Professional Documents
Culture Documents
GO-007-LNG Norman Lady - Cargo Operating Manual
GO-007-LNG Norman Lady - Cargo Operating Manual
Cargo Operating Manual 2.1d Relative Density of Methane and Air 4.7.1 Inert Gas Generators
2.2.1a Flammability of Methane, Oxygen and Nitrogen Mixtures 4.7.2 Nitrogen Generator
List of Contents 2.2.2a Structural Steel: Ductile to Brittle Transition Curve 4.7.3 Void Space Dryers
Issue and Update
Cargo Symbols and Colour Scheme Part 3: Distributed Control System (DCS) 4.8 Custody Transfer System
Electrical and Instrument Symbols 4.8.1 Custody Transfer System (CTS)
3.1 Cargo Control Room (CCR) Arrangement 4.8.2 Float Level Gauges
Introduction
4.8.3 Loading Computer
3.2 Vessel Control System
Part 1: Design Concept of the Vessel 3.2.1 Damatic XD Distributed Control System (DCS) Overview 4.9 Gas Detection Systems
1.1 Principal Particulars 3.2.2 Operator Stations 4.9.1 Fixed Gas Detection Systems
1.1.1 Ship Principal Particulars 3.2.3 Screen Displays 4.9.2 Portable Gas Detection Instruments
1.1.2 Principal Particulars of Cargo Machinery 3.2.4 Operation
3.2.5 Mimics 4.10 Valve Remote Control and Emergency Shutdown System
1.1.3 General Arrangement
3.2.6 Cargo and Ballast Operations 4.10.1 Cargo Valve Remote Control System
1.1.4 Tanks and Capacity Plan
4.10.2 Emergency Shutdown System
1.2 Rules and Regulations Illustrations 4.10.3 Ship Shore Link
3.1a Cargo Control Room Layout
1.3 Cargo System Technology 3.1b Cargo Control Room Console 4.11 Relief Systems
1.3.1 Cargo Containment System Principle 3.2.1a Distributed Control System Overview 4.11.1 Cargo Tank Relief Valves
1.3.2 Kvaerner-Moss Cargo Containment 3.2.2a Operator Station Keyboard 4.11.2 Line Relief Valves
1.3.3 Failure of Containment 3.2.3a Screen Display 4.11.3 Void Space Relief Valves
1.3.4 Void Spaces 3.2.3b Operating Panel Display
3.2.4a Operation 4.12 Ballast System
1.4 Hazardous Areas and Zones 3.2.5a Mimics 4.12.1 Ballast Piping
3.2.6a Ballast Operating Display Screens 4.12.2 Ballast Control and Indicating System
Illustrations
1.1.3a General Arrangement Part 4: Cargo and Ballast Systems Illustrations
1.1.3b Compressor Room Layout 4.1.1a Leakage Pipes
1.1.4a Tank Capacity Plan 4.1 Cargo Containment and Monitoring Systems 4.1.2a Temperature and Pressure Monitoring System
1.3.2a Construction of Containment System - Equatorial Ring and 4.1.1 Liquid Leakage Detection 4.1.3a High Level and Overfill Alarm System
Wedge Space 4.1.2 Temperature and Pressure Monitoring System 4.2a Cargo Piping System
1.3.2b Construction of Containment System - Rupture Discs 4.1.3 High Level and Overfill Alarm System 4.2b Manifold Arrangement
1.3.2c Construction of Containment System - Dome and Tank Access 4.2.3a Spray Pipes in the Cargo Tanks
1.3.2d Construction of Containment System - Insulation 4.2 Cargo Piping System 4.3.1a Main Cargo Pump
1.3.2e Construction of Containment System - Piping Insulation 4.2.1 Liquid Line 4.3.1b Pump Arrangement in Cargo Tank
1.3.4a Void Spaces and Ventilation 4.2.2 Vapour Line 4.3.2a Spray Pump
1.3.4b Relationship between Corrosion and Relative Humidity 4.2.3 Spray Line 4.4.1a High Duty Compressor
1.4a Hazardous Areas and Gas Dangerous Zones 4.2.4 Fuel Gas Line 4.4.1b High Duty Compressor Performance Curves
4.2.5 Vent Masts 4.4.2a Low Duty Compressor
Part 2: Properties of LNG 4.2.6 Inerting/Aeration Line 4.4.2b Low Duty Compressor Performance Curves
4.5a Cargo Heater
2.1 Physical Properties and Composition of LNG 4.3 Cargo Pumps 4.6a LNG Main Vaporiser
4.3.1 Main Cargo Pumps 4.7.1a Inert Gas System
2.2 Characteristics of LNG 4.3.2 Stripping/Spray Pumps 4.7.2a Nitrogen Generator
2.2.1 Flammability of Methane, Oxygen and Nitrogen Mixtures 4.7.2b Nitrogen System
2.2.2 Supplementary Characteristics 4.4 Gas Compressors
4.7.3a Void Space Dryers
4.4.1 High Duty Compressors
4.8.1a CTS Printout
2.3 Health Hazards 4.4.2 Low Duty Compressor
4.8.2a Whessoe Float Level Gauge
4.5 Cargo Heaters 4.8.3a Loading Computer Screen
Illustrations
4.9.1a Ballast and Void Spaces Gas Sampling System
2.1a Vapour Pressure Diagram of Liquid Cargoes
4.6 LNG Vaporisers 4.9.1b Boil Off Gas Pipe Vent Duct Gas Sampling System
2.1b Physical Properties of LNG
4.9.1c Cargo Areas Gas Sampling System
2.1c Composition of LNG from Major Export Terminals (Mol%)
4.7 Void Space Systems 4.9.2a Portable Gas Detectors
Illustrations Illustrations
6.1a February 2004 April 2005 7.1a September 2004 Sept. 2005
6.2.1a February 2004 7.2.1a February 2004 Sept. 2005
6.2.2a February 2004 7.3.1a February 2004 Sept. 2005
6.2.3a February 2004 7.4a February 2004
6.2.4a February 2004 7.6.1a February 2004
6.2.4b February 2004 April 2005 7.6.2a February 2004
Moist Air
Swing Check Valve Cylinder Piston Actuator Hopper Without Cover Connected Crossing Pipe Drain Trap
LNG Liquid
Wire Quick-Closing Valve Centrifugal Type Pump Observation Glass Lubricating Oil
Orifice
Safety / Relief Valve Gear Type Pump Deck Stand (Manual) Overboard Discharge
Bilge Water/Steam Exhaust
2-Way Cock (S-Type) Mono Pump Angled Screw Down Storm Valve Diesel Oil
Non-Return Valve
3-Way Swing Valves Electrical Signal
3-Way Cock Magnetic Valve Spool Piece
Reciprocating Type Pump Instrumentation
(L-Type / T-Type)
P Pneumatic Operated
Rose Box Surface Valve Restrictor
(Open/Shut)
CP Compound Gauge
Transformer DPI Differential Pressure Indicator
DPS Differential Pressure Switch
DPT Differential Pressure Transmitter
I Current to Press FD Flow Detector
P Converter FS Flow Switch
FT Flow Transmitter
P Press to Current IL Indication Lamp
I Converter LAH Level Alarm High
LAL Level Alarm Low
LI Level Indicator
Making Contact LIC Level Indicating Controller
LS Level Switch
LT Level Transmitter
Breaking PAH Pressure Alarm High
PAL Pressure Alarm Low
PI Pressure Indicator
Disconnection Switch PIC Pressure Indicating Controller
PIAH Pressure Indicator Alarm High
PIAL Pressure Indicator Alarm Low
Snap Switch PIAHL Pressure Indicator Alarm High Low
PS Pressure Switch
PT Pressure Transmitter
Earth SAH Salinity Alarm High
TAH Temperature Alarm High
TAL Temperature Alarm Low
TI Temperature Indicator
Shield Wire
TIC Temperature Indicating Controller
TIAH Temperature Indicator Alarm High
TIAL Temperature Indicator Alarm Low
Battery TIAHL Temperature Indicator Alarm High Low
TS Temperature Switch
TT Temperature Transmitter
GM Governor Motor VAH Viscosity Alarm High
VAL Viscosity Alarm Low
VCA Vacuum Alarm
DG Diesel Generator VCI Vacuum Indicator
VCT Vacuum Transmitter
VI Viscosity Indicator
VT Viscosity Transmitter
M AC Induction Motor XS Auxiliary Unspecified Switch
ZI Position Indicator
ZS Limit Switch
Zener Diode
Locally Mounted
XXX
Instrument
Maker: Nohab
Type: Polar SF 112 VS-F diesel-generators
Capacity: 1,500kW
No. of sets: 2
Steering No.5 Lower Cross No.4 No.3 No.3 No.2 No.2 No.1 No.1 Side Pipe Pipe
Compartment Double Tank Involved in No.3 Double Lower Cross Double Lower Cross Double Lower Cross Double Water Ballast Duct Duct
Bottom Double Bottom Bottom Water Ballast Tank Bottom Water Ballast Tank Bottom Water Ballast Tank Bottom Bottom
Tank Fuel Oil Double Bottom Water Ballast
Spare Water Ballast
Plan
Principal Dimensions
Escape
Hatch
Entrance Door
Vapour Heater Vapour Heater
Vaporiser
HD
Compressor
Vaporiser
Controllers
HD
Compressor
LD
Compressor
Cargo
Instrument
Air Receiver
Cargo Tank No.5 15,555 549,320 97,837.20 4,109,163 53.34 19.75 Port/
No.5 Side Tank 39 - 57 Starboard 1,628 57,492 1,669 42.39 17.39
Total 87,994 3,107,482 553,461.06 23,245,370 No.1 Lower Cross Tank 84 - 88 1141 40,294 1,170 176.28 4.92
NITROGEN BUFFER TANKS No.3 Lower Cross Tank 66 - 70 1,499 52,937 1,537 109.54 4.37
Total 40 1413 32.5 Aft Peak -7 - 17 262 9,253 269 5.49 12.41
Centres of Gravity
Compartment Frame Side Metres3 Feet3 Tonnes
Forward of Ap Ab Base
GAS OIL TANKS
Deep Tank Forward 95 - 111 3382 119,434 3215 215.21 11.06
Centres of Gravity
No.3 D.B. Tank 53 - 61 2522 89,063 2324 66.13 2.98 Compartment Frame Side Metres3 Feet3 Tonnes
Forward of Ap Ab Base
No.6 Side Tank Port/ 335 24.57 19.01 No.7 Side Tank 27 - 30 Starboard 76 2,684 64 19.42 20.08
30 - 39 Starboard 11,830 309
Total 6,574/6,534 No.8 D.B. Tank 18 - 30 154 5,438 130 16.63 1.66
232,157 6,057
No.6 No.5 Ballast No.4 Ballast No.3 Ballast No.2 Ballast No.1 Ballast
H.F.O. Side Tank Side Tank Side Tank Side Tank Side Tank
Tank
Deep
Tank
Fuel Oil Fore Peak
Aft Peak No.7 D.B. No.5 D.B. Tank Dry
Tank No.3 Bottom No.3 Lower No.2 Bottom No.2 Lower No.1 Bottom No.1 Lower
Tank Tank
Wing Tank Cross Tank Wing Tank Cross Tank Wing Tank Cross Tank
No.8 D.B. No.6 D.B. No.4 D.B. No.3 D.B. Tank No.2 D.B. Tank No.1 D.B. Tank
Tank Tank Tank
No.5 Ballast
No.7 No.4 Ballast Side Tank (Port) No.3 Ballast Side Tank (Port) No.2 Ballast Side Tank (Port) No.1 Ballast Side Tank Side Tank
Lubricating No.5 Ballast Side (Port)
Oil Side Tank Tank (Port) No.4 Double
I, II & III (Port)
Bottom Tank
No. 10 No.6 Side Tank
Fuel Oil (Port) No.3 Double
Feed Water Bottom Tank
Tank
No.8 Fresh Water Tank (Port)
Deep
No.9 Distilled Water Tank (Port) Fore Peak
Tank Frame 53
Tank
Fuel Oil
Aft Peak
Water Ballast No.6 Side Tank
Tank Fuel Oil (Stbd)
Frame 60
No.4 D.B. No.3 Lower No.3 Lower No.2 Lower No.1 Lower No.1 Double Bottom
Dry Tank Cross Tank Cross Tank Cross Tank Cross Tank Dry Tank
Fuel Oil Water Ballast Water Ballast Water Ballast
No.3 Ballast Pipe
Side Tank Duct No.2 Lower
Cross Tank
No.2 Double
Bottom Tank
No.3 Bottom No.2 Bottom No.1 Bottom
Wing Ballast Tank (Stbd) Wing Ballast Tank (Stbd) Wing Ballast Tank (Stbd) No.2 Bottom
Wing Tank
Frame 77
No.3 Double Bottom No.2 Double Bottom Spare No.1 Double Bottom
Fore Peak
No.4 Double Fuel Oil Tank Water Ballast Tank Dry Tank
Dry Tank
Bottom No.1 Double
Dry Tank Bottom Tank
Pipe Duct
The regulations covering gas carriers built before 1977 are contained in the
‘Code for Existing Ships Carrying Liquefied Gases in Bulk’ first advertised
under assembly resolution A 329 (IX). Its content is similar to the GC code,
though less extensive.
The proposed Coast Guard regulations and the Classification Society’s rules k) ISO draft proposal No.6954 ‘Guidelines for Overall Evaluation of Vibration
have cross references showing the corresponding IMO code numbers to allow in Merchant Ships, 1984’.
identification of the required paragraph.
l) ILO convention concerning crew accommodation on board ships, No.92 and
133.
m) ILO Guide to Safety and Health in Dock Work, 1977 and 1979.
Tank Dome
Rubber Seal
Dome Shell
Void Upper Hemisphere
Space
Equatorial
Forged Ring
Weld
Wedge
Space
Skirt Wedge Space
Dome Shell
Skirt
Lower Hemisphere
Insulation
1.3.2 Kvaerner-Moss Cargo Containment 2) A partial ‘secondary barrier’ must be fitted which must be capable A local cargo control room is located centrally on the main deck between No.3
of containing any envisioned leakage from the ‘primary barrier’ and 4 cargo tanks. This control room contains a control station for the DCS
The five tanks carry LNG at cryogenic temperatures and at a pressure close to (the tank plating itself) for a period of 15 days and must prevent system concerned primarily with cargo loading.
atmospheric pressure. There is no secondary barrier as the tanks, primarily due the temperature of the ship’s structure falling to an unsafe level.
to their spherical construction, have a high degree of safety against fracture or The failure of the primary barrier must not cause the failure of the Cargo Equipment
failure. The tanks are heavily insulated with approximately 215mm of secondary barrier and vice versa.
polystyrene foam to reduce natural boil-off to a minimum. The LNG compressor room, situated on the port side of the main deck between
3) A ‘spray shield’ must be provided to deflect any leakage down No.4 and 5 cargo tanks contains the following major items of equipment:
The tanks are constructed of 9% nickel steel. Each tank is covered by a into the secondary barrier and away from the hull structure.
The Low Duty (LD) gas compressor, used to:
spherical steel tank cover which is mainly for tank and insulation protection.
The cover also permits control of the hold space atmosphere.The lower edge In the exceptional case of a crack occurring in the tank nickel-steel material, a Send boil-off gas to the ship’s boilers
of each cover is welded to the deck, forming a watertight seal. A flexible rubber small leakage of LNG within the insulation will be detected at an early stage
seal is used at the point where the tank dome protrudes out from the cover. The by the gas detection system fitted at the equatorial ring area and at the drip pan. The High Duty (HD) gas compressors, used to:
tanks are each supported by a metal skirt from the equatorial ring, which The drip pan, installed directly below each cargo tank, is fitted with
transmits the weight of the tank and the cargo to the lower hull. The skirt is temperature sensors to detect the presence of LNG and an eductor system to Return LNG vapour ashore during loading operations
stiffened in the upper part by horizontal rings and the lower part by vertical allow for removal of the liquid. Return gas/vapour ashore during gassing-up and
corrugated stiffeners.
initial cooldown operations
The spray shield is formed by the aluminium foil surface of the tank insulation.
A special casting joint is fitted between the skirt and the tank’s equatorial ring The foil also protects the insulation as well as directing any leakage away. Any Circulate heated cargo vapour through the cargo tank
to provide the necessary strength at this point and to reduce heat conduction LNG liquid leakage drains by gravity from between the tank plating and the system during warm-up operations.
into the tank and a corresponding conduction of low temperature to the skirt insulation to the drip pan via a drain tube at the bottom. The drain at the bottom
and hull. of the insulation space is sealed in normal service by a bursting disc which is The two steam heated horizontal shell and tube type gas heaters, used to:
designed to fail at cryogenic temperatures.
The tanks contain a central pipe tower, fitted in the domes for the purpose of Supply warm gas to the boilers for burning and to supply gas
access into the tank and for the support of pipes and cables running to and from Liquid flow from the northern hemisphere collects in the drain channel which to the cargo tanks during warm-up operations prior to inerting,
the cargo pumps, spray pump (if fitted), discharge and filling lines, CTS is formed by the upper skirt ring stiffener and is directed to the leakage pipes aeration and entry.
(Custody Transfer System) capacitance level gauge, Whessoe float gauge located forward, aft, port and starboard of the tank. These pipes direct the
system, spray lines and a gas sampling pipe. liquid on to the void space deck and then to the drip pan.
Rupture Disc
Cross Section
Pressure Insulation
Nitrogen
Blank Flange
Bleed
Rupture Disc
Removed for
Gas Sampling
Rupture Disc
Rupture Disc
Skirt
Leakage Pipes
Produce gas to purge the inert gas from the cargo tanks prior During normal operation, the boil-off gas from the tanks is compressed using The LNG transfer system valves and pumps are normally operated from the
to cooldown the LD compressor and used as fuel for the boilers. The boil-off gas fuel supply CCR. The local valve controls are only used if the normal controls fail or
system is controlled so that the tank pressure is maintained at its predetermined emergency conditions arise.
Produce gas to maintain tank pressure when unloading, if the
value. Two methods are available to control the vapour pressure in the cargo
shore return gas is not available
tank: All the cargo pumps will be started in sequence and operated simultaneously
under bulk discharge conditions.
In each cargo tank are two vertical, submerged, electric motor driven cargo
1) Disposal of excess vapour via the boil-off gas system and
pumps. When all ten cargo pumps are in simultaneous operation, a full cargo
subsequently the steam dump system (if required). (Note: The ship must never start cargo pumps until asked to do so by the shore
can be unloaded in approximately 15 hours.
terminal control room.)
2) The venting of excessive vapour through the remotely operated
A vertical, submerged, electric motor driven spray pump is fitted in tanks 3 and
vent valve at vent mast No.4, via the heater. All liquid valves, except those on spray lines, should be kept closed when the
4, discharging to a spray header. Branches are led from the header to spray
transfer system is not in use. Under normal operational conditions, valves in
nozzles inside each tank. Liquid is sprayed into the tanks on the ballast voyage,
Unloading use should be fully open. However, loading valves are partially closed when
to maintain them at a temperature low enough to prevent excessive stress on
topping-off and pump discharge valves are automatically controlled within the
each tank structure, especially the equatorial ring, during loading.
Normally, as the cargo pumps in each tank pump out the cargo, cargo vapour permissible range to prevent overload or cavitation and to control the flow to
is returned from the shore and the pressure is monitored to ensure that the the shore. Any cavitation is indicated by fluctuations in pump current and
An Inert Gas (IG) plant is provided for inerting cargo tanks before and after
pressure in the cargo tanks remains within the acceptable range. In the event of discharge pressure. The vapour line valves at the tank domes are locked open
aeration and entry, and for inerting the void spaces if required. Dry air is also
the shore terminal being unable to return vapour, make-up vapour must be under normal circumstances. The blank flanges fitted to the manifolds must be
supplied from the plant for drying cargo tanks and hold spaces following any
generated by feeding LNG to the ship’s vaporiser. kept in place at all times except when connecting to either load or unload.
inspections and maintenance.
A small amount of cargo is left in all the tanks (called the heel), with an extra Pipework expansion bellows and welded joints should be inspected regularly
Two nitrogen generators are located in the aft storage room on the starboard
reserve being left in tanks 3 and 4 (the tanks fitted with spray pumps) for where possible and manifold flange joints are to be checked under nitrogen
side, to provide nitrogen for the following purposes:
cooling the cargo tanks and for fuel during the ballast voyage. During the pressure with a soap solution prior to loading or unloading. Special care must
Cargo compressor gland sealing ballast voyage, the cargo tanks are spray-cooled utilising the spray pumps and be taken to avoid LNG leaks, as the temperature of the liquid can cause steel
the extra cargo left on board for this purpose. decks to fracture.
Cargo tank wedge and insulation space inerting/purging
Cargo line purging The presence of water or other contaminants in the cargo system can be
eliminated by taking great care during refit and maintenance operations.
Boiler gas line purging
Inerting and purging procedures are to be strictly followed. Cargo manifold
A Custody Transfer System (CTS) is provided to enable accurate cargo strainers are fitted at the unloading port to prevent the possibility of shore
quantity measurement. The system includes the equipment to measure liquid contamination. At the loading port, the ship is protected against contamination
level, liquid and vapour temperatures and also the vapour pressure within each by a strainer fitted in the shore liquid line in addition to the ship supply
cargo tank. This data, together with the tank calibration data tables, is used to manifold strainers fitted at each loading.
perform cargo quantity calculations. A secondary float actuated mechanical
system (the Whessoe system) is also provided. The calibration of all the CTS
and tank equipment, is carried out by an independent firm of sworn measurers
who act jointly for buyers, sellers and customs.
Whessoe Gauge
Elevation
Level Alarm
8 9
Key
10
7 29
6 11 Cargo Tank Dome Arrangement
5
4 1 Discharge Pipe 15 Whessoe Level Indicator
Plan
2 Discharge Pipe 16 Omicron Level Alarm
17
3 Loading Pipe 17 DCS Connection
15
16
2 4 Spray Pipe 19 Access
25 Cable For Spray Pump
5 Spray Pipe 20 (Tanks 3 & 4 only)
28
12 6 Spray Pipe 21 Cable For Discharge Pump
3 26 Spray Pipe
7 22 Cable For Discharge Pump
(Tanks 3 & 4 only)
14 24
8 Ejector Pipe 23 Spare
30
1 9 Vapour Suction 24 Tank Safety Valve
23 13
Spray Pump Pipe
10 25 Spray Line Safety Valve
(Tanks 3 & 4 only)
Stainless Steel
Support Straps
From Equator Skirt
Aluminium Foil
(Spray Shield)
Stainless Steel
Support Straps
Tank Wall
(Primary)
Void Space
Ventilation
Trunking TANK HOLD SPACE
Incremental
Contraction Slot
Cold Side
Reinforcement
Spinning Weld
Crack
Barrier
Weld
Fixed Clamp
Any liquid flow from the upper hemisphere will be collected in the drain
channel formed by the upper ring stiffener of the skirt. There are four drain
pipes, port, starboard, forward and aft of the tanks, which lead any cargo
leakage to the catch basin. Any liquid flow in the lower hemisphere will be led
to the catch basin by a drain pipe at the south pole.
Any liquid collecting in the catch basin will raise a liquid alarm via the DCS
system. Whether the liquid is LNG cargo due to a tank leakage, or water due
to leakage from the water ballast tanks, can be determined by observing the gas
detector and the temperature indicators. A low temperature (-163ºC for LNG)
indicates cargo leakage, while temperatures above 0ºC indicate water leakage.
LNG
V2303 V2209
Compressors
V2314 V2314
Void Space
Dryers View of Void Space Showing
Leakage Pipe and Cargo Tank
Key
V2135
Nitrogen V2313 V2313
V2311 V2311
Recirculation
Fans 2000m3/h
Purging
V2216 V2216 V2216 V2216 V2216 Outlets
at Dome
The areas between the water ballast tanks, the double bottom tanks, underneath Illustration 1.3.4b Relationship between Corrosion and Relative Humidity
the cargo tank weather covers and the cargo tank are called void spaces. This
space around the tank and inside the tank skirt area is kept as dry as possible.
The atmosphere in this space is controlled and monitored. It is especially
important that the void spaces are monitored during cargo operations.
The pressure in the void spaces over that of the cargo tanks should not rise over 120
0.05kg/cm2. This value has been determined by the builders to avoid any
possible chance of the tank buckling when empty. There are two void space
relief valves for each void space which will open to atmosphere if this value is
exceeded.
Before LNG is loaded into the tanks, the void spaces should be thoroughly dry 100
to avoid any moisture penetration into the tank insulation.
The void spaces must also be free of carbon dioxide as CO2 gas will solidify at
a temperature of -78.5ºC.
80
The operation to dry or inert the void spaces is dealt with in section 4.7. There
is a void space heating and drying system to dry out these spaces, thereby
removing moisture and preventing any dew forming. This also has the added RATE OF
benefit of preventing corrosion. It can be seen from the graph in illustration CORROSION
1.3.4b that if the relative humidity is kept below 50/60%, the corrosion rate is
kept extremely low.
60
The void spaces are fitted with gas detection and leakage detection. These
systems indicate/alarm in the CCR, via the DCS system.
The void spaces are accessed via air lock chambers to assist in maintaining the
atmosphere. 40
The air in the void spaces is continuously recirculated via the recirculation fans
which are fitted on the outside deck above the LNG compressor room. The fans
supply dried and heated air from the void space atmospheric steam heater and
void space dryers to the vent outlets situated at the bottom of each void space
directly underneath the cargo tank lowest point. The air is exhausted from an 20
outlet situated adjacent to the cargo tank dome. In this way, the air is drawn
from bottom to the top, across the entire void space.
The void spaces may be inerted, if required, using the IG connection located at
the starboard manifold. There is normally a spoon blank fitted at this
0
connection. 0 20 40 60 80 100%
RELATIVE HUMIDITY
Elevation
Plan
Under the IMO code for the Construction and Equipment of Ships Carrying
Gases in Bulk, the following are regarded as hazardous areas:
Gas dangerous spaces or zones, are zones on the open deck within 3 metres of
any cargo tank outlet, gas or vapour outlet, cargo pipe flange, cargo valve and
entrances and ventilation openings to the LNG compressor house. They also
include the open deck over the cargo area and 3m forward and aft of the cargo
area on the open deck up to a height of 2.4m above the tank weather covers.
The entire cargo piping system and cargo tanks are also considered gas-
dangerous.
In addition to the above zones, the code defines other gas-dangerous spaces.
The area around the air swept trunking, in which the gas fuel line to the engine
room is situated, is not considered a gas dangerous zone under the above code.
TEMPERATURE (OC)
-165 -160 -155 -150 -145 -140 -135 -130 -125 -120 -115 -110 -105 -100 -95 -90 -85 -80 -75 -70 -65 -60 -55 -50 -40 -30 -20 -10 0 25 50 75 100
60
50
40
30
20
Propane
2mol % Ethane
10
9
8
7
Methane Ethylene Ethane Propylene Propane bar
6
5
Butadrene N. Butan
1.3
4
ata
3
1
0.9
0.8
0.7
0.6
-165 -160 -155 -150 -145 -140 -135 -130 -125 -120 -115 -110 -105 -100 -95 -90 -85 -80 -75 -70 -65 -60 -55 -50 -40 -30 -20 -10 0 25 50 75 100
TEMPERATURE (OC)
The actual composition of Qatar, Oman, Indonesia or Malaysia LNG will vary The boil-off vapour from LNG is lighter than air at vapour temperatures above
depending on its source and on the liquefaction process, but the main -110°C or higher depending on LNG composition, therefore when vapour is
constituent will always be methane; other constituents will be small vented to atmosphere, the vapour will tend to rise above the vent outlet and
percentages of heavier hydrocarbons, e.g. ethane, propane, butane, pentane, will be rapidly dispersed. When cold vapour is mixed with ambient air the
and possibly a small percentage of nitrogen. A typical composition of LNG is vapour-air mixture will appear as a readily visible white cloud due to the
given in Table 2.1b, and the physical properties of the major constituent gases condensation of the moisture in the air. It is normally safe to assume that the
are given in Table 2.1a. flammable range of vapour-air mixture does not extend significantly beyond
the perimeter of the white cloud. The auto-ignition temperature of methane, i.e.
For most engineering calculations (e.g. piping pressure losses) it can be the lowest temperature to which the gas needs to be heated to cause self-
assumed that the physical properties of pure methane represent those of LNG. sustained combustion without ignition by a spark or flame, is 595°C.
However, for custody transfer purposes when accurate calculation of the
heating value and density is required, the specific properties based on actual
component analysis must be used.
During a normal sea voyage, heat is transferred to the LNG cargo through the
cargo tank insulation, causing part of the cargo to vaporise, i.e. boil-off. The Table 2.1c Composition of LNG from Major Export Terminals (Mol%)
composition of the LNG is changed by this boil-off because the lighter
components, having lower boiling points at atmospheric pressure, vaporise
first. Therefore, the discharged LNG has a lower percentage content of Methane CH4 Ethane C2H4 Propane C3H8 Butane C4H10 Nitrogen N2 C5+ Density (kg/m3)
nitrogen and methane than the LNG as loaded, and a slightly higher percentage
of ethane, propane and butane, due to methane and nitrogen boiling off in Arzew 87.4 8.6 2.4 0.05 0.35 0.02 466
Table 2.1b Physical Properties of LNG Bonny 90.4 5.2 2.8 1.5 0.07 0.02 453
Methane CH4 Ethane C2H4 Propane C3H8 Butane C4H10 Pentane C5H12 Nitrogen N2 Das Is 84.83 13.39 1.34 0.28 0.17 0 465
Molecular Weight 16.042 30.068 44.094 58.120 72.150 28.016 Badak 91.09 5.51 2.48 0.88 0.03 0 N/A
Boiling Point at 1 bar absolute (ºC) -161.5 -88.6 -42.5 -5 36.1 -196 Arun 89.33 7.14 2.22 1.17 0.08 0.01 N/A
Liquid Density at Boiling Point (kg/m3) 426 544.1 580.7 601.8 610.2 808.6 Kenai 99.8 0.1 0 0.1 0.1 0 421
Vapour SG at 15ºC and 1 bar absolute 0.554 1.046 1.540 2.07 2.49 0.97 Lamut 89.4 6.3 2.8 1.3 0.05 0.05 463
Auto-ignition Temperature (ºC) 595 510 510/583 510/583 Ras Lafan 90.1 6.47 2.27 0.6 0.25 0.03 457
Gross Heating Normal: 55559 51916 50367 49530 49069 Skikda 91.5 5.64 1.5 0.5 0.85 0.01 451
Value at 15ºC (kJ/kg) Iso: 49404 48944
Vaporization Heat at Boiling Point (kJ/kg) 510.4 489.9 426.2 385.2 357.5 199.3 Withnell 89.02 7.33 2.56 1.03 0.06 0 460
The boiling point of methane increases with pressure and this variation is
shown in the diagram for pure methane over the normal range of pressures on +20
board the vessel. The presence of the heavier components in LNG increases the
boiling point of the cargo for a given pressure. 0
The relationship between boiling point and pressure of LNG will Lighter than air
- 20
approximately follow a line parallel to that shown for 100% methane.
- 40
Methane Vapour - 60
Temperature
°C - 80
-100
-120
Heavier than air
-140
-160
1.5 1.4 1.3 1.2 1.1 1.0 0.9 0.8 0.7 0.6 0.5
Area EDFE
B
21 flammable
E CAUTION
20
This diagram assumes complete mixing
19 which, in practice, may not occur.
F
18
17
Y
16
M
15
Mixtures of air and methane
N
14 cannot be produced above
G X line BEFC
13
D
12
11
%
10
O 9
x
y 8
g 7
e
n 6
5
4 Area HDFC
Capable of forming flammable
3 mixtures with air, but containing
2 too much methane to explode
1
Z C
A0 10 H 20 30 40 50 60 70 80 90 100
Methane %
Area ABEDH
Not capable of forming
flammable mixture with air
4) Under particular circumstances, with a methane concentration 5) If the vapour pressure is reduced, by removing more vapour than If the vapour pressure is reduced by removing more vapour than is generated,
below 40%, flameless explosions are possible when the LNG generated, the LNG temperature will decrease. In order to make the LNG temperature will decrease. In order to make up the equilibrium
strikes the water. It results from an interfacial phenomenon in up the equilibrium pressure corresponding to its temperature, the pressure corresponding to its temperature, the vaporisation of LNG is
which LNG becomes locally superheated at a maximum limit vaporisation of LNG is accelerated, resulting in an increased heat accelerated, resulting in an increased heat transfer from LNG to vapour.
until a rapid boiling occurs. However, commercial LNG is far transfer from LNG to vapour.
richer in methane than 40% and would require lengthy storage If the vapour pressure is increased by removing less vapour than is generated,
before ageing to that concentration. Reactivity the LNG temperature will increase. In order to reduce the pressure to a level
corresponding to the equilibrium with its temperature, the vaporisation of LNG
5) The flammable cloud of LNG and air may extend for large Methane is an asphyxiant in high concentrations because it dilutes the amount of is slowed down and the heat transfer from LNG to vapour is reduced.
distances downward (only methane when warmer than -100°C is oxygen in the air below that necessary to maintain life. Due to its inactivity,
lighter than air) because of the absence of topographic features methane is not a significant air pollutant and, due to its insolubility, inactivity, LNG is a mixture of several components with different physical properties,
which normally promote turbulent mixing. and volatility, it is not considered a water pollutant. particularly the vaporisation rates; the more volatile fraction of the cargo
vaporises at a greater rate than the less volatile fraction. The vapour generated
Vapour Clouds Cryogenic Temperatures by the boiling of the cargo contains a higher concentration of the more volatile
fraction than the LNG.
1) If there is no immediate ignition of an LNG spill, a vapour cloud WARNING
may form. The vapour cloud is long, thin, cigar shaped and, under Contact with LNG or with materials that are chilled to its temperature of The properties of the LNG, i.e. the boiling point, density and heating value,
certain meteorological conditions, may travel a considerable about -160°C will damage living tissue. have a tendency to increase during the voyage.
distance before its concentration falls below the lower flammable
limit. This concentration is important, for the cloud could ignite CAUTION
and burn, with the flame travelling back towards the originating Most metals lose their ductility at these temperatures; LNG may cause the
pool. The cold vapour has a higher density than air and thus, at brittle fracture of many materials. In case of LNG spillage on the ship’s
least initially, hugs the surface. Weather conditions largely deck, the high thermal stresses generated from the restricted possibilities
determine the cloud dilution rate, with a thermal inversion greatly of contraction of the plating will result in the fracture of the steel.
lengthening the distance travelled before the cloud becomes non-
flammable.
WARNING
The major danger from an LNG vapour cloud occurs when it is ignited.
The heat from such a fire is a major problem. A deflagrating (simple
burning) is probably fatal to those within the cloud and outside buildings
but is not a major threat to those beyond the cloud, though there will be
burns from thermal radiation.
Boiling point at 1 bar absolute: –196°C Carbon monoxide: <65 ppm by volume
Liquid SG at boiling point: 1.81 Sulphur oxides (SOx): <1 ppm by volume
Vapour SG at 15°C and 1 bar absolute: 0.97 Nitrogen oxides (NOx): <65 ppm by volume
Dew point of 100% pure N2: Below –80°C Soot: complete absence
The inert gas is slightly denser than air: 1.3-kg/m3 abs at 0°C.
Chemical Properties
WARNING
Nitrogen is considered as an inert gas; it is non-flammable and without
Due to its low oxygen content, inert gas is an asphyxiant.
chemical affinity. However, at high temperatures, it can be combined with
other gases and metals.
Plain carbon structural steels have a brittle to ductile behaviour transition In the event of a major leakage or spillage, the cargo operations must be
which occurs generally in the range -50°C to +30°C. This, unfortunately, stopped immediately, the general alarm sounded and the emergency deck water
precludes their use as LNG materials (carriage temperature -162°C). The effect spray system put into operation (refer to section 5.2.2).
is usually monitored by measuring the energy absorbed in breaking a notched
bar and a transition curve, as shown in Illustration 2.2.2b, is typical for plain
carbon steels.
For this reason, materials which do not show such sharp transition from ductile
to brittle fracture as the temperature is lowered, have found obvious
application for use in cryogenic situations in general and particularly in liquid
methane carriers, for example, invar (36% nickel-iron alloy), austenitic Illustration 2.2.2a Structural Steel: Ductile to Brittle Transition Curve
stainless steel, 9% nickel steel and some aluminium alloys such as 5083 alloy.
All of these materials behave in a ductile manner at -162°C, so that the chance
of an unstable brittle fracture propagating, even if the materials were
overloaded, is negligible.
In order to avoid brittle fracture occurring, measures must be taken to ensure Brittle Fracture transition Ductile
that LNG and liquid nitrogen do not come into contact with the steel structure fracture range (mixed fracture fracture
appearance)
of the vessel. In addition, various equipment is provided to deal with any
leakages which may occur.
The manifold areas are equipped with a stainless steel drip tray, which collects
any spillage and drains it overboard. The ship, in way of the manifolds, is Notched For a typical mild steel:
provided with a water curtain from the deck driving water main which is bar test T1 might be -30;
supplied from the bilge ejector pump. The deck fire main must always be energy T2 might be +15.
available and the manifold water curtain in operation when undertaking any absorbed Although this depends
on composition, heat
cargo operation. Additionally, fire hoses must be laid out to each liquid dome
treatment etc. the curve
to deal with any small leakages which may develop at valves and flanges. can shift to left or right.
Permanent drip trays are fitted underneath the items most likely to cause
problems and portable drip trays are available for any other requirements.
T1 T2
LIQUID DO NOT DELAY. Flood eye gently with clean fresh/sea water. Force eye open if necessary.
IN EYE Continue washing for 15 minutes. Obtain medical advice/assistance.
LIQUID DO NOT DELAY. Treat patient gently. Remove contaminated clothing. Immerse frostbitten area CONDITIONS OF CARRIAGE
ON SKIN in warm water until thawed (see Chapter 9). Obtain medical advice/assistance.
NORMAL
CARRIAGE Fully refrigerated. GAUGING Closed, indirect.
VAPOUR Remove victim to fresh air. If breathing has stopped, or is weak/irregular, give mouth-to-mouth/nose CONDITIONS
INHALED resuscitation. VAPOUR
SHIP TYPE 2G. Flammable.
DETECTION
Stop the flow. Avoid contact with liquid or vapour. Flood with large amounts of water to disperse spill and
SPILLAGE
prevent brittle fracture. Inform Port Authorities of any major spill.
MATERIALS OF CONSTRUCTION
UNSUITABLE SUITABLE
PHYSICAL DATA Mild steel. Stainless steel, aluminium, 9 or 36% nickel steel, copper.
HEALTH DATE
TVL 1000 ppm ODOUR THRESHOLD Odourless
EFFECT
OF Frostbite to skin or eyes. Not absorbed through skin.
LIQUID
EFFECT
Asphyxiation - headache, dizziness, drowsiness. Possible low temperature damage to lungs, skin. No
OF chronic effect known.
VAPOUR
FORMULA N2 NITROGEN
U.N. NUMBER 2040
FAMILY Noble Gas
APPEARANCE Colourless THE MAIN HAZARD
ODOUR Odourless FROSTBITE. NITROGEN
FIRE Non-flammable. Cool area near cargo tanks with water spray in the event of fire near to them.
AIR No reaction.
LIQUID DO NOT DELAY. Flood eye gently with clean sea/fresh water. Force eye open if necessary.
IN EYE Continue washing for 15 minutes. Seek medical advice/assistance. WATER
No reaction. Insoluble.
(Fresh/Salt)
LIQUID DO NOT DELAY. Handle patient gently. Remove contaminated clothing. Immerse frostbitten area
ON SKIN in warm water until thawed (see Chapter 9). Obtain medical advice/assistance. OTHER
LIQUIDS/ No reactions.
VAPOUR Remove victim to fresh air. If breathing has stopped, or is weak/irregular, give mouth-to-mouth/nose GASES
INHALED resuscitation.
Stop the flow. Avoid contact with liquid or vapour. Flood with large amounts of water to disperse spill and
SPILLAGE
prevent brittle fracture. Inform Port Authorities of any major spillage.
CONDITIONS OF CARRIAGE
PHYSICAL DATA
NORMAL
BOILING POINT RELATIVE
CARRIAGE Fully refrigerated. GAUGING Closed, indirect.
@ ATMOSPHERIC -195.8°C VAPOUR DENSITY 0.967 CONDITIONS
PRESSURE
SHIP TYPE VAPOUR
VAPOUR 2 @ -190°C
MOLECULAR 3G. Oxygen analyser required.
PRESSURE 10 @ -170°C 28.01 DETECTION
WEIGHT
kg/cm2 (A)
Liquid Vapour
ENTHALPY 7.33 @ -196°C 54.7 @ -195°C
SPECIFIC GRAVITY 0.9 (kcal/kg) 34.7 @ -150°C 52.0 @ -150°C
COEFFICIENT OF
LATENT HEAT OF 47.5 @ -196°C
MATERIALS OF CONSTRUCTION
0.005 @ -198°C VAPOURISATION
CUBIC EXPANSION (kcal/kg) 17.3 @ -150°C
UNSUITABLE SUITABLE
FIRE AND EXPLOSION DATA Mild steel. Stainless steel, copper, aluminium.
FLASH POINT Non-flammable FLAMMABLE LIMITS Non-flammable AUTO-IGNITION TEMPERATURE Non-flammable
EFFECT
OF Asphyxiation. Cold vapour could cause damage.
VAPOUR
Emergency
Escape
Via
Access
Window
Emergency
Escape
Breathing
Device
Automatic
Exchange
Telephone
Hot Intrinsically
Line Safe
Telephone Telephone
The CCR is located midships between cargo tanks 3 and 4. This room contains
the DCS process and input/output (I/O) and loading computer stations, as well
as the operating panels for the ballast remote control valves, cargo pumps, high
duty and low duty gas compressors, alarm and overfill alarms, cargo and void
space gas detection system and the ESD equipment.
Normal control of all cargo loading and discharging operations is carried out
from here.
The are telephones, including the shorelink ‘hotphone’ located on the aft
bulkhead and on the gas sampling section of the control console.
The CCR is accessed via two doors which act as an air lock to prevent any
cargo gases entering the room.
The air lock contains four fire extinguishers, one CO2 type and two 12kg and
one 25kg dry powder type.
In an emergency, escape from the control room is possible via the escape
window on the port forward side. There is an emergency breathing device
positioned near the window.
11 13 15 17 20 22 24 26 29 31 33 35 44 46 48 50 57 59 61 63 68 70 72 73 74 75
7
12 14 16 21 23 25 30 32 34 38 45 47 49 53 58 60 62
3
1
1 69 71 76
39 54
8 67 77
40 55 79 81
78
66 80
6
4 83 84 85
9
1 1
41 56 NEBB
18 27 36 51 64
19 28 37 52 65
5
43
10
42
Key
1 - DCS Workstation 26 - No.2 Cargo Tank Port and Starboard Cargo Pump Start/Stop Pushbuttons 52 - No.4 Cargo Tank Mimic Panel 78 - LPG Compressor Motor Current
2 - Ballast System Remote Control Valves Operating Levers 27 - No.2 Cargo Tank Mimic Panel 53 - No.4 Cargo Tank Spray Pump Discharge Pressure Gauge 79 - LPG Compressors Motor Current
3 - Port of Montoir Hotline Telephone 28 - Ballast System Illustration and Standing Orders 54 - No.4 Cargo Tank Spray Pump Motor Current Selector Switch
4 - Water Spray Pump Start/Stop Pushbuttons 29 - No.3 Cargo Tank Pressure Gauge 55 - No.4 Cargo Tank Spray Pump Throttle Valve Control Dial 80 - LPG/LNG Compressors Changeover
5 - Port and Starboard Ballast Pump Start/Stop Switch 30 - No.3 Cargo Tank Void Space Pressure Gauge 56 - No.4 Cargo Tank Spray Pump Start/Stop Pushbuttons Switch and Key Lock
6 - Gas Sampling Monitor for Ballast and Void Spaces 31 - No.3 Cargo Tank Port Cargo Pump Discharge Pressure Gauge 57 - No.5 Cargo Tank Pressure Gauge 81 - Cargo Tanks Ventilation Valve Control
7 - Ship/Shore Hotline Telephone for Japan Ports 32 - No.3 Cargo Tank Port Cargo Pump Motor Current 58 - No.5 Cargo Tank Void Space Pressure Gauge Dial Switch and Gauge
8 - Fire Alarm 33 - No.3 Cargo Tank Starboard Cargo Pump Discharge Pressure Gauge 59 - No.5 Cargo Tank Port Cargo Pump Discharge Pressure Gauge 82 - Inert Gas Flow to Consumers
9 - Port of Trinidad Mooring Release Pushbutton 34 - No.3 Cargo Tank Starboard Cargo Pump Motor Current 60 - No.5 Cargo Tank Port Cargo Pump Motor Current Indicating Light
10 - Ballast System Illustration and Standing Orders 35 - No.3 Cargo Tank Spray Nozzles Pressure Gauge 61 - No.5 Cargo Tank Starboard Cargo Pump Discharge Pressure Gauge 83 - Glycol Pump Running Indicator Light
11 - No.1 Cargo Tank Pressure Gauge 36 - No.3 Cargo Tank Port and Starboard Cargo Pump Start/Stop Pushbuttons 62 - No.5 Cargo Tank Starboard Cargo Pump Motor Current 84 - Cargo Tanks Ventilation Valve Control
12 - No.1 Cargo Tank Void Space Pressure Gauge 37 - No.3 Cargo Tank Mimic Panel 63 - No.5 Cargo Tank Spray Nozzle Pressure gauge Dial Changeover Switch (CCR/ECR)
13 - No.1 Cargo Tank Port Cargo Pump Discharge Pressure Gauge 38 - No.3 Cargo Tank Spray Pump Discharge Pressure Gauge 64 - No.5 Cargo Tank Port and Starboard Cargo Pump Start/Stop Pushbuttons
14 - No.1 Cargo Tank Port Cargo Pump Motor Current 39 - No.3 Cargo Tank Spray Pump Motor Current 65 - No.5 Cargo Tank Mimic Panel
15 - No.1 Cargo Tank Starboard Cargo Pump Discharge Pressure Gauge 40 - No.3 Cargo Tank Spray Pump Throttle Valve Control Dial 66 - Insulation Barrier Nitrogen Gas Pressure Gauge
16 - No.1 Cargo Tank Starboard Cargo Pump Motor Current 41 - No.3 Cargo Tank Spray Pump Start/Stop Pushbuttons 67 - Cargo Tanks High Level Alarm Indicator
17 - No.1 Cargo Tank Spray Nozzles Pressure Gauge 42 - ESD Pushbutton 68 - LD Compressor Speed Dial
18 - No.1 Cargo Tank Port and Starboard Cargo Pump Start/Stop Pushbuttons 43 - Manifold Mimic 69 - LD Compressor Running Light and Start/Stop Switch
19 - No.1 Cargo Tank Mimic Panel 44 - No.4 Cargo Tank Pressure Gauge 70 - Inboard HD Compressor Surge Pressure Controller
20 - No.2 Cargo Tank Pressure Gauge 45 - No.4 Cargo Void Space Pressure Gauge 71 - Inboard HD Compressor Running Light and Start/Stop Switch
21 - No.2 Cargo Tank Void Space Pressure Gauge 46 - No.4 Cargo Tank Port Cargo Pump Discharge Pressure Gauge 72 - Inboard HD Compressor Pressure Controller
22 - No.2 Cargo Tank Port Cargo Pump Discharge Pressure Gauge 47 - No.4 Cargo Tank Port Cargo Pump Motor Current 73 - Inboard HD Compressor Speed Controller
23 - No.2 Cargo Tank Port Cargo Pump Motor Current 48 - No.4 Cargo Tank Starboard Cargo Pump Discharge Pressure Gauge 74 - Outboard HD Compressor Surge Pressure Controller
24 - No.2 Cargo Tank Starboard Cargo Pump Discharge Pressure Gauge 49 - No.4 Cargo Tank Starboard Cargo Pump Motor Current 75 - Outboard HD Compressor Speed Controller
25 - No.2 Cargo Tank Starboard Cargo Pump Motor Current 50 - No.4 Cargo Tank Spray Nozzles Pressure Gauge 76 - Outboard HD Compressor Running Light and Start/Stop Switch
25 - No.2 Cargo Tank Spray Nozzles Pressure Gauge 51 - No.4 Cargo Tank Port and Starboard Cargo Pump Start/Stop Pushbuttons 77 - LD Compressor Speed Control Dial
Load
Computer
Ethernet
Main
System Bus
Reserve
8M Equipment
PIC R 0% %
8R
PIC R St Stb. Superh ed Steam l
Fieldbus R M 8-SLOT 8-SLOT 8-SLOT
Co Temp. Co l Valve e
2 1/0 0 1/0 0 1/0 1/0 1/0 1/0 25% 25% 75% 75%
0% %
4 1/0
Emergency Panel
5 1/0
STORE
T
WND DET PICK OVW M C CE EX PICK
T
ACT MR 7 8 9 DET
4 5 6 MOVE WND
FLD
DMON 1 2 3 CA
ACK
FLD ALM
LIST
ACK DISP 0 . - ACT
Scans the Event List OVW Selects a More General Display and Clears the Executes the Selecting a Picture to Another Monitor
C CE EX DMON
Towards Older Events Moves to a Higher Level in Hierarchy Entire Entry Entry
Scans Towards Scans Towards Selects a More Detailed Display. In Selecting a Picture by Number to
7 8 9 DISP
Previous Pictures Next Pictures DET Configuration the Function of this Key Own Monitor
Must be Defined Separately for Each Display
Scans the Event List 4 5 6
Towards Newer Events Selecting a Related Monitor Window
WND
PICK
For Picking a Related Operating Display Window After Pointing it by Cursor
After Pointing it by Cursor
1 2 3
MOVE Moving a Monitor Window
6. PICK key - for opening the related operating display window after pointing Inside the field the cursor is replaced by a pointer, which can only be moved
to it with the cursor. to the permissible positions by using the trackball. The operating fields include
keys, menus and/or entry fields for numerical values. Using the keys and
7. M key - storing a displayed screen in memory. menus is performed by pointing at the desired option with the pointer and
pressing the ACT key.
8. MR key - recalling a stored screen to the monitor.
Operations in an operating field can be stopped by moving the cursor off the
field and by pressing the CA key.
Monitor Number 1
12. Zone field continuation marker. The line has room for up to six The alarm area shows the number of events for different process zones and the
zone fields and when there are more the continuation marker will be colour of the zone field indicates the priority of the most urgent event. The
displayed information related to the first alarm in an alarm sequence is shown on the
alarm area’s event line. The event line allows the operator to scan through the
Graphic Display events and the related displays at the same time.
This provides the user with an overview of the controlled process and displays
the process in an illustrated format. The process status is displayed by means
of motor, valve and pump symbols, status data in text form such as ON/OFF,
measured values in bar graph format and various numerical values.
A hierarchical path shown at the left hand side of the operating screen display
indicates the current display and its selection path. The items at the centre of
the display are related to the operating tag and the standard, non-configuration,
keys are at the right hand side of the display. By touching the MORE key, the
next set of keys are displayed.
Operation in the operating display is started by picking the desired item to the
operating display. This is done by pointing at the item with the cursor and
pressing the PICK key. The display may include bar graphs, texts and
information on the items status. Actual operating keys are not yet displayed for
the item in this basic state, only the current information for the item is shown.
The screens are arranged in a hierarchy tree which consists of branches and
levels, with the route leading from one level to another called the hierarchy
path. The hierarchy menu is accessed by touching the MAIN INDEX key,
which will reveal the keys for the lower level screens and related displays. The
required screen will be displayed on the monitor by touching the relevant key.
Monitor Number 1
Command
Icon
SPRAY HEADER
0.15 bar 0.14 bar 0.15 bar 0.14 bar 0.01 bar
S
P
R
A
Y
C
R
O
STOP S STOP
TANK S
TANK TANK O TANK TANK
1 2 3 V 4 5
SPRAY 0.00 0.00 SPRAY
bar E bar
0A R 0A
22C 28C
Cursor
30C
SHORE CONNECTION
User Authorities 1. Title and/or tag number Control of valves is similar to motors and pumps, ie, the operation menu will
The users of the operating station can be divided into three groups: show which commands are available for that specific valve.
2. Running status(stop or running)
Display mode 3. Control mode selection status Open or Close Operation
Control mode Running an actuator is possible when the actuator is in manual mode M and
M = manual
the operations are enabled when the message NO OP is not on.
Maintenance mode A = automatic
The valve is operated by moving the cursor to the status symbol locating area
Display Mode L = local and pressing the ACT key. An operating field is displayed, containing the
In this mode it is possible to view the screens and pick the displays, but all symbol for the current status and an open and/or close selection key, depending
4. Text pointing area
process operations are disabled. on the application. The valve is opened or closed by moving the arrow to the
Running Operations required selection key and pressing the ACT key. The moving actuator will
Control Mode display a blinking status symbol.
In control mode most basic operations are enabled except for the following: Once the cursor is moved to the operating area, press the ACT key to reveal an
operating field showing the current status and a selection key.
Controller parameter tuning Intermediate Position Operation
I = start The method to start the operation is similar to an open/close type actuator. The
Changing of event limits exception is that the ACT key is held down to run the valve to the required
O = stop
Masking of events position and released to stop the operation at the required position.
Maintenance Mode With the arrow pointing to the I or O symbol, press the ACT key to either start Changing the Position Set Point
All operations are enabled which allows for maintenance to be done on the or stop the motor. Move the cursor to the measured value locating area and press the ACT key.
system and parameters tuned. An operating field with the current measured value and set point is displayed.
Control Mode Change The field also includes an entry field for the new set point, as well as arrow
Motor and Pump Control Modules The control mode can be changed on the monitor screen by moving the cursor keys for driving the se tpoint.
All motors and pumps covered in the DCS system are supported by modules over the control mode status symbol locating area and pressing the ACT key.
providing automatic, manual and local control, control status, operating status, An operating display will be revealed, indicating the current status and Enter the new set point using the numerical keys or adjust the set point with
interlocking, power demand, standby start, restart after blackout and shutdown. selection keys available, such as M, A or L. The current status will be indicated the arrow keys.
by an arrow, which can be moved up or down to another control mode by using
The operating menu for a motor or pump contains the event masking, operation the trackball.
and trend commands available at that time.
Trend Graph Display
All motor or pump control modules have control logic interlock functions to
prevent the motor or pump from being damaged. The interlocks prevent the The trend graph display is revealed by moving the cursor to the system title on
motor from being inadvertently started. Large motors (heavy consumers) have the screen display and pressing the ACT key. On the resulting operating display
a power interlock function that prevents the motor from being started if there screen press the GRAPH DISP key to reveal the related displays available and
is insufficient generator power available on the electrical network. select the TREND DISP key to show a trend graph for the system.
Some control modules will be configured with a blackout restart function. This Valve Actuator Control Modules
function causes a motor to be automatically restarted, when power is re- All valves in the DCS system are supported by modules that have either %
established after a blackout, provided the motor was running before the position or open/closed position feedback. The basic module functions cover
blackout occurred. A configured start delay on each motor is provided to automatic and manual, automatic or local control.
prevent too many motors starting at the same time.
1 1
LIMIT CTK1 CTK2 CTK3 CTK4 CTK5 CTK1 CTK2 CTK3 CTK4 CTK5
VALUE EQUATOR RING FORE -110.7 C -110.3 C -108.1 C -114.5 C -116.1 C
CTR / ATM 0.161 bar 0.160 bar 0.160 bar 0.156 bar 0.157 bar
HIGH PRESS. ALARM 0.22 PAH PAH PAH PAH PAH EQUATOR RING AFTER -111.6 C -110.5 C -110.4 C -119.2 C -118.3 C
LOW PRESS. ALARM 0.01 PAL PAL PAL PAL PAL EQUATOR RING PORT -104.9 C -109.1 C -109.2 C -118.8 C -117.2 C
LOW PRESS. STOP PMPS & COMPR 0.00 PCL PCL PCL PCL PCL EQUATOR RING STBD -111.7 C -108.2 C -108.2 C -121.2 C -116.6 C
VOID SPACE / ATM 0.000 bar 0.000 bar 0.001 bar 0.000 bar 0.002 bar FOUNDATION DECK FWD 25.0 C 22.7 C 22.2 C 22.8 C 26.4 C
HIGH PRESS. OPEN RELIEF VLV VOIDSP. 0.15 PCH PCH PCH PCH PCH
HIGH PRESS. ALARM 0.12 PAH PAH PAH PAH PAH
FWD BULKHEAD UPP 27.1 C 24.9 C 24.9 C 25.8 C 25.0 C
LOW PRESS. ALARM -0.02 PAL PAL PAL PAL PAL
LOW PRESS. N2 TO VOID -0.05 PCL PCL PCL PCL PCL FWD BULKHEAD LOW 21.3 C 22.1 C 22.9 C 23.1 C
LOW PRESS. DRY AIR TO VOID -0.07 PCLL PCLL PCLL PCLL PCLL VOID SPACE AFT BULKHEAD 25.5 C
LOW PRESS. OPEN RELIEF VALVE VOIDSP -0.08 PCLLL PCLLL PCLLL PCLLL PCLLL STBD BULKHEAD UPP 27.9 C 28.7 C 28.4 C 28.6 C 29.1 C
STBD BULKHEAD LOW 26.4 C 27.0 C 26.9 C 27.1 C 25.3 C
PORT BULKHEAD UPP 29.5 C 28.4 C 28.9 C 29.4 C 25.8 C
LIQUID CARGO FWD PRESSURE 0.00 bar PORT BULKHEAD LOW 26.5 C 26.7 C 26.6 C 27.6 C 29.1 C
LIQUID CARGO AFT PRESSURE 0.00 bar
VAPOUR CARGO PRESSURE 0.03 bar
VOID SPACE SUMP 20.2 C 15.2 C 10.9 C 6.5 C 21.2 C
FUEL GAS TO ENG. ROOM PRESSURE PAH LIQUID CARGO CROSSOVER FWD 28.1 C
LIQUID CARGO CROSSOVER AFT 22.4 C
VAPOUR CARGO CROSSOVER 30.3 C
EMERGENCY RELEASE QUICK CLOSING LOOP 6.67 bar LIQUID CARGO HEADER FORE 31.8 C
LIQUID CARGO HEADER AFT 30.5 C
Monitor Number 2
-0.24 bar
0 A
STB
M
No.3 BOTTOM No.2 BOTTOM No.1 BOTTOM
WING TK S WING TK S WING TK S
9.89 m 0.00 m 6.29 m
2836 m3 0 m3 1733 m3
100 % 0 % 100 %
DRAFT AFT No.5 SIDE No.4 SIDE No.3 SIDE No.2 SIDE No.1 SIDE DRAFT FWD
Draught Aft 8.74 m TANK STBD TANK STBD TANK STBD TANK STBD TANK STBD 8.06 m Draught Forward
0.00 m 15.45 m 15.47 m 15.28 m 15.05 m
AUTO 0 m3 1610 m3 2517 m3 1521 m3 1173 m3 AUTO
0 % 95 % 95 % 94 % 92 %
The DCS calculates the correct cargo tank levels with reference to the specific Ballast Control - to be Fitted in the Near Future
gravity of the cargo and the trim and list of the ship.
This function has a primary view, visualising the entire ballast system. From
The corrected level is then used by the DCS for the volume calculation from this view the tank levels of all vessel fluids used as ballast can be monitored
the cargo tank tables and the volume is finally corrected for the thermal and the ballast system pumps and valves can be controlled. The primary view
contraction factor of the tank shell. also shows the vessel heel data.
User set parameters are available in mimic 5.2 Custody Transfer for LNG/LPG Operator Interface
mode and specific gravity.
The cargo and ballast process views in the cargo control room show the fluid
Cargo Tank Temperature Monitoring control systems comprising tank, valve and pump symbols interconnected by
Each cargo tank is equipped with four PT100 probes for liquid and vapour piping and manifolds. The operator monitors the status of each device by
temperature measurement. displaying the views and operating the equipment as required. The starting and
stopping of pumps and the opening and closing of the valves is normally part
Ballast Tanks Monitoring of the automatic cargo and ballast tank filling and emptying sequences, which
Each tank, except the fore peak tank, is equipped with one pressure transmitter are initiated from the operator stations.
for the level measurement. Alarms are related to the levels.
Alarm suppression is activated when both ballast pumps are stopped. The
suppression can be switched off via mimic 25.1.
Level monitoring
Each cargo tank has a level transmitter used to indicate the level in the tank.
Rupture Disc
Cross Section
Pressure
Insulation
Nitrogen
Blank Flange
Bleed
Rupture Disc
Removed
Rupture Disc
Rupture Disc
Skirt
Polystyrene
Leakage Pipes
Insulation with
Stainless Steel
Cover
4.1 Cargo Containment and Monitoring Systems The Norman Lady’s cargo tanks are insulated with expanded polystyrene A leakage of LNG within the tank insulation will be detected at an early stage
foam, fitted to the tanks by a spiral generating system. This system generates by the gas detection system fitted at the equatorial ring area and at the drip pan.
polystyrene strakes (logs) as the machine moves spirally around the tank. The The drip pan, installed directly below each cargo tank is fitted with
General Description equipment automatically fuses adjacent polystyrene logs as the machine temperature, gas and liquid sensors to detect the presence of LNG. These will
advances around the sphere. alarm via the gas detection and DCS systems. An eductor system allows the
The cargo containment system consists of five insulated cargo tanks encased
within the inner hull and situated in-line from forward to aft. The spaces removal of the liquid.
The insulation consists of two polystyrene layers separated by a crack-
between the inner hull and outer hull are used for ballast and will also protect arresting layer of glass fibre. The upper hemisphere insulation is coated with
the cargo tanks in the event of an emergency situation such as a collision or a The aluminium foil surface of the tank insulation protects the insulation as well
square aluminium foil plates. The aluminium foil splash barrier on the lower as directing any leakage away. Any LNG liquid leakage drains by gravity from
grounding. hemisphere is automatically bonded to the outer surface of the insulation between the tank plating and the insulation to the drip pan via a drain tube at
during the log welding process. This process butt welds the logs to form a the bottom. The drain at the bottom of the insulation space is sealed in normal
The ballast spaces around the cargo tanks are divided into two double bottom continuous insulation layer. The insulation is not actually bonded to the tank
wing tanks, port and starboard for each cargo tank. The double bottom tanks service by a rupture disc.
surface and this allows the passage of nitrogen gas between the insulation and
extend to the side of the cargo tanks as far up as the trunkways. the tank. Liquid flow from the northern hemisphere collects in the drain channel which
Cargo tanks No.1 and No.5 are slightly different in size due to their position in is formed by the upper skirt ring stiffener and is directed to the leakage pipes
Containment located forward, aft, port and starboard of the tank. These pipes direct the
the ship. The sizes and capacities are as follows:
liquid onto the void space deck and then to the drip pan. These areas are all
Tanks 1 and 5: 31.0 metres diameter The LNG in the ship’s cargo tanks is carried at a pressure that is marginally protected with stainless steel sheet covers.
higher than atmospheric pressure. The cargo tanks are housed within holds and
Tanks 2, 3 and 4: 33.1 metres diameter each hold is separated by a watertight bulkhead. A positive pressure of inert gas All of the pipes except one are fitted with rupture discs. These discs are gas
Tanks 1 and 5 capacity: 15,490m3 or dry air (depending on operational requirements) is maintained in the void tight but are designed to fail at cryogenic temperatures and will therefore
space surrounding each tank. rupture when LNG comes into contact with them. The leakage pipe without a
Tanks 2, 3 and 4 capacity: 18,860m3
disc has a gas detection sensor fitted to provide early warning of a possible
There is no secondary barrier as the tanks, primarily due to their spherical The boiling point of LNG at atmospheric pressure is extremely low (-163ºC) leakage.
construction, have a high degree of safety against fracture or failure. The tanks and so special equipment and procedures must be used to handle LNG. The
are heavily insulated with approximately 215mm of polystyrene foam to piping system is designed to have the minimum number of bolted flanges. From illustration 4.1.1a the layout of the leakage pipes can be seen.
reduce natural boil-off to a minimum.
Welding is used wherever practicable to reduce the possibility of joint leakage.
The tanks are constructed of 9% nickel steel. Each tank is covered by a Any liquid leakage must be dealt with by spraying the area affected with water
spherical steel tank cover which is mainly for tank and insulation weather by means of the spray system provided, or by the use of a fire hose. This
protection. The cover also permits control of the hold space atmosphere. The prevents any fractures of the affected local steelwork.
lower edge of each cover is welded to the deck, forming a watertight seal. A
flexible rubber seal is used at the point where the tank dome protrudes out from Monitoring
the cover.
The DCS system provides monitoring of the cargo levels, pressures and
The tanks are each supported by a metal skirt from the equatorial ring, which temperatures. Together with the cargo and void space gas detection system, the
transmits the weight of the tank and the cargo to the lower hull. The skirt is DCS system monitors the cargo containment systems, the tanks and the void
stiffened in the upper part by horizontal rings and the lower part by vertical spaces etc for any signs which may indicate a failure of this containment and
corrugated stiffeners. possible gas or liquid leakage.
A special casting joint is fitted between the skirt and the tank’s equatorial ring In the case of a cargo leak, the gas detection analyses the void space via four
to provide the necessary strength at this point and to reduce heat conduction sampling points (see section 4.9, Fixed Gas Detection Systems) and raises an
into the tank and a corresponding conduction of low temperature to the skirt alarm locally at the LCCR and via the DCS system.
and hull.
If the leak is of a size where liquid is flowing, the leak would be directed via a
system of leakage pipes described in the next section, 4.1.1.
Tank/Void
Differential
Pressure
Tank/Void
Differential
Pressure
Tank Top
Temperature
Drip Pan
Temperature
General Description The relevant displays/mimics where tank and void space monitoring are
(See illustration 4.1.2a) displayed are:
The individual cargo tank measurement mimic
Monitoring equipment is provided in the CCR and the ECR via the DCS
system for the void spaces and inner hull temperatures and pressures to give The cargo tank spraying mimic
warning in the case of a failure of insulation or leakage of the containment Cargo tanks overview mimic
insulation barrier.
Each sensor is of the PT100 resistance type. The sensors are installed in the
secondary insulation barriers and alongside the inner hull associated with each
cargo tank. The temperature range of each sensor is : -200°C to +100°C.
For the inner hull temperature measurement, there are sensors in each tank.
One is located along the bottom of the tank in the pipe duct, one double
element type sensor in the liquid dome.
The temperature measurements are indicated for each sensor in service in the
CCR via the DCS system. Recording of these temperatures is also available via
the DCS system.
Temperature Measurement
The sensors are wired with four conductors (four wire cable) and all
terminations are sealed. There are spare sensors mounted in the tanks to
provide a degree of redundancy.
Pressure Measurement
99.2% 29.36M
230V AC Supply
High Level System HIGH AND OVERALL ALARM SYSTEM
Protective Cap 95% High
99.2% 99.2% 99.2% Overfill Level
230V AC Supply Alarm Alarm
TANK NO.1 TANK NO.2
Overfill System 95% 95%
Test Lift Button
99.2% 99.2%
TANK NO.3 TANK NO.4
95% 95%
Connection
Box 99.2%
TANK NO.5
95%
Cargo Tank Dome Shell
ACCEPT ALARM LAMP ON OFF
NORM FLASH HOLD TEST
Audible Alarms on Deck
TONSBERG NORWAY
Float Guide
High High
Low Density Float
Sensor Switch
SAFE AREA
Level Sensors
Tank No.s 2, 3 and 4
4.1.3 High Level and Overfill Alarm System Alarm Panel If one of the level switches, that is already in an alarm condition,
should be deactivated and then reactivated because of movement
Maker: Omicron The alarm panel has ACCEPT ALARM, RESET ALARM, ALARM HOLD, on the cargo liquid surface, the alarm will not be repeated due to
Type: OAS - 5 LAMP TEST and unit ON/OFF pushbuttons. There are LED indicators for all the ALARM HOLD function.
tank alarms and also loop and power/system failure.
The vessel’s cargo tank high level alarm system is fitted to comply with the (Note : Any loop/wiring or system faults must be rectified as soon as possible
IMO, DNV and USCG etc societies’ requirements. To comply with these Operation as a sensor with a loop failure will not alarm.)
requirements the high level alarm and overfill alarms are completely separate.
When a cargo tank float moves upwards, the relevant red LED on the
The level switches are of the float type and can be tested independently from intrinsically safe alarm module and the alarm panel will start to flash and the
the top of the tank. ACCEPT ALARM pushbutton will illuminate.
All the inputs from the level switches are connected directly to the input sides The alarm lamp and horn on deck as well as the buzzer on the alarm panel will
of intrinsically safe alarm units. These alarm units are bus wired to one start. The corresponding alarm will also be raised via the DCS system.
common output unit which interfaces with the SVC system. Separate outputs
for alarms and indication are available at the alarm/control panel mounted in Pressing the ACCEPT ALARM pushbutton will cause the common alarms
the Cargo Control Room. (horn and lamp) to stop. The LEDs on the intrinsically safe alarm unit and the
alarm panel will continue to flash. The operator should then press the RESET
In addition to tank alarms, the system also indicates and raises separate alarms ALARM pushbutton and the flashing LED(s) will illuminate steadily.
if a loop fails for the level switches and their associated wiring or if a processor
or a power failure occurs. The common alarm unit is configured to raise different alarms for either the
95% HIGH LEVEL or 99.2% OVERFILL alarm. This unit pulses the exterior
The level switch has two floats with built-in permanent magnets in each float. horn and illuminates the yellow lamp for high level or sounds continuously and
As the float moves upwards, a reed switch inside the housing is deactivated illuminates the red lamp for the overfill alarm. The horn and lamps are situated
and an alarm is raised. When the float moves downward, the reed switch is on a floodlight mast adjacent to No. 3 cargo tank dome.
closed again. This is the non-alarm position so the alarm loop fails safe (ie,
alarms) in the event of any open circuits/wire-breaks. The 99.2% OVERFILL alarm is also configured to automatically close the
filling valve for that tank.
Two resistors are connected to the reed switch inside the sensor. One is in
series and one is in parallel with the switch contacts. This enables the detection The overfill alarm has a remote reset OVERFILL pushbutton on the port outer
of broken or shorted alarm circuits. operating station in the CCR.
Each level switch is equipped with a mechanical testing device. The testing In addition to the above normal alarm functions, there is also an ALARM
device is located under a protective screw cap on top of the level switch’s HOLD function. This function handles all tanks separately and independently
junction box. By lifting the testing device slowly, the HIGH LEVEL alarm and is selected by pressing the ALARM HOLD button on the alarm panel. The
(95%) for that particular tank will be raised. Lifting the device further up will function remains in operation as long as the button is activated. The alarm hold
cause the OVERFILL alarm (99.2%) to be raised. function operates as follows:
When testing is complete, the test device should be pressed back down and the If, prior to loading, the ALARM HOLD pushbutton is already
protective screw cap replaced. activated, it must be released and reactivated. This clears any
previous alarms.
(Note: The high level and overfill alarm are to be tested prior to each loading.)
If the ALARM HOLD button is on, the first alarm from each tank
activates the alarm horn and light on deck, the buzzer on the
control panel and the DCS alarm. The appropriate LEDs on the
control panel and the intrinsically safe alarm module will also
flash.
Liq
R
GC
To No. 4
LN
uid
Vent Mast V2100
Va
015
Ni
V2052 V2138
V2
p
tro
32 1
ou
V21 V 213
ge
Liq
r
ou
r 120 V2051
V2
n
Liq
Vap ater
uid
V2051
PI He
u id
15
V21 V2051
30
V21
14 200
32 30 V21 V2 V2051
V21 V21 015
A
p.B 14A 016 206
1 V2
Co
m V21 V2 V V2026
34 HD
V21 31
To ou
r
V21 201
s Vap ater 14 V2 Vent V2004
iler V21
Dome
Bo He 35 Mast 003
V21 061 V2
V2
A (S)
016 002
36 V2 A V2101 V2
V21 200
13 35 V2 V2138
V21 V21
V2055
V2002 (P)
.A
V2
mp
Co No.1
20
D V2054
H
3
V21
28 V2054 Cargo Tank
6
pac
e 212
V2
V V2054
39 id S er
20
V21 Vo r Dry 14
V2
3A
V2054
Ai V23
V2
17 .
23
V21 mp
20
13 Co V2027
4
V21 14
LD V23
3
25 26
35 V21 V23
15
V21 t
V22 Pla
n V2008
Dome
G 15 N Vent 7
LN iser V23 e To 2 00
or pac Mast V2
Vap id S er
Vo r Dry (S)
11 25 Ai 6
V21 V21 m ans V2
00
d 39 Fro ing F ating V2103
Voi re V21 t
cula ace H
e
or V2138
r F osphe c ir
Re id S p V2006 (P)
ate V2058 V2068
He e Atm
ac V21
39
Fo r Vo No.2
Sp V2057
V2057 Cargo Tank
V2057
V2057
22
V2
V21 V2028
01
19 G
LP
2
V21 To nt
Pla Dome
m 011
G Fr o V2
LP G
To nt LP t
s Pla Pla
n Vent (S)
ace Mast 01
0
Sp V2
Void 10
To V21 V2108
V2010 (P)
18 V2138
V21 V2064 V2068 No.3
V2063
V2063
Cargo Tank
V2063
V2063
V2029
Spray
Pump
V2020
Dome
Vent 019
Mast V2 D
(S) FW
8
01
V2
V2109
V2066 V2138 V2018 (P)
No.4
V2065
V2065
Cargo Tank
A
V2065 015
V2
V2065
To V2030 Spray From
Emergency Pump Safety 120
V2
Discharge V2024 Valves
Dome
Astern
023 A 061 015
V2 200 V2 V2
V2
(S)
00
2 LAH
V2 016
A
V2 061
V2
V2002 (P) Overflow
Liq
No.5 201
Drain Tank
u
V2
200
id
Cargo Tank V2
016
Va
po
Ni
V2
ur
tro
Liq
ge
n
uid
4.2 Cargo Piping System The inert gas and dry-air system, located in the engine room, is used to supply The LPG system is de-commissioned and all lines are blanked and the electric
inert gas or dry air to the cargo tanks via piping which connects with the main motors disconnected.
Description cargo system through a double, non-return valve to avoid gas returning to the
engine room. When operational the system will take suction from the vapour header and
The cargo piping system is shown in illustration 4.2a in a simplified discharge liquid to the spray header.
perspective showing only the principal features of the system. All of the cargo piping is welded to reduce the possibility of joint leakage.
Flanged connections are electrically bonded by means of straps provided There is also a pipeline from the the liquid line which can be used as a hot
Liquid cargo is loaded and discharged via the two crossover lines midships between flanges to ensure that differences in potential, due to static electricity vapour suction.
between cargo tanks 3 and 4 and is delivered to and from each cargo tank liquid between cargo and other deck piping, tanks, valves and other equipment, are
dome via the liquid header which runs forward and aft. Each crossover line at avoided.
midships separates into two loading/discharging connections, port and
starboard, making a total of four loading/discharge connections. Both liquid and vapour systems have been designed in such a way that
expansion and contraction are absorbed in the piping configuration. This is
The cargo tank vapour domes can be connected by the vapour header running done by means of expansion loops and bellows on liquid and vapour piping
forward and aft along the trunk deck. The vapour main also has a cross- respectively.
connection at the midship manifold for use in regulating tank pressures when
loading and discharging. Fixed and sliding pipe supports and guides are provided to ensure that pipe
stresses are kept within acceptable limits.
When loading, the vapour header and crossover, together with the HD
compressors, are used to return the displaced gas from the tanks back to the All sections of liquid piping that can be isolated, and thus possibly trapping
shore installation. When discharging, the vapour header is used in conjunction liquid between closed valves, are provided with safety valves set at 5 bar,
with either the vapour crossover, or a vaporiser, to supply gas to the tanks to which relieve excess pressure to the collecting tank and on to No.4 vent mast.
replace the outgoing liquid cargo. This tank is situated on the deck above the cargo control room and has a level
alarm fitted to alert the operator to the situation. This is a safety measure,
The spray line can be connected to the liquid crossover lines and can be used although normal working practice is to allow any remaining liquid to warm up
to drain or to cool down each cargo tank, and also to spray during discharging and boil-off before closing any such valves.
if the return vapour is insufficient.
All major valves such as the midships manifold (port and starboard) valves,
The vapour header and stripping/spray headers are both connected to the individual tank loading and discharge valves, are remotely power operated
vapour dome of each tank. The vapour domes also house the tank safety from the DCS system, so that all normal cargo operations can be carried out
valves, pressure pick-up and sample points. The spray line on each tank from the Cargo Control Room. The pipeline layout at the manifolds is shown
consists of four spray lines inside the tank to distribute the incoming liquid into in illustration 4.2b.
the spray nozzles in order to assist in evaporation and thus achieve a better
cooldown rate. When an emergency shutdown is activated, the manifold valves are closed,
discontinuing loading or unloading operations.
The spray and vapour headers have branches to and from the LNG compressor
room with connections to the compressors, heaters and vaporiser for various A non-return valve is fitted at the discharge flange of each cargo pump. A hole
auxiliary functions. Removable bends are supplied for fitting where necessary is drilled in the valve disc to allow the tank discharge lines to drain down and
to allow cross-connection between the various pipework for infrequent uses be gas freed. Non-return valves are also fitted at the discharge flange of the
such as preparing for dry dock and recommissioning after dry dock. compressors. A small diameter spray nozzle is also fitted at the top of each
cargo pump discharge line to cool down the pipework.
The vapour header connects the vapour domes to each other for the venting of
boil-off gas, which discharges to atmosphere through vent mast riser No.4. The (Note: Electrical bonding by means of straps is provided between bolted
vapour main also directs the boil-off gas to the engine room for gas burning, flanges. Whenever a section of pipe or piece of equipment is unbolted, the Collecting Tank: Situated Above Cargo Control Room
via the LD compressor and gas heaters. bonding straps MUST be replaced when the flanged joint is remade.)
V2015A V2015A
V2046A
V2016A
V2061 V2061
V2061 V2061
V2034 V2410
V2410 V2410 V2410
A B C D E F G
Relief and
Relief and Gauge Valve
Gauge Valve
Gauge Valve Gauge Valve Gauge Valve Gauge Valve
Gauge Valve Gauge Valve
Gauge Valve
Drain Valve Drain Valve Drain Valve Drain Valve Drain Valve Drain Valve Drain Valve
The system comprises a 550/500/450/350mm butt welded, cryogenic stainless The system comprises a 300/550/450/400/300mm cryogenic stainless steel
steel pipeline connecting each of the five cargo tanks to the loading/discharge pipeline connecting each of the five cargo tanks by means of a common line to
manifolds at the ship’s side by means of a common line. the ship side vapour manifold, the LNG compressor room and No.4 vent mast.
At each tank liquid dome there is a manifold which connects to the loading and The line to the LNG compressor room allows for the vapour to be used in the
discharge lines from the tank to allow for the loading and discharge of cargo. following manner:
This manifold on the liquid dome connects to the tank discharge lines from the Sent ashore during cargo loading by means of the HD
port and starboard cargo pumps, the loading line and the spray line. compressors, in order to control pressure in the cargo tanks.
At certain points along the liquid line, blank flanges and sample points are During ballast/loaded voyages, the boil-off gas is sent to the
fitted to facilitate inerting and aeration of the system during dry dock/refit. engine room via the LD compressor and heater for use as fuel in
the boilers.
All sections of the liquid line outside the cargo tanks are insulated and covered
with a moulded cover to act as a tough water and vapour tight barrier. During repair periods the gas is vaporised and used to purge-dry
the cargo tanks if required.
At certain points along the vapour line, blank flanges and sample points are
fitted to facilitate inerting and aeration of the system during dry dock/refit.
All sections of the vapour line outside the cargo tanks are insulated and
covered with a moulded cover to act as a tough water and vapour tight barrier.
V2028 Q m
Q
700
m
600
Spray Pipes
200
500
400
300 150
200
Spray Pipes
Nozzles
100
100
1 2 3 4 P
The spray system piping consists of a main header, running along the ship from During transportation of LNG at sea, gas vapour is produced due to the transfer During normal operations, the pressure in the tanks is controlled by the use of
tank No.1 to tank No.5. This header is connected to the liquid crossovers for of heat from the outside sea and air, through the tank insulation; also energy is the boil-off gas in the boilers as fuel, or controlled via the vent mast (No.4
LNG cargo supply from the shore and to the two spray pumps. One pump is absorbed from the cargo motion due to the vessel’s movement. tank) and the common vapour line.
fitted in tank No.3 and the other in tank No.4, for the supply of LNG when the
ship is at sea. Under normal power conditions, the boil-off gas is used as a means of fuel in Each cargo tank is also fitted with two independent safety valves, comprising
the ship’s boilers. two 350mm lines exiting the tank top into their own pilot operated relief
The spray pipe header is connected to each tank dome by four spray pipes valves.
supplying the spray nozzles with liquid. The LNG can be sprayed through up The gas vapour is taken from the vapour header and passed on into the LD
to 20 nozzles in each tank to obtain a uniform distribution within the tank. The compressor. It then passes through the boil-off /warm up heater before going Sections of the vent line outside the cargo tanks are insulated and covered with
operator decides how many pipes and nozzles to use by opening or closing the to the ship’s boilers where it is burnt as fuel. a moulded cover to act as a tough water and vapour tight barrier.
nozzle inlet valves V2051, V2054, V2057, V2063 or V2065 to suit the speed
of cooling down required. The pipe runs along the port side of the main deck. The main gas isolating 4.2.6 Inerting/Aeration Line
valve V2140 is located immediately forward of the accommodation. The
The nozzles connected to pipe No.1, 2 and 4, each have a spray rate capacity nitrogen purging connection is also located at this point. The pipe then enters
The system comprises of a 300mm flanged line which supplies inert gas or dry
of 500kg of LNG at 1.53kg/cm2 pressure drop across the nozzle. The nozzles the machinery spaces and from that point the pipe runs inside a ventilated duct
air to the cargo tanks and pipelines for inerting and drying during refit periods.
connected to pipe 3 each have a capacity of 1,000kg of LNG. The nozzle pipe. This duct pipe has two exhaust fans situated on the open deck to draw the
characteristics/capacity diagram is shown in illustration 4.2.3a. surrounding air to the atmosphere. This vent duct is fitted with gas detection.
The inert gas/dry-air is supplied from the inert gas plant situated in the engine
room. The dry-air is supplied by the inert gas generator running in the dry-air
The system comprises a 80/50mm butt welded, cryogenic stainless steel
mode (see section 4.7.1, Inert Gas Generator).
pipeline connecting the spray pump in tanks three and four to the
stripping/spray header and serves the following functions by supplying LNG
The line is connected to the gas header and the liquid header by means of a
to:
spool piece. By selective use of the spool pieces and flexible hoses it is
possible to inert or aerate all or a single cargo tank.
The spray rails in each tank, used for tank cooldown and gas
generation.
There is also a spoon blank fitted at the void space air recirculation line to the
IG main cross-connection, located at the starboard manifold. The removal of
The main liquid line, used for cooling down lines prior to cargo
this blank enables the supply of inert gas or dry-air to the void spaces, if
operations.
required.
Priming of discharge lines in the cargo tanks to prevent line surge
when starting main cargo pumps.
All sections of the spray line outside the cargo tanks are insulated and covered
with a moulded cover to act as a tough water and vapour tight barrier. Gas Valve V2140 and Gas Duct Pipe Exhaust Fans
(Note: The pressure drop shown in illustration 4.2.3a, the spray nozzle
characteristic/capacity graph, will differ from the pressure drop indicated on
the spray pressure indicator PI-22, as the latter includes pressure drop in the
pipe from the control valve to the nozzles and also the static pressure from the
liquid in the pipe.)
Pump Discharge
140
Head Capacity
Upper
Bearing Electrical
Terminal Box 130
3
120
110
Rotor and
Minimum Pump Down 1
Shaft
Key METRES Min NPSH
HEAD
Stator Liquid Flow
100
Lubrication Flow 80
0
70
90
EFFCIENCY PERCENT
60
80 50 Pump Efficiency
Lower 40
Bearing
70
30
Motor Rating
Horsepower to Pump
300 SP. GR. = 0.50 (275 BHP)
20
SP. GR. = 0.60
HORSEPOWER 200
Impeller KILOWATTS
Inducer
0 100 200 300 400 500 600 700 800 900 1000 1100 1200
CAPACITY (m3/h)
4.3.1 Main Cargo Pumps a) Check the level of the liquid in the tank. The pumps must not be Operating a pump at, or close to, its design flow level is in the best interests of
started when the tank is dry. The cargo pump must be completely the pump lifespan and operating performance. However, operating the pump at
submerged in LNG. flow rates which are less than this cannot be avoided. This is especially the case
Maker: JC Carter when the shore receiving facility cannot accept the rated flow. However, it
Type: 60190-3450-32 b) Before starting the pump, open the throttle valve to about 25%. should be remembered that it is better to operate one pump at the design flow
Capacity: Rated at 750m3/h x 120 mLc Starting the pump with the valve fully open when pumping liquid rather than two pumps running at 50% flow. The pump’s rated flow should only
No. of sets: 10 (2 per cargo tank) which has a high specific gravity will overload the motor. be exceeded during the starting period while the discharge valve is adjusted.
Operating temperature: -163°C
Head capacity: 155m c) Start the cargo pump. The operator should keep a close watch on Stripping or Low Liquid Level Operation
Power: 275hp the discharge pressure and the motor current. The current
Speed: 1,780 rpm consumption should steady after the motor has been running for 3 As the end of a discharge approaches, the pump suction head will approach the
seconds. During starting, while the discharge pipe is being filled, NPSH for a given flow. From the above illustration (4.3.1a) the blue curve
The cargo tanks are fitted with two main cargo discharge pumps. These pumps the current may be above the ammeter red line. The current should displaying NPSH required as a function of flow rate can be seen. At
are single stage centrifugal pumps with one inducer stage. The single stage not exceed the maximum rated current by more than 50% for more approximately 0.80 to 1 metre liquid level above the pump inlet bell, the NPSH
helps to obtain a very low NPSH (Net Positive Suction Head). than 2 or 3 seconds when the tank is full. If the running current for the rated capacity will be reached. When the amount of liquid falls to this
after this time is more than 150% of the maximum rated current, level, the motor ammeter and the pump discharge pressure should be monitored
The pumps are of the submerged motor type, with the motor windings cooled stop the pump immediately and determine the cause of the high continuously by the operator.
by the pumped LNG. The LNG also lubricates and cools the pump and motor current, (possible suction blockage).
bearings. As the LNG serves as the lubricant and the coolant it is critically The low level alarm is triggered when the liquid level is about 1 metre above
important for the pump that the following operational procedure is strictly d) When the pump discharge pipe is filled to the discharge valve, a NPSH, the flow should be reduced by use of the throttling valve on the pump
adhered to. substantial increase in the discharge pressure and a corresponding discharge side. If any fluctuations are observed on the motor ammeter or on the
decrease in current should be observed. pump discharge pressure gauge during final pumping, the discharge flow rate
There is an automatic starting sequence available via the DCS system. This should be further reduced until the readings stabilise. When the flow is
automatic start will check all the interlocks and open the throttle valve e) Once the pump is operating normally, adjust the discharge valve throttled, it can be seen from the above graph that restricting the flow down to
accordingly before starting the pump. to obtain the required flow or pressure. The operator should about 230m3/h the required NPSH will be about 10cms. This level represents
monitor the pump motor running current, taking care not to exceed the minimum level attainable by pumping.
the maximum current level.
CAUTION
(Note: When the pump is operating correctly, closing the pump discharge valve It is of the utmost importance that the pumps are never allowed to run dry,
during operation will raise the head pressure and consequently reduce the even for short periods, as this will result in motor failure. A momentary
running current.) loss of priming during cargo stripping should not be considered as running
a pump dry. Up to 30 seconds of operation with dry suction but with fluid
The cargo pumps may be restarted concurrently a maximum of 3 times, after in the discharge pipe will not damage the pump or the motor.
the third time a 30 minute waiting period must be applied, after this time
another 3 starts may be made. This procedure must be adhered to as heat build- When the liquid level reaches less than one metre above the pump inlet, avoid
up from the high starting current may not be carried away during stripping stopping the pump if at all possible until the cargo has been fully discharged. If
operations. This may be due to the lack of liquid flow when (and if) the pump the shore facility is unable to accept the liquid for intermittent periods, it is
does not prime, due to the extremely low level of LNG during stripping preferable to keep the pump going and recirculate the liquid back into the tanks
operations. The pumps are started and stopped from the CCR via the DCS until the cargo discharge can be resumed and completed.
system. In an emergency all pumps will be stopped by activation of the
Emergency Shut Down System trip.
Discharging Pipes
Loading Pipe
Fixed Clamp
For Level Indicator Pipe
The operator should check the cargo liquid level before starting a pump and As well as the shutdown via the ESD system, the following will trip the pumps:
maintain at least 2kg/cm2 discharge pressure. This is to ensure the lubrication
Low current: <126A for 5 seconds
of the bearings on all pumps in cargo service.
High current: 100% current (motor starter setting)
The operator should always open the throttle valve to 25% open, before staring
Single phasing: 1 phase lost (motor starter setting)
a pump.
Low low cargo pressure: 0.0 bar
The operator should always monitor the motor ammeter and the discharge
High void/tank differential pressure: 0.04 bar
pressure gauge.
ESD low loop pressure: >3.0 bar
The operator should always try to run the pump at the design flow rate
whenever possible.
The operator should never blow hot air through a discharge line. This may turn
the impeller and rotor at high speed in the wrong direction, damaging the
bearings.
The operator should never operate the pump above the motor ammeter red line.
The operator should never assume that all electrical interlocks and safety
relays will continuously function correctly. The operator should be ready at all
times for any eventuality.
The operator should not allow sea water, water, steam or any cleaning agent
containing water to come into contact with a pump or its cables and
connections.
(Note: An insulation test of all pumps is to be carried out after leaving the
loading port in order to establish that all pumps are operational and to allow
time for the implementation of emergency procedures, should it be necessary.)
20
VOLTAGE 440
16
Upper
Bearing PRESSURE v's FLOW
14
12
SP. GR. = 0.601
SP. GR. = 0.57
10
SP. GR. = 0.50
Stator PRESSURE
Windings (kg/cm2)
Electrical 8
Terminal Box
6
Rotor and
Shaft
4
Stator 2
Key
0
Liquid Flow
Lubrication Flow
OCR = 30 AMPS
CURRENT 20
(Amperes)
10
Impeller
Inducer
0 4 8 12 16 20
CAPACITY (m3/h)
Specification The stripping/spray pumps will be stopped automatically should any of the
following occur:
Maker: JC Carter
Vapour header pressure below or equal to atmospheric pressure
Type: 6337-2113-3
plus 0.3kPa (ESDS: Stage 1)
Capacity: Rated at 40m3/h x 60mLc
No. of sets: 2
Extreme high level in cargo tank (99.2% volume)
Operating temperature: -163°C
One spray pump is installed in each of the tanks No.3 and 4. Activation of ship/shore pneumatic, fibre optic or electrical
shutdown (ESDS: Stage 1)
The pumps are in principle similar to the main cargo pumps and a similar
operating procedure should be used. Each spray pump has a capacity of 8m3/h Motor single-phasing
at a discharge head of 146mLc.
Low motor current
The performance curve is shown in illustration 4.3.2a.
High motor current (electrical overload)
The spray pumps are intended for the cooldown of cargo tanks before loading
after a ballast voyage. Low discharge pressure with time delay at starting
The pumps are started and stopped from the CCR via the DCS system. In an Activation of ESDS stage 2
emergency all pumps will be stopped by activation of the Emergency Shut
Down System trip. Cargo tank level low low
The instances when these pumps can be used are: The end of a DCS cargo automatic sequence
To cool down the liquid header prior to discharging. Spray Pump Safety System
To cool the cargo tank during ballast voyage prior to arrival at the In addition to the above shutdowns, the spray pump safety system will stop the
loading terminal by discharging LNG to the spray nozzles in the pumps and close the discharge valves if any of the following conditions occur:
tanks.
Low current: <10A for 5 seconds
To pump LNG from the tanks to the vaporisers (emergency case)
when forced vaporisation of LNG to the boilers is required. Low low cargo tank pressure: 0.0 bar
High void/tank differential pressure: 0.04 bar
To enable the tanks to be stripped as dry as possible for reasons
such as a cargo tank entry. ESD low loop pressure: 3.0 bar
Whenever possible, the stripping/spray pumps should be started early enough (Note: An insulation test of all pumps is to be carried out after leaving the
to avoid any possible starting problems due to very low tank levels (about 0.5m loading port in order to establish that all pumps are operational and to allow
minimum). time for the implementation of emergency procedures, should it be necessary.)
To / From
Other Compressors
Steam System
PI
Draw Off Line
Seal Gas Tanks/Ashore
69
System Shut Off From Nitrogen
and Regulating Valve System
Discharge
Compressor Discharge 3 Tank/Void
Gas Temp. Relays LCCR
Governor PCLA ESD
TE
78 121 System
PT
79
TI TI TI
SVC SVC
Discharge Discharge
Turbine Compressor Gas Press. Gas Temp.
Indic. Indic.
Inlet PDT
Vane 75
PS TS Low LO Control
88 87 Shut
-down TIT
Switch TE
73 85
L.O. Pressure
Valve L.O. Temp.
/Pressure TI
L.O. Cooler Safety
Suction
Cooling Shutdown
Water Valve
Bypass
Control
Steam Shut-off Valve TI Press.
Valve
For Steam Driven Pump
PI PI PI PI PI PI
PDT 68 68 70 90 88 84
76
Speed PI PI TI SI
Steam L.O.
Governor Pump 71 79 85 74
Shaft Driven
Impulse L.O Pump
Connection
Speed SVC Compressor SVC LCCR
Actuator Suction Gas Speed
Discharge Temp. Indic.
TS PS SS Surge Valve
Pneumatic Indicators ZA
Lubricating Oil Tank 85 84 86 Activated
Compressor
PT
71 Suction
Compressor
Pressure XA
Failure
4.4 Gas Compressors Compressor lubrication is provided by a gear driven oil pump which is housed Local Compressor Start Up Procedure
in the steam turbine bearing housing. The turbine and radial compressor have
The Norman Lady is equipped with three steam turbine driven gas a common lubricating oil supply system. This oil is drawn from the oil The compressors are started locally and once the compressor is running, speed
compressors (and heat exchangers) which are used for: reservoir tank by a pump and then fed to the bearing points via a filter and oil- control and monitoring is carried out from the CCR/ECR via the DCS system.
cooler unit. Excess oil is conveyed into the lubricating oil line by an overflow
The compression and heating of boil-off gas used as fuel for the valve which keeps pressure in the pipes at a constant level. Oil pressure will a) At the control panel, check the supply air pressure for the
boilers not exceed 1.8 to 2.5 bar at an oil supply temperature of 20º to 50ºC. governing and control air circuits. The air supplies should be 1.4
bar for the governor and 3.2 bar for the control. Ensure the LNG
The recirculation and heating of cargo vapour for heating the
Prelubrication and lubrication at the starting period is achieved by a small cooling water system is in operation (see section 5.3.1).
cargo tanks
turbine driven oil pump consisting of a vertical steam turbine and geared oil
The compression of vapour to be returned to the shore station pump directly coupled to the steam turbine. This geared oil pump provides the b) Check the level of lubricating oil in the reservoir tank. The level
when loading oil supply for the turbine and compressor until the mechanically driven main should be in the middle of the sight glass. Check the oil
gear oil pump is feeding oil. The pressure of the lubricating oil is monitored temperature. If it is below 10ºC, the oil heaters should be switched
The generation of cargo vapour and there is also an oil pressure shutdown trip which will stop the machine and on. The oil temperature should have risen above 10ºC before
start the turbine driven oil pump if the oil pressure drops below 1.2 bar. starting.
There is one low duty compressor, used for the gas supply to the boilers and
two high duty compressors, used for vapour return to the shore and for cargo The LD and two of the HD compressor turbines are supplied with saturated c) Close the steam control and emergency stop valve by turning the
tank heating. The compressors utilise a single stage centrifugal compressor steam from the secondary LP steam system. handwheel to the right, all the way to the end stop.
which is directly driven by a single stage axial impulse steam turbine.
Nitrogen is used as the seal gas for the compressors. Special shaft seals are d) Open the shut-off valve in the exhaust steam line and drain off
4.4.1 High Duty Compressors installed on the impeller side of the compressors. Labyrinth tips are cut into the any water which may have accumulated.
compressor shaft. Opposite the tips is a stuffing box, the tips cut into the
Maker: Airco Cryogenics artificial carbon stuffing. The stuffing box can be accurately adjusted to give e) Open the shut-off valve which is ahead of the steam control and
Type: Steam driven an extremely tight clearance resulting in very low losses. Two annular grooves emergency stop valve in the main steam line and drain off any
Capacity: 10,000m3/h are cut into the carbon sleeve and leakage gas is sucked off from the impeller water which may have accumulated.
No. of sets: 2 side annular groove and returned through a pipe connected to the suction side.
Suction temperature: -120ºC The sealing nitrogen is supplied into the second annular groove to provide a f) The automatic trip actuator should now be engaged by pulling on
Discharge temperature: -75ºC seal against leakage gas from the impeller side. On the turbine, a combined the trip handle.
Specific weight: 1.3kg/m3 radial and axial labyrinth seal shuts off the shaft passage (at the turbine casing)
Suction pressure: 1.05 bar to the outside. Vapour and leakage steam is led away by corresponding g) Read the cargo tank pressure and adjust the compressor suction
Pressure increase: 11,000mm WG (suction to discharge) connections. pressure set point locally at the control panel.
Discharge pressure: 2.15 bar
Each compressor has a local control panel with gauges fitted to show the h) Adjust the suction pressure transmitter (for suction pressure
Speed: 14,700 rpm
various pressures and temperatures relating to the machine operation. More control) to the minimum value. This means the nominal value for
Steam turbine output: 480kW
limited monitoring is available from the DCS system compressor mimics. the turbine speed controller is set to a minimum level.
The following conditions trip the HD compressors: Control of the compressor is achieved by regulating the turbine steam flow rate
i) Open the sealing gas supply valves. Ensure the sealing gas purge
The ESDS system to maintain the cargo tank pressure at a preset value. The suction pressure of
valves are closed.
the compressor is detected by a pressure transmitter and this signal, together
High differential pressure: void/tanks 1 - 5 with a speed signal, is sent to the compressor controller. The required suction
j) Open the main and exhaust steam shut-off valves and the
Low low pressure: tanks 1 - 5 pressure is set and the system then regulates the governor and guide vanes to
auxiliary oil pump will start. Drain off any water which may have
accurately control the compressor speed and output.
Compressor high outlet temperature accumulated. Turn the handwheel of the steam control valve
An anti-surge control system operates independently of the compressor slowly to the left until the end stop is reached.
Electrical power failure suction pressure control. This system monitors the pressure differential across
Compressor suction pressure low an orifice plate and the compressor pressure differential. According to the k) The operator should keep the oil pump in operation until the
measured value, the controller modulates a surge control valve returning gas bearing temperatures have reached a minimum of 20ºC. The
ESD close loop low pressure from the discharge side to the suction side of the compressor. This maintains impeller side compressor bearing temperature may fall below
the compressor in the safe operating region. 20ºC at standstill and therefore require particular attention.
Low or high temperature after heaters (aft or forward)
Monitor the oil pressure, it should be a minimum of 0.8 bar.
Overspeed (mechanical or electronic via DCS)
P2
CH4 -40OC
P1
Had(m)
P2
CH4 -120OC
P1
2,2
1,691 6963
2,1
1,0n = 14 7000u/min 1,05n
1,627 6389
6214 2,0
0,9n
1,48 5130 1,8
Surge Line
0,8n
1,375 4083 1,6
0,6n
1,19 2211 1,3
0,5n
1,13 1528 1,2
804 1,1
1,0
0 1000 2000 3000 4000 5000 6000 7000 8000 9000 10000 11000 12000 13000 14000 20000
INLET VOLUME FLOW m3/h
Discharge
Compressor Discharge TIALHC
Gas Temp. 99
Governor
TE
PT 78
79 PDCLA Diff. Press.
2 Tank/Atmos
Inlet PDT
Vane 75
PS TS Low LO Control
88 87 Shut
-down TIT
Switch TE
73 85
L.O. Pressure
Valve L.O. Temp.
/Pressure TI
L.O. Cooler Safety
Suction
Cooling Shut Down
Water Valve
Bypass
Control
Steam Shut-off Valve TI Press.
Valve
For Steam Driven Pump
PI PI PI PI PI PI
PDT 68 68 70 90 88 84
76
Steam L.O. PI PI TI SI
Pump Shaft Driven 71 79 85 74
L.O Pump
Steam
Compressor Local
LSS HC Stop
Lubricating Oil Compressor Panel
Instrumentation
Nitrogen
4.4.2 Low Duty Compressor c) Move the cursor to the CCR icon and press the ACT pushbutton q) Once the LD compressor is running under steady conditions
on the DCS panel to take control of the compressor. confirm that the engine room is ready to receive cargo vapour and
Maker: Airco Cryogenics transfer control to the ECR on the DCS screen.
Type: Steam driven d) On the compressor panel on the CCR console, turn the
Capacity: 3,000m3/h compressor speed controller back to 20%. r) Switch off the oil heaters if originally switched on. Open the
No. of sets: 1 cooling water valves to supply the oil cooler. The oil temperature
Suction temperature: -120ºC e) Crack open the steam to the vapour heater and set the steam at the cooler outlet should be 40 - 50ºC.
Discharge temperature: -75ºC control valve to 33ºC gas outlet temperature.
Specific weight: 1.3kg/m3 During operation, the oil and bearing temperatures should be monitored, the
Suction pressure: 1.05 bar (Note: It is important that the vapour heater is properly heated before gas is values should be as follows:
Discharge pressure: 1.95 bar allowed to pass through.)
Oil at cooler outlet: 60ºC
Speed: 18,200 rpm
f) Check the level of lubricating oil in the reservoir tank and for any Compressor bearing: 60ºC
This compressor is essentially for the compression and heating of the boil-off water present. The level should be in the middle of the sight glass.
Turbine bearing: 60ºC
gas when used as fuel for the ship’s boilers. The compressor is started locally Ensure that the oil temperature is above 10ºC before starting.
and can be monitored via the DCS system. The LD compressor is similar to the The turbine will trip at 65ºC.
HD compressors, being basically a lower capacity model. g) Open the steam chest drains on the turbine and drain off any water
which may have accumulated. The oil pressures should be monitored and should be as follows:
The following conditions trip the LD compressors:
Meanwhile the engine will be preparing for burning boil-off gas on free flow. Lubricating oil: 4.0 bar
The ESDS system
The turbine will trip at 65ºC.
High differential pressure: void/tanks 1 - 5 h) Open the turbine exhaust steam valve and the compressor
discharge valve.
Low low pressure: tanks 1 - 5 The oil filter flag should be monitored and the filter changed when the
differential pressure is 1.5 bar.
Compressor high outlet temperature i) Open the shut-off valve which is ahead of the steam control and
emergency stop valve in the main steam line and drain off any
Electrical power failure Local Compressor Stopping Procedure
water which may have accumulated.
Compressor suction pressure low
The operator must ensure that when the unit is stopped, the auxiliary LO pump
j) Open the exhaust and steam inlet valves to the auxiliary oil pump,
ESD closed loop low pressure must start as soon as the oil pressure drops below 1.2 bar and keep running
which will cause it to start. Once prelubrication has been achieved
until the compressor has come to a complete standstill.
Low or high temperature after heaters (aft or forward) and the oil pressure has reached 4.0 bar, the compressor may be
started.
Gas firing shutdown on port and starboard boilers a) Inform the engine room that the LD compressor is to be stopped.
The ECR will make arrangements for the boiler supply fuel to be
Fire alarm k) Open the SW cooling inlet and outlet valves to the LO cooler.
changed over.
Local Start-Up Procedure l) Adjust the control air pressure to the surge control valve to 4.5
When confirmation has been received from the engine room that the boilers are
bar, then crack open the steam valve to the turbine and allow the
The compressor is started locally. Operation after starting is carried out from now running on fuel oil transfer control to the CCR on the DCS mimic screen
turbine to warm through.
the cargo or engine control rooms, depending on which location has control. 5.21 Cargo Compressors.
The start-up procedure described is for the operations where the low duty m) After 10 minutes close the turbine drains.
compressor is required discharges vapour to the boilers, due to the pressure in b) Turn the handwheel of the steam control and emergency stop
the cargo tanks reaching 18mbar. valve to the right, all the way to the end position.
n) Open the surge control valve to the fully OPEN position.
a) Request the ECR to prepare for boil off gas burning/ c) On the compressor, close the valves in the suction and discharge
o) Fully open the steam inlet valve to the turbine and observe the
lines.
b) At the DCS mimic screen 5.21 Cargo Compressors, move the turbine speed increase and the green running light come on.
cursor over the Details area near the LD compressor and press the d) On the turbine, close the valves in the main steam and exhaust
ACT pushbutton on the DCS panel, to reveal which control room p) The automatic trip actuator should now be engaged by pulling on
steam lines.
has control. the trip handle.
e) Close the seal gas line and open the vent valve.
P2
CH4 -40OC
P1
Had(m)
P2
CH4 -120OC
P1
2,2
2,1
2,0
1,582 5940
1,9
1,05n
1,52 5400
1,0n = 18 200Rpm
1,8
Surge Line
1,7
1,313 1,5
3455
0,8n
1,4
1,23 2645 0,7n
1,3
1,116 1945 0,6n
1,2
1,114 1350 0,5n
1,1
1,0
0 1000 2000 3000 4000
INLET VOLUME FLOW m3/h
i) Close the main steam and exhaust steam valves, open the drain
valve.
The pressure of the lubricating oil is monitored by an oil pressure switch which
stops the machine and starts the auxiliary oil pump when the oil pressure drops
below l.2 bar. There is a dual oil filter to clean the oil and an oil cooler.
Compressor Shutdowns
Surge valve activated: I/O
Overspeed: 15,000 rpm
Lubricating oil pressure low: 3.6 bar
Lubricating oil temperature high: 65ºC
Low seal gas pressure: 0.2 bar
In addition, the DCS system will shutdown the compressor if any of the
following values are exceeded:
High outlet temperature: 100ºC
Suction pressure low: 0.0 bar
Low low cargo tank pressure tanks 1 - 5: 0.0 bar
High differential pressure void space/tank: 0.04 bar
ESD loop pressure low: 3.0 bar
Low gas temperature after LNG heater: -20ºC
High gas temperature after LNG heater: 70ºC (alarm at 60ºC)
Air To
Open
Positioner
VP 96
Manometer
Air To
PI Steam Control Valve
Open 98 V911A
Gas Inlet Control Valve C1
V2131 S
C2
Level
Controller
Air Pressure
Reducing Hand/ TIT96
Valve: 20 psi Auto HA96
Control Air Station
8.8 bar Remote Temperature
Temperature Indication DCS
V3025 Transmitter
Temperature
TC96 Controller
TIT TIAL TI V1033A
/Computing 96 HC99 99
PCV 96 Relay
Air Set with
Filter: 30 psi To Vent Mast Key
/Boilers/Tanks
Steam
Instrumentation
Panel Compressed Air
Condensate
Outlet Condensate
Instrumentation
/Control Air
4.5 Cargo Heaters When cargo is being used as fuel, the set point should be set to +45ºC. To Start Up the Heater
Heating the LNG vapour which is delivered by the HD If the gas outlet temperature reaches a high of +60ºC or a low of +5ºC, an h) Change over from MANUAL to AUTO at the hand/auto station.
compressors at the specified temperature for warming up the alarm is raised via the DCS system.
cargo tanks before gas freeing. i) Set the required temperature at the hand/auto station.
If the gas outlet temperature reaches a high of +70ºC or a low of -20ºC, the
Heating boil-off gas supplied to the main boilers via the LD steam supply to the heater is shut off. j) Monitor the gas vapour outlet and condensate temperatures.
compressor.
Operating Procedures To Warm Up the Cargo Heater To Shut Down the Heater
CAUTION
When returning heated vapour to the cargo tanks, the temperature at the a) Open the shell side vent valve. a) Switch the automatic control from AUTO to MANUAL. Set the
heater outlet should not exceed +85°C, to avoid possible damage to the manual signal to 50% at the hand/auto station.
cargo piping insulation and safety valves. b) Open the shell side condensate valves and check the drains.
b) Close the gas supply and outlet valves on the heater.
The vapour heaters are heat exchangers of the horizontal shell and tube type. c) Crack open the manual steam supply valve. Ensure that the steam
The heating surface consists of ‘U’ shaped tubes whose configuration is such to deck is available, ie the isolating valve is open. c) Close the steam supply valve to the heater when the temperature
that cargo vapour flows through the tubes and steam condenses outside the at the heater outlet is above 0°C.
tubes. The tube bundle and end cover are bolted to the shell to permit d) When all the air has been expelled from the shell, shut the vent
inspection or the plugging of damaged tubes, should this be required. valve. d) Open the steam side vent, then open the drain when all the steam
has vented.
CAUTION e) When water has been drained from the shell, shut the drain valve.
The vapour heaters should be thoroughly preheated by steam before the
admission of methane vapour. This prevents ice formation. After venting and warming up the heater, pressures and temperatures should
stabilise in approximately 30 minutes. Operation of the heater can now be
When shutting down the heaters, the methane vapour supply to the heaters initiated.
should be shut off before the steam supply, preventing any ice formation at the
end of the operation.
The heaters are pneumatically controlled. Methane supply to the vapour heater
is controlled by the cargo vapour temperature leaving the heater. This
temperature set point is adjustable.
V2037
TI
V2040A
Air to
PI 104 Open
PI V937A
Gas
Manometer
From
Vaporiser
B
Key
PI 103
V2122 PI Steam LNG Liquid
Manometer
LNG Vapour
Steam
V2135
Condensate
Vaporiser
Cargo Void Spaces Compressed Air
System /Atmospheric
Heater Control Air
/Instrumentation
LC 102
Level V1035A
Controller
The vaporiser’s main role is to vaporise liquid nitrogen and natural gas from There is a pneumatic level switch, LC102, mounted in the condensate receiver. d) Keep the vapour side valve open to the system until the vaporiser
the shore station before purging the cargo tanks, piping and void spaces. If the condensate level rises too high the steam valve is closed, shutting off reaches ambient temperature.
steam to the vaporiser. This action halts any increases in condensate water
Each vaporiser is a shell and tube type heat exchanger. The heating surface level which could lead to the formation of ice. Vaporiser Alarms and Trips
consists of straight tubes arranged so that cargo vapour flows through the tubes
Low condensate temperature alarm set point: +120°C
and steam condenses outside the tubes. The shell has a bellows arrangement to Operating Procedures
compensate for thermal contraction of the tubes in relation to the shell. The end Low low condensate temperature trip set point: +80°C
covers are welded to the tube sheets, but are flanged so that the tubes can be Set the LNG pipelines as detailed for the operation about to be undertaken.
Gas outlet high temperature (supply valve shuts): +30ºC
inspected or plugged on board the ship if required.
To prepare the LNG vaporiser for use: Gas outlet low temperature (supply valve shuts): -60ºC
The vaporiser is pneumatically controlled. The LNG supply to the vaporiser is
High condensate level alarm contact switch
controlled by the cargo vapour temperature leaving the heater. a) Open the shell side vent valve.
High high condensate level trip
The set point is adjustable. When used for nitrogen purging, the set point b) Crack open the shell side drain valve. Check that the condensate
drain valves are open. Local hand trip alarm
should be some degrees above the dew point of the tank atmosphere, the
suggested temperature is +20ºC. Common alarm trip alarm
c) Crack open the manual steam supply valve.
CAUTION
The vaporisers should be thoroughly preheated with steam before the d) When all air is expelled from the shell, shut the vent valve.
introduction of liquid. This protects the vaporiser. The bypass valve in the
steam inlet pipe should be used, if required. After approximately 30 minutes, when pressures and temperatures have
stabilised on the vaporiser:
Personnel should always be present when the vaporiser is put into operation,
in order to locally monitor the temperature in the steam exhaust line and the e) Slowly open the steam inlet manual valve to the fully open
cargo vapour outlet. There are no monitoring facilities on the DCS mimic page position.
for the vaporisers, the page is purely a vaporiser system piping diagram.
f) Open the instrument air supply to the vaporiser controls.
h) Fill up the vaporiser with liquid using manual control. Check all
flanges and joints for any signs of leakage.
i) When vapour is produced, switch the control for the liquid valve
to REMOTE and AUTOMATIC.
S S
S V2354A
PI V2350A
V2354B
To IG
Generator V2350
No.2 Fuel PI V2354B
System
Note: One of Two Inert Gas Plants
Poop Front Stbd
Regenerated
Water
Air From
Separator
Air Inlet Engine Room
V2355A V2355
Space
PI
TI TI 63
PHA
PHCO FCOA
PLA
Air Combustion Air PLCO THA TI
Air Cooler THCO Steam 64
Compressor
Scrubber Supply
(Roots Type)
PI
From/To
Fresh Water V452 PLA THA V344
Cooling PLCO THCO TI
System DPI
V451 PI 62 Steam Heated
LHA Dryer
LHCO
From No.2
IG Generator V2352 V2354
From
Bilge Eductor Fresh Water V2352 V2352A
System Circulating Pump V340 V340 Electrically
Water
V336 Inert Seal Heated Dryer
Gas
V336A Generator Test
To No.2 Point
Inert Gas
IG Generator PI Drain
Cooler
Inert Gas Plant Cooling Water Pump V335 Drain
(340m3/h at 5kg/cm2) V2353
V344 Refrigerant
Outlet
V330 V331 Refrigerant
Sea V329 PI Inlet Key
Chest To Central
LPG Plant Cooling Water Pump
FW Cooler Inert Gas Steam
(170m3/h at 5kg/cm2) To LPG Plant, R22 Refrigeration
Cargo Compressor Drain Compressor
Gaseous Nitrogen Sea Water
V407A
LO Coolers and
V407
Water Spray System
V341 PI Gas Oil Fresh Water
From Bilge System To Aft Peak Tank To Bilge System Condenser/Receiver
Air Instrument Air
S S
S V2354A
PI V2350A
V2354B
To IG
Generator V2350
No.2 Fuel PI V2354B
System
Note: One of Two Inert Gas Plants
Poop Front Stbd
Regenerated
Water
Air From
Separator
Air Inlet Engine Room
V2355A V2355
Space
PI
TI TI 63
PHA
PHCO FCOA
PLA
Air Combustion Air PLCO THA TI
Air Cooler THCO Steam 64
Compressor
Scrubber Supply
(Roots Type)
PI
From/To
Fresh Water V452 PLA THA V344
Cooling PLCO THCO TI
System DPI
V451 PI 62 Steam Heated
LHA Dryer
LHCO
From No.2
IG Generator V2352 V2354
From
Bilge Eductor Fresh Water V2352 V2352A
System Circulating Pump V340 V340 Electrically
Water
V336 Inert Seal Heated Dryer
Gas
V336A Generator Test
To No.2 Point
Inert Gas
IG Generator PI Drain
Cooler
Inert Gas Plant Cooling Water Pump V335 Drain
(340m3/h at 5kg/cm2) V2353
V344 Refrigerant
Outlet
V330 V331 Refrigerant
Sea V329 PI Inlet Key
Chest To Central
LPG Plant Cooling Water Pump
FW Cooler Inert Gas Steam
(170m3/h at 5kg/cm2) To LPG Plant, R22 Refrigeration
Cargo Compressor Drain Compressor
Gaseous Nitrogen Sea Water
V407A
LO Coolers and
V407
Water Spray System
V341 PI Gas Oil Fresh Water
From Bilge System To Aft Peak Tank To Bilge System Condenser/Receiver
Air Instrument Air
The gas system consists of the water separator, safety valve, constant pressure Sea water pressure before the cooling tower CONTROL AIR PRESSURE LOW: The control air pressure is too low
valve, two electro-pneumatically operated shut-off valves, an oxygen analyser,
Fresh water pressure in the burner chamber cooling jacket. Pilot and Main Burner Control
a refrigerated gas cooler and two desiccant dehumidifiers.
Plant Shutdowns The pilot burner is ignited from a glow plug which operates from a low voltage
The water separator is of the centrifugal type, where the water droplets are
transformer. The main flame is monitored by a photo-cell connected to an
separated and collected in the bottom of the separator. The water is fed out The following circumstances will cause an alarm and subsequent shutdown of electronic flame relay. This relay will shut down the main burner, via the main
through the cooling tower water seal. There is a pressure gauge and a safety the inert gas generator: programming unit, if the flame is too weak or has gone out. In the case of a
lifting valve on the gas outlet manifold. The constant pressure valve is fitted to
Burner chamber cooling jacket high water temperature flame failure, the RESET FLAME FAIL RELAY switch on the control panel
avoid pressure fluctuations in the combustion chamber. From here the gas is
must be activated to reset the flame relay and enable a new burner start
led by means of the shut-off valves to the atmosphere outlet or to the cargo High gas temperature after cooling tower sequence.
system, depending on the operator’s selection.
Sea water pressure low
The main programming unit controls the start and shutdown sequences of the
The shut-off valve in the pipe to the cargo system is fitted with an interlocking Fresh water pressure low burner and monitors all alarm and shutdown functions. The unit raises alarms
system. This interlock prevents the generator starting if the valve position is
Air pressure high or stops the plant if any levels exceed the set parameters. Incorrect O2 content
incorrect ie, gas to consumer.
of the combustion gas will cause an alarm to be raised and the gas will vent to
Burner failure atmosphere, when operating in the consumer mode. The TEST PROGRAM
Cooling Water System
pushbutton starts a self-test sequence of the programming unit.
Alarms
The cooling water system comprises both fresh water and sea water systems.
Control Panel Description
The fresh water used in the burner chamber cooling jacket is recirculated The system has alarm outputs to the SVC system but the alarm must also be
through the fresh water cooler by the fresh water pump. Sea water is used to accepted locally by pressing the STOP HORN pushbutton to silence the The control panel contains the following equipment:
cool the turning chamber walls and for cooling and cleaning the inert gas in the audible alarm and the STOP FLASH pushbutton to cancel the flashing lamp on
cooling tower. The water flow regulation is carried out via hand operated the alarm panel at the centre of the control panel. As well as the alarms Switch Function
valves. mentioned previously in plant shutdowns, there are the following alarms: MANUAL/NORMAL Selection of manual or automatic
Lamp Indicates OPERATION burner start
Monitoring
FLAME FAILURE: Burner flame is out or weak WATER CIRCULATION Water pumps start/stop
A flow meter is installed in the fuel oil system for the measurement of oil
HIGH AIR PRESSURE High air pressure after compressor AIR COMPRESSOR Air blower start/stop
consumption.
S S
S V2354A
PI V2350A
V2354B
To IG
Generator V2350
No.2 Fuel PI V2354B
System
Note: One of Two Inert Gas Plants
Poop Front Stbd
Regenerated
Water
Air From
Separator
Air Inlet Engine Room
V2355A V2355
Space
PI
TI TI 63
PHA
PHCO FCOA
PLA
Air Combustion Air PLCO THA TI
Air Cooler THCO Steam 64
Compressor
Scrubber Supply
(Roots Type)
PI
From/To
Fresh Water V452 PLA THA V344
Cooling PLCO THCO TI
System DPI
V451 PI 62 Steam Heated
LHA Dryer
LHCO
From No.2
IG Generator V2352 V2354
From
Bilge Eductor Fresh Water V2352 V2352A
System Circulating Pump V340 V340 Electrically
Water
V336 Inert Seal Heated Dryer
Gas
V336A Generator Test
To No.2 Point
Inert Gas
IG Generator PI Drain
Cooler
Inert Gas Plant Cooling Water Pump V335 Drain
(340m3/h at 5kg/cm2) V2353
V344 Refrigerant
Outlet
V330 V331 Refrigerant
Sea V329 PI Inlet Key
Chest To Central
LPG Plant Cooling Water Pump
FW Cooler Inert Gas Steam
(170m3/h at 5kg/cm2) To LPG Plant, R22 Refrigeration
Cargo Compressor Drain Compressor
Gaseous Nitrogen Sea Water
V407A
LO Coolers and
V407
Water Spray System
V341 PI Gas Oil Fresh Water
From Bilge System To Aft Peak Tank To Bilge System Condenser/Receiver
Air Instrument Air
Running Lamps Indication Function i) Check the water pressure to the cooling tower by observation of
a) Turn the TO ATMOSPHERE/TO CONSUMER switch to the TO
the SEA WATER PRES. pressure gauge; the pressure should be
MAIN SWITCH ON Main electrical isolator/power on ATMOSPHERE position. The valves will change over.
approximately 1-1.5kg/cm2. The inlet flow can be adjusted if
IGNITION Glow plug on necessary by means of the inlet valve V336. b) Turn the BURNER switch to position 0. The oil solenoid valve to
the burner will close and the program unit will reset, ready for a
AIR/OIL TO PILOT BURNER Pilot burner air/fuel oil valves open j) Check the gas pressure, the normal pressure should be new start if required.
LOW OIL Low fuel oil pressure approximately 0.2kg/cm2.
c) Turn the OIL PUMP switch to position 0 and the oil pump will
LOW AIR Low air pressure k) Ensure that the water level in the cooling tower is normal. stop. The operator should now wait approximately 1 minute for
OIL TO BURNER Burner fuel oil valve open the plant to cool down.
l) Check the fresh water pressure by observation of the FRESH
FLAME ESTABLISHED Flame is alight WATER PRES. pressure gauge; the pressure should be d) Turn the AIR COMPRESSOR switch to position 0 and the air
approximately 1.5-2kg/cm2. compressor will stop.
Switches (local running lamps) Function
WATER CIRCULATION Start/stop water circulation pumps m) Start the oil pump by turning the OIL PUMP switch to the I e) Turn the WATER CIRCULATION switch to position 0 and the
position. water pumps will stop.
AIR COMPRESSOR Start/stop air compressor
OIL PUMP Start/stop oil pump n) Check the oil pressure by observation of the OIL PRES. pressure f) Stop the inert gas cooler refrigeration compressor and isolate the
gauge; the pressure should be approximately 20-25kg/cm2. cooler.
S S
S V2354A
PI V2350A
V2354B
To IG
Generator V2350
No.2 Fuel PI V2354B
System
Note: One of Two Inert Gas Plants
Poop Front Stbd
Regenerated
Water
Air From
Separator
Air Inlet Engine Room
V2355A V2355
Space
PI
TI TI 63
PHA
PHCO FCOA
PLA
Air Combustion Air PLCO THA TI
Air Cooler THCO Steam 64
Compressor
Scrubber Supply
(Roots Type)
PI
From/To
Fresh Water V452 PLA THA V344
Cooling PLCO THCO TI
System DPI
V451 PI 62 Steam Heated
LHA Dryer
LHCO
From No.2
IG Generator V2352 V2354
From
Bilge Eductor Fresh Water V2352 V2352A
System Circulating Pump V340 V340 Electrically
Water
V336 Inert Seal Heated Dryer
Gas
V336A Generator Test
To No.2 Point
Inert Gas
IG Generator PI Drain
Cooler
Inert Gas Plant Cooling Water Pump V335 Drain
(340m3/h at 5kg/cm2) V2353
V344 Refrigerant
Outlet
V330 V331 Refrigerant
Sea V329 PI Inlet Key
Chest To Central
LPG Plant Cooling Water Pump
FW Cooler Inert Gas Steam
(170m3/h at 5kg/cm2) To LPG Plant, R22 Refrigeration
Cargo Compressor Drain Compressor
Gaseous Nitrogen Sea Water
V407A
LO Coolers and
V407
Water Spray System
V341 PI Gas Oil Fresh Water
From Bilge System To Aft Peak Tank To Bilge System Condenser/Receiver
Air Instrument Air
e) Check the alarm panel. The alarms LOW SEA WATER t) Turn the HIGH AIR/LOW AIR switch to the LOW AIR position. b) Turn the OIL TO BURNER switch to position 0. The operator
PRESSURE, HIGH TEMPS/LOW PRESSURE FRESH WATER should now wait approximately 1 minute for the plant to cool
and HIGH/LOW OXYGEN CONTENT will be on and can be u) Turn the OIL TO BURNER switch to position I. The burner down.
accepted. should start, check the flame through the sight glass on top of the
combustion chamber. c) Stop the oil pump by turning the OIL PUMP switch to the 0
f) Start the water pumps by turning the WATER CIRCULATION position.
switch ON. The sea water supply, fresh water and drain pumps (Note: The previous steps, r), s), t) and u) should preferably be carried out
will start. The fresh and sea water pressure alarms are cancelled. swiftly, ie, with only 1 or 2 seconds between each step.) d) Turn the AIR COMPRESSOR switch to position 0 and the air
compressor will stop.
g) Start the air blower by turning the AIR COMPRESSOR switch to v) If burner ignition has not taken place within 4 seconds of the OIL
the I position. TO BURNER switch being turned on, the switch must be turned e) Stop the inert gas cooler refrigeration compressor and isolate the
back to position 0, in order to stop the oil supply. The operator cooler.
h) Check the air pressure at the gauge. Normal pressure should be should investigate the cause of the burner not firing or try again
approximately 0.5-0.7kg/cm2. after waiting for approximately 1 minute for the chamber to f) Stop and isolate the dehumidifier dryers.
purge.
i) Check the water pressure to the cooling tower by observation of g) Turn the WATER CIRCULATION switch to position 0 and the
the SEA WATER PRES. pressure gauge, the pressure should be w) If normal ignition has taken place, the operator should wait for a water pumps will stop.
approximately 1-1.5kg/cm2. The inlet flow can be adjusted if period of 10 seconds and then turn the HIGH AIR/LOW AIR
necessary by means of the inlet valve V336. switch to the HIGH AIR position and the HIGH OIL/LOW OIL h) Turn the MAIN SWITCH (power) OFF.
switch to the HIGH OIL position.
j) Check the gas pressure; the normal pressure should be Changeover Between Atmosphere and Consumer
approximately 0.2kg/cm2. x) Turn the AIR/OIL TO PILOT BURNER switch to position 0. The
pilot burner will be extinguished. The inert gas can be led either to atmosphere or to the consumer (cargo system)
k) Ensure that the water level in the cooling tower is normal. by this switch. The plant must be started with the switch in the TO
y) Check the oil consumption via the flow meter, the normal ATMOSPHERE position, due to an interlock on the consumer valve.
l) Check the fresh water pressure by observation of the FRESH consumption is approximately 210kg/h.
WATER PRES. pressure gauge; the pressure should be When the O2 content is within limits, the switch is turned to the TO
approximately 1.5-2kg/cm2. z) Check that the O2 analyser is functioning and that the O2 content CONSUMER position and inert gas is led to the cargo tanks. The gas will
of the gas is within limits for use in the cargo system. The O2 automatically be led to atmosphere if the O2 content is above or below the
m) Start the oil pump by turning the OIL PUMP switch to the I content can be adjusted using the valve adjacent to the pressure limits. The changing over is delayed by a time delay relay in connection with
position. gauges. the O2 alarm.
S S
S V2354A
PI V2350A
V2354B
To IG
Generator V2350
No.2 Fuel PI V2354B
System
Note: One of Two Inert Gas Plants
Poop Front Stbd
Regenerated
Water
Air From
Separator
Air Inlet Engine Room
V2355A V2355
Space
PI
TI TI 63
PHA
PHCO FCOA
PLA
Air Combustion Air PLCO THA TI
Air Cooler THCO Steam 64
Compressor
Scrubber Supply
(Roots Type)
PI
From/To
Fresh Water V452 PLA THA V344
Cooling PLCO THCO TI
System DPI
V451 PI 62 Steam Heated
LHA Dryer
LHCO
From No.2
IG Generator V2352 V2354
From
Bilge Eductor Fresh Water V2352 V2352A
System Circulating Pump V340 V340 Electrically
Water
V336 Inert Seal Heated Dryer
Gas
V336A Generator Test
To No.2 Point
Inert Gas
IG Generator PI Drain
Cooler
Inert Gas Plant Cooling Water Pump V335 Drain
(340m3/h at 5kg/cm2) V2353
V344 Refrigerant
Outlet
V330 V331 Refrigerant
Sea V329 PI Inlet Key
Chest To Central
LPG Plant Cooling Water Pump
FW Cooler Inert Gas Steam
(170m3/h at 5kg/cm2) To LPG Plant, R22 Refrigeration
Cargo Compressor Drain Compressor
Gaseous Nitrogen Sea Water
V407A
LO Coolers and
V407
Water Spray System
V341 PI Gas Oil Fresh Water
From Bilge System To Aft Peak Tank To Bilge System Condenser/Receiver
Air Instrument Air
O2 Analyser This compressor can supply refrigerant to the air conditioning system as well
as the inert gas cooler.
Maker: Servomex
Dehumidifier Dryers
Type: 264A xendos 1800
Funnel Rotor Unit Regeneration
Range: 0 - 25% oxygen Adjusting Wet Air
Heater
Maker: Alfsen og Gunderson AS Wet Air
Damper Fan
(Steam/Elec.)
The analyser is a microprocessor-based electronics unit for the continuous Flow rate: 2,500m3/h 2500m3/h
monitoring of the oxygen levels in the inert gas generator outlet. Type: AG-SR-122E (electrically heated)
Type: AG-SR-122S (steam heated)
The gas sample continuously flows through the analyser sensor because of the No. of sets: 2 Regenerated Air 5oC
2500m3/h
higher pressure in the inert gas system. This ensures that the oxygen content is
continuously measured. The analyser has a 4-20mA output signal which is There are two dehumidifier dryers fitted to the inert gas outlet. One is heated Inert Gas Bypass
Cooler
proportional to the oxygen content and this signal is the input signal to the O2 with steam and the other with electrically powered heaters. The air dryers start
automatically when the inert gas generator is started.
indicator on the control panel. Adjustment of the alarm set points can be made From
V2352 Dry Air
2500m3/h
via the membrane keys on the unit front. Inert Gas
The dehumidifiers consist of an inlet air filter, preheater, silica gel rotor, wet Generator Filter Pre-heater
Rich O2 Outlet AI
140
440V 60Hz AI HC
Tah
Electrical Supply 140 130
120
Tah
120 XA AAh/hh AS AE PIC
Common TS 140 140 140 140 130
Fault SVC 120
XA PIC AT HC
120 140 131
FI
PdAH PdAH DCS
FEED AIR COMPRESSOR 140
104 106
Control Panel 147-1 148-1
PdS PdS PI
PI
104 106 TT 157 TI 109
113 N2
120 120 142-1 Membranes
142-2 141 M
M After Cooler Cooler
Oil 147-2 148-2 FCV
Separator 130
V9B
110 111 112
S
LA PAI
Oil Cooler
PS
S AD4B 119
DCS
PI
150
PAI
From GS 150
Air System
PS
N2 To Atmosphere
150
Operating Panel
PT
KVAERNER - MEDAL DCS 150
NITROGEN GENERATOR
142-3
Nitrogen To Consumers
Buffer Tank (See Illustration 4.7.2b)
165 160 161
3581104 h
SELECT
REMOTE
LAMP Nitrogen
TEST
Key
START
BUFFE Start/Stop Buffer Tank
System
ALARM
Gaseous Nitrogen START ACCEPT 1 2 - +
Electrical Signal
PAI
Pd/Ah
PRESSURE
-
PRESSURE
-
ALARM LOW
DIFF. ALARM HIGH PS
YA COMMON
- ALARM
HC HAND OPERATED CONTROLLER
4.7.2 Nitrogen Generator This vessel is arranged geometrically, in the same way as a shell and tube heat
exchanger. As the air flows along the bore of the fibres, O2, CO2 and H2O
Maker: Kvaerner - Medal (vapour) contained in the air permeate faster than N2 (Nitrogen) to the low
Type: Membrane pressure side of the fibres. The air in the bore is gradually depleted of the fast
Capacity: 21Nm3/h at 5bar and 5% O2 permeating gases and becomes nitrogen enriched.
Oxygen Meter The air flow rate through the membrane module can be adjusted to obtain
Maker: Teledyne different levels of nitrogen purity.
Range: 0-10% O2
Description of System Operation
Feed Compressor
Maker: Kaeser The compressed air from the air feed compressor is fed to the nitrogen
Type: SM 11 Oil lubricated screw fresh water cooled generator inlet and firstly passes through a series of three automatic filters.
Capacity: 50Nm3/h at 8 bar These protect the membranes from any harmful solid particles and also from
Motor: 7.5Kw any oil and water present in the air. These filters have automatic drains.
Nitrogen is used on the vessel for the following purposes: The air then passes through a 1kW electric heater which will heat the air to
approximately 50ºC, which is the optimal temperature for the design capacity.
As a sealing gas for the cargo compressor glands
Purging the gas fuel line and boiler gas burner manifold The heated air is now fed via a manifold to each individual membrane
separator. The permeated gases such as the O2, CO2 and H2O (vapour) are
Inerting and gas freeing of the level indicators vented off to atmosphere and the nitrogen leaves the membrane. The nitrogen
Bleeding to the cargo tank wedge spaces is then collected in a manifold and passes through a flow control valve. By
adjusting the flow with this valve the nitrogen purity will be adjusted, as the
Nitrogen vapour is bled into the wedge space and into the upper insulation longer the air is in the membrane system, the higher the purity (Refer to the
space at the top of the tank via valve V2209, from the nitrogen generator. The manufacturer’s manual for further in-depth information). If the nitrogen purity
nitrogen vapour then flows down along the surface of the tank shell to a is out of the set specification it will dump the product to atmosphere. The
drainpipe. The nitrogen vapour and any LNG leakage gas is exhausted into the variable area flow meter is installed at this point to allow the operator to
void space where it mixes with the dry air atmosphere in this space. monitor the nitrogen flow.
The generator is fitted in the starboard side of the aft store on the first platform The generator is equipped with an oxygen analyser to continuously monitor the
level of the engine room and the feed air compressor is fitted next to the GS oxygen content in the product nitrogen. Should the oxygen content rise, an
compressors, also on the first platform level. alarm will be initiated. If the oxygen content continues to rise, a second alarm
(oxygen content high high) will be initiated and the delivery valve will close
Principle of Operation and the dump valve will open. When the oxygen content has fallen to the limits
within the set parameters, the dump valve will close and the delivery valve will
The generator uses a membrane system to produce nitrogen. The principle of open.
the membrane’s operation is selective permeation. Each gas has a characteristic
permeation rate which is a function of its ability to dissolve and diffuse through The nitrogen is then fed to the N2 buffer tanks on deck. The feed pipe to the
a membrane. This characteristic allows a gas like oxygen, which dissolves and tanks is fitted with pressure switches which control the start and stop of the
diffuses at a fast rate, to be separated from a gas like nitrogen which dissolves generator.
and diffuses at a much slower rate.
Normal Operation
The key components of the generator are the membrane modules. Each module
contains many hollow fibre membranes to achieve the maximum membrane The generator is completely automatic in its operation and once set up will
surface per unit of volume. Compressed air is fed to the bore side of the hollow require little operator intervention.
fibre bundles enclosed in the pressure vessel.
The system is started from the main control panel, after setting the compressors
to standby mode.
Vent Vent
Mast at Tank No.5 Mast at Tank No.4
Double Poop
Pipe Front Boil-Off Gas Supply
From LD Compressor Cargo Heaters
V2140A V2140 S2140 /Cargo Heaters
V2226
V2228
Wedge Space Wedge Space Wedge Space Wedge Space Wedge Space
V2228 V2228
Key
If the GS compressor is required to supply the feed air, press the SELECT
SERVICE AIR pushbutton and the Service Air Inlet Valve indicator lamp will
light. Otherwise the nitrogen generator’s feed air compressor will supply the
necessary air.
When the buffer tanks reach 1.95 bar, production is vented to atmosphere for
10 minutes and then the generator will stop. The Select Consumer light will
start flashing. If during the 10 minutes the pressure in the buffer tank drops by
0.15 bar, the consumer valve will open and the vent valve will close.
The generator will start automatically when the buffer tank pressure falls to
1.49 bar.
During normal operation, the system and compressor will cut in and out under
the control of the line pressure switches. The compressor will run off load for
a certain time before it stops.
Alarms
Any alarm activates the alarm horn and a flashing red lamp on the panel. A
remote alarm is raised via the DCS system.
From Tank 1
Void Space
V2306
To Tank 1
From Tanks Void Space
2 - 5 Void Recirculation Fans: Top of LNG Compressor Room Suction
Spaces
V2310 V2310
V2303
To Tanks
2-5
Void Space
Void Space
Recirculation Fans
2,000m3/h
V2316
V2311 V2311
V2135
System Description
The available cold temperature in the boil-off vapour is used for drying the
void space atmosphere. Drying is carried out in two heat exchangers of the
shell and tube type in which cargo vapour flows through the tubes.
Moisture in the void space atmosphere will condense outside the tubes and
then freeze to ice. The ice formation will reduce the heat exchange within the
dryer. When the temperature of the void space atmosphere coming out from the
dryer is higher than -50ºC, regeneration is necessary.
The supply of void space atmosphere and cold cargo vapour is shut off and
heated cargo vapour is introduced through the tubes. The ice will now melt and
the water is drained off through a drain pipe.
The dryers are used one at a time. When one is in service, the other is
regenerated. After the flow has passed the dryer, it will be heated to
approximately 30ºC in the steam heater.
LNG/C ''NORMAN LADY'' HOEGH FLEET SERVICES A.S. LNG/C ''NORMAN LADY'' HOEGH FLEET SERVICES A.S.
PLACE: Lake Charles TIME: 18:02 UTC PLACE: Lake Charles TIME: 18:02 UTC
VOYAGE NUMBER: RY-0903 Tank 1 Tank 2 Tank 3 Tank 4 Tank 5 VOYAGE NUMBER: RY-0903 Tank 1 Tank 2 Tank 3 Tank 4 Tank 5
Product LNG Product LNG
Tank Vol. 100% in m3 15556.275 18953.232 18979.546 18950.408 15555.498 Tank Vol. 100% in m3 15556.275 18953.232 18979.546 18950.408 15555.498
Level Reading 1 in meter 27.928 30.215 30.237 30.618 28.145 Level Reading 1 in meter 0.303 0.387 0.441 5.054 0.335
Level Reading 2 in meter 27.928 30.215 30.237 30.618 28.145 Level Reading 2 in meter 0.303 0.387 0.441 5.054 0.335
Level Reading 3 in meter 27.928 30.215 30.237 30.618 28.145 Level Reading 3 in meter 0.303 0.387 0.441 5.054 0.335
Level Reading Average in meter 27.928 30.215 30.237 30.618 28.145 Level Reading Average in meter 0.303 0.387 0.441 5.054 0.335
Specific Gravity Correction in meter 0.009 0.009 0.009 0.009 0.009 Specific Gravity Correction in meter 0.009 0.009 0.009 0.009 0.009
Tape Correction in meter -0.004 -0.004 -0.004 -0.004 -0.004 Tape Correction in meter -0.034 -0.038 -0.038 -0.034 -0.034
Trim Correction in meter 0.001 0.001 0.001 0.001 0.001 Trim Correction in meter 0.002 0.002 0.002 0.002 0.002
List Correction in meter 0.000 0.000 0.000 0.000 0.000 List Correction in meter 0.000 0.000 0.000 0.000 0.000
Corrected Liquid Level in meter 27.934 30.221 30.243 30.625 28.151 Corrected Liquid Level in meter 0.280 0.360 8.832 5.031 0.312
Liquid Volume m3 15148.087 18554.471 18578.762 18653.215 15188.909 Liquid Volume m3 3.803 6.688 18578.762 1181.784 4.701
Thermal Factor Liquid 0.99500 0.99500 0.99500 0.99500 0.99500 Thermal Factor Liquid 0.99499 0.99499 0.99499 0.99499 0.99499
Correction Volume m3 15072.347 18461.698 18485.868 18559.949 15112.964 Correction Volume m3 3.784 6.654 8.788 1175.863 4.677
Temperatures Vapor -138.9 -137.0 -140.9 -147.0 -137.4 Temperatures Vapor -159.5 -159.4 -159.3 -159.7 -159.5
Average Temp. Vapor All Tanks -140.2 Average Temp. Vapor All Tanks -159.5
Temperature Liquid mid 1 -159.2 -159.1 -159.2 -159.1 -159.3 Temperature Liquid mid 1 -88.3 -97.0 -103.6 -112.3 -90.6
Temperature Liquid mid 2 -159.2 -159.2 -159.2 -159.1 -159.2 Temperature Liquid mid 2 -144.5 -147.8 -148.8 -151.2 -145.7
Temperature Liquid bottom -159.2 -159.1 -159.2 -159.1 -159.3 Temperature Liquid bottom -144.5 -147.8 -148.8 -151.3 -145.8
Temperature Liquid Av. Each Tank -159.2 -159.1 -159.2 -159.1 -159.3 Temperature Liquid Av. Each Tank -125.8 -130.9 -133.7 -138.3 -127.4
Temperature Liquid Av. All Tanks -159.2 Temperature Liquid Av. All Tanks -131.2
Tank Pressure 0.150 0.150 0.151 0.148 0.149 Tank Pressure 0.139 0.139 0.139 0.138 0.138
Tank Pressure x 980,662 0.150 146.7 mmHG: 909.5 Tank Pressure x 980,662 0.139 135.9 mmHG: 900.2
Corr. Volume Ambient Temp 29.0 C Corr. Volume Ambient Temp 33.0 C
Quantity on Board: ON ARRIVAL Ships Figure 85692.827 Density 430.103 t/m3 Quantity on Board: ON ARRIVAL Ships Figure 85692.827 Density 430.103 t/m3
Quantity on Board: Atm. Pressure 1017 Quantity on Board: ON DEPARTURE 1199.767 Atm. Pressure 1019
Survey Figure 85692.827 mmHG. 762.811 Quantity: DISCHARGED 84493.060 mmHG. 764.311
Diff. Survey Fig. - Ships Fig. 0.000 (mb x 0.75006 = mmHG) Survey Figure 84493.060
Diff. Survey and Ships Figure 0.000 (mb x 0.75006 = mmHG)
4.8 Custody Transfer System signal which varies according to the pressure in the tank.
4.8.1 Custody Transfer System (CTS) Independent Very High Level Alarm System
Two high level alarms per tank are provided by independent point sensing
Level Measurement elements. Float sensors inside the cargo tanks detect the cargo at predetermined
The level measurement system consists of a microwave horn antenna and a levels (see section 4.1.3, High Level and Overfill Alarm System).
transmitter/receiver mounted inside a 50mm pipe mounted in the tank central
column which extends over the full depth in which the level is to be measured.
The liquid level is determined by measuring the time taken for a transmitted
signal to travel to and from the liquid level surface. The time taken is measured
and converted into a distance measurement (the ullage). The values for the size
and shape of the tank are stored in the signal processing unit and so the system
can calculate the exact contents of the tank. The system also employs time-
averaging techniques to balance out the effects of liquid movement.
Cargo tank gauging is via the transmitter on the Whessoe gauge. The speed of
the radar signal travelling (propagating) within the tank is influenced by the
varying vapour densities and temperatures. To compensate for this the system
automatically compares results to previously measured pipe joint signatures
and calibrates the system accordingly. This ensures the accurate measurement
of contents independent of tank conditions. This automatic calibration means
that no separate mechanical operations are required to verify the accuracy of
the system.
Temperature Measurement
The sensors are wired with four conductors (four wire cable) and all
terminations are sealed. There are spare sensors mounted in the tanks to
provide a degree of redundancy.
Pressure Measurement
Handle To Raise
The Float
Cushion Spring
Nitrogen Purge
Connection
Inspection Hatch
Spherical Float
Open Save Print Stab Stress Comp D Surv Crg Sat L Sum D Sum Onl Exit
Flow Innage con. Volume Volume Temp. Weight Obs. dens. FSM Max Volume LCG TCG
Code Compartment name Cargo Type
(m3/h) (m) (%) (m3) ( C) (t air) (t/m3 air) (tm) (m3) (m) (m)
C1 NO 1 CARGO TANK Default Cargo 0.00 0.000 0.0 0.0 15.00 0.0 0.9989 0 15556.3 0.00 0.00
C2 NO 2 CARGO TANK Default Cargo 0.00 0.000 0.0 0.0 15.00 0.0 0.9989 0 18953.2 0.00 0.00
C3 NO 3 CARGO TANK Default Cargo 0.00 0.000 0.0 0.0 15.00 0.0 0.9989 0 18979.6 0.00 0.00
C4 NO 4 CARGO TANK Default Cargo 0.00 0.000 0.0 0.0 15.00 0.0 0.9989 0 18950.4 0.00 0.00
C5 NO 5 CARGO TANK Default Cargo 0.00 0.000 0.0 0.0 15.00 0.0 0.9989 0 15555.5 0.00 0.00
Cargo 0.0% Ballast 0.0% Fuel Oil 0.0% Diesel Oil 0.0% Lub. Oil 0.0% Fresh Water 0.0% Misc. 0.0% Dry 0 ton
Intact Stability X
X Longitudinal Strength - SEAGOING CONDITION X
X
WARNING: Max GZ deq: IS OUT OF LIMIT Max BM: 159703 tm at 99.54 m from AP Max SF: 2989 t at 36.60 m from AP
-4 -100
-200
-8
Displ 14.59 ton SEAGOING CONDITION D fwd 1.97 m Trim 3.42 m aft KG 14.59 m
DW 14.59 ton Max SF % 71 Max BM % 80 D mid 3.63 m Heel 0.0 S.S GM 18.78 m
3
Swd 14.59 ton/W D aft 5.43 m
4.8.3 Loading Computer During cargo operations the Loadmaster program constantly upgrades the Displaying accumulated weights for the subtotal categories
information. Prior to or during cargo operations the operator can check, using
Maker: Kockumation AB manual inputs, that the sequence of loading or discharge will always remain Use the horizontal scroll bar to see remaining field in the load types screen.
Program: Loadmaster within the acceptable limits.
Definition of Load Types
General The Loadmaster program is run from Windows and as such is accessed via the
Windows menu bar at the top of the screen. In addition to the menu bar there
Load type is a description of the current load based on information from the
The Loadmaster program is computerised system for planning and evaluating are two fixed display areas, the results bar and status bar (which cannot be
trim and stability book. Several common load types are predefined. The
ship loading and discharge. It quickly calculates ship stability and stress changed or hidden).
operator can define additional ones by using the load types codes A-D.
characteristics based on any loading condition specified by the user.
The results bar provides information on the current loading condition. This bar
The following values are associated with each load type:
The program is developed from the technical information supplied by the is always visible on the far right hand side of the main window and is
builders that reflects the physical characteristics of the ship. The information continuously updated to reflect any changes in the loading condition.
Upper Part of the Screen
includes the following data:
The status bar is a single text line located at the bottom of the main window.
Principal particulars Code: The code is used in the cargo load that should be used in the
The program uses this space to display messages about the current status and
system to link a certain load type to each tank space
Operating lightship warnings about data entry.
Load line data Name: For the operator’s easy identification of the load type
In addition to the above there is the workspace, the area of the screen where
Draught mark locations the different views of the load condition are displayed.
Load category:
Visibility restriction data General Program Operation Predefined short name for load category
Hydrostatic tables LIQ for density input
Cross curves of stability Main Menu Bar
OIL1 - OIL5 for density vac 15C/API 60ºF inputs
The layout of the main menu bar follows Windows conventions. The File,
Bonjean tables Windows and Help items all provide selections consistent with other Windows For load category LIQ
programs.
Required GM curve
Density: Current density value for the cargo
Capacity tables Procedure to Operate the Loadmaster
Variable centre/free surface tables For load category OIL1 - OIL5
To Work with Load Types
Lightship weight distribution API 60F: API value for liquid at 60ºF
Allowable bending moments and shear forces In this part all the load types that should be used in the system are prepared. Dens vac 15C: Density value for liquid in a vacuum at 15ºC
Every tank, cargo compartment/position, store position etc. must have a load
The program allows for the loading condition information to be stored to disk. type assigned to it. This assignment is done in the screens where its possible to Lower Part of the Screen
These stored conditions can be recalled at any time for modification or re- enter the weight, for example cargo tanks and Misc Tanks screens. For tanks,
evaluation. In addition stored loading conditions can be sent ashore for review density values are defined per load type. Sub total: Define to which subtotal category the weight shall be
on a shore based computer. summarised
Procedure to Access the Load Type Screen
The Loadmaster system is an on-line stand alone computer with a direct Density: Relevant only when the load load category has been set to
interface to the various tank and draught gauge systems and is linked to the a) Place the cursor on the load type key area and click the left mouse liquid
vessel’s DCS system. The Loadmaster system automatically reads the gauge button.
system data at specified intervals and calculates all the tank and vessel Weight: Summary of the weight for the tanks and other cargo positions
characteristics. It is possible to vary the time of each update from 1 minute b) Press the F1 function key. with this load type
intervals to 30 minutes. Volume: Summary of the loaded volume for tanks with this load type
It is possible to work with following items in the load types screen.
Determination of load/discharge rates and projections of time to finish are Max Volume: Maximum available volume in tanks with this load type
possible. Defining densities for the various loads
Open Save Print Stab Stress Comp D Surv Crg Sat L Sum D Sum Onl Exit
Flow Innage con. Volume Volume Temp. Weight Obs. dens. FSM Max Volume LCG TCG
Code Compartment name Cargo Type
(m3/h) (m) (%) (m3) ( C) (t air) (t/m3 air) (tm) (m3) (m) (m)
C1 NO 1 CARGO TANK Default Cargo 0.00 0.000 0.0 0.0 15.00 0.0 0.9989 0 15556.3 0.00 0.00
C2 NO 2 CARGO TANK Default Cargo 0.00 0.000 0.0 0.0 15.00 0.0 0.9989 0 18953.2 0.00 0.00
C3 NO 3 CARGO TANK Default Cargo 0.00 0.000 0.0 0.0 15.00 0.0 0.9989 0 18979.6 0.00 0.00
C4 NO 4 CARGO TANK Default Cargo 0.00 0.000 0.0 0.0 15.00 0.0 0.9989 0 18950.4 0.00 0.00
C5 NO 5 CARGO TANK Default Cargo 0.00 0.000 0.0 0.0 15.00 0.0 0.9989 0 15555.5 0.00 0.00
Cargo 0.0% Ballast 0.0% Fuel Oil 0.0% Diesel Oil 0.0% Lub. Oil 0.0% Fresh Water 0.0% Misc. 0.0% Dry 0 ton
Intact Stability X
X Longitudinal Strength - SEAGOING CONDITION X
X
WARNING: Max GZ deq: IS OUT OF LIMIT Max BM: 159703 tm at 99.54 m from AP Max SF: 2989 t at 36.60 m from AP
-4 -100
-200
-8
Displ 14.59 ton SEAGOING CONDITION D fwd 1.97 m Trim 3.42 m aft KG 14.59 m
DW 14.59 ton Max SF % 71 Max BM % 80 D mid 3.63 m Heel 0.0 S.S GM 18.78 m
3
Swd 14.59 ton/W D aft 5.43 m
Weight, Volume, The operator can choose to enter any of these values Man-tk: To disconnect a specified compartment from online Tanks changed to manual input will be indicated with M and not be updated by
Ullage, Sounding, and the others will be calculated with reference to environment tank radar system.
Percent fill: entered value.
Defaul: Reset to predefined value for KG, FS or TCG after a manual The online load condition may be copied to the offline mode via the store
KG, TCG, LCG, FS: These values are displayed from predefined curves modification condition in online and the fetch condition in offline. The copy procedure can
(KG and FS) or as fix values(TCG and LCG), but can also be performed in the other direction from offline to online.
manually be changed by the operator. Repor: To create a Condition Report
Online Gauging
Operating Procedure Print: To print different Reports
The loadmaster online loading calculation program allows level, temperatures,
Define the content in each tanks as follows. Error Messages level rate and density values supplied by tank radar system to be collected.
a) Position the cursor in the highlighted field Weight, Volume, Error messages are displayed in the bottom line of the screen. To confirm that Online values may be entered manually in the event of a sensor failure.
Percent Fill or level (sounding or ullage). a message has been read, press the ESC key.
Sensor errors are indicated with a red letter :
b) Enter the current value.The condition is calculated after each Loadmaster Online to the Tank Radar
entry. L = Online level not available
The Loadmaster has two working modes, online and offline. They should be
To modify the predefined values for KG, FS, TCG or LCG. D = Online density not available
seen as two separate working areas that are totally independent of one another.
a) Position the cursor in the field which needs to be modified. T = Online temperature not available
In the ONLINE mode, all the online tanks are updated automatically or at the
operator’s request, but in the OFFLINE mode each input must be made
b) Enter desired value and press ENTER. The background colour A = More then one of the above mentioned error indications
manually.
will change when the cursor is moved to a new position.
Data exchange between the two working modes is performed via the Stored
To change to the predefined value for KG, FS, TCG or LCG after a manual No online updating is then performed.
Condition screen. In the current mode the present condition is stored and it can
modification. be accessed in the other mode.
From the measured levels and keyboard input, the Loadmaster program is
a) Position the cursor in the field which needs to be predefined. This continuously calculating stresses and stability.
(Note: When operating in OFFLINE, the program is still collecting data e.g.
field will have a coloured background. levels in the background. If any warning limits are exceeded an alert message
(Note: The levels collected from the tank radar system are corrected for trim
will be issued to the operator even though the program is working in OFFLINE
b) Place the cursor on the Defaul key area and click on the mouse and list. Therefore it is of great importance that all items which are not gauged
mode.)
left button or use SHIFT + F6. are entered manually in a corrected way.)
Working with inputs are described on the previous pages.
(Note: The online temperatures displayed are used in the calculations. For
correct weight calculations it is important to make a correct keyboard input
Online Supervision
into the LOADTYPE screen, to define a correct API/density for the tanks that
do not have density or/and temperature online.)
Screens and commands are similar to those in the offline mode.
Online temperature information. b) Place the cursor on the Defaul key area and click on the left
This screen displays the contents in all the tanks and the complete condition is
mouse button or use SHIFT + F6.
calculated after each entry.
Procedure for a Manual Request to Update the Tank Radar Values
The following command keys are available.
Some of the values displayed for each tank are:
a) Place the cursor on the ONLUPD key area.
Defaul: To obtain a predefined (=default) value back for the selected
b) Press the mouse left button or press CTRL + F3 to update all Name: Name of tank KG, FS or TCG, whichever is selected.
online values.
Load Type Code: Refer to the Load Type picture for finding the code on Repor: To create a condition report.
Procedure to Toggle Between the Manual or Online Input for each the Load Type with the properties of the content in
Compartment. tank. Print: To print different reports.
a) Change to a MANUAL input. Density: The value for density associated to the selected load Error Messages
type code will be displayed. This value may be
b) Place the cursor into the level, weight, volume, density or overwritten by the operator. Error messages are displayed in the bottom line of the screen. To confirm that
temperature field to prepare for a status change. The level, weight a message has been read, press the ESC key.
and volume fields are the same tank radar input.
Weight, Volume, The operator can choose to enter any of these values
Stability
Ullage, Sounding, and the others will be calculated with reference to
c) Place the cursor on the MAN-TK key area (manual input for the
Percent fill: entered value.
above chosen tank value) and press the left mouse button or press This picture shows the GZ-curve, analysis of the curve and GZ-table.
CTRL + F5.
KG, TCG, LCG, FS: These values are stored as curves (KG and FS) or as
No entries are possible in this picture.
fixed values(TCG and LCG), but may be overwritten
This will disconnect the online input for the current item. A yellow letter will
by the operator.
appear in the second column to indicate that the current values are based on Stress Bars
manual input. L = level, weight or volume, D = density, T = temperature, M =
Operating Procedures
more than one of L, D or T are closed for a manual input. The calculated shear forces and bending moments are displayed in tabular
form. The shear forces and bending moments as a percentage of allowed limits
To define the contents in the tanks
d) Enter a suitable value. are also displayed as bars. The shear forces and bending moments as a
percentage are also displayed as curves in the stress curve screen.
For each tank
e) Change to online input.
(Note: There are different colours for shear forces and bending moments in the
a) Position the cursor in the highlighted field, Weight or Volume or
f) Place the cursor in the level, weight, volume, density or bar graph, blue = bending moments, red = shear forces.)
Percent Fill or level (sounding or ullage).
temperature field to prepare for a status change. The level, weight
and volume fields are the same tank radar input. The locations at which the stress is calculated are prescribed by the
b) Enter the value. The condition is calculated after each entry.
classification society and the frame numbers are displayed both in the table and
on the x-axis of the bar graph.
To modify the predefined values for KG, FS, TCG or LCG.
a) Select the seagoing condition or the harbour condition. The discrepancy between current condition (left side of the screen) and manual Error messages are displayed in the bottom line of the screen. Press the ESC
gauged draughts (right side of the screen) is displayed in the lower part of the key to confirm that a message has been read.
b) Click the relevant button to select the set of limits not currently in screen.
use. Conditions
Operating Procedures
(Note: If the size of the bars and the values in the table change, the % values To store the present load condition, to transfer an already stored condition or
for the limits for the shear forces and the bending moments will also change.) To change the sea water density to clear a stored condition.
Stress Curve a) Position the cursor in the field for the sea water density. The conditions stored in the end of the list are used for the classification
society’s reference. They may be transferred but they cannot be cleared by the
The calculated shear forces and bending moments compared with the limits b) Enter the actual value for the sea water density and press the operator.
defined by the classification society are displayed both in tabular form and as ENTER key.
curves. More information on absolute values and also on the limits are found By using the functions in this screen the operator is able to obtain a start
in the Stress Bars screen. When the sea density is changed the program will make a new calculation of condition very quickly.
the current condition.
(Note: There are different colours for shear forces and bending moments in the Operating Procedure
bar graph, blue = bending moments, red = shear forces.) Procedure to Compare the Calculated Draughts against the Gauged
Draughts To store current the condition.
The locations at which the stress is calculated are prescribed by the
classification society and the frame numbers are displayed both in the table and The draughts of the current condition are displayed on the left side of the a) Position the cursor in the highlighted field Condition Name.
on the x-axis of the curves. screen and are based on whatever entries have been made by the operator or
transferred from the tank gauging/automation system. b) Enter an appropriate name for the later easy identification of the
Operating Procedures condition.
a) Enter the actual sea water density in the list in the upper left
a) Select the seagoing condition or the harbour condition. corner of the screen. c) Position the cursor in the desired Condition Number.
b) Click the relevant button to select the set of limits not currently in b) Enter the gauged draughts and the corresponding locations in the d) Place the cursor on the store key area and click the mouse left
use. area of the screen called the manually gauged draughts. button.
(Note: If the size of the bars and the values in the table change, the % values Result e) Press the function SHIFT key and the F2 key.
for the limits for the shear forces and the bending moments will also change.)
The discrepancy (if any) between the current condition and the manually To transfer an already stored condition
Observations gauged draughts will be displayed in the bottom of the screen.
a) Position the cursor in the desired Condition Number.
This screen is used to define sea water density, warning limits for draughts If they are different it may be that an unknown weight or inaccurate sea water
deadweight and to observe the condition of the ship. density has been entered. b) Place the cursor on the store key area and click the mouse left
button.
Warnings will be issued when any of the calculated results exceed the The following command keys are available.
corresponding limit value. c) Press the function SHIFT key and the F1 key.
Defaul: To obtain a predefined (default) value back for the selected
KG, FS or TCG, whichever is selected. (Note: The current condition in the Loadmaster will be replaced by transferred
condition.)
Repor: To create a condition report.
To clear a stored condition.
Print: To print different reports.
a) Position cursor in the desired Condition Number.
From a large number of screens, the condition report can be created, using the
REPOR function key.
The report will be stored in a predefined directory under the name rcndrep.txt.
