels of study accuracy not being achieved.
The Chinese client (an investor without any technical For processing, when assessing a project, the primary source
personnel) was proposing to invest in an iron ore project in of potentially fatal flaws is associated with the development
Australia (hematite property in Western Australia). Initial and interpretation of the flow sheet, which is in turn based on
test work had been conducted with known equipment (Eriez the nature of samples and the adequacy of test work.
WHIMS) with positive results; however, these units have
Process design including equipment selection and sizing
high unit capital costs, high power requirements and low
and the development of capital and operating costs represent
unit capacities. The equipment vendor proposed to change
two other areas where potential flaws may be found.
the equipment to conventional drum wet magnetic separators
with rare earth magnets, which would have significantly It is important that technically competent people manage
lower unit capital and operating costs. However, they would the test work program and subsequent process design and
be unable to generate the magnetic forces required to recover study.
the hematite. The proposed equipment was not tested and In the case of existing operations, the availability of records
the metallurgy generated with the WHIMS test work was and the ability to inspect the operation makes conducting a
adopted for the proposed equipment which indicated a very technical due diligence relatively straightforward. Potential
robust project value (NPV) for the project. flaws may arise through current or potential bottlenecks, the
quality of operational staff, the condition of the plant and the
Case study 2 ability of the plant to handle future ore types.
A major Western gold producer allowed geological staff
to conduct a metallurgical study without metallurgical REFERENCES
staff input. An equipment vendor conducted the test work Pincock (now RPM), 2011. Independent engineer/due diligence
(centrifugal concentrator). While the gravity concentration reviews, Perspectives, 111(November).
stage was investigated, the remainder of the proposed flow
sheet, namely crushing, grinding, gravity concentration, direct
smelting of gravity concentrate and cyanidation of gravity
ACKNOWLEDGEMENTS
tailings, was not tested. Furthermore, no mineralogical studies The author wishes to acknowledge assistance and input
were undertaken on feed samples or intermediate products from RPM colleagues namely Dick Addison and Don Larsen
eg gravity concentrate. In a subsequent study, it was assumed (Principal Metallurgical Engineers, Denver) as well as Bob
that it would be technically and economically possible to Denis (Executive Geological Consultant, Brisbane).
direct smelt the gravity concentrate with 100 per cent gold
recovery. When the technical due diligence challenged this APPENDIX 1 – FEASIBILITY STUDY
assumption, further test work was undertaken and it was A Feasibility Study, whether claimed to be Bankable,
discovered that the gravity concentrate: Definitive or some other rarely met descriptor, is the
•• was mainly pyrite, assaying only 30 to 80 g/t Au when culmination of a series of studies, typically starting with
5000 to 8000 g/t (0.5–0.8 per cent Au) is the threshold for Conceptual and progressing through Scoping and Pre-
direct smelting Feasibility. The intent of the study process is to decrease the

4 we are metallurgists, not magicians


Fatal flaws in technical due diligences

project risk with increasingly thorough technical studies that Table 1 presents a summary of the study progress, showing
define an optimal project development with accurate costings the decreasing level of risk and increasing level of detail
and financial evaluation. and accuracy by decreasing the number of options through
Note that the major mining houses, which typically conduct trade-off studies, particularly in mining, processing and
these studies in-house, use different terminologies for infrastructure.
these study phases however employ the same processes in As in a technical due diligence, a Feasibility Study address
determining the optimum project solution. Some companies each major study discipline, that is geology, mining,
(eg Vale) have a preference for the front end engineering processing, infrastructure, social/indigenous, environmental
design, which typically involves three front end loading (FEL) and financial analysis, except that in a technical due diligence,
stages (FEL 1, FEL 2 and FEL 3). This approach has a primary it tends to be undertaken by individual subject experts rather
focus on establishing the engineering design and subsequent than a team.
capital and operating costs; it relies on a body of information
The relationship between studies, with a metallurgical
(eg metallurgical test work) of Feasibility Study standard
flavour, and the project development cycle is presented in
that needs to be completed before the preliminary study
(FEL 1) commences. FEL 1 typically consists of a mass, water Figure 1.
and energy balance while FEL 2 prepares the preliminary A number of projects experience problems when a study
equipment design, layout, schedule and cost estimates. FEL 3 stage is bypassed, for example jumping from a Scoping Study
is more akin to the final design phase (the EPCM stage in to Feasibility Study or from a Conceptual Study to a Pre-
Figure 1), where major equipment specifications are prepared, Feasibility Study. This occurrence lies almost exclusively in the
definitive estimates are prepared as well as electrical domain of junior mining companies and appears to occur due
equipment, line and instrument lists, preliminary 3D model to a combination of inexperience, attempts to save money and
and project execution plan. Unlike a Feasibility Study, where decrease the project development period. In fact it rarely does
all of the project information is located in one document, this and often substantially increases both costs and the chances of
body of information is separate to the FEL study process and project failure. Moreover, this approach assumes that the project
generally not readily accessible. is technically and economically viable, which undermines
For the assessment of projects, Feasibility Studies are the the purpose of the study process. The Pre-Feasibility Study,
main source of information while supplemented by site visits, for example, serves a very important role and represents a
other documentation as well as meetings with managers critical stage where the options are investigated, tested and
and subject experts, the outcome of a technical due diligence resolved (so-called trade-off studies), allowing a single project
depends heavily on the quality and accuracy of the associated development pathway to be interrogated in greater depth with
Feasibility Study. regards to costs during the Feasibility Study.

FIG 1 – Relationship between project studies and project development cycle.

we are metallurgists, not magicians 5


A J H Newell

TABLE 1
Project studies.

Project stage Conceptual Study Scoping Study Pre-Feasibility Study Feasibility Study EPCM
Activity Examine concept Examine options Trade-off studies One option Construction
Resource Internal Internal/consultants Internal/consultants/EPCM Internal/consultants/EPCM EPCM contractor
contractor contractor
Basis Comparable projects Database Fixed flow sheet 20% of the engineering 100% of the
Experience Probable flow sheet Layout drawings Engineering drawings engineering
Benchmarked costs Estimate based on data from Preliminary process and Process and Engineering
similar projects information drawings information drawings drawings
Some cost factoring Some estimates based Material take-offs Material take-offs
on similar projects Firm quotations (most Contracts
Budget quotations (key equipment equipment, all consumables and
and consumables and contract rates) contract rates)
Capex accuracy ±100 ±50 ±25 ±15 ±5
Contingency ±50 ±20 ±15 ±10 ±10
Opex accuracy ±50 ±40 ±20 to ±25 ±10 to ±15 ±5
Study/activity 12.5–25 k 125–250 k 625 k–1500 k 2.5–5 million 25–50 million
costs
Duration 4 weeks 3–6 months 6–12 months 12–18 months 18–36 months
Geology Limited drilling More drilling Infill drilling Infill drilling Drilling
Geological Develop resource model Indicated Resources Resource model Continue to upgrade
understanding Ore types Inferred Resources Condemnation drilling resources
Inferred Resources Exploration potential Measured and Indicated
Geotechnical and hydrological Geotechnical and hydrological Resources
studies studies Geotechnical and hydrological
studies
Mining Desktop study Whittle Studies Whittle Studies Mine design Prestripping
Probable production rate Mining options Optimum production rate Schedules Developing audits
Probable mining Mine scheduling studies Mine scheduling studies Mining fleet and drives/
method Capex and opex Reserves Reserves Shafts
Equipment and labour Blast fragmentation studies Detailed capex and opex Purchase
requirements Capex and opex equipment/hire
Typical capex and opex contractor
Processing Desktop study Mineralogy Bench-scale testing Pilot plant (if required) Site preparation
Typical flow sheet and Limited bench-scale testing Variability testing Detailed comminution testing Source equipment/
plant Ore characterisation Comminution testing Comminution and process Installing
Product volumes Basic comminution data Dewatering testing modelling equipment/
Typical flow sheet Process options Flow sheet fixed Mass and water balance Building and
Mass and water balance Probable flow sheet Mass and water balance Equipment selection and sizing commissioning
Typical capex and opex Mass and water balance Equipment selection and sizing Power and water requirements plant
Equipment selection and sizing Power and water requirements Detailed capex and opex Training operators
Power and water requirements Develop capex and opex: budget firm quotations: equipment,
Develop capex and opex: budget quotations for key equipment and consumables)
quotations for key equipment and consumables, labour
consumables, labour
Infrastructure Review Infrastructure requirements: Infrastructure options Infrastructure design Install infrastructure
Outline sources of power and water Indicative contracts for power (tailings dam)
Roads, accommodation, logistics and water (if appropriate)
Environmental Regulatory requirements Data collection and baseline Prepare and submit Monitoring
studies (usually takes two years) environmental impact statement programs
Social and Review Discussions with locals Develop strategy and Continued negotiations
Indigenous Establish needs initiate negotiations Signed agreements
Marketing Desktop study Product uses / Discussions with potential buyers Product samples for buyers Off-take agreements
potential for substitution Refine study Negotiations
Identify market and buyers
Existing and future market size
Competitors – existing producers
and future projects
Future prices

