You are on page 1of 8

Validation of A Consumer

Healthcare Facility
A Case Study in Time & Cost Reduction
By R.J. Noy, Ph.D.
SmithKline Beecham Consumer Healthcare

A
s national health ser- dation requirements between
vices throughout the A recent upgrade sterile injectables and a med-
world have become icated mouthwash. As a result,
starved of cash and more reliant at SmithKline the full force of a validation
on patient self-medication, OTC exercise was required. Certain
healthcare products have Beecham’s facility standards, which clearly could
become increasingly important in the UK raised the not be compromised, had to be
to the healthcare and pharma- the same as they are for pharma-
ceutical industries. SmithKline age-old validation ceuticals. Still, both internal and
Beecham’s Maidenhead facility external sources advised us that
specializes in consumer health- battle of approved while validation documentation
care products, particularly oral methodologies is a prerequisite for compliance,
care medications. Since 1994, certain facets of the validation
the site has undergone a major versus their cost. process need not be as rigorous.
refurbishment to upgrade its This paper sets out the scope,
facilities. At the same time, it philosophy, schedule, time and
was necessary to continue production to meet the cost savings for the validation of an oral healthcare
demands of the marketplace. manufacturing facility in the light of these recommen-
In conjunction with this major renovation, valida- dations. At no time during the validation investigation
tion was included in the remit and steps were taken to did SmithKline’s standards fall below the legal base-
validate the process equipment and facilities for all line of critical pharmaceutical quality requirements.
licensed products manufactured on-site. However,
since the Maidenhead site manufactures mostly unli- SCOPE AND STRATEGY
censed consumer healthcare products, no validation in
the true pharmaceutical sense was required. Table 1 indicates the scope of the validation pro-
While the site was undergoing its upgrade, it was ject required to obtain an ML from the UK MCA.
decided to introduce a dedicated facility to produce Because the full validation team was not organized
medicated mouthwash. Consequently, true valida- until late in the project, the study was partly retro-
tion was needed for the process equipment and asso- spective on new equipment and facilities. Given that
ciated infrastructure. the manufacturers of the systems were unfamiliar
The EC-GMP guidelines do not distinguish vali- with validation requirements, the validation team

12 Special Edition: Facility Qualification


R.J. Noy, Ph.D.

was able to assemble documents and ensure the preparation of SOPs, protocols and test sheets. The
careful installation and commissioning of the facili- validation manager was required to direct the valida-
ties according to the requirements of the SmithKline tion effort and have the depth of background to set
validation team. standards for testing and develop the technical phi-
One of the most important aspects of this fast-track losophy for the exercise. Shortly after this appoint-
validation exercise was setting up an implementation ment, a validation engineer was recruited to act as a
team that met at regular intervals (weekly) or on a deputy to the validation manager. The technicians
rapid-response basis. If problems became critical dur- who actually performed the testing were chosen
ing the project, they were discussed quickly, and solu- soon after the validation manager had been appoint-
tions were sought and responded to in minutes or ed. Table 3 shows the type of personnel sought for
hours. This proved to be an excellent strategy as these vital responsibilities.
major difficulties were overcome and the validation We adopted the systems and subsystems method
project continued unabated. Table 2 outlines the of approach, and the validation master plan submit-
members of the validation implementation team. ted to the MCA reflected this philosophy.
The second most important element was the for- Budget constraints and the overall resources
mation of a validation team, which was created over required to complete the exercise were other major
the course of six weeks. One of the members was an considerations. Senior management continually asked
experienced validation manager familiar with the the same question: Why does a mouthwash facility

Special Edition: Facility Qualification 13


R.J. Noy, Ph.D.

Table 2: Validation Implementation Team

Table 3

14 Special Edition: Facility Qualification 14


R.J. Noy, Ph.D.

need to be validated to ethical manufacturing stan- plan was chosen because we had all of the O/M
dards? In a way, this question was justified, since the manuals from the suppliers, as well as SAT and
product was a medication for oral use only. However, installation documentation, such as weld details,
the active ingredient was a very effective biocide in passivation data and other information.
large concentrations. Poor manufacturing practices The next system to be validated was the bulk man-
could have resulted in disastrous consequences. ufacturing plant. (As luck would have it, obtaining
The underlying culture of the site was a consumer the vendor documentation followed according to
goods manufacturing plant. Site development included plan.) By October or November 1995, we started on
a major upgrade in cGMPs and the transition to a the filling and packaging hall, which was dedicated
healthcare culture. These goals called for a massive for all mouthwash products and used mostly for unli-
change in culture and the creation of validation proce- censed products. The licensed mouthwash was sec-
dures to satisfy an inspection from the MCA. ondarily packed on this line, but it was not labeled
there. Dedicated equipment was used for this job.
DOCUMENTATION Test sheets were largely devised from the ven-
dor’s O/M manuals, though SmithKline’s own in-
Documentation was the starting point of the pro- house expertise in packaging technology was of ben-
ject. Without validation SOPs to drive the validation efit. PLC validation of all equipment was compared
protocols, it was impossible to begin the study. against the URS and FDS (information supplied
Most of the project team had to agree to, approve from the user and the vendor respectively). By the
and sign all SOPs and protocols, which was a major end of January 1996, we were in position to request
achievement in itself. Table 4 gives a summary of an inspection from the MCA.
the major levels of documentation used to define,
initiate and record validation data. DEPTH OF VALIDATION
The next major decision regarding the reduction
of time and expense involved determining which In order to complete the schedule by the end of
tests to perform and to what depth and detail. January 1996, a certain amount of fast-tracking
(Table 6 provides examples of some of the savings was required. As indicated earlier, the biggest
adopted during this
study.) Table 4: Amount of Documentation Used During Project
The validation master
plan was written first and TITLE PURPOSE
submitted to the MCA for Validation Master Plan (1) Overall Plan
overall “approval” of the Validation SOPs (35) Drives Generic Methodology
methodology and ap- Validation Protocols (54 Specific Methodology
Test Sheets (Many) Data Gathering
proach. This document
O/M Manuals (12) Data From Vendors
was submitted in July Technical Files (10) Additional Data
1995 and approved short- Work Instructions (102) Site and Facility Instructions
ly after. Validation work (Equivalent to SOPs used at the plant)
began in August 1995 Validation Reports (15) Reporting to the Validation Work
with the preparation of Remedial Action Reports (1) Description of Remedial Action Required
SOPs and protocols. System Error/Failure Sheets (26) Identifying Errors
The water plant and Master Index (1) Ease of Documentation Location
ring main were the first Certificates (3) Final Approval
Review Protocols (3) Annual Review
systems to be validated
Change Control Dossier (3) Recording Technical Changes
using the documents and Training Records (1) Training of Staff
test sheets described in Maintenance Records (3) Maintenance and Asset Register
this paper. The water (The figures in parentheses indicate the number of versions of each document.)

15 Special Edition: Facility Qualification 15


R.J. Noy, Ph.D.

Table 5: Depth of Requirements

questions were how far to carry out the validation, TEST SHEETS AND FORMS
particularly in terms of testing, and how to keep
the cost and time at a minimum. The use of a mas- Design Qualification (DQ) - Minimal DQ was
ter index, which cross-referenced all of the SOPs undertaken as the project was well into the construction
and protocols, was very advantageous in keeping phase when the validation team arrived. Still, a DQ ret-
track of the work. It also provided a quick refer- rospective validation review was performed quickly,
ence while an inspector was on-site. Table 5 offers and the following record forms were completed:
a summary of the depth of requirements required • Design safety form
for this exercise. • Layout review record form
The URS was not officially written at the kick- • GMP review record form
off of the project, as the validation team arrived • PLC, PC, C/I review record form
fairly late in the proceedings. However, upon • Commissioning and start-up review record form
arrival, the validation team worked according to
the following URS: Installation Qualification - The IQ test sheets
and forms were reduced to the list shown below by
• Materials of construction philosophy combining common parameters, such as materials of
• Cleanability construction, lubricants and elastomers. Similarly,
• Maintenance the utilities and services test sheets and forms were
• Performance of equipment and processes combined to include electrics, water, gases, drains,
• Critical parameters identified etc. IQ also incorporated the following:
• Operating ranges of critical parameters
defined • Associated items form
• Essential design criteria defined • Critical information form
• Requirements of the PLC, PC and C/I • Consumable information form
• Training requirements identified • Drawing information and verification form
• Documentation unambiguous • Specification information form

16 Special Edition: Facility Qualification 16


R.J. Noy, Ph.D.

• Lubricant, materials of construction, and elas- • Cleaning verification form


tomer form • Critical process steps form
• Weld information form • Critical operating parameters form
• Vessel and tank information form • Controls form
• Controls, instrumentation, indicators and safety • Product composition form
devices check sheet • Quality of product produced form
• Utilities and services information and test sheet • Disaster recovery form
• Error/failure log form • Integrated line testing form
Finally, a validation report was written summa-
Operational Qualification - The OQ test and infor- rizing these results in about two pages.
mation sheets were rationalized and made easier to
complete by the test engineer. These sheets, which were Cleaning Qualification - The test and informa-
very similar to those for IQ, were composed of objec- tion sheet approach was undertaken. The definition
tive, method, acceptance criteria, results and pass/fail of cleaning at SmithKline is taken in the broadest of
blocks. OQ included in the following documents: terms, ranging from chemical sanitization of the
• Prerequisites form (all IQ errors must be closed purified water plant storage tank, feed tank and ring
out before continuation to OQ) main to CIP of the bulk manufacturing tanks and
• FDS comparison form manual cleaning of the line items. Due to this diver-
• SOP information form sity, the decision was made to use detailed validation
• Noise level test form reports, which took the form of technical reports that
• Speed and rotation test form included acceptance criteria.
• Flow rate test form
• Critical devices and interlocks test form PLC Qualification and Validation - The protocol
• Screen identification form was called the “Validation Qualification Protocol” and
• Leak and tank capacity test form comprised the following test and information sheets:
• Stirrer efficiency test form • Specification test sheet for URS and FDS
• Error/failure log form comparison
The error/failure forms were generated for both • Control system data form
IQ and OQ because errors and failures inevitably are • Input test form
found during testing. In all cases remedial action • Timer, counter and data register test form
was taken to rectify the faults. This activity was a • Output test form
prerequisite for both OQ and PQ investigations, as • PLC module test form
well as for PLC validation. • Blackout/disaster recovery test form
• Critical device calibration test form
Performance Qualification - The PQ test sheets • PLC incident form
were similar to the OQ test sheets. They largely • Error/failure form
referred to the technical report prepared by R&D on Not all of the test and information sheets were
the three consecutive batches of two different vari- applicable. A summary sheet was added to the front
ants of the formulation which had been prepared of the documents to indicate which forms were used
during the experimental work batch phase of the and the number of pages of each.
project. The following documents were included:
HVAC and Room Environment Qualification -
• Prerequisites form (All OQ errors and failures Test and information sheets similar to those for the
must be closed out before PQ starts) process systems were used for HVAC and room envi-
• Measurement devices form ronmental qualification. However, extra test sheets,
• Raw materials requirements form along with a specialized OQ sheet, were added for room
• Instrumentation and devices form data. The PQ of the bulk manufacturing area was a daily

17 Special Edition: Facility Qualification 17


R.J. Noy, Ph.D.