1
HC. GAS SAMPLING SYSTEM OGS 3.0/16
FOR BALLAST AND VOID SPACES
7. LABORATORY 8. WORKSHOP
SAMPLE
AUTOMATIC PURGE (DIM)
POINT
UP
6 7 8
MANUAL
DOWN
CALIBRATION SAMPLE (DIM) SELECTOR
9 10 11 12 13 14
OMICRON
TONSBERG - NORWAY
4.9 Gas Detection Systems Sample Point Location Boil-Off Gas to the Boiler Pipe Vent Duct System
1 Steam exhaust from steam/LNG heater
4.9.1 Fixed Gas Detection Systems Maker: Omicron
2 Upper funnel Type: OGS 21/1 IR
3 Ventilating duct: gas pipe to boilers
Accommodation and Machinery Spaces Detection System This system panel is situated on the bridge and continiously monitors a sample
4 Top of lift shaft from the vent duct surrounding the boil-off gas pipe to the boilers.
Maker: Omicron
5 First platform: port side
Type: OGS 3.0/16 If the methane concentration of any sample point reaches 30% LEL, an audible
6 First platform: starboard side alarm is sounded and the corresponding indicator lamp is lit on the panel.
Introduction
7 Laboratory on 3rd platform If the methane concentration of any sample point reaches 50% LEL, an audible
The OGS 3 gas detector is based on the measurement of infrared radiation 8 Workshop on 2nd platform alarm is sounded, the corresponding indicator lamp is lit on the panel and the
passing through a volume of gas. The OGS 3 employs a dual beam, dual main gas valve V2140 is tripped.
9 Engine Control Room on 3rd platform
wavelength measuring principle with separate optical detectors.
10 Inner bottom
Different types of gas have unique absorption spectra and can be easily
11 Boiler casing: port
identified by proper selection of the infrared wavelength at which absorption
is measured. Radiation at another wavelength measures the overall 12 Boiler casing: starboard
transmission through the optical system and in the air volume.
13 Cargo control room
By comparing the transmission of the two wavelengths, the gas concentration
in the air is determined. Selecting a wavelength with the unique characteristic
of a particular gas prevents other types of gas present in the sample activating Illustration 4.9.1b Boil-Off Gas Pipe Vent Duct Gas Sampling System
the detector and giving false alarms.
Radiation from two infrared sources passes through two narrow banded filters 1 GAS DETECTOR IN DOUBLE PIPE
selecting a measuring wavelength and a reference wavelength. Radiation is Key
divided by a beamsplitter into an external and internal path. The external path 1. Sample Point in Full Text
is viewed by the measuring (main) detector which detects if the selected gas is 2. LED Colour and Function Legend
% HC. HIGH GAS ALARM HYDROCARBON 3. LCD Display - % Hydrocarbon
present. The internal path is viewed by the compensation detector, this 3
L.E.L. LOW GAS ALARM SENSOR 4. Accept Alarm Button
monitors and compensates for any drift in the infrared source or detectors. 2 5. Reset Alarm Button
SYSTEM FAILURE
6. Buzzer
7. Blank
The four signals, two from each of the detectors, are amplified, digitised and 8. Lamp Test Button
ALARM 2 ACCEPTED
fed into a microprocessor. The microprocessor calculates the gas concentration 9. On/Off Switch
and the results are presented as either a voltage, a current or a digital output
ACCEPT RESET LAMP
signal. Internal signals are compared with test limits to monitor the electronics BUZZER ON/OFF
ALARM ALARM TEST
and optical parts and if values outside the test limits are detected specific error
4 5 6 7 8 9
messages are displayed.
If the methane concentration of any sample point reaches 30% lower explosive LOW GAS ALARM = 30 %
limit LEL, an audible alarm is sounded and the corresponding indicator lamp
is lit on the panel.
HIGH GAS ALARM AND GAS TO ENGINE TRIP = 50 %
Key
1
HC. GAS SAMPLING SYSTEM OGS 3.0/32
FOR BALLAST AND VOID SPACES 1. Type and Number of Sampling Points
2. Sample Points in Full Text
3. LED Colour and Function Legend
1. TOP VOID 1 2. BILGEWELL VOID 1 2 4. LCD Display 2 x 20 Characters
5. Dis/Reconnect Switch
Upper Void
3. UPPER INS. VOID 1 4. LOWER INS. VOID 1 6. Mode Selector
7. Manual Selector
5. TOP VOID 2 6. BILGEWELL VOID 2 8. Sample Point Selector
9. Accept Alarm Button
7. UPPER INS. VOID 2 8. LOWER INS. VOID 2 10. Reset Alarm Button
11. Buzzer
9. TOP VOID 3 10. BILGEWELL VOID 3 12. Power Reset
13. Lamp Test Button
11. UPPER INS. VOID 3 12. LOWER INS. VOID 3 14. On/Off Switch
DISCONNECTED ACTIVE
DIS/RE-
CONNECT
5
4
SAMPLE Skirt
AUTOMATIC PURGE (DIM)
POINT
UP
6 7 8
MANUAL Polystyrene
Leakage Pipes
Insulation with
DOWN Stainless Steel
CALIBRATION SAMPLE (DIM) SELECTOR Cover
Location of Cargo Area Gas Detection Points: Cargo Tank No.1 Gas Detection Point
OMICRON
TONSBERG - NORWAY
A separate gas detection system is set to givean alarm at a 30% LEL in the
cargo hold and miscellaneous areas listed below. The control unit is similar in
operation to the accommodation and machinery spaces gas detection system.
The control unit is situated in the cargo control room. The unit has a cycle time
of 36 minutes.
40 60
20 80
8 12
B
BATT.
4
0 100 20
40 60
80 20
40 60
80
SPAN GAS INLET TOXIC GAS 20
40 60 16
80
(PUSH)
0 100 0 100 DETECT. 0 20
0 1
100
% O2 BATT
. %LEL %LEL % LEL
0
2 4 6 8
10
BATT
. % LEL
COMB O2
BATT. SPAN 100
100 BATT CO2 PREP
CHECK.
METER LIGHT CO2
10
OFF 20 OFF MEAS
CHG.
COMB OXYGEN
ZERO ADJ. CAL ADJ.
- + - + ALARM RESET
OUT
MODEL NP-237H
RIKEN KEIKI RIKEN KEIKI GX-7 RIKEN KEIKI
Maker: Riken
The portable gas detection equipment on board is both comprehensive and well Model: OX-226
proven. Each instrument is certificated and comes with manufacturer’s No. of sets: 1
operating instructions and recommended spares and test kits. The certificates
are to be suitably filed and the monthly tests recorded. The ship carries two personal oxygen meters for the testing of the atmosphere
in tanks that have been gas freed before tank entry. An O2 detector head with
The instruments are stored in the ship’s computer room on the main deck extension cable line can be fitted into the bayonet fitting on top of the unit for
accommodation. testing of the cargo and ballast tank atmosphere prior to entry.
Hydrocarbon and LEL Detector Operation and calibration instructions are printed on the rear of the unit.
Maker: Riken The use of the equipment and any maintenance carried out should be logged in
Model: NP-237H the appropriate file in the ship’s computer room.
No. of sets: 2
Oxygen Meter/Analyser
The ship carries two Riken portable combustible detectors designed for the
measurement of hydrocarbon gas/vapour % concentration and % LEL during Maker: Riken
purging and gas freeing. Normal operating instructions are carried inside the Model: GX-7
cover of each unit with additional instructions detailed in the manufacturer’s No. of sets: 1
handbook.
The ship carries two oxygen meters for the testing of the atmosphere in tanks
On a monthly basis, each unit should be tested for gas sensitivity with the span that have been gas freed before tank entry. An O2 detector head with extension
gas test sampling bags which are stored in the ship’s computer room.
cable line can be fitted into the bayonet fitting on top of the unit for testing of
the cargo and ballast tank atmosphere prior to entry.
The use of the equipment and any maintenance carried out should be logged in
the appropriate file in the ship’s computer system.
Automatic Dew Point Meter/Analyser
Dew Point Meter/Analyser
Personal Multi-gas Analyser
Maker: Shaw
No. of sets: 2
Maker: Riken
Model: GX-2001
The ship carries two dew point meters to measure the moisture in air or gas
Type: H2S, O2 and HC LEL%
samples with positive pressure. The battery powered hygrometer indicates both
No. of sets: 2 dew point temperatures and water vapour to less than one part per million, on
the large meter dial. As the reading is specific to water vapour, calibration is
The ship carries two Riken GX-2001 personal H2S ppm and O2 % detectors accurate for different gases.
which are designed to be clipped to the clothing of the operator. Operation and
calibration instructions are printed on the inside of the stowage container. The dew point meters are sent ashore every twelve months for reconditioning
and recalibration.
The use of the equipment and any maintenance carried out should be logged in
the appropriate file in the ship’s computer room.
P SVC Closed
I Signal/Indication
P SVC Open
Actuator I Signal/Indication
To Engine Room
Instrument Air To
System To Quick Closing
CO2 Valves
Alarm Panel 7psi
Alumine Active LNG Compressors/
PI PI PI PI
Air Dryers Cargo Heaters/
Vaporizers Control Air
V1438 ESD System
V3002 V3001
PI
To AL V3000 V3000 V3000 V3000
Power Air 8.8 bar
Engine Room PI Power Air
Working Air Cargo Instrument Air Receiver 8.8 bar
System LNG Compressor Room
PI (1.5m3) ESD Emergency Air Circuit
To Deck 2
Working Air V1432
System
To Air Receiver
Working Air (4m3)
Receiver V1433 Drain
Remote Control Of Throttling Valves
V1431 0 - 100%
V1424 P SVC Position
I Feedback/Indicator
SVC Order
XE111
Signal
V1424
ESD Shutdown
Signal
Drain FCV126 Close
To
Working Air
System PCAL
168
Open
Control Pneumatics, Solenoids,
Pressure Transducers and Converters
are located in Panels adjacent to the
Cargo Tank Domes Power Air 8.8 bar
Power Air
PC
For Cargo Valves
Automatic Drain SA HC
HC SA 5 5 5A
PC
3 3 3 XC
XC 5
PC 3 SI SI
Drain SI SI
5B 5A PC
3 3A 3B 5B Key Power Air 8.8 bar
PCV
Air
PCV Type Type
3 5
235 Quincy 245 Electrical Signal ESD Emergency Air Circuit
Instrument Air Compressors
Instrumentation
4.10 Valve Remote Control and Emergency Shutdown System 4.10.1 Cargo Valve Remote Control System Cargo Valve Operation
The Emergency Shutdown System (ESD) is designed to ensure a controlled Type: Pneumatic/electronic The cargo valves are normally closed. To open a valve, the valve’s control
shutdown of cargo equipment both ashore and on the ship to avoid any unsafe circuit is pressurised by the opening of the solenoid operated control valve in
conditions arising. It is essential that the machinery is stopped and valves The actuator air system supplies air to all cargo valve actuators. Air is supplied the pneumatic valve panel. This action is initiated by the operator selecting the
closed in the correct order to avoid any pressure surges ashore or on board. from the instrument air compressors at 8.8 bar. The air is filtered, dried and open command via the DCS system. These valves are situated at the cargo tank
stored in a 1.5m3 receiver, located in the LNG compressor room. After this dome or at a convenient location close to the actual valve. The control air
In the event that the ship accidentally moves away from the jetty, it is of the receiver there is one pipe for the supply of power air for the actuators and one pressure opens a pilot valve for the supply of working air to the actuator and
utmost importance that all plant is stopped to allow emergency disconnection pipe for the rest of the pneumatic control system. The last pipe is branched into the cargo valve opens.
without the risk of LNG spillage. the emergency air, control air and instrument air circuits.
The valves take approximately 10 seconds to open and 15 seconds to close.
The valve remote control system and the ESD system are both operated by Actuator Air The cargo valves are closed by releasing the control air circuit by the control
pneumatic air fed from the cargo instrument air system. This system is itself valve.
fed from the main instrument air system. This air system supplies air to all the actuators. The air supply is controlled by
a 3-way valve, FCV 126. This valve will open for the power air supply when The valves in the cargo discharge and spray pump lines close automatically
Compressed air is supplied to this system from whichever of the three the emergency air circuit is pressurised. If the emergency loop pressure is when the pump motors stop. This arrangement contains a pneumatic time relay,
instrument compressors is/are selected for duty. The compressor(s) will cut in released, this valve will open to atmosphere and the actuator air will vent off. which after a delay time will enable these cargo valves to be operated again.
and out automatically according to the air pressure in the instrument air
receiver. The instrument air receiver has an outlet valve, which feeds the cargo The remotely operated shut-off valves at the crossovers and the dome A detailed description of the valve operation follows after the cargo gate valve
instrument air system via a system of filters and dryers to ensure the quality of connections are fitted with air return actuators. The actuators on the throttling illustration (4.10.1b) overleaf.
the compressed air. valves in the loading lines control the variable valve position, enabling remote
flow control of the loading rate.
The instrument air receiver, filters and dryers are located in the engine room.
The cargo instrument air receiver is located in the LNG compressor room. The control air circuit for each actuator is pressurised with air by hand operated
3-way valves to the shut off cargo valves and spring loaded valves to the filling
Cargo Tank High Level Shut-off System pipe throttling valves.
The cargo tanks each have an independent high level alarm and shut-off
function which works independently. The shut-off function is connected to the
Omicron high level alarm system (see section 4.1.3 for further details). When
the liquid level in the tank reaches a position equal to 99.2% full by volume, a
signal is sent to the tank loading valve remote control system to close the valve
automatically. When this valve is activated, red warning lights will flash and
an alarm horn will sound on deck.
A prewarning alarm is sounded when the tank volume reaches 95%. This
activates an alarm in the CCR and an alarm horn with a different tone from
above will sound on deck, accompanied by an orange flashing warning light.
The reset for this system is at the DCS system control console in the cargo
control room. For further details, see section 4.1.3, high level alarm and
overfill system.
Pneumatic Gate Valve Closed: Actuator Opening Pneumatic Gate Valve Open: Actuator Closing
Accumulator
Chamber
Spindle
Piston Seals
Key
Compressed Air
Exhaust
Exhaust Port
to Atmosphere
Open Stroke Limit Valve
Non-Return Valves
(See illustration 4.10.1b) The operator selects the CLOSE command from the DCS system valve
operation menu. The system opens another solenoid operated control valve for
Opening that valve and the compressed air in the control line is exhausted.
The operator selects the OPEN command from the DCS system valve The three-way differential slide valve, located at the bottom left of the unit,
operation menu. The system opens the solenoid operated control valve for that moves to the right via the action of the spring and the drop in air pressure. This
valve and compressed air fills the accumulator chamber via non-return valve opens the port to supply air from the accumulator chamber to the top of the
B. This valve prevents the air from being exhausted. piston chamber which forces the piston down, closing the gate valve.
The air also enters the piston chamber via non-return valve A, through the port The closing speed is regulated by the setting of the closing speed needle valve
immediately above the valve. This lifts the piston when the air pressure reaches and can be set from approximately 15 seconds to one minute.
a level high enough to overcome the friction of the piston seals.
When the piston moves to within 25mm of the bottom of the chamber it will
The piston lifts the valve gate spindle at a speed which is regulated by the open the close stroke limit valve. This valve is similar in operation to the open
setting of the opening needle valve. stroke limit valve, bleeding air from the signal line to cause a pressure switch
to register this loss and send a close signal to the control valve. This stops the
As air is entering the piston chamber, air also flows to the three-way exhausting of control air.
differential slide valve, located at the bottom left of the unit. This is forced to
the left which opens the exhaust port and vents the air from the top part of the The piston will then remain in the closed position.
piston chamber to atmosphere. The slide valve is held against a spring by the
control air pressure.
When the piston moves to within 25mm of the top of the chamber it will open
the stroke limit valve. This valve will bleed air from the signal line which will
in turn cause a pressure switch to register this pressure loss and send a close
signal to the control valve, shutting off the supply of control air.
The control line remains pressurised therefore the piston will remain in this
position until a close cycle is initiated.
There is an emergency closing/opening facility for this type of valve. The top
cap is removed and a special threaded tool is inserted into the piston chamber
which is then screwed in to the piston crown. The valve piston can then be
jacked open or closed as required.
Compressed Air
Electric Cable
7.0 Bar
Air Supply
SV1
From Air
Receiver
PS
3 Internal Telephone Cargo Control Room
Hotline Automatic
Fibre Optic and Pneumatic Telephone Cabinet Under Port Manifold Exchange
Telephone
Converter Conference
Room Room
220V 60Hz
1
5
24V 6
From / To
DC
7
8
To Manifold NEBB System
220V Valves
60HZ
At C.C
Console
OPTICAL FIBRE Junction
Box SV1
Accommodation
SV2
ESD Relay
Panel
Manifold
Port
Optical Fibre
Transmission PS
Panel PS
Cut 3
Junction
Off Box
Relay LNG Compressor
Box Dome Dome Dome Dome Dome Room
Tank 5 Tank 4 Tank 3 Tank 2 Tank 1
Junction
Box
PS
Emergency Quarter
Manifold
Head
Stbd
4.10.2 Emergency Shutdown System Each cargo tank dome The arms will lift clear allowing the mooring arrangements to be released. The
sections of shore arms remaining bolted to the ship’s manifold flanges have to
Port and starboard manifold platforms
The emergency shutdown (ESD) system is a safeguard provided in addition to be removed and returned when convenient.
the individual safety devices for plant and equipment. The system may be 2) High temperature (fire). Fusible plugs, designed to melt at
activated manually or automatically from on board or from ashore and has two between 98ºC and 104ºC, are fitted at the following locations: ESD System Testing
levels of priority, namely ESD1 and ESD2.
Catwalk aft of each cargo tank dome The ship’s ESD1 system is to be tested prior to arrival at the loading or
The ESD panel is fitted in the local cargo control room. It is interfaced to the Two at each port and starboard manifold platforms unloading ports.
DCS system and has links to the Pyle and Miyaki systems.
3) Electrical power failure: In the event of a failure of the electrical A different activation point, including manual pushbuttons or the removal of a
ESD1 may be initiated from on board or from ashore and will result in a power supplies. fusible plug, should be utilised at each test, to allow a complete check of the
shutdown of the cargo system both on board and ashore. system just prior to arrival in port. After arrival alongside and with arms
4) Low pneumatic control air pressure. A low-low control air connected, operation of ESD1 will be checked by the ship and the shore while
ESD2 can only be initiated manually from the terminal or automatically if the pressure of 3 bar will initiate an ESD1 trip. To prevent spurious the ship’s manifold is warm and then checked again after the cooldown is
ship drifts outside the working area of the loading/unloading arms. Activation tripping, a time delay is incorporated which may be adjusted completed.
of an ESD2 will automatically initiate an ESD1 and, after stopping cargo between 0 and 30 seconds and is normally set at 10 seconds.
operations, cause the disconnection of the loading/unloading arms (in certain The closure time of the shore valves will be checked by the terminal, but the
terminals). 5) An ESD1 signal from the shore. A shutdown signal from the shore closing times of the ship’s manifold valves should be checked at every test by
link. the cargo engineer or chief officer. The closing time for the ship’s manifold
Initiation of ESD1 causes the following on board: valves must be within 30 seconds. The shore valves for loading and unloading
6) Low pressure in the pneumatic shore to ship link. After the terminals close within 15 seconds.
a) The low duty (LD) and high duty (HD) compressors stop. pneumatic link has been pressurised from the shore, the override
key switch at the ESD cabinet in the local cargo control room
b) All cargo and spray pumps stop. console can be switched to normal. Loss of air pressure will
initiate an ESD1. The pneumatic hose link is not connected under
c) ESD quick-closing manifold valves shut within 30 seconds. The normal conditions, but it is tested by ship/shore on a routine basis
emergency air circuit ensures ESD valve operation in the event of (following NWS requirements).
a loss of main air.
Automatic initiation is carried out in the event of:
d) The inert gas generator blower stops. Low pressure in the loading arm hydraulics
e) An ESD shutdown signal is transmitted to the shore terminal via Low pressure in the hydraulic circuit of the emergency
the ship-to-shore link. release coupling of the individual loading/unloading arms
Power loss in the control system
Initiation of ESD1 causes the following actions in the loading terminal:
Excess angle of the loading/unloading arm slewing or apex angle
Stops the terminal loading pumps
High level in the surge drum
Shuts the terminal ESD valves within 15 seconds
Fire alarm on the jetty
Immediately opens the terminal loading pumps’ kickback valves
Loss of signal between the ship and shore ESD link
ESD1 is initiated on board by the following actions:
Activation of ESD2
1) Manual initiation: Switches are positioned at the following
locations: The ESD2 system can only be activated from the shore terminal and
automatically activates ESD1. After the cargo operations have been stopped
Cargo control room there is a time delay and a warning before the terminal loading/unloading arms
LNG compressor room emergency release couplers operate. A section of the emergency release
coupler incorporating a valve remains attached to the ship’s manifold flanges.
Emergency headquarters
OR
STOP COMPRESSORS.
ALARM.
There is an emergency air loop system to quickly close all valves in the cargo Linked ship-shore emergency shutdown systems have been required by 36-way Miyaki connectors designed for Zone 1, Div II, temp rise T4 are fitted
handling system in the case of a fire or pipe fracture. SIGGTO since the early days of LNG loading and discharge installations. They port and starboard. These are for use at P’yeong Taek, Inchon and Bintulu.
minimise the consequences of an accident or, if abnormal conditions arise, they
The emergency loop system consists of a special air circuit, pressurised from allow the process to be shut down with minimum spillage of liquid. Thus A 37-way Pyle national connector system for Oman is fitted port and starboard.
the control panel. The circuit is fitted with fusible plugs, melting at 102.5ºC, consequent risk to jetty and ship’s structures and escape of flammable vapour
and manual releases (described in the ESD section), located at strategic points is avoided. Since both the ship and the shore terminal exchange liquid and WARNING
around the cargo system. vapour, the shipside and shoreside emergency shutdown systems must be Four way earth bonding connectors are provided but not used due to
linked. This is to avoid: ISGOTT regulations prohibiting their use.
The emergency circuit is supplied with air from the main control air circuit
header via spring loaded valve HCV-122 in the control panel. The pressure on Excessive surge pressure on the loading arm connection causing A 13-way ITT Cannon MIL - Std connector is fitted port and starboard. These
this valve keeps valve FCV-124 open. In the case of any small leakages, the damage. The upstream valve is closed first. are for use at Arun and Bontang.
pressure will be maintained through restriction valve FO 125. The capacity of Overfilling the ship or shore tanks.
this valve is so small that the emergency circuit pressure will blow off if a Pneumatic Systems
fusible plug melts or a manual release is opened. Risk of damage or spillage due to excessive movement of the
ship with respect to the berth. Two quick-connect male umbilical pneumatic connectors are provided at the
The emergency circuit controls the three-way valve FCV 126 in the power air manifolds for use with the similar systems used at Ras Laffan and other
header. The pressure in the emergency circuit will open this three-way valve In addition to the safety requirement for ESD, the ship to shore link has been terminals. These directly trip the loading valves on pressure loss and are sensed
to pressure from the air receiver. If the emergency circuit is released, the valve extended to handle communications by telephone. Each loading/unloading by the ESD system.
will open to atmosphere and the pressure drop in the power circuit will close terminal has the ship/shore communication and ESD system integrated and all
the actuator controlled cargo valves. terminals have a common ship/shore interface connection.
The emergency air circuit can also be released from the control panel by The key switch which selects which ship/shore link method to be used
opening the hand control valve HCV 123. (dependent on the terminal) has an inhibit position to prevent spurious ESD
signals being transmitted to the shore before the ship’s systems are ready.
Flanged Pipe
to Vent Mast
High Pressure
Pilot Valve
Low Pressure
Pilot Valve
4.11.1 Cargo Tank Relief Valves Operation Under Pressure Using the Main Pilot Valve Each section of the cargo pipework, except the vapour line, that can be isolated
When the pressure in the tank is less than the opening pressure, the main pilot by two valves has an overpressure relief valve fitted.
valve allows the tank pressure to act on the larger upper area of the diaphragm
Maker: Luceat and pallet assembly, keeping the valve closed.
Type: R2101-HP The cargo manifold relief valves and the relief valves on the liquid header are
No. of sets: 15 set to lift at 10 bar and relieve pressure back to a collecting tank above the
When the pressure in the tank is more than the opening pressure, the main pilot cargo control room. This tank vents to vent mast No.4.
No. per tank: 3 valve is forced to vent the pressure on the upper area to the atmosphere,
causing the valve to fully open. The collecting tank is fitted with a level alarm which raises an alarm via the
Settings:
Overpressure: 0.25 bar DCS system.
Operation Under Vacuum Using the Auxiliary Pilot Valve
Flow rate per valve: 2,2811Nm3/h When the vacuum in the tank is lower than the opening vacuum, the auxiliary Relief valves between the tank dome and the throttle valve release pressure
pilot valve allows atmospheric pressure to act on the larger upper area of the back to the nearest cargo tank dome.
Vacuum Relieving: -1kPa gauge diaphragm and pallet assembly, keeping the valve closed.
Flow rate per valve: 4,302Nm3/h
When the vacuum in the tank is more than the opening vacuum, the auxiliary
Each cargo tank is fitted with two pressure/vacuum relief valves as required by pilot valve shuts off the port to the atmospheric and allows the tank vacuum to
the IMO code. act on the larger upper area of the diaphragm and pallet assembly, causing the
valve to open.
The cargo tank relief valves are fitted at the vapour domes of each tank and
vent to their associated vent mast riser. The relief valves are of the PORV (pilot
operated relief valve) type. A cargo tank pressure sensing line relays the
pressure directly to the pilot operating valve. In this way, the accurate
operation required at the relatively low pressure inside the tank is assured.
The cargo relief valves are set up initially by the manufacturers for the
requirements on the ship. If an overhaul of the valves by ship’s staff is carried
out, the valves must be checked and reset to the original settings. (See
manufacturer’s instructions for details.)
It is extremely important that the vent mast is checked on a regular basis and
drained of any accumulation of water. This is to ensure that the relief valves
operate at their correct settings, which would otherwise be altered if water
were to accumulate in the vent mast and flow onto the valve assembly.
Port Starboard
View Inside Instrument Cabinet at Cargo Tank Dome Showing Pressure Transmitters
FCV
33
Open Void Space Cargo Power Air
Relief Valves
SVC Signal From:
PDICA 5: -0,08 bar
PDICA 5: 0,015 bar
PDIAH 3: 0,05 bar d.p.
FCV
34
Atmosphere V-2245
Void Space
FCV
34
Key
Electrical Signal
V-2245
Instrumentation
Void Space
4.11.3 Void Space Relief Valves The cargo tanks and void spaces are also protected against differential pressure
between each other. Pressure switch 3PDIAH will initiate the above sequence
The void spaces are protected against an overpressure of 0.15 bar or an if the differential between the tank and void space exceeds 0.05 bar.
underpressure of -0.08 bar. If void space pressure switch 5PDICA is activated
by either of these pressures, a signal is sent to the DCS system which will open
solenoid valve FCV33 and supply air to the pressure control valves FCV34.
These control valves will supply power air to the actuators of the butterfly
valves. These valves will open to vent the void space to atmosphere.
Illustration 4.11.3b Monitoring of Pressure Relatives (Tank - Void Space - Atmosphere)
0.1 0.1
0.0 0.0
Safety Stop LNG Compressor Position 72
Low Pressure Alarm (One Pressure Switch in Suction Line)
Position 4 (Each Void)
Stop LNG Compressor Tank Vent Fans
Dry Air to Void Pumps and Spray Valves Position 3 Stop LNG Compressor
Requested Position (Each Tank) and Pumps Position 2 (Each Tank)
(Common Cutout)
Open Relief Valve Void Position 3
Open Relief Valve Position 5 (Each Tank)
(Each Void)
-0.1 -0.1
Sea Suction
Overboard No.5 Side Tank No.4 Side Tank No.3 Side Tank No.2 Side Tank No.1 Side Tank
(Port) (Port) (Port) (Port) (Port)
V56 HC V60
1A
V13
SI HC PI 801
1 20a
1 1
Emergency
Bilge Suction
V54A V54 V52 V52 No.3 Bottom Wing No.1 Bottom Wing
Ballast Tank (Port) No.2 Bottom Wing Tank (Port)
Pump V64 V59 Tank (Port)
V71
Emergency 1,200 m3/h
Connection For
V96 V94 V92 V90 V88 V86 V84 V82 V80 V78 V74
Backflushing
Main Condenser
V57 V23 V99 V69 V72
V70
V63
From
Bilge System No.2 No.3 No.2 No.1
V33 V58 V59A Double Bottom
From Lower Cross Lower Cross Lower Cross
Spare Water Tank Tank Tank
Fire and Deck
Ballast Tank
Wash System V33
V98 V97
V57 V72
V95 V93 V91 V89 V87 V85 V83 V81 V79 V77 V73
V71
V64 V59
No.3 Bottom Wing No.2 Bottom Wing No.1 Bottom Wing
Tank (Starboard) Tank (Starboard) Tank (Starboard)
HC Ballast
V66 2A Pump V61
1,200 m3/h
No.5 Side Tank No.4 Side Tank No.3 Side Tank No.2 Side Tank No.1 Side Tank
Overboard (Starboard) (Starboard) (Starboard) (Starboard) (Starboard)
Key Sea Suction
Sea Water
Bilge
Electrical Signal
4.12 Ballast System Ballast Valves 4.12.2 Ballast Control and Indicating System
4.12.1 Ballast Piping The hydraulic valves are all located in the duct keel, adjacent to the actual The ballast system is primarily controlled via the DCS system. Operation is
ballast tank. The hydraulic pump unit is situated between the two ballast carried out from the ballast primary window which this visualises the entire
pumps in the engine room. Commands from the DCS system are transmitted ballast system. From this view the tank levels of all vessel fluids used as ballast
Ballast Pumps to electrically operated solenoid valves located in a section of the local cargo can be monitored and the ballast system pumps and valves can be controlled.
control room automation cabinet. The valves may be operated locally in the The primary view also shows the vessel heel and trim data.
Maker: Worthington event of a failure of the remote operation electrical/hydraulic systems. The
Type: 10-LNCV-12 vertical centrifugal valves are designated as follows:
Capacity: 1,200m3/h Ballast system and alarm status can be viewed in more detail by selecting the
Speed: 1,750 rpm second (lower) level ballast or status views. The cargo control function
Ballast Tank Valve No. Hydraulic Block comprises the following:
No. of sets: 2
Side tank 5 port V96 216
Manual control Route guidance
Stripping Ejector Bottom wing 3 port aft V94 234
Bottom wing 3 port forward V88 231 Automatic routing Heeling control
Maker: Golar Side tank 4 port V92 213 Operator Interface
Type: 4” - 5” - 5”
Side tank 3 port aft V90 210
Capacity: 120 m3/h at 3m suction lift The cargo and ballast process views show the fluid control systems comprising
Driving water at 106m3/h Side tank 3 port forward V84 207
tank, valve and pump symbols interconnected by piping and manifolds. The
No. of sets: 1 Bottom wing 2 port aft V86 228 operator monitors the status of each device by displaying the views and
Bottom wing 2 port forward V82 225 operating the equipment as required. The starting and stopping of pumps and
In the ballast system there are two ballast pumps with suction from all ballast Side tank 2 port V78 204 the opening and closing of the valves is normally part of the automatic cargo
tanks. Each pump is of the electric vertical centrifugal type with a discharge and ballast tank filling and emptying sequences, which are initiated from the
Bottom wing 1 port aft V80 222
capacity of 1200m3/h. The pumps are primed from the stripping ejector. The operator stations.
pumps are located at the forward end of the engine room, at tank top level. The Bottom wing 1 port forward V74 219
hydraulic unit which drives the remote operated ballast valves is located at this Side tank 1 port V71 201 In the manual operating mode, the pumps and certain valves are controlled
level, centrally between the two ballast pumps. Double bottom 2 aft V65 413 from the module operating menu for each individual item of equipment. In
Double bottom 2 forward V69 410 addition to tank, valve and pump symbols, some views contain a global control
In normal service, the port pump is connected to all port tanks and the module which makes it possible to control the operation of several tanks,
starboard pump to all the starboard tanks. However, it is possible to draw from Lower cross 3 V99 407
pumps and valves simultaneously. The cargo and ballast second (lower) level
both sides with one pump. The ballast pumps can have suction simultaneously Lower cross 2 V98 404
process views are displayed via a hot spot on the process view, the navigator
from a number of tanks, this reduces the water velocity in the pipe branches Lower cross 1 V97 401 function or the navigator button on the operator panel.
and valves. Side tank 5 starboard V95 316
Bottom wing 3 starboard aft V93 334 The global control module symbol comprises a box with text components that
From the cargo control room, all the ballast valves can be hydraulically show the current operational state of the module. The text varies depending on
controlled. The same pipes and valves are used both for the filling and Bottom wing 3 starboard forward V87 331
the selections made via the commands on the global control module operation
emptying of all the ballast tanks. Side tank 4 starboard V91 313 menu. The text box at the left of the symbol shows the selected control mode
Side tank 3 starboard aft V89 310 for the module, ie, ballast or stripping mode. The mode field shows the selected
Special drop valves (hydraulically operated) are installed for direct emptying Side tank 3 starboard forward V83 307 operating mode, ie, manual or auto.
to the open sea. The bottom wing tanks can be filled directly through the drop
Bottom wing 2 starboard aft V85 328
valves. The ballast levels can be seen on the DCS system ballast primary window.
Bottom wing 2 starboard forward V81 325
Each tank has a graphic representation of the level and a read out of the
The ballast eductor works as a stripping pump for the ballast tanks and as a Side tank 2 starboard V77 304 contents in cubic metres. The tank level sensors are of the Autronica pressure
priming unit for the ballast pumps. This is a water driven unit with a discharge Bottom wing 1 starboard aft V79 319 transmitter type.
capacity of 100m3/h. The stripping ejector driving force comes from the ejector Bottom wing 1 starboard forward V73 322
pump (106m3/h). At the bottom of the screen is a graphic representation of the ship’s trim and
Side tank 1 starboard V70 301
heel, measured in metres forward and aft and degrees respectively.
Ballast operations from the DCS will be fitted in the near future.
Text display
(Information Window)
DYFI
Dynamic Filter Process
BS100
PREWARNING
FAULT
These lamps can be custom
assigned. FUNCTIONS DISABLED
MAINS AUTRONICA
Detectors
Prewarning
Amber (yellow) lamp illuminates
with a pulsating light when a
prewarning situation occurs.* The five element keypad consists of four arrow keys
and one 'carry-out' (enter key). The keypad is used to access
and handle information on the system. The four arrow keys
Fault control the cursor on the control panel text display.
Amber (yellow) lamp illuminates for
any fault. Pulsating light.* These keys scroll the menu and move the cursor
up and down in the menu text on the text display.
These keys also scroll figures and letter values.
Function Disabled
Amber (yellow) lamp illuminates These arrow keys scroll the menu and move the cursor
when any part of the system left or right in the menu on the text display.
FIRE
BU70
'Carry-out' (entry) key. Selects the menu part on which the PREWARNING
FAULT
Mains
Green lamp illuminates when the Repeater Panel
power is on. Common Fire Alarm Output 2 Minutes Delayed Engine Control Room
Failure Output
To Engine Room Monitoring System
(No Time Delay)
Common Fire Alarm Output
Mains
(230 VAC) 24V DC For Flame Detectors
Part 5 Cargo Auxiliary and Deck Systems Prewarning g) Close the panel door.
5.1 Fire Detection System In certain conditions, such as a rise in the detector ionisation level, a detector In the normal condition, the MAINS indication lamp will be the only indicator
may trigger a prewarning alarm. This may be a prelude to an actual fire alarm, illuminated when the door is closed.
so the alarm should be thoroughly investigated.
Maker: Autronica Fire Alarm
Type: BS-100/4 The following indications appear on the control panel in the event of a
prewarning: The following indications appear on the control panel in the event of a fire
The BS-100/4 fire detection system is a computerised, fully addressable alarm:
analogue fire alarm system with analogue detectors. The central control unit The text display indicates the address(es) of the detector(s)
with back-up battery, operating panel and power supply is contained in a which are in the in prewarning mode The red FIRE indication lamp flashes and the buzzer sounds
central cabinet on the bridge. There is a repeater panel in the fire headquarters. The text display indicates the address(es) of the detector(s)
The yellow prewarning lamp flashes and the internal
buzzer sounds which initiated the first fire alarm. The display will also show
The system is interfaced to the Valmarine DCS system via a converter and any items which may be disabled, eg, bells, sounders etc
RS232 serial interface. The DCS system indicates loop status and can also The display and printer will show text such as:
control the fire pumps. The operator can also access deck plans indicating the If the alarm was preceded by a prewarning alarm, the prewarning
‘PV05 ADDRESS NO. 0605 lamp will illuminate steadily
exact location of individual detectors.
INVESTIGATE PREWARNING LOCATION’
The display and printer will show text such as:
The system uses a wide range of detectors and sensors to suit different needs ‘AL 01 ADDRESS NO. 0605’
If more than one prewarning event is registered, the display will change to:
and conditions. It includes detectors with different alarm parameters, for
example, ion and optical smoke detectors, heat and flame detectors, manual All sounders/fire doors/alarms/fan stops are activated
‘PV07 ADDRESS NO. 0607 (as connected/programmed)
call points, short circuit isolators and timers where required. The detectors are
2 PREWARNINGS REGISTERED’
wired in a loop configuration with 4 loops in total. A fault in the system or a
false alarm is detected immediately since the function of the detectors and Action to be Taken in the Event of a FIRE Alarm
All active prewarnings may be seen via the menu function; ‘SHOW STATUS’
other installed loop units are automatically and continuously tested.
‘PREWARNING’. Access to the menu is obtained by pressing the enter key on Follow all precautions described in the local fire instructions. When the scene
the front panel. of the fire has been investigated and the necessary action carried out, the
Operation
sounders may be switched off.
Action to be Taken in the Event of a Prewarning
The operating panel consists of a text display information window, indication
lamps, operating buttons and a five button/arrow keypad. These control items a) Open the control panel door.
a) Follow all the precautions as described in the local fire
enable the entire fire detection and alarm system to be controlled.
instructions. b) Press the SOUNDER SILENCE button.
The five arrow keypad consists of four arrow keys and one ‘carry-out’ (enter)
b) Open the control panel door. c) All alarm devices (including the internal buzzer) will be muted.
key. The keypad is used for accessing system information. The four arrow keys
control the cursor on the control panel text display. The red FIRE indication lamp will switch to a steady light.
c) Press the SOUNDER SILENCE button. The buzzer will give a
short signal approximately every fourth minute as long as the All alarm outputs from the control panel will be turned off when the
The up and down arrow keys are used for scrolling in the menu and for moving
door remains open. SOUNDER SILENCE button is pressed.
the cursor up or down in the menu text on the text display. The keys also scroll
figures and letter values when they are to be entered in the menu functions.
d) The PREWARNING indication lamp will now change to a steady (Note: There are various silent alarm functions such as; day/night/master clock
light. time controlled functions and sounder activation time delays available, see the
The left and right arrow keys are used for scrolling in the menu and for
moving the cursor to the left or right in the menu, on the text display. manufacturer’s manual for further information on these functions.)
e) Press the RESET button. The following text will shortly appear in
the display; ‘RESET PROCEDURE IN PROGRESS WAIT .....’. If the MORE ALARMS indication lamp illuminates, see the next section.
The ‘carry-out’ (enter) key selects the menu part to which the cursor currently
This text will remain on the display for up to 60 seconds. The
points.
reset procedure is executed within this 60 second period. d) Press the RESET button. The following text will appear in the text
display; ‘RESET PROCEDURE IN PROGRESS WAIT.....’ This
f) If the detectors have now returned to a normal condition, the text will remain on the display for up to 60 seconds. The reset
following text will appear in the display; ‘RESET OK’ procedure is executed within this 60 second period.
‘NORMAL CONDITION’.
Text display
(Information Window)
DYFI
Dynamic Filter Process
BS100
PREWARNING
FAULT
These lamps can be custom
assigned. FUNCTIONS DISABLED
MAINS AUTRONICA
Detectors
Prewarning
Amber (yellow) lamp illuminates
with a pulsating light when a
prewarning situation occurs.* The five element keypad consists of four arrow keys
and one 'carry-out' (enter key). The keypad is used to access
and handle information on the system. The four arrow keys
Fault control the cursor on the control panel text display.
Amber (yellow) lamp illuminates for
any fault. Pulsating light.* These keys scroll the menu and move the cursor
up and down in the menu text on the text display.
These keys also scroll figures and letter values.
Function Disabled
Amber (yellow) lamp illuminates These arrow keys scroll the menu and move the cursor
when any part of the system left or right in the menu on the text display.
FIRE
BU70
'Carry-out' (entry) key. Selects the menu part on which the PREWARNING
FAULT
Mains
Green lamp illuminates when the Repeater Panel
power is on. Common Fire Alarm Output 2 Minutes Delayed Engine Control Room
Failure Output
To Engine Room Monitoring System
(No Time Delay)
Common Fire Alarm Output
Mains
(230 VAC) 24V DC For Flame Detectors
Action to be Taken in the Event of a ‘More Alarms’ Situation d) Contact Autronica technical or service personnel.
Follow all precautions described in the local fire instructions. When the scene
of the fire has been investigated and the necessary action carried out, the
sounders may be switched off.
V513 Anchor
V518
V514 V514 V514 V514 V514 V514 Chain Washing
Isolating
Valve
V518
V505 V502 V502 Ejector
V527
Chain Locker
V521
V502 V502 V502 V502 Ejector
V522 Fwd Pump Room
V526 and Duct Keel
Ejector Fore
V515 V515 V515 V525
Deep Tank
V515 V515
V501A
V522
No.5 Cargo No.4 Cargo No.3 Cargo No.2 Cargo No.1 Cargo V517
Isolating Tank Tank Tank Tank Tank
Valve V503 V503
Starboard
Port Near Stbd Accommodation
V520 V520 V520 V520 V520 V520
Boilers
V511 V511 V509
V513 Anchor
V518
V514 V514 V514 V514 V514 V514 Chain Washing
Isolating
Valve
V518
V505 V502 V502 Ejector
V527
Chain Locker
V521
V502 V502 V502 V502 Ejector
V522 Fwd Pump Room
V526 and Duct Keel
Ejector Fore
V515 V515 V515 V525
Deep Tank
V515 V515
V501A
V522
No.5 Cargo No.4 Cargo No.3 Cargo No.2 Cargo No.1 Cargo V517
Isolating Tank Tank Tank Tank Tank
Valve V503 V503
Starboard
Port Near Stbd Accommodation
V520 V520 V520 V520 V520 V520
Boilers
V511 V511 V509
In the event of a fire on board, the locations listed below have the following Emergency stops for engine room and accommodation supply and
exhaust fans
controls:
Start/stops for the engine room fire pumps - forward and aft
Bridge
Start/stops for the fuel oil pumps
Emergency stops for engine room and accommodation supply and
exhaust fans Control (shutting) of the boiler superheated steam outlet valves
From Bilge
Ejector Pump
Cargo
Control
Room
No.5 Cargo No.4 Cargo No.3 Cargo No.2 Cargo No.1 Cargo
Tank Tank Tank Tank Tank
To LPG Plant
Manifold Area To Cargo Hold Eductors/
LPG Compressor Room (Starboard) Manifold Water Curtains
Water Curtain
Bilge Ejector
Pump System
To
IG Refrigeration
Plant Coolers
To
Ballast
To and Bilge
IG To Eductors
Plant Main
Condenser PC
Flushing 52
Bilge
Ejector
To
Pump
SW Engine Room
Cooling
System
Regulating Valve
Sea Chest
LPG Sea Water Pump Each main spray branch, except No.1 cargo tank, has a manually operated e) Vent off the pump casing and ensure that it is flooded.
Maker: Thune Eureka isolating valve located at the distribution rail. The spray pumps can be started
No. of sets: 1 locally, or from the ECR or CCR (via the DCS system) and the emergency f) Start the pump and slowly open the discharge valve to the system.
Type: CGB 100 headquarters. The manifold water curtain(s) will now be supplied.
Capacity: 170m3/h at 5kg/cm2
Each branch sub-divides into smaller branches. The accommodation front is
Inert Gas Plant Sea Water Pump covered by 3 sub-branches. The spray nozzles are fitted approximately 1.2
Maker: Thune Eureka metres apart and 450 or 650mm from the surface they are protecting. There are
No. of sets: 1 various drains provided throughout the system.
Type: CGD 200
Capacity: 340m3/h at 5kg/cm2 Procedure to Supply the Deck Spray System Using the LPG Sea Water
Pump
Bilge Ejector Pump
Maker: Thune Eureka Assuming all valves in the system are closed.
Type: CGB 100
a) Open the spray section supply valve(s) as required at the
Capacity: 132m3/h at 7mth
distribution rail.
Spray Nozzles
b) Open the pump suction valve V330 and ensure the discharge
Type: 11/4 H 16 W cap
valve V331 is slightly open.
Capacity: 100 litres/min at 1.5kg/cm2
c) Ensure the deck water spray line supply valve is open.
The accommodation block front, LNG and LPG compressor rooms, cargo tank
liquid and vapour domes, main cargo valves and manifolds are protected by
d) Vent off the pump casing and ensure that it is flooded and ensure
water spray from the effects of fire, gas leakage, or liquid spill by a water spray
that the pump turns freely by hand.
system.
e) Start the pump and slowly open the discharge valve V331.
Normally the the LPG SW pump is used to supply the water spray system and
the system. The inert gas plant cooling water pump can be used via a cross-
f) Check the delivery pressure is approximately 5 bar.
connection valve. These pumps deliver water to a common distribution rail,
along which are fitted individual branches with isolating valves.
Manifold Curtain
The branches are as follows:
The water curtains that protect the vessel’s hull during cargo operations are fed
Accommodation block from the deck driving water system. This system is supplied with sea water
from the bilge ejector pump.
No.5 cargo tank
No.4 cargo tank Procedure to Supply the Manifold Water Curtains
Cargo control room
Assuming all valves in the system are closed.
No.3 cargo tank
a) Open the port or starboard manifold curtain supply valve(s) as
LPG compressor room
required at the manifold area.
Starboard manifold area
b) Open the bilge ejector pump sea chest suction valve and ensure
LNG compressor room the discharge valve is slightly open.
V518
V514
V518
V527
V502
V526
V525
V503
V514
View of Emergency Fire Pump Engine Inertia Start
View of Emergency Fire Pump Engine and Hydraulic Tank
Fire Main
Diesel Oil Tank
Diesel Hydraulic
Engine Oil Tank
V528
V531
Hatch
Water Spray
Covering
FO Transfer
Pump
The pump is mounted in a compartment shared with the fuel oil transfer pump
which is also hydraulically driven. This design enables a high degree of
waterproof integrity etc.
The hydraulic tank is also used to supply the adjacent FO transfer pump which
is electrically driven. The hydraulic tank capacity is 240 litres.
The diesel engine has an air start motor which is solenoid valve operated. The
engine starting air receiver is also fitted in the same area of the focsle store.
There is also a manually operated Bryce Berger hydraulic starter.
HL
11 11 11 24 HL 11 11
23
30 18 32 32
27 750 kg
Container
25 25
31
1,500 kg
26 Container
Dry Powder Room: Main System
Aft System Procedure to Operate a Hose Box Outlet b) The relief cock (16) is to be opened.
Maker: Totalit If a fire occurs, requiring the use of the system, the procedure is as follows: c) The main powder cock (30) is to be closed manually.
Type: PLO 1,500/750
a) Remove the hose and trigger pistol from the hose box. d) The stop cock (18) in the flushing pipe (17) is to be opened.
The system consists of a dual 1,500/750kg system situated in the powder room,
located in the starboard forward accommodation block on the upper deck. b) Fully open the release cylinder valve. e) The stop cock (18) is to be closed as soon as the powder container
has been relieved of pressure by operating the powder pistols.
The remote hose stations for the system is located along the cargo tank dome c) Check the pressure reducing valve (53) and open stop cock (52). Observe the low pressure gauge (22).
catwalk. These stations are equipped with nitrogen release bottles enabling the
dry powder systems to be activated remotely. d) Open the hose connection cock and operate the hand trigger valve f) Close the stop cock ‘HA’ in the high pressure pipeline.
as required.
The system has dry powder containers filled with 1,500 and 750kg of ‘Totalit’ g) The powder pipeline and powder hose should be thoroughly
dry powder. The main pressure nitrogen bottles are fitted adjacent to the main (Note: If the fire is extinguished, the operator should stand by in case of any cleaned through, preferably using a compressed air line and
containers. There is a main dry powder valve with automatic opening. This re-ignition. During this time the pistol trigger should be operated at short reducer (lower than 12 bar) via the flushing connection (31). The
feeds a distribution manifold with a number of outlets and each outlet has a intervals to flush the lines to ensure they remain clear.) pipeline and hose should be blown through with the cocks open.
distribution valve. The distribution valve has a pneumatic piston for opening Afterwards, stow the hoses in the figure eight configuration.
as well as a manual control. Each of the outlets is connected via a pipe to a hose Remote Release Failure
station. h) The pressure in the release cylinder and the secondary pressure in
In the event of a remote release failure, the powder can be released locally at the reduction valve should be checked using the following
Each hose station has a 30 metre hose fitted with a pistol type trigger nozzle the main container using the following procedure: procedure:
with a stopcock. To initiate the release of the dry powder from the hose
stations, there is a 3 litre 150 bar nitrogen bottle fitted with a handwheel, a) Manually open the powder direction cock (34) for the pipeline 1. Close the stop valve (52) on the secondary pressure side of the
pressure reducing valve and pressure gauge. required. reduction valve (53).
Theory of Operation b) Manually pull down the release lever (8). 2. Open the release cylinder (54) by turning the valve counter-
clockwise. The pressure in the bottle must not be more than 150
When the hose box nitrogen release cylinder (54) and local stop cock (52) is If the PLO 1500 unit is not sufficient or has run down, the PLO 750 unit should bar and not less than 50 bar. The secondary pressure in the
opened, nitrogen flows through the pneumatic piping (47) to the corresponding be used as follows: reduction valve must not be more than 8 bar and not less than 5
outlet release piston (34) for the direction cock (35) on the manifold. Nitrogen bar.
also flows to the main nitrogen bottles’ release lever pneumatic piston (7), a) Manually close the stop cock (32) for the PLO 1500 unit.
releasing nitrogen into the main container via the pressure regulator (23) and 3. Close the release cylinder (54) by turning the valve clockwise.
then through the pressurising valves (25). The regulator ensures the nitrogen b) Open the PLO 750 unit’s supply stop cock (32) and manually pull
pressure does not exceed 14 bar in the main container. down the release lever (8). 4. Open the stop valve (52) again.
The powder is then fluidised and pressurised to 14 bar by the nitrogen. When Post Operation Procedure for the Main Systems (Note: If the pressure in the release cylinder is lower than 50 bar, it must be
this service pressure is reached, limit valve (28) opens and pressurised nitrogen replaced. The nitrogen for the cylinders must be ‘high percentage nitrogen’ ie,
flows through the piping (14) to the pneumatic release piston (29) which then At the hose box: a nitrogen content of at least 99%.)
opens the main cock (30) for the powder. The pressurised powder in the
container flows through the syphon tubes in the container and out into the a) Close the cylinder valve. i) Close any direction cocks (35) which are open.
powder pipe line to the hose box powder pipe and pistol unit.
b) Close the hose connection cock. j) Open the main container filling orifice (20) and refill with ‘Totalit
(Note: If the main powder container pressure reaches 16 bar, the safety valve Super Powder’ using the correct filling funnel.
will open.) c) Stow the hose in a figure of eight configuration and secure.
Dry Powder
Room
NORMAN LADY
Port No.1
PLA 250 Dry Powder Unit
Deck Systems
Maker: Totalit
Type: PLA 250
There are seven 250kg dry powder systems strategically located around the
upper deck. These independent systems are equipped with a nitrogen release
bottle enabling the dry powder systems to be activated locally.
CO2
Room 13
C
No.5 No.4 No.3 D
Cargo Tank Cargo Tank Cargo Tank
Engine
Room
LNG compressor room 6 cylinders c) Proceed directly to the CO2 room to ensure that the correct
The starter cylinders release CO2 gas to operate the gang release pistons on the number of cylinders have discharged for the particular area.
Electric motor room 2 cylinders port side of the CO2 room.
LPG compressor room 4 cylinders d) If the starter system fails to operate the cylinders, the CO2 can be
g) CO2 will now fill the affected area. released by operating the cylinder levers by hand.
Cargo control room 2 cylinders
Cargo tank ventilation masts 6 cylinders h) Proceed directly to the CO2 room to ensure that the correct e) CO2 will now fill the pipe to the ventilation masts.
number of cylinders have discharged for the particular area.
Incinerator room 3 cylinders
Procedure in the Event of a Fire in the LNG Compressor Room
Paint store 2 cylinders i) If the starter system fails to operate the cylinders, the CO2 can be
released by operating the cylinder levers by hand. a) Go to the emergency headquarters on the starboard side of the
WARNING main deck. Unlock the control cabinet for the LNG compressor
Release of CO2 into any space must only be considered when all other j) Do not re-enter the engine room for at least 24 hours and ensure room and open the door.
options have failed and then only on the direct instructions of the Master. that all reasonable precautions have been taken, such as
maintaining boundary inspections, noting cooling down rates b) The alarm sirens will activated due to the door releasing the
Flooding of the protected areas is achieved by the operation of the valves from and/or any hot spots which may have been found. After this spring operated valve which directs compressed air from the
the control cabinet in the emergency headquarters on the starboard side of the period, an assessment party using radio communication and engine room to the LNG compressor room alarm sirens.
main deck. wearing breathing apparatus and lifelines can enter the space
quickly through a door, which is then shut behind them. Check c) Proceed directly to the CO2 room and manually release the six
Upon opening the control cabinet door, the CO2 alarm is activated and the that the fire is extinguished and that all surfaces have cooled prior cylinders marked LNG - COMPRESSOR ROOM.
ventilation fans for that area are stopped. The pilot gas is directed by the to ventilating the engine room. Premature opening could cause re-
operation of the respective valve onto the gang release line for the selected ignition if oxygen contacts hot combustible material.
area.
For added safety, the master valve is interlocked with the release locker door
in the closed position.
CO2
Room 13
C
No.5 No.4 No.3 D
Cargo Tank Cargo Tank Cargo Tank
Engine
Room
Procedure in the Event of a Fire in the Electric Motor Room Procedure in the Event of a Fire in the Cargo Control Room c) Go to the control cabinet on the starboard side of the central CO2
flooding system room on the main deck aft. Unlock the control
a) Go to the emergency headquarters on the starboard side of the a) Go to the emergency headquarters on the starboard side of the cabinet for the incinerator and open the door.
main deck. Unlock the control cabinet for the electric motor room main deck. Unlock the control cabinet for the control room and
and open the door. open the door. d) Pull the handle to activate the three cylinders in the central CO2
flooding system.
b) The alarm sirens will activated due to the door releasing the b) The alarm sirens will activated due to the door releasing the
spring operated valve which directs compressed air from the spring operated valve which directs compressed air from the e) Proceed directly to the CO2 room to ensure that the correct
engine room to the electric motor room alarm sirens. engine room to the control room alarm sirens.
number of cylinders have discharged for the particular area.
c) Proceed directly to the CO2 room and manually release the two c) Proceed directly to the CO2 room and manually release the two
f) Ensure that all reasonable precautions are taken, such as the
cylinders marked EL MOTOR ROOM. cylinders marked CONTROL ROOM. cooling of the boundary and/or any hot spots which may be found.
d) Do not re-enter the electric motor room for at least 24 hours and d) Do not re-enter the control room for at least 24 hours and ensure
ensure that all reasonable precautions have been taken, such as that all reasonable precautions have been taken, such as
maintaining boundary inspections, noting cooling down rates maintaining boundary inspections, noting cooling down rates
and/or any hot spots which may have been found. After this and/or any hot spots which may have been found. After this
period, an assessment party using radio communication and period, an assessment party using radio communication and
wearing breathing apparatus and lifelines can enter the space wearing breathing apparatus and lifelines can enter the space
quickly through a door, which is then shut behind them. Check quickly through a door, which is then shut behind them. Check
that the fire is extinguished and that all surfaces have cooled prior that the fire is extinguished and that all surfaces have cooled prior
to ventilating the electric motor room. Premature opening could to ventilating the control room. Premature opening could cause
cause re-ignition if oxygen contacts hot combustible material. re-ignition if oxygen contacts hot combustible material.
Procedure in the Event of a Fire in the LPG Compressor Room Procedure in the Event of a Fire in the Paint Store
a) Go to the emergency headquarters on the starboard side of the a) Close the paint store door and the ventilation flap, in order to
main deck. Unlock the control cabinet for the LPG compressor isolate the fire.
room and open the door.
b) Go to the control cabinet on the starboard side of the central CO2
b) The alarm sirens will activated due to the door releasing the flooding system room on the main deck aft. Unlock the control
spring operated valve which directs compressed air from the cabinet for the paint store and open the door.
engine room to the LPG compressor room alarm sirens.
c) Pull the handle to activate the two cylinders in the locker on the
c) Proceed directly to the CO2 room and manually release the four main deck on the port side below the paint store.
cylinders marked LPG - COMPRESSOR ROOM.
Three sets of fireman outfits Boiler heavy fuel oil supply pumps
Boil-off gas valve V2140
Recharging compressor for the self contained breathing apparatus
bottles
Breathing Apparatus Compressor
Automatic exchange telephone
Release valve to close engine room skylight hatch Maker: Bauer
Model: U1H
Drager emergency escape breathing device Operating pressure: 200 bar
Spare fire hoses and fire axes Motor: 2.2kW
CO2 system release cabinets for the following areas: Starting Procedure
Engine room
a) Check the oil level in the compressor sump and replenish it if
LNG room necessary.
Electric motor room
b) Open the filling valve and the vent valve first, then the bottle
Cargo control room valve.
LPG room
c) Turn the switch on the starter panel to the ON position and press
Cargo tank ventilation masts the START pushbutton.
Quick-closing system for the following valves:
d) Close the vent valve after the compressor has started producing
Diesel oil storage tank outlet valve air.
Port HFO storage tank outlet valve
e) When the pressure gauge indicates 200 bar, close the bottle valve,
Starboard HFO storage tank outlet valve followed by the filling valve.
Gas ventilation flap valve
f) Open the vent valve and stop the compressor by pressing the
STOP pushbutton on the starter panel.
To Outboard
Inert Gas
Generator V335 To
IG Refrigeration Plant LPG Plant
Condenser
Inboard
Inert Gas V412
Generator V409 V409 V409
From/To To
Fresh Water V452 Water Spray
Cooling System Overboard
System LD HD HD HD/LD
V451 PI V335
Compressors
Inboard LO Coolers
Inert Gas Generator From Outboard
Fresh Water Inert Gas V479
Circulating Pump Generator V340 V340
V407A V408 V408 V408
From
Auxiliary
Circulating
Pump Connection From
Tube and Shell Type Fire and Deck Wash
Fresh Water Cooler System
V407 From
Bilge Main
From/To Emergency
Auxiliary To Bilge
Circulating Aft Peak Suction
Pump V331 Tank
V323
PC
52 Sea Water
PI HC PI HC
HC Cooling 3a 3a 3c 3c
3b
Pump IG Plant
PCV PI LPG Plant
Key 52 (650m3/h at 25mth) CW Pump
CW Pump
(340m3/h at 5kg/cm2)
From (170m3/h at 5kg/cm2)
Sea Water
Bilge
Eductor Starboard
Electrical Signal
Forward
Bilge
Instrumentation
V330 V407A Well
V322
Bilge Sea
Sea Chest
Fresh Water Chest V329
5.3 Cargo Compressor Room Systems Operating Procedures LPG Circulation Pump System
5.3.1 Cooling Water System Inert Gas Cooling Water Pump System a) Ensure that the deck water spray line supply valve V479, the LPG
plant supply valve, the overboard and aft peak tank filling valves
a) Ensure that the engine room SW cooling system and LPG cooling are closed.
Inert Gas Sea WaterCooling Pump system cross-connection valves are closed.
Maker: Thune Eureka b) Ensure that the sea chest pump suction valve V329 is open.
No. of sets: 1 b) Ensure that the IG cooling system stop valves V335 are closed.
Type: CGD 200 centrifugal vertical c) Ensure the discharge valve V407 is slightly open and suction
Capacity: 340m3/h at 5kg/cm2 c) Ensure that the sea chest suction valve V329 is open. valve V407A is open.
Speed: 1,750 rpm
d) Open the pump suction valve V330 and ensure the discharge d) With the pump isolated, ensure that the pump turns freely by
LPG Sea WaterPump valve V331 is slightly open. hand.
Maker: Thune Eureka
No. of sets: 1 e) With the power off, ensure that the pump turns freely by hand. e) Vent off the pump casing and ensure that it is flooded.
Type: CGB 100 centrifugal vertical
Capacity: 170m3/h at 5kg/cm2 f) Vent off the pump casing and ensure that it is flooded. f) Ensure that the inlet valves V408 and outlet valves V409 on all
the compressor coolers to be used are open and that the drain
Sea water pump is used to cool the LNG high duty (HD) and low duty (LD) g) Ensure that the inlet and outlet valves on all the IG plant and valves are shut.
compressors’ lubricating oil coolers, the inert gas refrigeration plant cooler and coolers to be used are open and that the drain valves are shut.
the inert gas generator scrubber towers. g) Open the overboard valve V412 from the cooler discharge line.
h) Open the overboard valve V341 from the cooler and IG plant
The compressor coolers are supplied with sea water circulated by the LPG discharge line. h) Start the LNG circulation pump and slowly open the discharge
cooling water pump and may be cross-connected from the IG sea water system valve V407.
or the engine room SW cooling system. i) Start the IG pump and slowly open the discharge valve V331.
i) Check that the pump delivery pressure is at least 2 bar.
The IG refrigeration plant cooler and the IG generators are supplied with sea j) Check that the delivery pressure ia approximately 3.5 bar.
water from the IG cooling water pump. This system may be cross-connected j) Check that all the in-use coolers are venting off at the outlet water
from the LPG sea water cooling pump. k) Check that all the in-use coolers are venting off at the outlet water boxes to ensure that no air is entrained in the units. Ensure the
boxes to ensure that no air is entrained in the units. Ensure the vent valves are tightly closed.
The auxiliary SW circulating pump can also be used to supply the cooling vent valves are tightly closed.
water in an emergency. The compressors can now be used as required. See section 4.4 for further
The IG plant can now be started as required. See section 4.7.1 for further information.
Both the IG and LPG pumps are normally used together, with the cross- information.
connection valve used when required if one pump is not available.
The IG cooling water pumps also supply the water spray system.
LNG
Vaporiser
Cargo Heater
V911 V1033
V888 V942 V942
V1040 V1040 V1040
Cargo Heater
To
Atmospheric
Condenser
V911 V911A V911 V1033A V1033 V1033
V1032
V1032 V1032
Key
Steam V911 V1033
V1032
V1032 V1032
Condensate
Exhaust
V1032
V908 V1032 V1032
To Contaminated Main Deck Steam Exhaust Line
Steam Condenser V1002 From Forward Winches
5.3.2 Steam to Cargo Consumers This is fitted to provide the oil supply for the turbine and compressor before
and during starting until the mechanically driven main gear oil pump is up to
Cargo Equipment Steam Supplies speed and feeding oil.
All the steam requirements for the vessel are generated in the two main boilers. The steam supply to the vaporisers is controlled by valve 937A. This valve is
In each boiler, steam from the steam drum is led to the primary superheater regulated by the level controller according to the condensate level. If the level
section. Steam from the superheater outlet is led to the internal desuperheater, rises too high, the steam valve is closed, shutting off steam to the vaporiser.
situated in the steam drum, from where it is distributed to the various steam
services (for further information about the desuperheated steam system, see the The steam supply to the cargo heaters is controlled by valve 911A. This valve
vessel’s Machinery Operating Manual, section 2.1.1). is regulated by the level controller according to the condensate level. If the
level rises too high, the steam valve is closed, shutting off steam to the heater.
Superheated steam from the outlet of each boiler is also led to two external This action halts any increases in water level which could lead to the formation
cooling/pressure control valve desuperheaters. The internal desuperheater of ice.
supplies the steam required during normal steaming conditions, with No.1
desuperheater ‘making up’ if the demand exceeds the output of the internal The steam supply to the atmospheric heater is controlled by valve 946A. This
desuperheater. These desuperheaters supply the ship’s services. valve is regulated by the signal from the heater’s temperature controller. The
controller regulates the valve in accordance with the temperature received
High duty compressors A and B, the low duty compressor, the cargo heaters from a temperature sensor located in the void space outlet.
and the vaporisers are all fed with 10kg/cm2 steam from the low pressure steam
system. There are various steam traps and drains fitted to the system to remove
condensate and therefore improve the efficiency of the heat exchangers.
The low pressure steam service system is supplied from the low pressure steam
generator at a pressure of 10 kg/cm2. In an emergency, the LP steam services
can be supplied from the desuperheated steam system. The low pressure steam
service system also feeds the winches and windlasses. For further information
about the low pressure steam system, see the vessel’s Machinery Operating
Manual, section 2.1.5.
Cargo Machinery
The low pressure steam is supplied from the engine room to a steam header
located in the LNG compressor room. The desuperheated steam for HD
compressor C is supplied directly from the engine room to the compressor.
V1001
V905
V902
V905 V1005
LNG
Compressor V1005
Room
V1005
V905 V905
V1028
V905 V1005
V1005
PCV
915A V905 V905
V1005
V915A
Deaerating V918C
Vent
Tank
Port and
Cooling Starboard
Water Overboard
From Vaporiser De-icing
in LNG Room
V934 V934
TCV
914A H.F.O Tank
Hot V1009 V1000
Water V1030
Heater
V914 V914A V914
1st Poop Dk Port To Fire Pump
V1010
V913B V1030 V1000 Sea Chest
V914
De-icing
V1011
V917
V901A PCV
Makeup from V912A V913A To FO Tanks
PIC 013A
Desuperheated 53
Steam System To FO Tanks Key
V900A and Boilers Contaminated
V815 PT V913 Steam Exhaust
53 V912 V901 Condenser
Cont. Condenser
Steam
V904 V1002
V814 V814A V814B PI V900 Condensate
53
LP Steam
V904 V904A V904 Instrumentation
To LP Steam TI PI To To
Generator IG Dehumidifier Electrical Signal
Generator 10 bar at 20 tonnes/h Dryer Filter Tank Filter Tank
Heating Coils Mooring Winch
5.4 Deck Machinery and Systems Each winch uses a double acting 2 cylinder steam engine driving a single Operating Procedure - Normal
reduction gear in an oil bath. The main gear case bearings and the crosshead
are force lubricated from a plunger type pump. The winches are ready for service, the steam system supply valves are open
5.4.1 Mooring Winches, Windlasses and Deck Steam System
and there is no condensate (eg, arriving in harbour):
Operating Procedure for Winches Unused for a Long Period
Windlass a) Open the winch steam supply valve.
If the winches have been left unused for a long period of time, the following
Maker: AS Pusnes Mekaniske Verksted procedure should be applied: b) Engage the drum or head coupling by moving the coupling lever,
Chain stopper type: WRW 14 if necessary, moving the control lever gently around the
Cable lifter type: M60 CU 14a0.14a a) Check the oil level in the gear case by observation of the dipstick. NEUTRAL position. When engaged, lock the coupling lever with
the locking pin.
Mooring Winches b) Check that the supply steam valves are closed (on all winches)
and check that all control levers are at the NEUTRAL position. c) Control the winch by slowly moving the control lever in the
Windlass Winches required direction.
Maker: AS Pusnes Mekaniske Verksted c) Open the deck steam system supply valve.
Type: 30/60 SM d) To hoist/heave in, push the control lever slowly in the HEAVE
No. of sets: 2 d) Check that all the drums and heads have their drives disengaged direction. The speed increases proportionally with the lever
and that the brakes are on. Set the control lever to the LOWER travel.
Focsle Centre Winch position.
Maker: AS Pusnes Mekaniske Verksted e) To lower/pay out, pull the control lever slowly in the LOWER
Type : 30 SM e) Open the exhaust valve. direction.
No. of sets: 1
f) Open the bypass valve (between the supply and exhaust lines). Sensitive Winch Handling Procedure
Focsle Port and Starboard Outer (Spring) Winches
Maker: AS Pusnes Mekaniske Verksted g) Open the drain cock. When very slow or delicate winch handling is required, the procedure is as
Type: 30 SM follows:
No. of sets: 2 h) Open the supply steam valve until the winch runs very slowly and
leave in this condition for approximately 2 minutes. a) Before engaging or connecting up to the load, close the steam
Aft Port and Starboard Outer (Spring) Winches supply valve.
Maker: AS Pusnes Mekaniske Verksted i) Close the drain cock and the bypass valves. This will cause the
Type: 30 SM winch to accelerate. If any water shocks are observed, repeat the b) Set the control lever to the HEAVE position.
No. of sets: 2 draining sequence.
c) Connect up the load. The winch is now controlled by means of
Aft Mooring Deck Port Starboard Outer Winches j) Slowly close the supply steam valve until the winch is idling adjusting the steam supply valve: Open the valve slowly to hoist
Maker: AS Pusnes Mekaniske Verksted slowly. Lubricate all the bearings (for further in-depth lubricating and close it slowly to lower the load. When lowering, the load will
Type: 30 SM instructions refer to the manufacturer’s manual). run away in a controlled manner, opening the valve
No. of sets: 1 (anticlockwise) will apply a braking effect.
k) Increase the speed to full slack-rope speed for approximately 3 or
Aft Mooring Deck Midship Winches 4 seconds.
Maker: AS Pusnes Mekaniske Verksted
Type: 30 SM l) Move the control lever to the NEUTRAL position. The winch is
No. of sets: 2 now ready for service. If the winch is not to be used immediately,
the steam supply valve should be closed.
The deck winches and windlass are fed from the deck steam system. This
system is fed from the engine room low pressure steam generator. For further
information about the deck steam system, see the vessel’s Machinery
Operating Manual section 2.1.2 Desuperheated Steam System.
Live Steam
Valve
Exhaust Steam
Valve
Views of WInch/Windlass Drive Cylinders and Main Gear Wheel Showing Pistons etc
b) When the anchor is fully home, the winch heave can then be
increased to ensure the anchor is seated correctly for lashing.
d) Close the steam supply valve and disengage the cable lifter.
View of the Windlass Hydraulic Brake
No.4
5.4.3 Pilot and Accommodation Ladders Illustration 5.4.3a Required Boarding Arrangement for Pilot
3 to 7 metres depending on
Man-ropes without Spreader
size of pilot launch and swell
knots. Min. diameter Min. 180cm long
28mm (If required
by pilot)
TOLIP PILOT
Hoisting
Winch
Upper Deck
Hoisting Wires
Hoisting
Winch Hoisting Wire
Plan
Maximum
Angle 55°
Hoisting
Rail For Upper Rest's Pilot Ladder
Winch
Platform
Turn
Table
One aluminium alloy accommodation ladder is provided on each side of the h) Check there is a lifebuoy available, that the deck is clear of
main deck. The ladders are traversed, lowered and hoisted by means of obstructions and a heaving line is ready. If using the ladder in
compressed air motors operated from a control stand situated at the ship’s side. port, a safety net is to be rigged.
(Note: The ladders are designed to reach the ballast water line with an angle Securing
of inclination of not more than 55°. Always leave at least 2 layers of wire on
the lowering drum. Always check it is safe to lower or raise the ladder.) a) Hoist the ladder until the handrails are just below the davit.
Procedure for Lowering the Accommodation Ladder b) One man wearing harness and an inflatable life jacket unlashes
the platform and ladder ropes.
The accommodation ladder on the port or starboard side is controlled from its
own control stand. Compressed air motors are used to hoist/lower and to swing c) Swivel and remove the stanchions from the upper and lower
the ladder in and out. platforms of the ladder.
WARNING d) The second man wearing harness and an inflatable life jacket
This procedure requires work to take place outside of the ship’s rails. removes the pins securing the ladder handrails, one at a time. He
Appropriate personal protective equipment should be donned including then lowers each handrail in turn, so that the handrails rest flat on
lifelines attached to a suitable strong point. At night there must be the ladder.
adequate illumination to safely complete the task.
e) When the men are clear, hoist the ladder until it is vertical.
Rigging
f) Secure the ladder with all the lashings.
a) From the stowed position, un-ship all of the wire lashings.
g) Close the main air supply valve. Apply the covers to the winch
b) Ensure the air supply valve is open, blow the air supply line free and air motor. Remove the hose from the air motor and stow it to
of water and drain the water filter. ensure that the deck is kept clear.
e) One man is to go down the ladder until he is just below the davit,
and raise each handrail in turn. The man at the ladder top secures
the handrails with the pins. In order to move up and down the
ladder safely, the safety harness can be attached to the wire
lashings.
5.4.4 Deck Cranes The local start and stop pushbuttons for each crane are on the lower pedestal.
The wire rope is of 20mm nominal diameter and should be lubricated regularly
Hose Handling Crane with an appropriate lubricant.
Maker: Acta The wire sheaves are provided with roller bearings on steel axles. All bearings
No. of sets: 2 have grease nipple lubrication.
Type: HHC-30-26.7-12
SWL: 2.67 tonnes at 12 metres radius Hoisting Machinery
The winch unit consists of:
Provisions Crane Drum with bearing and brackets
Maker: Acta Winch gear with spring operated/pressure release fail safe brake
No. of sets: 1
Hydraulic motor with safety valve to freeze movement in case of
SWL: 4 tonnes at 12 metres radius
pressure drop
Description
Starting Procedure
Electro hydraulically driven deck cranes are provided for handling the cargo
a) Check that the control levers are in NEUTRAL.
hoses, fuel hoses and provisions and stores. The hose handling cranes are
positioned above the port and starboard manifolds and the provisions crane is
b) Check that the wire is run correctly in the sheaves and that the
positioned on the main deck at the port aft end of the engine casing.
wire rope ends are securely clamped.
Crane Control
c) Check the oil level and condition of the hoses and connections.
The crane is controlled from an open platform above the slewing ring.
Entrance to the platform is by ladder. All motions have stepless speed control
d) Start up the electric motor/hydraulic pump.
from 0 to maximum. Two motions can be operated at the same time with full
capacity, but with reduced speed.
e) If the ambient temperature is less than 10ºC, let the crane run until
the oil temperature is a minimum of 10ºC.
Load Limiting System
Each hydraulic circuit is provided with equipment for limiting hydraulic
f) Check that all movements (hoist-luffing-slewing) are operational
pressure to preset values corresponding to the crane capacity. These do not stop
without load.
the electric motor but divert the oil supply back to the holding tank.
g) The crane is ready for use.
Limit Switches
The crane is provided with an automatic hook stop when the hook reaches the
Parking the Hose Handling Crane
maximum top and bottom positions.
a) Park the crane with the jib in a horizontal position and resting on
Electro-Hydraulic Power Pack
the jib support cradle.
The crane is provided with a built in power pack. The electric pump/motor is
b) Stop the pump/motor.
located in the centre of the pedestal with the output shaft pointing upwards and
driving the hydraulic pump through a flexible coupling and shaft. The resevoir
c) Fit the jib securing bracket.
for the hydraulic oil is located in the upper rotating part of the crane pedestal.
The hydraulic oil circuit has a full flow suction filter with a changeable filter
insert.
The starter panels for the hose handling cranes are situated in the LPG electric
motor room, aft of the LPG switchboard and the starter panel for the provisions
crane is situated on the distribution board on the No.1 deck cross alleyway.
Lifeboat
Deck - 1 Deck - 2
Cabin
Acc 113 Acc Vent lift wc
Vent Lift wc
Vent Vent
Cabin Crew
Boiler Engine Swimming Boiler Engine
107 Day Room
Casing Casing Pool Casing Casing
Cabin
103
Cabin
104
Cabin
Incinerator 208
Room Cabin
108
Cabin
Acc AB Seam Acc
Vent Change Cabin Vent Linen 214
Vent Room Vent
116
Drying
Cabin
Room Cabin 218
120
Laundry
Cabin Cabin Cabin
132 236 222
Lifeboat
Key
Alarm Horn
Alarm Bell
Alarm Pushbutton
Deck - 3 Deck - 4
2nd wc 2nd
Engineer's Engineer's
Bedroom Day Room
3rd
Engineer's
Air Acc Vent lift wc Engine lift wc Bedroom
Conditioning Vent Vent
Engine
Vent Cargo
Boiler Engine Conference Engineer's
Casing Casing Room Bedroom
Hatch Cargo
Engineer's
Cadet Day Room
Engine
Vent
Air Acc Drying Officer TV Room Engine Changing Electrician's
Vent Room Cabin
Conditioning Vent Vent Room
Store Laundry
Catering
Cadet Officer's
Bedroom wc 3rd Officer's
Dispensary
Cabin
Key
Alarm Bell
Alarm Pushbutton
Deck - 5 Deck - 6
wc
Accessories
Spare
Cabin Pantry wc
Chief Engineer's
Bedroom
Chief
lift wc
Engineer's
Office
Chief Engineer's
Day Room
Hatch
Captain's
Day Room
wc
G
Captain's
Chief Office
Officer's
Office
Captain's
Bedroom
wc
Chief
Officer's
Bedroom Chief
Officer's
Day Room
wc
Key
Alarm Bell
Alarm Pushbutton
Illustration 5.5.1d Fire Detection and Alarm - Upper Deck and Engine Room
Key
CO2 Siren-Air Operated Alarm Horn Gas Detector - Portable Gas Detector Points
Lifeboat
Deck - 1 Deck - 2
Cabin
Acc 113 Acc Vent lift wc
Vent Lift wc
Vent Vent
Cabin Crew
Boiler Engine Swimming Boiler Engine
107 Day Room
Casing Casing Pool Casing Casing
Cabin
103
Cabin
104
Cabin
Incinerator 208
Room Cabin
108
Cabin
Acc AB Seam Acc
Vent Change Cabin Vent Linen 214
Vent Room Vent
116
Drying
Cabin
Room Cabin 218
120
Laundry
Cabin Cabin Cabin
132 236 222
Key
Cabin Cabin Cabin Cabin Cabin
230 226
140 136 128 Fire Hydrant 2 1.2"
CO2 Nozzle
Lifeboat
9L Water/CO2
12kg Powder
6.8kg CO2
Fire Flaps
Deck - 3 Deck - 4
2nd wc 2nd
Engineer's Engineer's
Bedroom Day Room
3rd
Engineer's
Air Acc Vent lift wc Engine lift wc Bedroom
Conditioning Vent Vent
Engine Conference
Vent Cargo
Boiler Engine Room
Engineer's
Casing Casing Bedroom
Hatch Cargo
Engineer's
Cadet Day Room
Engine
Vent
Air Acc Drying Officer TV Room Engine Changing Electrician's
Vent Room Cabin
Conditioning Vent Vent Room
Store Laundry
Catering
Cadet Officer's
Bed Room wc 3rd Officer's
Dispensary
Cabin
Key
9L Water/CO2
12kg Powder
6.8kg CO2
Fire Flaps
Deck - 5 Deck - 6
wc
Accessories
Spare
Cabin Pantry wc
Chief Engineer's
Bedroom
Chief
lift wc
Engineer's
Office
Chief Engineer's
Day Room
Hatch
Captain's
Day Room
wc
Captain's
Chief Office
Officer's
Office
Captain's
Bedroom
wc
Chief
Officer's
Bedroom Chief
Officer's Key
Day Room
wc Fire Hydrant 2 1.2"
9L Water/CO2
12kg Powder
6.8kg CO2
Fire Flaps
Key
Dry Powder 750kg Container Dry Powder Room International Ship 9L Water/CO2 12kg Dry Powder Release Quick Closing Valve Stop Deck Fans Fire Spray Line
750
Shore Connection
Low Velocity Spray
250 Dry Powder 250kg Container Fire Hydrant 2 1.2" Hold Eductors 12kg Powder 2.5kg Dry Powder Emergency Stop Gas Valves Stop Duct Keel Fans
Applicator
Dry Powder Hose Box Hose Boxes with 18m - 2"/20m 1½ Hose CO2 Nozzle 6.8kg CO2 Fire Hydrant 2 1.2" Emergency Stop Gas Valves Fire Flaps Emergency Fire Pump
with Remote Control and with Unifire V-16 Jet / Fog Nozzle 50m3/h 113mwg
Dry Powder Room Hose Reel W/20m - 1½ Hose CO2 Remote Release 34kg/CO2 Stop Fuel Oil Pumps Stop Accommodation Fans Fire Pumps
and Unifire V-16 Jet / Fog Nozzle and Gas Supply Boilers 2x100m3/h 120mwg A Fire Hydrant 2 1.2"
Lifeboat
Deck - 1 20 Deck - 2
6
20
Cabin
Acc 113 Acc Vent lift wc
Vent Lift wc
Vent Vent
Cabin Crew
Boiler Engine Swimming Boiler Engine
107 Day Room
Casing Casing Pool Casing Casing
Cabin
103
Cabin
104
Cabin
Incinerator 208
Room Cabin
108
Cabin
Acc AB Seam Acc
Vent Change Cabin Vent Linen 214
Vent Room Vent
116
Drying
Cabin
Room Cabin 218
120
Laundry
Cabin Cabin Cabin
132 236 222
20
20
Lifeboat
Key
Survival Suits
Life Jacket
6 Liferaft
Smoke Mask
Deck - 3 Deck - 4
2nd wc 2nd
Engineer's Engineer's
Bed Room Day Room
3rd
Engineer's
Air Acc Vent lift wc Engine lift wc Bed Room
Conditioning Vent Vent
Engine
Vent Cargo
Boiler Engine Conference Engineer's
Casing Casing Room Bed Room
Hatch Cargo
Engineer's
Cadet Day Room
Engine
Vent
Air Acc Drying Officer TV Room Engine Changing Electrician's
Vent Room Cabin
Conditioning Vent Vent Room
Store Laundry
Catering
Cadet Officer's
Bed Room wc 3rd Officer's
Dispensary
Cabin
Key
Life Jacket
Smoke Mask
MOB Lifebouy
Deck - 5 Deck - 6
wc
Accessories
Spare
Cabin Pantry wc
Chief Engineer's
Bedroom
Chief
lift wc
Engineer's
Office
Chief Engineer's
Day Room
Hatch
Captain's
Day Room
wc
Captain's
Chief Office
Officer's
Office
Captain's
Bedroom
wc
Chief
Officer's
Bedroom Chief
Officer's Key
Day Room
wc
Life Jacket
Survival Suits
Lifebuoys
GMDSS VHF
Key
LOADING
(approximately 12 hours) Gas freeing of cargo tanks.