6 we are metallurgists, not magicians


Fatal flaws in technical due diligences

TABLE 1 cont ...

Project stage Conceptual Study Scoping Study Pre-Feasibility Study Feasibility Study EPCM
Financial analyses Assumed values Exchange rates Exchange rates Detailed NPV analysis –
High level analysis Discount rate Discount rate various scenarios
NPV – used to compare options (trade- NPV – used to compare options (trade-
off studies) and sensitivity analysis off studies) and sensitivity analysis
Risk and mitigation analysis Identify Preliminary Detailed Review
Based on Pincock (now RPM) 2007; 2009. EPCM – engineering procurement construction management; NPV – net present value.

A problem often encountered with studies conducted by •• Limited mine planning and lack of detailed mining
junior mining companies is that they have been conducted schedules
in a haphazard fashion, typically by different groups of •• Source of samples not always revealed and often some
consultants assigned with a particular section obviously uncertainty about representativity
working in isolation. This is typically driven by ‘the rush to
•• where samples cannot be obtained for test work
market’ syndrome, where attracting finance overshadows
(mainly occurs earlier study phases examining
the need for a thorough understanding and study of the
underground deposits), metallurgical responses are
project. This approach is often characterised by the presence
based either on local, provincial or country metallurgy
of conflicting data indifferent parts of the study as well as
for that deposit type
limited test work, general lack of supporting detail, optimistic
capital and operating cost estimates and the use of current •• No comminution (also with Russian TEOs) or dewatering
and unrealistic metal prices for revenue calculations. test work conducted
Employing adjectives such as Definitive (should be by •• Equipment sizes are generally much smaller in size and
definition) or Bankable (confirmed by a bank?) to a Feasibility more numerous
Study does sound warning bells, suggesting a marketing •• spiral classifiers commonly used; unusual to see
rather than a study document. hydrocyclones
Often significant differences in critical numbers are found in •• thickeners are rarely used
various parts of the study and other supporting documents, •• Marketable product grades are lower with higher
making it difficult to form an opinion. In these cases, there levels of penalty elements accepted (eg 18 per cent Cu,
would not appear to have been a study manager controlling 40 per cent Zn and 55 per cent Pb)
and integrating the overall study process, resulting in little
•• Rarely issues with infrastructure – sources power and
or no communication occurring between the disciplines.
water are typically provided by the state
Studies are an iterative process and require integration
through review and communication by all disciplines. For a •• Different methodology for calculating operating costs
processing engineer, knowledge of the geological (or block) •• the value of the mined material is included in the
model, the mining schedule as well as what constitutes a mining operating cost, which is included as a cost in
marketable product are critical elements in developing and the processing operating cost
designing a flow sheet that would successfully process LOM •• depreciation is included as an operating cost which
feed and thus maximise the project value. is normally considered as a separate cost in typical
Note that there are so-called Western and non-Western type Western financial analyses
Feasibility Studies; in most cases, non-Western Feasibility •• product transport costs for projects located in
Studies, with the general exception of the Russian Technio- development regions are typically subsidised by the
Economicheskiye Obosnovaniye (TEO), do not meet the buyer.
standards of a Western Scoping Study let alone a Western type
A Feasibility Study considers the following disciplines,
Pre-Feasibility Study. They tend to follow a formulaic approach
which parallel the technical due diligence assessment process:
as prescribed by guidelines held by the Design Institutes.
•• Geology – ownership of tenures; regional and deposit
The main differences encountered with non-Western descriptions; geological or block model; data acquisition
Feasibility Studies are: (drilling methods, core recovery, logging, sampling,
•• Often a geological model may not exist (except Russian assaying, twinning etc); density determinations; quality
TEOs) of the resource estimate (inferred and indicated – data
•• does not include ore types validation, modelling method, QA/QC, interpretation
•• issues with quality assurance / quality control (QA/ (‘geo-imaginitus’), grade/tonnage relationships etc),
exploration history and upside.
QC) procedures as well as assaying methods
•• Mining – open cut relatively straightforward,
•• Resources are not JORC compliant; while other
underground more complicated and depends
methods of estimating resource are reasonable (for
upon the deposit style (cf thin veins and need for
example, Russian), they cannot be simply ‘converted’
backfilling), mining permits, mining design, waste
into a JORC classification without undertaking a full
dumps and stockpiles, trade-off studies, mine schedule
review, which is very difficult to do when:
and production plans, pit wall slope, rock stability
•• the drill core has been destroyed or lost (cf when the and strength (geotechnical studies), dewatering
metal is classified by a country as strategic eg uranium requirements (hydrogeology), equipment, capital and
in the USSR or tungsten and rare earths in China) operating costs (methodology, budget quotations,
•• the actual coordinate system used to locate drill holes quantity take-offs, consumable and personnel estimates,
is not known accuracy, contingencies, equipment/services sources

