MEASUREMENT SHEET
Submitted by:
Bhakunde Fish Farm
Date of Measurement :
नेपाल सरकार म.ले.प.फारम नं: ५१०
सािबकको फारम नं: १७६
कायालय कोड नं . :
काय वीकार / स प तवे द न
आयोजनाको नामः तवेदनको म तः
कामको नामः Construction/Remodelling of Fish Pond of Bhakunde Fish Farm
लागत अनुमानको कुल रकमः 163,135.00 काम सु भएको म तः
कै फयत
कामको ववरण सु लागत अनुमान बमोिजमको खुद भएको कामको फरक (सु लागत अनुमानको आधारमा)
.न लागत अनुमान आधारमा)
. इकाई प रमाण दर ज मा प रमाण दर ज मा प रमाण दर ज मा प रमाण दर ज मा प रमाण दर ज मा
A Civil Works
Excavation in Marshy soil for the construction of Fish
Pond including removal of stumps and other deleterious 1,750.00 93.22 163,135.00 1,750.00 93.22 163,135.00 - - -
1 Cu.m
matter, all lifts and lead as per specifications and
instruction of the Engineer.
Sub total B 163,135.00 - 163,135.00 -
काम स प गनु पन म तः
नापी प रमाण सू ची स झौता बमोिजमको अ याव धक काम भएको अिघ लो बलमा चढे को हाल भएको काम
पाना नं एकाइ प रमाण वीकृत दर ज मा रकम प रमाण ज मा रकम प रमाण ज मा रकम प रमाण ज मा रकम
न.
A Civil Works
Excavation in Marshy soil for the construction of Fish Pond
including removal of stumps and other deleterious matter, all
1 Cu.m 1750.00 93.22 163,135.00 1,750.000 163,135.00 0.00 1,750.00 163,135.00 0.00
lifts and lead as per specifications and instruction of the
Engineer.
Sub total B 163,135.00 163,135.00 0.00 163,135.00
Grand Total 163,135.00 163,135.00 163,135.00
यो िबलबमोिजम काम भएको ज मा ः 163,135.00 हाल काम भएको बाँक िदनपु न ः 163,135.00 यस िबल बमोिजम ग रएको भु ानी
अिघ लो िबलस म भु ानी भएको ः 0.00 क ा गनु पन भौचर न:ं
अिघ लो भु ानी िबलको म सङ् याः क. मोिबलाइजेसन पे क ः - भु ानी िमित:
अिघ लो भु ानी िबलको भौ.न.ं ख. मालसामानको पे क ः भु ानी रकम
ग. मेिसनरी औजारको बहाल ः
घ. अ ीम आय कर रकम ः
ङ. धरौटी रकम ः
च. अ य क ी गन पन रकम ः
खदु िदनु पन रकम ः
िनमाण यवसायीको सही: तयार गनको सहीः जाँच गनको सहीः वीकृ त गनको सहीः
नाम: नाम नाम नाम
पदः दजाः दजाः दजाः
िमितः िमितः िमितः िमितः
Total
S.N. Description of Works Unit Rate (NRs.) Amount (NRs.) Remarks
Quantity
A Civil Works
Excavation in Marshy soil for the construction of
Fish Pond including removal of stumps and other
A.1 Cu.m 1,750.00 93.22 163,135.00
deleterious matter, all lifts and lead as per
specifications and instruction of the Engineer.
Sub Total of A 163,135.00
Say Nrs 163,000.00
Measurement Sheet
DETAILED ESTIMATE
Submitted by:
Bhakunde Fish Farm
Date of Submission :
Abstract of Cost
Total
S.N. Description of Works Unit Rate (NRs.) Amount (NRs.) Remarks
Quantity
A Civil Works
Excavation in Marshy soil for the construction of
Fish Pond including removal of stumps and other
A.1 Cu.m 1,750.00 93.22 163,135.00
deleterious matter, all lifts and lead as per
specifications and instruction of the Engineer.
Sub Total of A 163,135.00
Say Nrs 163,000.00
Estimate Sanction Form
F.Y 2080/81
A The drawings and measurements of the proposed work are based on field verification.
B The design and estimate of the proposed work is based on departmental norms and
general principles in practice.
C The proposed estimate is prepared on the basis of approved rate and rate analysis
norms.
D All the numbers and arithmetical calculations carried out in this estimate are correct.
Prepared by : …………………………
Engineer
Quantity Estimate
Summary of Rate
Rate Without
S.N. Description of items Unit Remarks
VAT (NRs)
Excavation in Marshy soil for the construction of Fish Pond including removal of stumps
1 and other deleterious matter, all lifts and lead as per specifications and instruction of the Cu.m 93.22
Engineer.
Estimated by:
Government of Nepal
RATE ANALYSIS
Name of Work : Construction/Remodelling of Fish Pond of Bhakunde Fish Farm
Location: Pokhara-18, Bhakunde
FY 2080/081
Resources
Remarks
Item A. Labour B. Materials C. Equipments Total Rate
Description of work T&P Sub-total
No. (per unit)
Per Class Unit Qty Rate Cost Type Unit Qty Rate Cost Type Unit Qty Rate Cost
1 Excavation in all types of soil in canal as per Skilled 1.0 1214 1,214.00 Excavotar m3 6.00 3,890.87 23,345.22
m-day DoR
drawing and technical specifications including
Unskilled 4.0 852 3,408.00 9.1.V
removal of stums amd other deleterious 300 m-day
materials as directed by the Engineer. m3 Total of A = 4,622.00 Total of C = 23,345.22 27,967.22 93.22 /m3
Name of Work : Construction/Remodelling of Fish Pond of Bhakunde Fish Farm
Location: Pokhara-18, Bhakunde
Basic Rate Based on Approved District Rate of Kaski
FY 2080/081
S.N. Description of Items Unit Rate Remarks
1 Skilled labour m-day 1,214.00 Distr. Rate Page No. 4
2 Unskilled labour m-day 852.00 Distr. Rate Page No. 4
3 Driver(Heavy) m-day 922.00 Distr. Rate Page No. 4
4 Heavy equipment operator m-day 922.00 Distr. Rate Page No. 4
5 Helper m-day 852.00 Distr. Rate Page No. 4
6 Diesel Liter 157.50 As per NOC
Prepared By:
Hourly Cost of Heavy Equipment as per DoR Norms
Description Unit Rate
Diesel Liter 157.50
Operator Day 922.00
Prepared By: