Professional Documents
Culture Documents
I declare that all the information contained in this project report is personal effort which was
done practically at the work place and has never been submitted to any Institution, university or
to any awarding body for any academic award.
Name: ……………………………………………………………..
Sign: ………………………………………………………………...
Date: ………………………………………………………………...
i
APPROVAL
------------------------------------------------------- --------------------------------------------------------
------- ------
Name Signature/stamp/Date
ii
ACKNOWLEDGEMENT
We have taken effort in this real life project. However, without the kind support and help of
many individuals and the institution at large it would not have been possible. We would like to
extend our sincere thanks to all of them.
We are highly obliged to Fountain Head Institute of Management and Technology Lira, our Real
life project lecturer Mr. DICKENS WANGAYA for their guidance and constant supervision
and providing us with the necessary items for the project completion.
We also express our sincere gratitude to our parents for having enabled us reach school in time,
and their encouragement which helped us in the completion of this real life project.
We also thank and appreciate our colleagues in developing the project and people who have
willingly helped us out with their abilities and knowledge to complete this real life project.
iii
DEDICATION
I dedicate this real-life project to the Almighty God from whom abundant grace follows in a
special way I also dedicate this report to my parents for their perseverance and dedication
towards my education.
iv
LIST OF ACRONYMS
v
TABLE OF CONTENTS
DECLARATION........................................................................................................................................i
APPROVAL...............................................................................................................................................ii
ACKNOWLEDGEMENT........................................................................................................................iii
DEDICATION..........................................................................................................................................iv
LIST OF ACRONYMS.............................................................................................................................v
ABSTRACT.............................................................................................................................................viii
CHALLENGES.......................................................................................................................................viii
Conclusions..............................................................................................................................................viii
CHAPTER ONE........................................................................................................................................1
INTRODUCTION.....................................................................................................................................1
1.1 LOCATION OF THE PROJECT......................................................................................................1
1.2 OBJECTIVES/ AIMS.........................................................................................................................1
1.3 BILL OF QUANTITY.........................................................................................................................1
Table 1: BOQ.............................................................................................................................................2
A SUMMARY OF TOOLS AND EQUIPMENT WITH THEIR USES................................................3
Table 2: tools and equipment.......................................................................................................................3
CHAPTER TWO.......................................................................................................................................4
2.1 Introduction.........................................................................................................................................4
2.2 The working principle of star-delta motor starter............................................................................4
2.3 Design of the circuits...........................................................................................................................5
Figure 1: control diagram............................................................................................................................5
b. The wiring circuits diagram.................................................................................................................6
Figure 2: wiring diagram.............................................................................................................................6
CHAPTER THREE...................................................................................................................................7
3.1 ACTIVITIES CARRIED OUT...........................................................................................................7
3.2 FABRICATION...................................................................................................................................8
Spot welding...............................................................................................................................................8
Figure 3 students during spot welding.........................................................................................................8
Marking, drilling and cutting...................................................................................................................9
Figure 4: students marking, drilling and cutting..........................................................................................9
vi
Cleaning and painting...............................................................................................................................9
Figure 5.students cleaning and painting the box..........................................................................................9
3.3. CONSTRUCTIONS.........................................................................................................................10
Mounting..................................................................................................................................................10
Figure 6.students mounting indicator lamps..............................................................................................10
Wiring the circuits...................................................................................................................................11
Figure 7.students wiring the circuits..........................................................................................................11
Testing......................................................................................................................................................11
3.4 COMMISSIONING...........................................................................................................................12
2.8. Conclusions........................................................................................................................................12
3.5 Achievements.....................................................................................................................................12
CHAPTER FOUR...................................................................................................................................13
4.1. Conclusion.........................................................................................................................................13
4.2 Recommendation:..............................................................................................................................13
4.3 References..........................................................................................................................................13
2.11 APENDIX.........................................................................................................................................14
Figure 8: tools used during testing.............................................................................................................14
Figure 9: students at work.........................................................................................................................14
vii
ABSTRACT
This is a report on Star-Delta motor starter connection in Lira Institute of Technology, Lira City
West.
CHALLENGES
Inadequate protective gears such as gloves, goggles and breathing mask.