(approximately 24 hours)
Drainage of liquid lines (45 mins)
6.1 Operating Procedures Overview Except in special circumstances (described in section 7) where a single tank or
void space may need to be isolated, the cargo tanks should be connected
together through the vapour line and the void spaces should be connected
The cargo control system is designed to be operated from the cargo control together via the recirculation loop by keeping the valves in these lines open.
room. However, some operations are required locally.
When the ship returns to cargo duties after a dry docking or refit, the tanks and
Equipment and plant such as compressors and pumps are protected by means lines will be full of ambient air. Before liquid cargo is reintroduced into the
of tripping devices which will shut down the plant in the event of an abnormal system, the tanks and lines must be oxygen (O2) and carbon dioxide (CO2) free.
temperature, pressure or other condition which may be harmful to the plant or
equipment if left unattended. In most cases an alarm will be raised before the
The tanks and lines should be oxygen free to avoid the formation of any
shutdown, giving personnel time to attend to the problem before a shutdown
explosive mixture.
occurs.
The tanks, lines and void spaces should be carbon dioxide free as this will
It should be emphasised that personnel should conduct their own routine
solidify at -78.5ºC.
inspections of running machinery in line with recommendations issued by the
individual equipment manufacturers.
There should be no humidity in the tanks and lines as this will lead to the
formation of ice.
There are certain cargo operating parameters that are worthy of special
mention, as follows:
The void spaces should be free from any moisture as this may penetrate the
tank insulation.
Void Space Pressure
The methods of drying and inerting the tanks, void spaces and lines is
To avoid even a remote possibility that the cargo tank shell may buckle, the
described in the appropriate following sections.
pressure of the void spaces should never exceed 0.05 bar over that of the cargo
tanks. There are void space pressure relief valves fitted to avoid this possibility,
see section 4.11.3 Void Space Relief Valves for further information.
To avoid thermal stress on the cargo tank shell and piping, sudden cooling
down must be avoided. The cooling down rates shown in section 6.2.4 should
be strictly followed.
The greatest care must be taken to ensure that the cargo tanks are never
overfilled.
LNG
V2303 V2209
Compressors
V2315 V2315
Void Space
Dryers
V2311 V2311
Recirculation
Fans 2,000m3/h
Purging
V2216 V2216 V2216 V2216 V2216 Outlets
at Dome
Key
Starboard IG Connection at Starboard Manifold Port
Nitrogen Nitrogen Nitrogen
Buffer Buffer
From Tank From IG Outlet Tank Dry Air
Nitrogen 15m3 Engine Room at Starboard Manifold 25m3
Generator IG Plant Moist Air
V2352 V2352 V2352A
System
Liq
LN V2100
uid
Va
V2138
Ni
01 5 V2052
po
32 1 V2
213
tro
V21 V
ur
ge
V2051
Liq
r
ou
Vap ater
n
Liq
PI V2051
uid
He 15
uid
V21 V2051
30 14
32 30 V21 V21 200 V2051
V21 V21 V2
.B 14A 061
Co
mp V21 V2
V2026
34 HD 016 015
A
V21 31 V2 V2
To r 1
ou V21 220 120
iler
s Vap ater V21
14 V
V2
Dome
Bo He 35 Vent 003
V21 061 V2004 V2
V2 Mast
S)
2(
V2101 00
36 A V2
13 V21 016 V2138
V21 35 V2 A V2055
V21 .A 200 V2002 (P)
V2
mp V2
Co No.1
20
V2054
HD
3
V21
28 V2054 Cargo Tank
e 26
pac V21
V2
V2054
3 9 id S er
20
V21 Vo r Dry 14
V2
3A
V2054
Ai V23
V2
17 .
23
V21 mp 25
20
13 Co V2027
4
V21 V21 14
LD V23
3
35 15 26
V22 V23 V21 nt Dome
15 Pla
G
LN iser V23 e N
To 2 007
or pac V2008 V2
Vap id S er Vent
Vo r Dry S)
11 25 A i Mast 6(
V21 V21 m ans V2
00
d 39 Fro ing F ating V2103
Voi re V21 t
cula ace H
e
or V2138
r F osphe c ir
Re id S p V2006 (P)
ate V2058 V2068
He e At m
ac V21
39
For Vo No.2
Sp V2057
V2057 Cargo Tank
V2057
V2057
22
V21 V2028
19
V21
V2
Dome
01
011
2
V2
s Vent (S)
ace Mast 01
0
Sp V2
Void V21
10
To V2108
V2010 (P)
18 V2138
V21 V2064 V2068 No.3
V2063
V2063
Cargo Tank
V2063
V2063
V2029
Spray
Pump
Dome
01 9
V2020 V2 D
Vent (S) FW
18
Mast
V20
V2109
V2066 V2138 V2018 (P)
No.4
V2065
V2065
Cargo Tank
V2065
A
V2065 015
Spray V2
To V2030
Pump
Emergency
120
Discharge Dome V2
Astern 02 3
V2024 V2 061
A V2 015
S) 016 200
A V2
( V2 V2
0 02
V2
35 2 061
V2002 (P) V2 V2
Liq
352A
No.5 V2 201
uid
V2 200
Cargo Tank 352 V2
Va
V2
016 po
Ni
V2 ur
tro
Engine Room
ge
IG Plant
Key
n
Inert Gas
6.2.2 Inerting Cargo Tanks Procedure to Inert after Refit h) By sampling at the vapour dome, check the atmosphere of each
tank using a portable oxygen analyser. The oxygen content is to
Inert gas, with an oxygen content of between 2% and 3% and a dew point of a) Prepare the dry-air/inert gas plant for operation in the inert gas be between 2% and 3% and the dew point is between -25°C to -
between -25°C to -45°C, is produced by the dry-air/inert gas plant at a flow mode. 45°C.
rate of 2,500Nm3/h. The inert gas is primarily nitrogen and carbon dioxide,
containing between 2% and 3% oxygen with a dew point of between -25°C to b) Install the flexible connection between the flange at the end of the i) During tank inerting, purge the air contained in the lines and
-45°C. inert gas/dry-air feeder line and the liquid manifold or access to equipment for about 5 minutes by using the valves and purge
the liquid header. sample points. It is important to ensure that all pipework and dead
Inerting After Refit ends are purged.
c) Install the flexible connection between the flange on the vapour
Before introducing vapour or liquid cargo into the cargo system, it is essential header line and the inlet flange at each tank’s vent mast. j) When the inerting of all the tanks and associated pipework and
that all air is purged from the system to prevent the formation of flammable equipment is completed, disconnect the flexible connection to the
mixtures. In this operation, the object is to replace all air in cargo tanks and d) Open the following valves: vent pipes and replace the flange blanks on the vapour line.
cargo pipework with inert gas.
k) Pressurise the tanks to 0.15 bar.
Position Description Valve
Inert gas from the ship’s IG plant is connected to the LNG liquid header and
led to the bottom of each cargo tank. The displaced air escapes to atmosphere Open Aft liquid manifold valve V2016 l) When all the tanks and pipework have been dried out, stop the
via the LNG vapour header and vent riser. Oxygen measurement is carried out plant. Close the supply valves V2353, V2352, V2354A and
Open Aft liquid ESD valve V2016A
using a portable analyser on samples drawn from each of the five sampling manifold valves V2016 and V2016A to the LNG header.
points in each cargo tank. Venting continues until the oxygen concentration at Open Inert gas supply valve V2352, V2352A Disconnect the flexible hose and replace the flange on the inert
all points is consistently between 2% and 3% and the dew point between -25°C gas supply line.
e) Open the following tank filling valves:
to -45°C.
Position Description Valve (Note: Until the ship is ready to load LNG for gas filling, the tanks may be
The inerting of LNG liquid and spray lines, including manifold crossovers, maintained under inert gas for as long as is necessary. If required, pressurise
Open No.5 cargo tank liquid header block valve V2024 the tanks to 0.05 bar above atmospheric pressure.)
pump risers, vaporisers and relief valve lines, is carried out at the same time as
the inerting of the tanks. LNG vapour lines at the manifold crossover and in the Open No.5 cargo tank liquid filling valve V2023
LNG compressor room are inerted on completion of the rest of the system. WARNING
When purging these pipelines, the volume of inert gas being discharged at deck Open No.4 cargo tank liquid header block valve V2020 Inert gas from this generator and pure nitrogen will not sustain life. Great
level can be minimised by routing the displaced gas, via the pressure build-up Open No.4 cargo tank liquid filling valve V2019 care must be exercised to ensure the safety of all personnel involved with
line, to vent at the vent riser. any operation using inert gas of any description in order to avoid
Open No.3 cargo tank liquid header block valve V2012 asphyxiation due to oxygen depletion.
This operation would be carried out before the ship’s arrival at the loading port. Open No.3 cargo tank liquid filling valve V2011
Other operations which will be carried out in preparation for first loading
would be: Open No.2 cargo tank liquid header block valve V2008
Purging/filling insulation spaces with nitrogen Open No.2 cargo tank liquid filling valve V2007
Purging/filling hold spaces with dry-air. Open No.1 cargo tank liquid header block valve V2004
Open No.1 cargo tank liquid filling valve V2003
As the IG plant is required for this latter operation, it would normally be
carried out either immediately before or immediately after inerting. Nitrogen f) Open the tank vapour valves V2109, V2108, V2103, V2101 and
purging can be carried out at any time before arrival. The inerting operation V2100 to vent through the vent mast on each tank.
takes about 24 hours.
g) Start the inert gas production. When the oxygen content is 4%
(unless oxygen content percentage is specified by the terminal)
and the dew point is between -25°C to -45°C, open the valve
V2353, upstream of the two non-return valves V2352 on the dry-
air/inert gas discharge line. Also open valve V2354A to allow the
inert gas to pass into the liquid header.
Liq
Va
LN V2100
uid
po
V2138
Ni
V2052
ur
1 5
32 213 201
tro
V21 V V
Liq
ge
V2051
Liq
r
ou
Vap ater
n
PI V2051
uid
uid
He 15
V21 V2051
30 14
32 3 0 V21 V21
V21 V21 200 V2051
.B 14A V2 A
mp V21 016 061 015 V2026
Co V2 V2 V2
34 HD
V21 31
To r
ou V21 220
1
iler
s Vap ater V21
14 V 120
Vent Dome
Bo He 35 V2 Mast 003
V21 061 V2004 V2
V2 00A
old 2 S)
anif e V2 2(
00
m M Lin 36
V2101 V2
Fro iquid 13 V21 A V2138
L
V21 V21
35 016 V2055
.A V2 V2002 (P)
V2
mp
Co No.1
20
V2054
HD
3
V21
28 V2054 Cargo Tank
e 26
pac V21
V2
V2054
3 9 id S er
20
V21 Vo r Dry 14
V2
3A
V2054
Ai V23
V2
17 p.
23
V21 m
20
13 Co V2027
4
V21 14
LD V23
3
25 26
35 V21 V23
15
V21
V22 rise
r
Dome
15 o Vent
G
LN iser V23 e Vap 007
or pac LN
G Mast V2008 V2
Vap id S er To
Vo r Dry S)
11 25 A i 6(
V21 V21 m ans V2
00
Fro ing F ating
d 39 t e V2103
Voi re V21 ula eH
or circ Spac V2138
r F osphe R e V2006 (P)
ate Void V2058 V2068
He e At m
ac V21
39
F or No.2
Sp V2057
V2057 Cargo Tank
V2057
V2057
22
V21 V2028
19
V21
V2
Dome
01
Vent 011
2
Mast V2
ace
s
0 (S)
Sp 01
Void 10 V2
To V21 V2108
V2010 (P)
18 V2138
V21 V2064 V2068 No.3
V2063
V2063
Cargo Tank
V2063
V2063
V2029
Spray
Pump
Dome
Vent 01 9
Mast V2020 V2 D
(S) FW
8
01
V2
V2109
V2066 V2138 V2018 (P)
No.4
V2065
V2065
Cargo Tank
A
015
V2065 V2
V2065
V2030 Spray
To Pump
Emergency 120
A V2
Discharge 200
3
Dome V2
Astern 02
V2024 V2 A 061
016 V2 015
( S) V2 V2
0 02
V2
061
V2002 (P) V2
Liq
No.5 201 Key
uid
V2
Cargo Tank 200
V2
Va
016 po Inert Gas/Vapour
Ni
V2 ur
tro
Liq
ge
n
uid
LNG Liquid
LNG Vapour
Inert Gas
6.2.3 Gassing Up Cargo Tanks There are exceptional cases where it may be necessary to undertake the (Note: For safety reasons, ensure the water curtain on the connected side is in
purging of one or more tanks at sea using LNG liquid already on board. In this operation.)
After a lay up or dry dock period, the cargo tanks are filled with inert gas or case the liquid will be supplied to the LNG vaporiser via the stripping/spray
nitrogen. If the purging has been done with inert gas, the cargo tanks have to header using the stripping/spray pump of No.3 or No.4 cargo tank containing k) Using the DCS system mimic, open the following cargo tank
be purged and cooled down when the vessel arrives at the loading terminal. LNG liquid. loading valves:
This is because, unlike nitrogen, inert gas contains 15% carbon dioxide (CO2), Position Description Valve
which will freeze at around -78°C and produces a white powder which can Due to local regulations on venting methane gas to the atmosphere, some port
block valves, filters and nozzles. authorities may require the entire operation to be carried out with the exhaust Open No.1 tank loading valves V2004, V2003
gases being returned to shore facilities.
Open No.2 tank loading valves V2008, V2007
During purging, the inert gas in the cargo tanks is replaced with warm LNG
vapour. This is in order to remove any freezable gases such as carbon dioxide Operating Procedures to Purge the Cargo Tanks with LNG Vapour Open No.3 tank loading valves V2012, V2011
and to complete the drying of the tanks. Open No.4 tank loading valves V2020, V2019
It is assumed, although unlikely, that all valves are closed prior to use.
Description Open No.5 tank loading valves V2024, V2023
a) Install the following spool pieces:
l) Open valve V2120, if using the port vapour manifold, and inform
LNG liquid is supplied from the terminal to the liquid manifold where it passes Liquid manifold header to vaporiser supply line the shore terminal to prepare for receiving gas to shore.
to the stripping/spray header via the appropriate ESDS liquid valve. It is then
fed to the LNG vaporiser and the LNG vapour produced is passed at +20°C to Liquid header to vapour line
m) Open valve V2016, if using the aft port liquid manifold, and
the vapour header and into each tank via the vapour domes. b) Swing the liquid header to vaporiser supply line spectacle piece request the shore terminal to commence the supply of LNG to the
into position. ship at a constant pressure of 5 bar.
At the start of the operation to fill the cargo tanks, the piping system and LNG
vaporiser are vapour locked. The stripping/spray header can be purged into the c) Prepare the LNG vaporiser for use. n) Adjust the tank pressure by decreasing/increasing the flow rate of
cargo tanks via the vapour dome through the arrangement of spray valves
LNG from the shore. The pressure can also be released by
containing the control valve until the liquid reaches the LNG vaporiser. The d) Adjust the set point of the temperature control valve to +20°C. adjusting the pressure relief valve setting at No.4 vent mast,
LNG vapour is lighter than the inert gas, which allows the inert gases in the
however, most terminals prefer the gas to be returned to shore.
cargo tanks to be exhausted up the tank filling line to the liquid header. The e) Adjust the set point of the pressure control valve V2203A to 6kPa
inert gas then vents to the atmosphere via the vent masts. (or required value) by using the inching control (manual control). o) Monitor the inert exhausting gas at each liquid dome. Use the mid
cargo tank sampling cock initially, followed by the sample cock at
When 5% methane (the percentage figure will be specified by the particular f) Open valves V2201 and V2200A to enable the supply to reach the the top of the loading line.
port authority) is detected at the vent mast riser, the exhaust gas is directed LNG vaporiser.
ashore via the HD compressors, or to the boilers through the gas burning line.
p) Purge all pipework and dead ends with warm LNG vapour or
This operation can be done without the compressors, subject to existing back g) Open LNG vaporiser inlet valve(s) V2203. nitrogen if available.
pressure, or with one or more HD compressors in service. If possible, it is
better not to use the compressors to avoid creating turbulence inside the tanks. h) Open LNG vaporiser outlet valve(s) V2235. q) When 5% methane is detected at the sampling points at all tanks
inform the shore terminal so that they can divert the exhaust gases
The operation is considered complete when the methane content, as measured i) Open valve V2118 to allow the supply to the vapour header. to the terminal facilities.
at the top of the cargo filling pipe, exceeds 80% by volume.
j) Open the following valves to the vapour domes:
The target values for N2 gas and inert gas CO2 is equal or less than 1%. These
values should be matched with the LNG terminal requirements.This normally
entails approximately 2 complete changes of the volume of the atmosphere in Position Description Valve
the cargo tank. Open No.1 tank header valve V2100
On completion of purging, the cargo tanks will normally be cooled down. Open No.2 tank header valve V2101
Open No.3 tank header valve V2103
Open No.4 tank header valve V2108
Open No.5 tank header valve V2109
Tons
20
Spray Pipe 1 4 1 4
4 1&2
-0
Co
ol
Spare Units do
-20 wn Filling Rate
PI 1 2 3 4 Ra 1,500 m3/h
22 te
Li Each Tank
3 m
ita
-40 tio
n Start
EQUATOR 9
SPRAY
O
C/ Loading
TEMPERATURE h
RATE (OC)
(kg/h 103) -60
15.9 Hours
-80 Loading
2
Finished
-100
Spray Pipe 1
Maximum Temperature at Equator Before Loading (-113 OC)
-120
Initial Spray Rate
1
Maximum Temperature at Equator When the Liquid Level is 1 m Below (-138 OC)
-140
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30
0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 TIME (h)
PRESSURE AT PI-22 (kg/cm2)
Position Description Valve Whenever a cargo tank is cooled down completely from ambient temperature,
Open No.1 cargo tank vapour valve V2000 the tank shell temperature, measured at the equator (from sensor TI-10), should
be recorded on the relevant time/temperature graph form.
Open No.2 cargo tank vapour valve V2101
Open No.3 cargo tank vapour valve V2103
Open No.4 cargo tank vapour valve V2108
Open No.5 cargo tank vapour valve V2109
Open Vapour header to LNG compressor room valve V2110
Open LNG compressor room discharge valve V2119
Open Vapour manifold ESD valve V2120
Liq
mp Room
Co
uid
G
LN
Va
V2100
015
p
V2138
Ni
V2 V2052
ou
132 31
tro
V2 V21
r
ge
V2051
Liq
r
ou
Vap ater
n
Liq
PI V2051
uid
He 15
uid
V21 V2051
30 14 200
32 30 V21 V21 V2 V2051
V21 V21
p.B 14A 061 015
A
m V21 016 V2 V2 V2026
34 Co V2
V21 HD
To r 31 1
ou V21 V2
20
120
iler
s Vap ater V21
14
V2
Vent Dome
Bo He 35 Mast 003
V21 061 V2004 V2
V2
S)
2(
A 00
36 016 V2101 V2
V21 V2 0 A
13 35 220 V2138
V21 V21 V V2055
V2002 (P)
.A
V2
mp
Co No.1
20
V2054
HD
3
V21
28 V2054 Cargo Tank
e 26
pac V21
V2
V2054
39 id S er
20
V21 Vo r Dry 14
V2
3A
i V2054
A V23
V2
17 .
23
V21 mp
20
13 Co V2027
4
V21 14
LD V23
3
35 25 5 26
V22 V21 V23
1
V21 t
P lan Dome
15 Vent
G
LN iser V23 e N
To 2 007
or pac Mast V2008 V2
Vap id S er
Vo r Dry S)
11 25 A i 6(
V21 V21 m ans V2
00
d 39 Fro ing F ating V2103
t e
Voi re V 1
2 cula ace H
or ir V2138
r F osphe c
Re id S p V2006 (P)
ate Vo V2058 V2068
He e Atm
ac V21
39
Fo r No.2
Sp V2057
V2057 Cargo Tank
V2057
V2057
2
V 212 V2028
19
V21
V2
Dome
01
Vent 011
2
Mast V2
s (S)
ace 01
0
Sp V2
Void 10
To V21 V2108
V2010 (P)
18 V2138
V21 V2064 V2068 No.3
V2063
V2063
Cargo Tank
V2063
V2063
V2029
Spray
Pump
Dome
Vent 019
Mast V2020 V2 D
S) FW
8(
01
V2
V2109
V2066 V2138 V2018 (P)
No.4
V2065
V2065
Cargo Tank
A
V2065 015
V2
V2065
V2030 Spray
To Pump 120
Emergency
A V2
Discharge Dome 200
3 V2
Astern
V2024 V 202 061
A V2 015
016 V2
2 (S) V2
00
V2
061
V2002 (P) V2
Liq
No.5 201 00
uid
V2 2
V2
Cargo Tank
016 Va
po
Ni
V2
ur Key
tro
Liq
ge
n
uid
LNG Liquid
LNG Vapour
d) When the temperature in the liquid header at all the cargo tanks Then start the spray pumps as follows:
has fallen to -120ºC, the gate valve V2015 may be fully opened
and the loading valves at No.2, 3 and 4 cargo tanks can be opened. a) Open the spray pump discharge valve V2068.
The vessel is now ready to load. b) Open the 1 and 4 tonne nozzle valves on each tank.
Liq
G C
LN V2100
uid
Va
V2138
Ni
015 V2052
po
32 31 V2
tro
V21 V21
ur
ge
V2051
Li q
r
ou
Vap ater
n
Liq
PI V2051
ui d
He 15
uid
V21 V2051
30 14
32 30 V21 V21 200 V2051
V21 V21 V2 A
.B 14A 061 015
Co
mp V21 016 V2 V2 V2026
34 HD V2
V21 31
To r
201
ou V21 0
iler
s Vap ater 211
4 V2 212 Vent Dome
Bo He 35
V V Mast 003
V21 061 V2004 V2
V2
A 2 (S)
016 00
3 6 V2 200
A V2101 V2
13 V21 5 V2 V2138
V21 V21
3 V2055
V2002 (P)
.A
V2
mp
Co No.1
20
V2054
HD
3
V21
28 V2054 Cargo Tank
e 26
pac V21
V2
V2054
39 id S er
20
V21 Vo r Dry 14
V2
3A
V2054
Ai V23
V2
17 p.
23
V21 om
20
13 V2027
4
V21 DC 14
V 3
2
3
L
35 25 15 26
V22 V21 V23 V21 nt
15 Pla Vent
Dome
G
LN iser V23 e N
To 2 007
or pac Mast V2008 V2
Vap id S er
Vo r Dry (S)
11 25 Ai 06
V21 V21 m ans V2
0
d 39 Fro ing F ating V2103
t e
Voi V21 ula eH
or here circ Spac V2138 V2006 (P)
rF p R e
ate tmos o id V2058 V2068
e
H eA
ac V21
39
For
V No.2
Sp V2057
V2057 Cargo Tank
V2057
V2057
22
V21 V2028
19
V21
V2
Dome
01
Vent 011
2
Mast V2
es (S)
S pac 01
0
V2
Void 10
To V21 V2108
V2010 (P)
18 V2138
V21 V2064 V2068 No.3
V2063
V2063
Cargo Tank
V2063
V2063
V2029
Spray
Pump
Dome
Vent 01 9
Mast V2020 V2 D
(S) FW
0 18
V2
V2109
V2066 V2138 V2018 (P)
No.4
V2065
V2065
Cargo Tank
V2065
A
015
V2065 V2
V2030 Spray
To Pump 120
Emergency V2
Discharge Dome
Astern 023 A
061
V2024 V2 200 V2
V2 015
V2
2 (S)
V2
00
20 16A
V
061
V2002 (P) V2
Liq
No.5 201 0
u
V2 20
id
Cargo Tank V2
016
Va
po
Ni
V2
ur Key
tro
Liq
ge
n
uid
LNG Liquid
LNG Vapour
6.3 Ballast Passage 6.3.1 Cooling Down Cargo Tanks Prior to Arrival f) Start the spray pump and circulate the LNG back to No.3 tank (or
No.4 tank) via the spray nozzles.
Cooling Down Cargo Tanks During a Ballast Voyage When loading orders are received, the quantity of coolant (heel) has to be
decided, taking into consideration the length of ballast voyage and chartering g) Open the following spray ring block and nozzle valves to allow a
The spray cooling system is fitted to cool down the cargo tanks before the instructions. flow to the tanks:
loading of cargo. This is in order to protect the tank shell against the thermal
stresses and shocks of sudden expansion. The coolant is taken in one (#3 or #4). Regarding the temperature restriction to Position Description Valve
be kept in the equator profile during the voyage due to low filling-up ratio,
The spray system consists of the piping and the spray pumps. The piping refer to the Appendix to Classification Certificate. Open No.1 cargo tank spray ring block valve V2052
consists of a main header, running along the ship from tank No.1 to tank No.5.
Open No.1 cargo tank spray ring nozzle valves V2051A, V2051B
This header is connected to the liquid crossovers for LNG cargo supply from A spray programme has to be made in such a way that the cargo tanks’ equator
the shore and to the two spray pumps. One pump is fitted in tank No.3 and the temperature, on arrival in port, is according to the charter’s instruction/order. Open No.2 cargo tank spray ring block valve V2055
other in tank No.4, for the supply of LNG when the ship is at sea.
Open No.2 cargo tank spray ring nozzle valves V2054A, V2054B
The use of BOG as fuel has to be optimised during the voyage.
The spray pipe header is connected to each tank dome by four spray pipes Open No.4 cargo tank spray ring block valve V2064
supplying the spray nozzles with liquid. Two of the pipes serve as spare units. The spray pump(s) have to be used at the designed flow when operated. Low Open No.4 cargo tank spray ring nozzle valves V2053A, V2053B
The LNG is sprayed through the 10 spray nozzles in each tank to obtain a flow will give an unacceptably high down thrust load on the pump lower
uniform distribution within the tank. There are also 10 spray nozzles spare in bearing. Open No.5 cargo tank spray ring block valve V2066
each tank. The spray nozzles are connected to the main system by four spray
Open No.5 cargo tank spray ring nozzle valves V2065A, V2065B
pipes of which pipes No.1 and No.2 would normally be used. Pipe No.1 CAUTION
supplies two nozzles and pipe No.2 supplies eight nozzles. The spare units, The pressure and ampere load for the pump(s) have to be watched
pipes 3 and 4 also supply the same number of nozzles. carefully to avoid a possible breakdown of the bearing. h) Once the pipelines are cooled down, the flow rate can be
increased by opening up the spray nozzles and shutting No.3’s
The nozzles connected to pipe No. 1, 2 and 4, each have a spray rate capacity Preparation for Cooling Down the Cargo Tanks nozzles, ensuring that the pressure build up is controlled at all
of 500kg of LNG at 1.53kg/cm2 pressure drop across the nozzle. The nozzles times. In an emergency or critical situation, excess pressure can
connected to pipe 3 each have a capacity of 1,000kg of LNG. a) The LD compressor would normally be in operation supplying be vented through the valve to No.4 vent mast.
BOG to the boilers.
If severe flashing occurs, the remaining nozzles may be used in order to keep i) The cooling down rate must not exceed 9°C per hour, measured at
the minimum cooldown time. The spray rates are remotely controlled from the b) Open the following vapour header tank valves: the equatorial ring.
DCS system by operation of the shut-off valves. The cooling down rate must
not exceed 9ºC per hour measured at the equatorial ring. j) The cargo tank is ready for loading when the temperature of the
Position Description Valve tank shell at the equator has dropped to at least -113°C. This
Open No.1 cargo tank vapour header valve V2100 temperature represents a total cooling down time of
approximately 20 hours.
Open No.2 cargo tank vapour header valve V2101
Open No.3 cargo tank vapour header valve V2103
Open No.4 cargo tank vapour header valve V2108
Open No.5 cargo tank vapour header valve V2109
c) Cool down the spray pipes using the spray pump in No.3 or No.4
tank.
d) Open valve V2068, from the spray pump to the spray header.
e) Open valves V2058 and V2057 A and B if using No.3 spray pump
and tank.
(Note: The maximum loading rate is 7,500m3/h with all five tanks open. See The loading rates are dependant on the capacity of the shore side pumps,
the appendix to classification certificate.) below is a guide to the rates which can be safely taken.
5 tanks open: 7,500m3/h
a) The chief officer is to prepare a detailed loading and deballasting
plan which includes the trim and stability conditions during 4 tanks open: 6,000m3/h
loading and the topping up procedures to be included. 3 tanks open: 4,500m3/h
b) The pre-arrival meeting is to be held within 72 hours and the pre- 2 tanks open: 3,000m3/h
arrival checklists are to be completed.
1 tanks open: 1,500m3/h
c) A pre-loading meeting is to be held together with the terminal Compressor Vapour Return Capacity
representatives. The ship/shore safety list is to be filled in.
1 HD compressor running: 12,000m3/h
d) The CTM is to be carried out together with the terminal 2 HD compressors running: 36,000m3/h
representatives, surveyors and authorities.
(LD compressor: 3,000m3/h)
e) All connections (bonding wire, telephones, loading and bunkering
arms) at the manifold are to be carried out according to the
terminal’s cargo handling manual.
Liq
o mp Room
C
uid
G
LN
Va
V2100
015
Ni
po
V2 V2052
tro
32 31 V2138
ur
V21 V21
ge
V2051
Li q
r
Liq
ou
n
PI Vap ater V2051
ui d
uid
He 15
V21 V2051
3 0 1 4 200
32 130 V21 V21 V2 V2051
V21 V2 5A
.B 14A 206
1
201
Co
mp V21 016 V V V2026
34 V2
V21 HD
To r 31 20 1
ou V21 V2 120
iler
s Vap ater V21
14 V2
Vent Dome
Bo He 35 Mast 003
V21 061 V2004 V2
V2
S)
2(
A 00
36 016 V2101 V2
13 V21 V2
200
A
V21 35 V2
V2055
V21 .A
V2138 V2002 (P)
V2
mp
Co No.1
20
V2054
HD
3
V21
28 V2054 Cargo Tank
e 26
pac V21
V2
V2054
3 9 id S er
20
V21 Vo r Dry 14
V2
3A
V2054
Ai V23
V2
17 .
23
V21 mp
20
13 Co V2027
4
V21 14
LD V23
3
25 15 26
V22
35 V21 V23 V21 nt
Pla Dome
15 N Vent
G
LN iser V23 e To 2 V2008 007
or pac Mast V2
Vap id S er
Vo r Dry S)
11 25 A i 6(
V21 V21 m ans V2
00
d 39 Fro ing F ating
t e V2103
Voi re V21 ula eH
or
r F osphe ecirc Spac V2006 (P)
ate R V2138
He e At m 39 Void V2058 V2068
No.2
ac V21 Fo r
V2057
Sp
V2057 Cargo Tank
V2057
V2057
22
V21
V2
V2028
01
19
2
V21
Dome
Vent 011
Mast V2
s (S)
ace 01
0
Sp V2
Void 10
To V21 V2108
V2010 (P)
18
V21 V2064 V2068 V2138
No.3
V2063
V2063
Cargo Tank
V2063
V2063
V2029
Spray
Pump
V2020 Dome
Vent 01 9
Mast V2 D
(S) FW
18
V 20
Liq
No.5 201 00
uid
V2 2
V2
Cargo Tank
Va
016
po
Ni
V2
Key
ur
tro
Liq
ge
n
uid
LNG Liquid
LNG Vapour
6.4.2 Cargo Lines Cooldown o) When the gas analyser shows 50% Lower Explosion Limit (LEL), Position Description Valve
the ship’s vent mast must be closed and the vapour must then be
Open No.1 cargo tank liquid line valves V2003 V2004
Inerting and Gassing Up sent to the boilers for use as fuel and/or to the shore for flaring (or
in accordance with terminal requirement). Open No.2 cargo tank liquid line valves V2008 V2007
a) Shipboard management (ie, Master, chief officer and chief Open No.3 cargo tank liquid line valves V2012 V2011
engineer) and cargo engineer plan the operation. p) The gasup (purging) is completed when the CO2 readings at all
outletsis <1% by volume (refer to the terminal requirement) at the Open No.4 cargo tank liquid line valves V2020 V2019
b) All gas measuring equipment is to be tested and calibrated. manifolds, vent mast connections, drains and gauge piping. Also
Open No.5 cargo tank liquid line valves V2024 V2023
all outlets on compressors and adjacent piping must be measured
c) All relevant safety regulations are to be adhered to. for any traces of O2 or CO2. c) Open the port aft ESD valve V2016A and starboard forward ESD
valve V2015A.
d) The Master will advise when the operation can commence. q) All additional equipment used during the process is to be rigged
down. Blind flanges are to be refitted and drains and test points d) Open the manifold block valves V2015 and V2016 on the side
e) The cargo engineer is to check the tanks for any leftovers and are to be closed before the cooldown is commenced. arms connected. Open the ESD valve V2015A and V2016A and
secure all hatches in the tanks. The check list for closing down the request the shore to supply LNG at a slow rate to cool down the
cargo tanks is to be filled in. The cargo engineer is to be the last r) The cargo engineer is to prepare the HD compressors for use shore arms and liquid header.
person to leave the tank. before the cooldown is commenced.
e) Open the three gate valves V2061, connecting the spray crossover
f) The cargo lines are to be checked for any signs of water by s) The cool down of the cargo tanks is to be carried out according to to the liquid crossover, allowing a limited flow into the liquid
opening the drains, flanges etc. the respective cargo handling manual and the temperature lines.
requirements laid down in the appendix to the classification
g) The inert gas generator is to be tested and adjusted in due time certificate. The pre-cooling must be thoroughly monitored by observation of the
before the operation is commenced. temperatures and pressures. Temperature monitoring at the liquid header and
t) All temperatures, pressures and the cooldown rate are to be crossover connection and at each cargo tank is available at the DCS mimic.
h) The dehumidifiers are to be reactivated and made ready for use. recorded according to the cooldown report. The pressure at the header between the two crossovers is also available via the
DCS system mimics. If a high pressure is observed at this point, the HD
i) The inert gas is to be checked at regular intervals for the correct u) The shore terminal is to be advised in due time for cooling down compressor(s) should be started and the flow rate reduced.
O2, dew point and CO2 content. The chief officer/cargo engineer the remaining loading arm(s).
is to take the final readings. f) When the temperature at the liquid header at the tanks has fallen
Pre-Cooling of Liquid Pipes Before Loading to approximately -120°C, the gate valves may be opened slowly
j) The chief officer is to prepare a detailed purging, loading and and the last shut-off valve at the manifold/crossover can be
deballasting plan including trim and stability conditions during Company Directives opened.
loading.
The cargo tanks will normally be maintained at -113ºC during a ballast voyage
k) A pre-loading meeting is to be held together with the terminal by regular spraying. As long as the tanks are at this temperature, cooling down
representatives. The ship/shore safety list is to be filled in. of the cargo liquid pipes may now commence. The operation must be started
in due time before loading.
l) All connections (bonding wire, telephones. loading and bunkering
arm) at the manifolds are to be carried out according to the LNG is introduced into the liquid crossover and liquid header at a limited flow
terminal’s procedure. rate. The liquid flashes off immediately due to the high temperature within the
pipes and the vapour that is generated is introduced to each tank via the filling
m) When the cooldown of the loading arm is completed and the pipe. The pre-cooling is then carried out as follows:
vaporiser is made ready, the purging of the cargo tanks and lines
can commence. The outgoing temperature from the vaporiser is to a) Set up the HD compressors to discharge vapour ashore via the
be set to approximately 10ºC. vapour manifold and prepare for operation.
n) The gas analyser is to be put into operation at the ship’s vent mast b) Open the liquid line from the crossovers to each cargo tank by
to continuously check the inert gas for any sign of LNG vapour opening the following valves:
concentration.
Liq
res
mp Room
uid
C o
G
LN V2100
Va
Ni
015 V2138
p
V2 V2052
ou
tro
32 31
V21 V21
Liq
r
ge
V2051
Liq
r
ou
uid
n
PI Vap ater V2051
uid
He 15
V21 V2051
30 14 200
32 30 V21 V21 V2 V2051
V21 V21 A
.B 14A 206
1 015
Co
mp V21 016 V V2 V2026
34 V2
V21 HD
To r 31 1
ou V21 220 120
oile
rs Vap ater V21
14 V
V2
Vent Dome
B He 35 061
Mast 003
V21 V2 V2004 V2
S)
2(
A 00
36 016 A V2101 V2
V21 V2 0
13 35 220 V2138
V21 V21
V V2055
V2002 (P)
p.A
V2
om No.1
20
C V2054
HD
3
V 212
8 V2054 Cargo Tank
6
pac
e 212
V2
V V2054
39 id S er
20
V21 Vo r Dry 14
V2
3A
V2054
Ai V23
V2
17 p.
23
V21 m
20
13 Co V2027
4
V21 14
LD V23
3
25 6
35 V21 15
V21
2 t
V22 V23 Plan Dome
15 N Vent
G
LN iser V23 e To 2 007
or pac Mast V2008 V2
Vap id S er
Vo r Dry S)
11 25 Ai 6(
V21 V21 m ans V2
00
d 39 Fro ing F ating V2103
t e
Voi re V21 c ula ce H
or ir V2138
r F osphe c
Re id Sp
a V2006 (P)
ate o V2058 V2068
He e Atm
ac V21
39
For
V No.2
Sp V2057
V2057 Cargo Tank
V2057
V2057
2
V 212 V2028
19
V21
V2
Dome
01
Vent 011
2
Mast V2
es (S)
ac 01
0
Sp V2
Void V21
10
To V2108
V2010 (P)
18 V2138
V21 V2064 V2068 No.3
V2063
V2063
Cargo Tank
V2063
V2063
V2029
Spray
Pump
Dome
Vent 019
Mast V2020 V2 D
(S) FW
018
V2
V2109
V2066 V2138 V2018 (P)
No.4
V2065
V2065
Cargo Tank
V2065
A
015
V2065 V2
V2030 Spray
To Pump 120
Emergency V2
Discharge Dome
Astern 023 200
A 061
V2024 V2 V2
V2 015
S) V2
0 2( 6A
V 20 V201
061
V2002 (P) V2
Liq
No.5 201 0
uid
V2 20
V2
Cargo Tank
Va
016
po
Ni
V2 Key
ur
tro
Liq
ge
n
uid
LNG Liquid
LNG Vapour
6.4.3 To Load Cargo with Vapour Return to Shore via the High Request the shore terminal to start loading at a slow rate and check that all Any alarms sounding would then clearly be cargo alarms.