logging of environmental parameters, such as tempera- • Validation master plan review


ture, particles, RH, oxygen and air flow characteristics. • Validation reports, protocols and SOPs review
• Trend and daily log analysis
General Qualification - This area is defined as the • Change control dossier review
daily, weekly or monthly logging of equipment, utili- • SOPs and work instructions review
ties, production processes and other data. Daily logs • Batch records review
of pressures, UV lamp intensities, temperatures, air • Customer complaint review
flow, etc., were recorded manually to ensure the facil- • Reject materials review
ity remained in control. For its part, the QA/QC • Process changes and deviations review
Department prepared daily logs of raw materials, such • Maintenance and calibration record review
as water, actives, excipients, packaging components, • Audit and self-inspection review
batch records and out-of-spec results. However, it • Retained sample and stability record review
proved to be difficult to fully educate the Engineering • Out-of-spec results review
and Production Departments, as they were not fully • Training records review
conversant with the daily logging of data. The educa-
tion and training of this personnel is an ongoing exer- CERTIFICATION AND HAND-OVER
cise by both the QA/QC and Validation Departments.
At the end of the validation project, the facility
CHANGE CONTROL was “handed over” to the new owners of the facility,
namely the Production Department. This involved
Change control often frightens many of the estab- the acknowledgement and transfer of a formal cer-
lished and older personnel on the production floor. tificate verifying that validation had met cGMP and
To them, it means slowing production schedules, GEP standards. Time will tell if the new owners of
more paperwork, etc. For an FMCG factory, this is the facility are able to run a cGMP facility to the
even more pronounced and obvious. However, the level required by the inspectorate.
need for change control in a cGMP facility is essen-
tial to keep compliant with required standards. The OVERALL COST AND TIME
change control procedures again were rationalized
to make the system user-friendly.
REDUCTION
Table 6 summarizes how much time and money
VALIDATION REPORTS were saved using the fast-track validation methodol-
ogy described in this paper. Although subjective in
These reports were written at the end of the full its content, this table gives an accurate picture of the
validation of process equipment or utilities. They validation project and the ways expenditures of time
proved to be an excellent way of summarizing the and money were kept in check.
exercise, describing what went wrong and how it The overall costs were probably half to two-
was remedied. The inspectorate also found this an thirds the costs normally associated with an ethical
excellent way of understanding the project and its pharmaceutical product (prescription-only medi-
faults. It was in no way detrimental to our applica- cine). The total time taken to obtain the license, up
tion for a license. In fact, it helped us a great deal. to and including PQ, was 17 weeks at a cost of 3%
of the book value of the facility.
VALIDATION REVIEWS
CONCLUSION
This will occur in October 1996 at the anniversary
of the OQ sign-off. The check list approach will be The result of the exercise was a good one for the
used to complete the following major categories: SmithKline Validation Department. The company

18 Special Edition: Facility Qualification


R.J. Noy, Ph.D.

Table 6: Estimated Time & Cost Reductions

received its first license for the new site. The team JOURNAL OF VALIDATION TECHNOLOGY
involved in the inspection requirements was truly a
“dream team,” the dynamics of which will be diffi-
RELATED ARTICLES
cult to assemble again. The team’s meeting and May 1996
planning strategy was excellent, as was the commu- 1. Wayne T. Flaherty, “Facility Validation: Management Issues.”
February 1995
nication between members. The project was within 2. Patricia Stewart, “New vs. Existing Facilities: Two
budget due to the rational and targeted validation Approaches for Developing IQs.”
strategy that was adopted.
The URS was in compliance, and although a
formal DQ was not written, cGMP compliance
was achieved, specifications were attained, docu-
ments from vendors were forthcoming and cGMP
boundaries were well defined. Additionally, in
most cases, design changes were recorded and
vendors audited. Finally, SmithKline proved to a
high degree of assurance that the oral healthcare
facility was in control. All that remains is that the
company continue to operate accordingly over the
lifetime of the facility. ❏

Special Edition: Facility Qualification 19

You might also like