we are metallurgists, not magicians 7


A J H Newell

(currency), transport and insurance, dewatering and institutions for determining, assessing and managing
reserves (proven and probable)). environmental and social risks.
•• Metallurgy – location and nature of samples, test
work program – mineralogy, preconcentration, REFERENCES
comminution parameters, separation and dewatering; Equator Principles Association, 2011. Equator Principles [online].
water quality; technical management of waste streams Available from: <http://www.equator-principles.com/>.
(eg detoxification); flow sheet; mass and water balances; Pincock (now RPM), 2007. Minimum report contents for engineering
design criteria; equipment selection, sizing and list; studies, Perspectives, 70 (December).
comminution and preferably flow sheet modelling; Pincock (now RPM), 2009. Minimum engineering study requirements,
process description; drawings – general arrangement, Perspectives, 95 (March).
PFD, P&IDs and one-line electrical; consumable
requirements (power, water, labour, milling media
etc); capital and operating costs (methodology, budget APPENDIX 2 – PROCESSING DUE DILIGENCE CHECKLIST
quotations, quantity take-offs, factoring, accuracy,
contingencies, mobile equipment, equipment/services Existing operation
sources (currency), transport and insurance etc); product Historical and current records – production, operating costs,
schedule. recoveries, product grades etc.
•• Environmental – suitable and sufficient baseline studies Site inspection
have been conducted; appropriate regulatory approvals, Operation
permitting and licences eg details of environmental •• how the plant is being operated – number of operators,
impact assessment or statement (EIA/EIS); stakeholder operator activity, housekeeping etc
engagement, environmental management systems
•• condition of the plant – need for equipment replacement,
(EMS) and environmental/social management plans
nature and magnitude of maintenance costs
(EMP) completed; reclamation and closure plan;
operating costs; closure costs. •• process bottlenecks
•• Infrastructure – requirements/sources/distribution/ •• review sample collection including final concentrates,
reticulation of power and water; if connected to grid assay facility, laboratory (routine and future ore testing).
power, route map; logistics (roads, rail, airports, Future plans – ore sources, grades, ore types, mineralogy etc
ports etc – getting equipment, consumables and •• Will future ores have different characteristics or grades
personnel to site; getting product to market); buildings that will affect the metallurgical performance in terms:
(offices, warehouses, maintenance/repair shops, •• throughput
accommodation); allowance for location, climate and
•• recoveries
seismicity (buildings); construction schedule.
•• product grades
•• Social/indigenous – needs to demonstrate a good
relationship with local people; support for the project, •• What procedures are in place to measure and record any
program of assistance and ongoing interaction. changes in ore types? For instance:
•• Marketing – suitability of product and product •• weekly testing on site
specifications, size of market, future of market •• off-site testing
(competition, growth, substitution etc), product terms •• frequency
(penalties, credits etc), smelting and refining terms, •• How would the current flow sheet and equipment
future product prices, product transport route map, handle any changes in ore characteristics?
arrangements and costs etc.
•• Any potential bottlenecks?
•• Financial evaluation – typically based on discounted cash
•• increased hardness – comminution circuits
flow methodology, with NPV used as the measure;
only as good as the quality and reliability of the inputs: •• grade changes – separation and dewatering circuits
capital and operating costs (eg estimate basis, nature of •• Flow sheet changes required?
the contingencies), future metal prices, exchange rates, •• potential costs
inflation rates, discount factor etc). Any NPV must be
•• downtime for installation
based on at least Indicated Reserves if a public document
and for a Feasibility Study bankers like to generally see •• Equipment changes or upgrades required?
at least six years of reserves. •• potential costs
•• Project execution – management plan and procedures •• downtime for installation.
(owner/EPCM structure and organisation, key Future water and power supplies – quantities, availability,
personnel and qualifications, project responsibility list supply agreements
(owner-managed and EPCM-managed projects), EPCM
Reconciliation between mine and plant
contractor procedures (engineering, procurement,
construction and reporting etc)), implementation Tailings Storage Facility (TSF) capacity – need for another TSF
schedule, list of probable contracts and facilities, likely- Future costs – basis for sustaining capital, any capital
qualified contractor listings, equipment delivery (long upgrades/expansions, supporting studies, production and
lead items, logistical plans etc). revenue forecasts etc.
In addition, bankers considering projects in non-Western
parts of the world also like to know that the project would Project (largely based on a Feasibility Study)
meet the Equator Principles (Equator Principles Association, Nature of Feasibility Study
2011). These are series of guidelines adopted by financial •• internal or external?