Time delay due to late delivery of materials needed in the installation
Frequent but minor accident obtained while cutting and grinding.
Inadequate knowledge about some tools and materials used.
Conclusions.
All went well during the wiring and lastly we managed to wire the star-delta motor starter
efficiently and perfectly due to the support from our supervisor and it work as required.
viii
ix
x
CHAPTER ONE
INTRODUCTION
The real life project was done from Lira Substation in lira town
1
Table 1: BOQ
S/ ITEMS DESCRIPTION QUANTI RATE TOTAL
NO TY
2
13. Washers 4 500 2000
TOTAL 585,000=
01 Bench vice It was used to hold the work piece firm for use
03 Tape measure It was used to measure the required length on a work piece
06 Painting brush It was used to sweep paint on the metal piece in the process of
painting.
07 Welding torch It was used to hold the welding rod and connect it to electricity for
work.
3
08 Sand paper It was used to sweep dirt on the metal piece and make it clear for
painting.
09 Try square It was used to make and test the squareness of a material.
10 Anvil It was used to shape the mile steel plate when making a shutter.
11 First angle grinder The grinder is used make the metal piece smooth from the rough
welded joints.
12 Pair of dividers It was used to make circles on the shutter of known diameter.
CHAPTER TWO
2.1 Introduction.
This chapter introduces and talked about the procedures and steps taken during the full real life
project that is the star-delta motor starter connection, the new knowledge acquired and the
general problems experiences and its solutions
The principle of operation of star-delta motor starter states, during starting a motor, winding are
connected in star configuration and this reduces the voltage across each winding which also
reduces the tongue by a factor of three. After a period of time, the winding are reconfigured as
delta the motor runs normally
4
2.3 Design of the circuits.
a) The control circuits diagram.
5
Figure 1: control diagram
6
CHAPTER THREE
Welding
Marking
Drilling
Cutting
Painting
Grinding
mounting
Wiring
Fittings
Testing
7
3.2 FABRICATION.
Under this process many activities were done these include.
Spot welding.
We spot welded for the uniformity of the box.
8
Marking, drilling and cutting
Three holes of 16cm diameter were drilled on the top of the box at a distances of 7.5 cm apart
from each other for the indicating lamps and another two holes for the push Burton switch of
22cm diameter and 16cm apart from each other. And a softwood of 28cm2
Figure 4:
students marking, drilling and cutting
9
Figure 5.students cleaning and painting the box
3.3. CONSTRUCTIONS.
Mounting.
The three indicating light/lamp were mounted on the 16mm diameter drill hole and the
push Burton switch were mounted on the two 22cm diameter with the green starting from
the left and the rails were mounted on the soft board fastened at the base of the box.
10
Wiring the circuits.
The circuits was wired using the wiring diagram as drawn above.
Testing.
Four different test were done on the circuits those test are
*Continuity test.
This test was done to check on the continuity of the phase and normally open and
normally close circuit, like point 2 of NC push Burton to point 13 of coil B of continuity.
11
#. Short circuit test.
The test was carried out between the neutral and live to check if there is any short circuits
between the phase an the neutral
3.4 COMMISSIONING.
1) Visual inspection.
The circuits was visually inspected by checking the mechanical strength and for loss connections
within the terminals of the circuits.
2) Functional test.
The circuits were tested thoroughly and then energize and finally it worked.
2.8. Conclusions.
The knowledge and skill acquired from the project, can now be installed in any motor control
system in any workshop.
More project should be provided and examined to encourage better craftsmanship and skills to
students.
More time should be allocated for real life projects.
Thanks rains to UBTEB for making Technical Educations more practical skills/ work than
theory.
3.5 Achievements.
The achievement include the following.
12
I gained social skills through frequent interaction with many colleagues.
CHAPTER FOUR
4.1. Conclusion
The real life project provides hands-on approach to all the technical information provided in the
lecture rooms.
The project to design and wire was undertaken and successfully completed and tests carried out
to registered desirable results
More projects should be provided and examined to encourage better craftsmanship of the
students and more time should also be allocated for real-life projects.
4.2 Recommendation:
4.3 References
13
2.11 APENDIX
14
Figure 9: students at work
15