8 we are metallurgists, not magicians


Fatal flaws in technical due diligences

•• where they suitably competent to conduct or manage Modelling


the Feasibility Study? •• conducted in a satisfactory fashion for the comminution
Ore types circuit
•• have they been identified? •• basis for circuit and equipment sizing and selection?
•• reasonableness of classification (degree of oxidation, •• identified behaviour and impact upon design criteria
degree of alteration, mineral gangue ratios of different ore types and mine composites
(eg chalcopyrite/pyrite ratio), mineral/mineral ratios, •• where appropriate, for the separation circuit.
impurity or gangue mineral (eg As level)) Mass, water and energy balance
•• included the geological model (and thus the mine •• basis: optimum mining rate study, flow sheet, other data
schedule)? or sources
Samples – nature of samples and composites: number, type •• source for values used in calculations (eg ore, water,
(drill core, air core etc), location, representative in nature, product and intermediate stream SGs, mass and metal
mining year etc stage recoveries)
Mineralogy – conducted for all ore types and composites; •• sufficient flexibility to handle potential process
identified economic and impurity types, associations, grain variations (‘average’ and ‘design’ cases).
size and rock types; degree of liberation
Metal losses
Test work program
•• metal losses for each ore type has been satisfactorily
•• undertaken by reputable and independent test identified
work provider (cf equipment vendor – under some
•• addressed the potential for improved recoveries or
circumstances)
concentrate grades
•• conventional or ‘novel’ or using ‘novel’ equipment Metal recoveries and product grades
•• if ‘novel’, a pilot plant or pilot scale test and •• demonstrated as a function of ore types, mining
demonstration plant required composite types and head grades
•• has addressed the obvious flow sheet options •• full analysis of final concentrate (credit and penalty
•• sufficient test work has been conducted on an elements and levels identified).
appropriate range and number of samples Design criteria
•• has preconcentration been examined •• basis and source for selection of Design Criteria; is it
•• has site water or synthetic water been used in test work reasonable and supported?
•• ore variability test work been conducted •• transfer sizing for SAG – ball mill circuits
•• material handling – flow, rill angles, abrasiveness, slurry •• circulating loads
viscosity etc •• product and intermediate product per cent solids
•• other characteristics: oxygen demand etc •• media and reagent consumption rates
•• feed grade-recovery relationship been established for •• scale-up factors used to estimate residence time
each ore type and mining composite (eg conditioning, flotation, heap leaching etc)
•• has the product been satisfactorily characterised in •• addresses needs of climatic and operating culture
terms of: requirements (eg cold climate, regulated holiday
•• full assay – credit and penalty elements periods etc)
•• dewatering requirements and equipment requirements Equipment
•• if a concentrate, TML •• basis for selection, number and sizing: reasonable
•• other properties such as size range, friability etc •• equipment source
•• have the tailings been satisfactorily characterised for •• equipment vendor: reputable, critical spares identified,
range of ore types and blends in terms of: process and equipment warranties, availability for
commissioning
•• mineralogical characteristics
•• duty specifications: reasonable.
•• potential for pollution and acid generation
Mine schedule
•• dewatering properties
•• an optimum mining rate has been determined
•• backfill and ‘dry stacking’ (where the size range,
particularly the amount of fines, is important) •• basis: process capital and operating costs used
•• environmental studies such as detoxification of process •• limited by market
water for release into the environment. •• includes ore types and thus mining composites.

Flow sheet Water


•• water quality
•• basis for and reasonableness of flow sheet selection
•• impact upon separation and final product
•• conventional or ‘novel’
•• need to wash final product
•• unnecessarily complex
•• need to produce pure water
•• appropriate use of surge capacity within the flow sheet
(eg stockpiles, bins or holding tanks with sufficient •• fresh and process water circuits
residence to decouple critical parts of the flow sheet) •• complexity
•• potential bottlenecks. •• adequate storage

we are metallurgists, not magicians 9


A J H Newell

•• recovered water: assumptions, recovery from TSF, •• accuracy (typically ±10 per cent FS): has it been achieved
allowances for evaporation losses etc or demonstrated?
•• water sources available to sustainability supply •• cost elements
processing water requirements (including mine water). •• quantities reasonable: consumables, power, water,
Power requirements labour schedule
•• basis (installed equipment, typical operating load, •• unit prices reasonable: with quotations for key
simulations etc) equipment; based on data from similar, current projects
Trade-off studies •• EPCM costs – reasonable for the location and
•• have been applied in a satisfactory manner to select complexity of the project
between processing, flow sheet or equipment options •• what has been factored: piping, installation,
•• for example, ‘dry’ stacking, finer grind etc commissioning, first fill etc – reasonable and supported
•• comminution circuits. •• basis for determination of sustaining capital costs and is
it reasonable?
Product schedule
•• contingency: appropriate for commodity, project
•• basis:
complexity and country location.
•• appropriate mine schedule
Marketing
•• reasonable metal recoveries
•• has a marketing study been conducted?
•• achievable product grades
•• suitable standard?
•• varies appropriately with ore types or mine blends.
•• has it satisfactorily identified:
Process description
•• current market, uses and growth
•• satisfactorily describes the process flow sheet.
•• potential buyers and actual market size for
Operating cost proposed product quality and volumes
•• methodology/basis: reasonableness (benchmark against •• competition
similar projects in same operating environment)
•• other operations (expansions) or projects
•• accuracy (typically ±10 per cent FS): has it been achieved starting up
or demonstrated?
•• potential substitution
•• cost elements
•• product specifications and terms (credits, penalties,
•• what has been included? size ranges, moisture content, other properties)
•• quantities reasonable: consumable, labour schedule •• price history and future prices.
•• unit prices reasonable with quotations for key Risks
consumables including power
•• has a risk analysis been conducted?
•• labour costs: salaries and on-cost reasonable
•• how does it assess the degree of risk?
•• maintenance cost basis: factoring, reasonable.
•• does it identify and rank all potential risks?
Capital cost
•• does it provide any recommended mitigating measures?
•• methodology/basis: reasonableness (benchmark against
•• does it analyse residual risk (after application of the
similar projects in same operating environment)
mitigation)?

10 we are metallurgists, not magicians

You might also like