Duty Compressors systems are tight and that LNG cargo is entering the tanks via the spray header.
4. Notify the terminal one hour prior to the topping up of the first LNG cargo
The procedure is as follows: Confirm that the temperature of the tank shell at the equator for the first tank tank. Reduce the loading rate to about 3,500m3/h.
to be loaded is at least -113°C.
a) Set up the HD compressors to discharge vapour ashore via the 5. At the passing of the 95% alarm (or corresponding level) of the first tank,
vapour manifold and prepare for operation. f) On No.1 tank, crack open the tank loading valve V2003 and stop the BOG to the engine room (if used) and physically check that the main
confirm that LNG liquid is entering the tank. gas valve is closed.
b) Open valve V2010, the vapour header to HD compressors vapour
supply. g) Start loading slowly into the other four tanks by opening valves 6. Topping up of the cargo tanks shall be carried out with no less than 10
V2007, V2011, V2019 and V2003, continuing spraying to minute intervals between each tank. At about 15 minutes before starting
c) Open the HD compressors inlet valves, V2113. maintain the temperature and reduce gas generation. As the topping up, the communication with the shore control room/loading master
pressure rises, the HD compressors may be started and gas sent shall be confirmed.
d) Open the HD compressors outlet valves, V2115 and V2114A. ashore.
7. When two of the tanks have been completed, reduce the loading rate to about
e) Open valves V2117 and V2119, the discharge from the HD h) Once loading into all tanks is confirmed and the gas pressure is 2,500m3/h. Reduce the loading rate to about 1,000m3/h prior to topping up the
compressor to the vapour header manifold. under control, the loading rate can be increased as required and last cargo tank.
the flow rates to each tank adjusted to allow for the final topping
f) Open valve V2120, the vapour manifold to shore. off. 8. The tank filling valve of the last tank to be topped up must remain in the
OPEN position for liquid draining purposes. Stop the last loading pump when
Set up the cargo tanks and the liquid header to load as follows: i) As the tank temperature reaches -138°C, the spray crossover the tank level reaches about 25-30cm from the finish level. When the draining
valves V2061 can be closed and once the spray line is drained, of the loading arm is completed, all liquid valves must be closed at the
a) Open the valves V2061, the liquid crossover to spray header. close the tank spray ring block valves V2052, V2055, V2058, manifold and confirmed closed.
V2064 and V2066.
b) Open the spray ring block valves to each tank V2052, V2055, 9. The loading is not completed until all the valves at the manifold are closed.
V2058, V2064 and V2066. j) The loading rate is reduced as the tanks near capacity, to allow for
a controlled topping off. 10. If necessary, never hesitate to use the ESD.
c) Open the manifold liquid valves V2016A, V2016, V2015 and
V2015A. Topping Up Procedures 11. If the Chief officer or his deputy at any time feels he needs assistance at
any time, he is free to call for it.
d) Open the cargo tank liquid header block valves V2004, V2008, 1. The Chief Officer is responsible for carrying out all the stages of LNG
V2012, V2020 and V2024. loading, including topping of tanks. His attention shall be focused on cargo If at any time during the cargo transfer procedure, including the topping up
operations only during the topping up period. procedure, when reaching an alarm status without such an alarm being
e) Open the following first spray nozzle valve on each tank: activated, the cargo transfer should be stopped immediately until the reason(s)
2. The cargo engineer shall assist the chief officer during the topping up of the for the failure has been identified.
tanks.
Position Description Valve (Note ! This topping up procedure is to be included in the loading plan.)
Open No.1 cargo tank spray nozzle valve V2051 One qualified deck officer shall be stationed at the tank domes during topping
up of the cargo tanks, in order to monitor the actual level. k) When all the shore loading pumps have stopped, stop the HD
Open No.2 cargo tank spray nozzle valve V2054 compressors and prepare for the draining of the liquid lines to the
The deck officer has to report to the CCR when the level is about 30cm below final tank.
Open No.3 cargo tank spray nozzle valve V2057
the finish level.
Open No.4 cargo tank spray nozzle valve V2063 l) All LNG remaining in the downward leg of the loading arms and
Closing of the loading valve(s) shall be visibly checked and confirmed. the manifold connection is to be drained to the tanks through the
Open No.5 cargo tank spray nozzle valve V2065
spray line assisted by nitrogen pressure from ashore. The LNG
3. Deballasting should be completed/interrupted one hour prior to the topping and vapour manifolds are then purged with nitrogen until an
In order to get liquid to the spray valves, open cross-connection valve V2961 up procedure. This is to avoid alarms being activated from the ballast panel acceptable hydrocarbon content is reached.
and close in valve V2061A. during during the topping up procedure.
m) Close vapour manifold valve V2120.
Disconnect
Loading Arms Disconnect and park arms Fit blanks to ship's manifold
Engage storm locks flanges
Terminal stops flow at ship's
request Fit blanks to liquid loading and
vapour return arm flanges
Remove
Stopping Gangway Terminal staff action Ship's staff witness
Terminal stops flow CCR requests stop
Loading pumps shut down
Draining
Terminal shuts terminal liquid CCR shuts manifold liquid
loading valves loading valves
p) Open the spray header block and spray inlet valves to No.4 tanks
V2064 and V2063A.
Sea Suction
Overboard No.5 Side Tank No.4 Side Tank No.3 Side Tank No.2 Side Tank No.1 Side Tank
(Port) (Port) (Port) (Port) (Port)
V56 HC V60
1A
V13
SI HC PI 801
1 20a
1 1
Emergency
Bilge Suction
V54A V54 V52 V52 No.3 Bottom Wing No.1 Bottom Wing
Ballast Tank (Port) No.2 Bottom Wing Tank (Port)
Pump V64 V59 Tank (Port)
V71
Emergency 1,200 m3/h
Connection For
V96 V94 V92 V90 V88 V86 V84 V82 V80 V78 V74
Backflushing
Main Condenser
V57 V23 V99 V69 V72
V70
V63
From
Bilge System No.2 No.3 No.2 No.1
V33 V58 V59A Double Bottom
From Lower Cross Lower Cross Lower Cross
Spare Water Tank Tank Tank
Fire and Deck
Ballast Tank
Wash System V33
V98 V97
V57 V72
V95 V93 V91 V89 V87 V85 V83 V81 V79 V77 V77
HC Ballast
V66 2A Pump V61
1,200 m3/h
No.5 Side Tank No.4 Side Tank No.3 Side Tank No.2 Side Tank No.1 Side Tank
Overboard (Starboard) (Starboard) (Starboard) (Starboard) (Starboard)
Key Sea Suction
Sea Water
Bilge
Electrical Signal
6.4.4 Deballasting Ballast Operations Procedure to Set Up for Deballasting: To Pump to Sea
Company Directives In the ballast system there are two ballast pumps with suction from all ballast a) Shut sea suction valves V60, V61 and sea crossover valve V58.
tanks. Each pump is of the electric vertical centrifugal type with a discharge
a) Carefully follow the instructions in the trim and stability capacity of 1200m3/h. b) Open the pump overboard valve V56.
particulars booklet and the instruction book for the DCS system
as per the discharge/loading plan. In normal service, the port pump is connected to all port tanks and the c) Open the pump discharge valves V54 and V55.
starboard pump to all the starboard tanks. However, it is possible to draw from
b) It should be remembered that free liquid surfaces seriously reduce both sides with one pump. d) Open the pump suction valves V52 and V53. Block valves V52
the stability of the vessel. and V53 should be still open.
From the cargo control room, all the ballast valves can be hydraulically
c) Ensure that all ballast operations are under full control, ie, there controlled. The same pipes and valves are used both for the filling and e) Open the tank suction valves. The tanks are taken down one pair
should be no water in any empty spaces and ensure that tanks emptying of all the ballast tanks. at a time, as required, to maintain draught, trim and stability. The
which are supposed to be empty are in fact empty. The operator(s) loading of the cargo tanks should counteract the amount of ballast
should make reference to the vessel’s trim and stability The ballast eductor works as a stripping pump for the ballast tanks and as a discharged.
particulars. priming unit for the ballast pumps. This is a water driven unit with a discharge
capacity of 100m3/h, using drive water from the engine room bilge ejector f) Start the ballast pumps. Should the discharge rate require the use
d) Local conditions such as mud etc, should be taken into pump. of only one pump, the crossover line could be used by opening
consideration when ballasting. valve(s) V59 and V59A, making the tank discharge lines
Procedure to Set Up for Deballasting: To Run to Sea common. The main ballast pump is used to take as much as
e) Gravity ballasting and deballasting should be used wherever possible out of the tanks, leaving the final draining to be
possible. a) Open sea suction valves V60, V61 and sea crossover valve V58. completed via the eductor.
(Note: Ensure the maximum draught is regularly checked during b) Open block valves V52 and V53. g) Open the eductor discharge valve V66.
ballasting/deballasting, especially alongside during low tide.)
c) Open the tank valve (e.g. for No.3 side tank port and starboard) h) Open the eductor drive water supply valve V33 and start the
Ballast Pumps V90/V84 and V89/V83. fire/bilge pump.
Maker: Weir d) Run ballast to sea, keeping the vessel upright and ensure that the i) Stop the main ballast pumps and shut the suction, discharge
Type: Mark 3 UXL vessel’s trim and stability is maintained at all times. valves and overboard valves, V52, 53, 54, 55 and 56.
Capacity: 1,200m3/h
No. of sets: 2 e) Once the level in the tanks has equalised with the sea level it will j) Shut the block valves, V52 and V53.
be necessary to use the pumps to continue with the ballast
discharge. k) Open the suction crossover valves V59 and V59A.
Liq
G C
LN
uid
V2100
Va
Ni
V2138
015 V2052
po
tro
32 213
1 V2
V21
ur
V
ge
V2051
Liq
r
ou
n
Liq
PI Vap ater V2051
uid
He
u
15
V21
id
V2051
30
V21
14 200
32 30 V21 V2 V2051
V21 V21 A
.B 14A 061 015
mp V21 016 V2 V2 V2026
34 Co V2
V21 HD
To r 31 1
ou V21 220 120
iler
s Vap ater V21
14 V
V2
Vent Dome
Bo He 35 Mast 003
V21 061 V2004 V2
V2
(S)
016
A
002
36 V2 A
V2101 V2
13 V21 200 V2138
V21 35 V2 V2055
V21 .A V2002 (P)
V2
mp
Co No.1
20
V2054
HD
3
V21
28 V2054 Cargo Tank
e 26
pac V21
V2
V2054
39 id S er
20
V21 Vo r Dry 14
V2
3A
i V2054
A V23
V2
17 .
23
V21 mp
20
13 Co V2027
4
V21 14
LD V23
3
25 26
35 V21 15
V21 nt
V22 V23 Pla Dome
15 N Vent
G
LN iser V23 e To 2 007
or pac Mast V2008 V2
Vap id S er
Vo r Dry (S)
11 25 Ai 06
V21 V21 m ans V2
0
d 39 Fro ing F ating V2103
Voi V21 ulat e He
or here cir c ac V2138 V2006 (P)
rF p Re id Sp
ate tmos Vo V2058 V2068
e
H eA
ac V21
39
For
No.2
Sp V2057
V2057 Cargo Tank
V2057
V2057
22
V21 V2028
19
V21
V2
Dome
01
Vent 011
2
Mast V2
s S)
ace 0(
Sp 01
Void 10 V2
To V21 V2108
V2010 (P)
18 V2138
V21 V2064 V2068 No.3
V2063
V2063
Cargo Tank
V2063
V2063
V2029
Spray
Pump
Dome
Vent 019
Mast V2020 V2 D
S) FW
8(
01
V2
V2109
V2066 V2138 V2018 (P)
No.4
V2065
V2065
Cargo Tank
V2065 A
015
V2065 V2
V2030 Spray
To Pump 120
Emergency V2
Discharge Dome
Astern 023 200A 061
V2024 V2 V2 V2 015
V2
S)
2( 016
A
00
V2 V2
061
V2002 (P) V2
Liq
No.5 201
uid
V2 200
V2
Cargo Tank Key
Va
016
po
Ni
V2
ur
tro
Dry Air
Liq
ge
n
uid
Moist Air
Witness and check rigging of gangway. Initiate ESD1 signal from ship/shore.
Witness and log ESD1 operation
of all shore valves.
Witness and log ESD1 operation
of all ship's valves.
Predischarge Carry out safety inspection.
Meeting Terminal staffreview discharge
Complete and sign safety checklist.
schedule and confirm safety checks.
Check O2 levels at sampling points. Safety Carry out safety checks jointly Check through terminal safety
Checks with ship. checks jointly with terminal staff.
Company Directives
Liq
G C
LN
uid
V2100
Va
Ni
015 V2052 V2138
po
V2
tro
32 3 1
V21 V21
ur
ge
V2051
Liq
r
ou
n
Liq
PI Vap ater V2051
uid
He
u
15
V21
id
V2051
30 14 200
32 30 V21 V21 V2 V2051
V21 V21 A
.B 14A 061 015
mp V21 016 V2 V2 V2026
34 Co V2
V21 HD
To r 31 1
ou V21 220 120
iler
s Vap ater V21
14 V
V2
Vent Dome
Bo He 35 Mast 003
V21 061 V2004 V2
V2
S)
A 2(
016 00
36 V2 A
V2101 V2
13 V21 200 V2138
V21 35 V2 V2055
V21 .A V2002 (P)
V2
mp
Co No.1
20
V2054
HD
3
V21
28 V2054 Cargo Tank
e 26
pac V21
V2
V2054
39 id S er
20
V21 Vo r Dry 14
V2
3A
i V2054
A V23
V2
17 .
23
V21 mp
20
13 Co V2027
4
V21 14
LD V23
3
25 6
35 V21 V23
15
V21
2
nt
V22 Pla Dome
15 N Vent
G
LN iser V23 e To 2 007
or pac Mast V2008 V2
Vap id S er
Vo r Dry (S)
11 25 Ai 06
V21 V21 m ans V2
0
d 39 Fro ing F ating V2103
Voi V21 t
ula e H
e
or here circ Spac V2138 V2006 (P)
rF p e
ate tmos R id V2058 V2068
e
H eA
ac V21
39
Fo r Vo No.2
Sp V2057
V2057 Cargo Tank
V2057
V2057
22
V21 V2028
19
V21
V2
Dome
01
Vent 011
2
Mast V2
s (S)
ace 01
0
Sp V2
Void 10
To V21 V2108
V2010 (P)
18 V2138
V21 V2064 V2068 No.3
V2063
V2063
Cargo Tank
V2063
V2063
V2029
Spray
Pump
Dome
Vent 019
Mast V2020 V2 D
S) FW
8(
01
V2
V2109
V2066 V2138 V2018 (P)
No.4
V2065
V2065
Cargo Tank
V2065
A
015
V2065 V2
V2030 Spray
To Pump 120
Emergency V2
Discharge Dome
Astern 023 200
A
061
V2024 V2 V2
V2 015
S) V2
2( 6A
00 201
V2 V
061
V2002 (P) V2
Liq
No.5 201 0
uid
V2 20
V2
Cargo Tank
016 Va Key
po
Ni
V2
ur
tro
Liq
ge
n
uid
LNG Liquid
LNG Vapour
The cargo lines are cooled down and the cargo plant is prepared to the highest f) Open filling valve V2011 on the No.3 tank or filling valve V2019
possible level before arrival at the loading/discharging port as per terminal on the No.4 tank.
requirement. This is in order to commence the discharging as soon as the vessel
is moored and all procedures have been completed. At the same time as the g) Using No.3 or No.4 spray pump, LNG is passed via the spray
cargo lines are cooled down, the cargo lines are pressure tested for any leakage header to the spray line tank manifold, then through the crossover
by increasing the pressure to 5 bar. Spool pieces/reducers with their required valve into the liquid header, returning to No.3 or No 4 tank via the
filters are to be mounted. loading line.
Liquid line cool down is carried out using the spray pump in No.3 or No.4 tank h) After the spray pump is started, slowly fully open valve V2068,
to pump LNG from No.3 or No.4 cargo tank through the spray header to the the spray pump discharge valve into the spray header and
liquid manifold pipework. commence spray line cooldown and then liquid line cooldown, in
turn.
Vapour displaced from the crossover pipework passes through the liquid
header and spray bypass and return valves of No.1, 2, 4 and 5 cargo tanks and i) During line cooldown, monitor the following;
then back to No.3 or No.4 tank via the filling line.
Cargo tank levels
Vapour from the tanks will be burned in the boilers using the LD compressor Liquid crossover pressure
and gas heaters.
Liquid crossover temperature
Although the text and illustration indicate No.4 tank spray pump being used, Liquid header temperature
No.3 pump could be used.
Vapour header pressure
Procedure to Cool Down the Liquid Lines
j) Line cooldown will be complete when the liquid header
a) Open valve V2068, the discharge valve from No.4 spray pump, temperature falls below -100°C.
approximately 15%.
k) When the cooldown is completed, stop the spray pump. If the time
b) At the manifold, open the liquid/spray header crossover valves between cooldown completion and berthing is extensive, the
V2061 and the forward and aft liquid ESD valves V2016A and spray pump may be restarted.
V2015A.
(Note: Return of cooldown liquid to the bottom of the tank via the loading line
c) Open the liquid line from the crossovers to each cargo tank by can give rise to localised temperature increase at the tank bottom sensor.
opening following butterfly valves: Sufficient time should be allowed for this to stabilise prior to gauging.)
Liq
Co
uid
G
LN V2100
Va
Ni
015 V2052 V2138
p
V2
tro
32 1
ou
V21 V 213
ge
r
Liq
V2051
Liq
r
ou
n
PI Vap ater V2051
uid
uid
He 15
V21 V2051
30 14 200
32 30 V21 V21 V2 V2051
V21 V21 A
.B 14A 1 015
mp V21 016 V 206 V2 V2026
34 Co V2
V21 HD
To r 31 201
ou V21 V2 120
iler
s Vap ater V21
14 V2
Vent Dome
Bo He 35 Mast 003
V21 061 V2004 V2
V2
A (S)
016 002
36 V2 A V2101 V2
13 V21 200
35 V2 V2138
V21 V21
V2055
V2002 (P)
.A
V2
mp
Co No.1
20
D V2054
H
3
V21
28 V2054 Cargo Tank
e 26
pac V21
V2
V2054
39 id S er
20
V21 Vo r Dry 4
V2
3A
1 V2054
Ai V23
V2
17 .
23
V21 mp
20
13 Co V2027
4
V21 14
LD V23
3
25 26
35 V21 V23
15
V21 t
V22 Pla
n
Dome
G 15 N Vent 7
LN iser V23 e To 2 00
or pac Mast V2008 V2
Vap id S er
Vo r Dry (S)
11 25 A i 6
V21 V21 m ans V2
00
d 39 Fro ing F ating V2103
Voi re V21 t
ula ce H
e
or c V2138
r F osphe c ir
Re id Sp
a V2006 (P)
ate V2058 V2068
He e Atm
ac V21
39
For
V o No.2
Sp V2057
V2057 Cargo Tank
V2057
V2057
2
V 212 V2028
19
V21
V2
Dome
01
Vent 011
2
Mast V2
S)
es 0(
S pac V2
01
Void 10
To V21 V2108
V2010 (P)
18 V2138
V21 V2064 V2068 No.3
V2063
V2063
Cargo Tank
V2063
V2063
V2029
Spray
Pump
Dome
Vent 019
Mast V2020 V2 D
S) FW
8(
01
V2
V2109
V2066 V2138 V2018 (P)
No.4
V2065
V2065
Cargo Tank
V2065
A
015
V2065 V2
V2030 Spray
To Pump 120
Emergency V2
Discharge Dome
Astern 023 A 061
V2024 V2 200 V2 015
V2 V2
S)
2( 6A
00 201
V2 V
061
V2002 (P) V2
Liq
No.5 201
uid
V2 200
Cargo Tank V2
016 Va
po
Ni
V2
ur Key
tro
Liq
ge
n
uid
LNG Liquid
Company Directives
After the discharging arms are connected to the ship’s manifold, the
discharging arms are pressurised with N2. This is delivered from the shore at
up to 3 bar. The connections are then tested for leaks using soapy water.
On completion of testing the discharge arm connections, the vessel uses its
spray pump(s) to cool down the shore arms.
The ship/shore safety checks will have been completed; the BOG burning shut
down, custody transfer completed and the ship/shore vapour line opened.
b) Open the spray line to No.3 tank valves V2058 and V2057 and
establish a 3 bar recirculating pressure before discharging to the
arm.
e) After starting the spray pumps, slowly open the spray pump
discharge valves V2068 and V2108, to cool down the spray
header back to No.3 or No.4 tank via the spray line.
f) Once the spray header has cooled down, increase the flow rate at
shore terminal request by opening valve V2068 and closing the
spray valve V2057.
g) Once the shore arms are cooled down and the shore terminal
request the spray pump to be stopped, close the spray header
crossover valves V2034.
h) Drain the spray line back to No.3 tank via valves V2058 and
V2057.
Liq
o mp Room
C
uid
G
LN
Va
V2100
Ni
p
V2138
015
ou
V2052
tro
32 213
1 V2
V21
r
V
ge
Liq
V2051
Liq
r
ou
n
PI Vap ater V2051
uid
uid
He 15
V21 V2051
30 14 200
32 30 V21 V21 V2 V2051
V21 V21
.B 14A 206
1
015
A
Co
mp V21 01 6 V V2 V2026
34 V2
V21 HD
To r 31
ou V21 201 120
iler
s Vap ater 14 V2 V2
Vent Dome
Bo V21
He 35 061
Mast 003
V21 V2 V2004 V2
(S)
A 02
016 V2101 V2
0
36 V2 A
13 V21 200 V2138
V21 35 V2 V2055
V21 .A V2002 (P)
V2
mp
Co No.1
20
D V2054
H
3
V21
28 V2054 Cargo Tank
e 126
pac
V2
V2 V2054
39 id S er
20
V21 Vo r Dry 4
V2
3A
1 V2054
Ai V23
V2
17 .
23
V21 mp
20
13 Co V2027
4
V21 14
LD V23
3
25 26
35 V21 V23
15
V21 t
V22 Pla
n
Dome
G 15 N Vent 7
LN iser V23 e To 2 00
or pac Mast V2008 V2
Vap id S er
Vo r Dry (S)
11 25 A i 6
V21 V21 m ans V2
00
d 39 Fro ing F ating V2103
Voi re V21 t
ula ce H
e
or c V2138
r F osphe cir
Re id Sp
a V2006 (P)
ate V2058 V2068
He e Atm
ac V21
39
For
V o No.2
Sp V2057
V2057 Cargo Tank
V2057
V2057
2
V 212 V2028
19
V21
V2
Dome
01
Vent 011
2
Mast V2
S)
ace
s 0(
Sp 01
10 V2
o Void V21 V2108
T
V2010 (P)
18 V2138
V21 V2064 V2068 No.3
V2063
V2063
Cargo Tank
V2063
V2063
V2029
Spray
Pump
Dome
Vent 019
Mast V2020 V2 D
S) FW
8(
01
V2
V2109
V2066 V2138 V2018 (P)
No.4
V2065
V2065
Cargo Tank
V2065
A
V2065 015
V2
V2030 Spray
To Pump 120
Emergency V2
Discharge Dome
Astern 023 A 061
V2024 V2 200 V2 015
V2 V2
S)
2( 16 A
00 20
V2 V
061
V2002 (P) V2
Liq
No.5 201 0
uid
V2 20
V2
Cargo Tank
016 Va
po
Ni
V2
ur Key
tro
Liq
ge
n
uid
LNG Liquid
LNG Vapour
6.6.4 Discharging Cargo Discharging Cargo with Vapour Return From Shore
Company Directives Using No.1 tank as the first tank to commence discharging.
In co-operating LNG operations, the ship must be compatible with the Vapour Return
terminals and the ship and shore personnel must be familiar with each other’s
equipment and the division of all responsibilities. a) Open the crossover valves between compressor supply line and
vapour header V2118 and V2119.
Each terminal has its own procedures, which have to be strictly followed,
regarding the following operations: b) Open vapour manifold valve V2120.
Approaching the terminal
Liquid Header
Mooring
Connecting c) Open the cargo tank liquid header block valves V2004, V2008,
V2012, V2020 and V2024.
Loading
Disconnecting d) Open the discharge valve V2002 on the No.1 tank approximately
25%.
Departure
e) Open the liquid manifold block valves, V2016 and V2015.
CAUTION
It is of the utmost importance that the cargo pumps are never allowed to f) Open the liquid manifold ESD valves, V2016A and V2015A.
run dry, even for short periods, as this will result in motor failure. A
momentary loss of priming during cargo stripping should not be g) When the shore terminal is ready to receive cargo, start the first
considered as running a pump dry. Up to 30 seconds of operation with dry pump. With the pump running, open the discharge valve slowly
suction but with fluid in the discharge pipe will not damage the pump or into the fully open position to obtain a discharge pressure of 2 bar.
the motor.
h) Check the motor current at the ammeter, the current should be
steady after the motor has been running for 3 seconds. During
starting, while the discharge line is being filled, the current may
be over the ammeter red line. Do not exceed the maximum rated
current by 50% for more than 2 or 3 seconds when the tank is full.
If the running current after this time is more than 150% above the
maximum rated current, stop the pump immediately and
determine the cause of high current (possible blockage).
Terminal Ship
Start Pre discharging meeting
Terminal confirms readiness. Ship's staff work through terminal
Discharge
Terminal supplies return gas safety check list jointly with
at ship's request. terminal staff Terminal Ship
Final CTS
Gauging Final CTS gauging by Final CTS gauging by ship's
loading master. designated cargo officer.
Ship's CCR must notify terminal of
all activities. Complete documentation. Complete documentation.
Ship's CCR confirms readiness
and starts first cargo pump.
Carry Out
Safety Checks Terminal staff jointly with ship's
Stopping staff.
Towards the end of the discharge, the flow of the pumps will diminish. In order a) Close vapour manifold valve V2120.
to maintain the pressure differential over the pump, the discharge valve will
have to be throttled in. This should be done at the low level alarm, about 1 b) Close the liquid manifold block valves V2016 and V2015.
metre above the non pumpable level.
c) Open the liquid/spray line crossover valves V2061.
If any fluctuations are observed on the motor ammeter or the pump discharge
pressure gauge during final pumping, the discharge flow rate should be further d) Open the spray header valves to No.5 tank V2065.
reduced until the readings stabilise. When the flow is throttled down to about
230m3/h the required non pumpable level will be about 10cms. This level e) Request the shore terminal to pressurise the loading arms with
represents the minimum level attained by pumping. nitrogen gas and check that the liquid manifold drain valves are
liquid-free.
(Note: When the liquid level reaches 1 metre or less, avoid stopping the pump
if at all possible until the cargo has been fully discharged. If the shore facility f) On completion of liquid drainage, carry out vapour purging. The
is unable to accept the liquid for intermittent periods it is better to keep the hydrocarbon content in the liquid and vapour manifold
pump going and recirculate back into the tanks until discharge can be resumed connections at the purge valves should be confirmed as 2% or
and completed.) below.
All LNG remaining in the downward leg of the loading arms and manifold g) Close all manifold, tank loading and open one cargo tank spray
connection is to be drained to the tanks through the spray line assisted by line to reduce the pressure in the cargo lines.
nitrogen pressure from ashore. The LNG and vapour manifolds are then purged
with nitrogen until an acceptable hydrocarbon content is reached. h) Carry out the final custody transfer.
Sea Suction
Overboard No.5 Side Tank No.4 Side Tank No.3 Side Tank No.2 Side Tank No.1 Side Tank
(Port) (Port) (Port) (Port) (Port)
V56 HC V60
1A
V13
SI HC PI 801
1 20a
1 1
Emergency
Bilge Suction
V54A V54 V52 V52 No.3 Bottom Wing No.1 Bottom Wing
Ballast Tank (Port) No.2 Bottom Wing Tank (Port)
Pump V64 V59 Tank (Port)
V71
Emergency 1,200 m3/h
Connection For
V96 V94 V92 V90 V88 V86 V84 V82 V80 V78 V74
Backflushing
Main Condenser
V57 V23 V99 V69 V72
V70
V63
From
Bilge System No.2 No.3 No.2 No.1
V33 V58 V59A Double Bottom
From Lower Cross Lower Cross Lower Cross
Spare Water Tank Tank Tank
Fire and Deck
Ballast Tank
Wash System V33
V98 V97
V57 V72
V95 V93 V91 V89 V87 V85 V83 V81 V79 V77 V73
V71
V64 V59
No.3 Bottom Wing No.2 Bottom Wing No.1 Bottom Wing
Tank (Starboard) Tank (Starboard) Tank (Starboard)
HC Ballast
V66 2A Pump V61
1,200 m3/h
No.5 Side Tank No.4 Side Tank No.3 Side Tank No.2 Side Tank No.1 Side Tank
Overboard (Starboard) (Starboard) (Starboard) (Starboard) (Starboard)
Key Sea Suction
Sea Water
Bilge
Electrical Signal
6.6.5 Ballasting Ballast Operations Procedure to Set Up for Ballasting: To Pump From the Sea
Company Directives Ballast operations can be carried out in the automatic mode via the DCS a) Open the sea suction valves V60, V61 and sea crossover valve
system, the following is a manual procedure for deballasting. V58.
a) Carefully follow the instructions in the trim and stability
particulars booklet and the instruction book for the DCS system. In the ballast system there are two ballast pumps with suction from all ballast b) Open the pump suction valves V52 and V53.
tanks. Each pump is of the electric vertical centrifugal type with a discharge
b) It should be remembered that free liquid surfaces seriously reduce capacity of 1200m3/h. c) Open the pump discharge valves V54 and V55.
the stability of the vessel.
In normal service, the port pump is connected to all port tanks and the d) Shut the block valves V52 and V53.
c) Ensure that all ballast operations are under full control, ie, there starboard pump to all the starboard tanks. However, it is possible to draw from
should be no water in any empty spaces and ensure that tanks both sides with one pump. e) Open the drop valve(s) V57.
which are supposed to be empty are in fact empty. The operator(s)
should make reference to the vessel’s trim and stability From the cargo control room, all the ballast valves can be hydraulically f) Open the tank suction valves. The tanks are filled one pair at a
particulars. controlled. The same pipes and valves are used both for the filling and time as required to maintain draught, trim and stability. The
emptying of all the ballast tanks. loading of the ballast tanks counteracts the amount of LNG cargo
d) Local conditions such as mud etc, should be taken into discharged.
consideration when ballasting. The bottom wing tanks can be filled directly through the sea suction.
g) Start the ballast pumps. Should the loading rate require the use of
e) Gravity ballasting and deballasting should be used wherever Procedure to Set Up for Ballasting: To Run From the Sea only one pump, the crossover line could be opened via valve(s)
possible. V59 and V59A, making the tank filling lines common.
a) Open the sea suction valves V60, V61 and sea crossover valve
(Note: Ensure the maximum draught is regularly checked during V58. On completion of loading ballast, shut down the ballast system.
ballasting/deballasting, especially alongside during low tide.)
b) Open the block valves V52 and V53.
Ballast Pumps
c) Open the tank valve (eg, for No.3 bottom tank port and starboard)
Maker: Weir V93 and V94.
Type: Mark 3 UXL
Capacity: 1,200m3/h d) Run ballast from the sea, keeping the vessel upright and ensuring
No. of sets: 2 that the vessel’s trim and stability is maintained at all times.
There is an automatic ballasting sequence available via the DCS system, refer e) Once the level in the tanks has equalised with the sea level it will
to section 3.2.6a DCS System: Cargo and Ballast Operations. be necessary to use the pumps to continue with the ballast
loading.
Liq
o m R
uid
GC
LN V2100
Va
Ni
V2138
015 V2052
po
V2
tro
V21
32
V2 131
ur
ge
V2051
L iq
r
ou
n
Liq
PI Vap ater V2051
u id
He
uid
15
V21 V2051
30 14 200
32 30 V21 V21 V2 V2051
V21 V21 A
.B 14A 061 015
mp V21 016 V2 V2 V2026
34 Co V2
V21 HD
To r 31 201
ou V21 V2 120
oile
rs Vap ater V21
14 V2
Vent Dome
B He 35 061
Mast 003
V21 V2 V2004 V2
(S)
A 02
36 016 V2101 V2
0
V2
1 3 V21 200
A
V2138
V21 35 V2 V2055
V21 .A V2002 (P)
V2
mp
Co No.1
2
V2054
03
H D
V21
28 V2054 Cargo Tank
e 26
pac V21
V2
V2054
39 id S er
2
V21 Vo r Dry
03
4
V2
1 V2054
Ai V23
A
V2
17 .
2
V21 mp
34
13 Co 14 V2027
V21
03
LD
25 V23
35 V21 15 26
V22 V23 V21 Pla
nt
Dome
G 15 N Vent 7
LN iser V23 e To 2 00
or pac Mast V2008 V2
Vap id S er
Vo r Dry (S)
11 25 A i 6
V21 V21 m ans V2
00
d 39 Fro ing F ating V2103
Voi re V 1
2 t
ula ce H
e
or c V2138
r F osphe cir
Re id Sp
a V2006 (P)
ate V2058 V2068
He e Atm
ac V21
39
For
V o No.2
Sp V2057
V2057 Cargo Tank
V2057
V2057
V2122 V2028
19
V21
V2
Dome
01
Vent 011
2
Mast V2
S)
ace
s 0(
Sp 01
10 V2
o Void V21 V2108
T
V2010 (P)
18 V2138
V21 V2064 V2068 No.3
V2063
V2063
Cargo Tank
V2063
V2063
V2029
Spray
Pump
Dome
Vent 019
Mast V2020 V2 D
S) FW
8(
01
V2
V2109
V2066 V2138 V2018 (P)
No.4
V2065
V2065
Cargo Tank
V2065
A
015
V2065 V2
V2030 Spray
To Pump 120
Emergency V2
Discharge Dome
Astern 023 A 061
V2024 V2 200 V2 015
V2 V2
S)
2( A
00 016
V2 V2
061
V2002 (P) V2
Liq
No.5 201 00
uid
V2 2
V2
Cargo Tank
016 Va
po Key
Ni
V2
ur
tro
Liq
ge
n
uid
LNG Liquid
6.7 Pre Dry Dock Operations Position Description Valve Confirm that the gas content at the drain valve is less than 1% volume of
methane.
This section describes the operations for the period leading up to a dry dock. Open Port and starboard manifold
spray/liquid header valves V2061 j) Disconnect the vapour arm.
6.7.1 Stripping and Line Draining
Closed Port and starboard manifold liquid header k) Open the following valves to allow the lines to warm up:
It is assumed that the cargo tanks have been discharged to their maximum ESD valves V2016A, V2015A
using the main cargo pumps which have been shut down. The stripping/spray Position Description Valve
Open No.1 cargo tank spray line valves V2052, V2051
pumps are situated in No.3 and No.4 tanks and it will only be possible to
Open Port and starboard manifold
discharge these two tanks. Discharge is via the port side manifold and the Open No.2 cargo tank spray line valves V2055, V2054
spray/liquid header valves V2061
procedure is as follows:
Open No.3 cargo tank spray line valves V2058, V2057
a) At the manifold crossover: Open Port and starboard manifold liquid header
Open No.4 cargo tank spray line valves V2064, V2063
ESD valves V2016A, V2015A
Open valve V2015 on the forward manifold.
Open No.5 cargo tank spray line valves V2066, V2065
Open No.1 cargo tank spray line valves V2052, V2051
Close valves V2016A and V2015A on both manifolds and V2016
on the aft manifold. c) Open the forward manifold valve V2015. Open No.2 cargo tank spray line valves V2055, V2054
b) At the stripping/spray header: d) Close the liquid/spray header crossover valve V2061 when the Open No.3 cargo tank spray line valves V2058, V2057
Open valve V2061, the spray header to the liquid forward manifold pressure drops to 0 bar. Repeat this operation a further Open No.4 cargo tank spray line valves V2064, V2063
manifold. twice. On the last operation, shut the forward manifold liquid
valve V2015 at approximately 0.1 bar in order to eliminate the Open No.5 cargo tank spray line valves V2066, V2065
c) At No.3 and No.4 tanks: risk of liquid flowing back from the ship’s liquid line.
Open Liquid header block valves on all cargo tanks V2004
Open the stripping/spray discharge valves V2068 for No.3 and V2008,V2012
No.4 tanks. e) Open the test drain valve on the loading arm to ensure that there
V2020, V2024
is no liquid present. Repeat the operation with the other liquid
Start the stripping/spray pumps. arm.
Open Liquid header block valves on all cargo tanks V2003
Whenever possible the spray pumps should be started early enough to avoid V2007, V2011
f) Once the arms are empty of liquid, continue to purge with
any possible starting problems due to very low tank levels (about 0.5m V2019, V2003
nitrogen, checking the methane content at the drain valve. When
minimum).
the required amount of methane (usually less than 1%) is
l) When the lines are warmed up, the valves should be closed again.
On completion: indicated at the drain valve, inform the shore terminal and they
will close the shore terminal ESD valves.
m) Prepare the cargo system for warming up the cargo tanks.
d) Stop the final pump.
g) When purging is complete, proceed with the disconnection of the
Close valve V2015 on the forward manifold.
liquid arms.
Open valves V2066 and V2065 to drain the spray header line
back to No.5 tank. h) Complete the ballasting operations for final measurement and
sailing condition.
Purging and Draining of Loading Arms
Shortly before departure:
Purging is carried out one line at a time as follows:
i) Vapour line disconnection:
a) Open valve V2061, the spray header to the forward liquid
manifold. Close manifold vapour ESD valve V2120.
Open the vapour bypass valve.
b) Open the following spray line valves:
Purge the vapour line with nitrogen at 0.2 bar.
Close the drain valve.
Liq
G C
LN
uid
Va
Ni
015 V2052
p
V2 V2138
tro
32 31
ou
V21 V21 V2100
ge
r
V2051
Liq
r
ou
n
Liq
PI Vap ater V2051
uid
He
uid
15
V21 V2051
30 14 200
32 3 0 V21 V21 V2 V2051
V21 V21 5A
.B 14A 061 201
mp V21 016 V2 V V2026
34 Co V2
V21 HD
To r 31 20 1
ou V21 V2 120 V2004
iler
s Vap ater V21
14 V2
Vent Dome
Bo He 35 Mast 003
V21 061 V2
V2
S)
A 2(
016 V2
00
36 V2
13 V21 0A
V21 35 220 V2055
V21 .A
V V2138 V2002 (P)
V2
V2101
mp
Co No.1
20
V2054
HD
3
V21
28 V2054 Cargo Tank
e 26
pac V21
V2
V2054
39 id S er
20
V21 Vo r Dry 14
V2
3A
i V2054
A V23
V2
17 .
23
V21 mp
20
13 o
4
V21 C 14
LD V23 V2027
3
25 26
35 V21 V23
15
V21 nt
V22 Pla
V2008
Dome
5 N Vent
G
LN iser V 231 e To 2 007
or pac Mast V2
Vap id S er
Vo r Dry (S)
11 25 A i 6
V21 V21 m ans V2
00
d 39 Fro ing F ating
Voi re V21 t
cula ace H
e
or
r F osphe c ir
Re id S p V2138 V2006 (P)
ate V2058 V2068
He e Atm
ac V21
39
For Vo
V2103 No.2
Sp V2057
V2057 Cargo Tank
V2057
V2057
22
V2
V21 V2028
01
19
2
V21
Dome
Vent 011
Mast V2
S)
ace
s 0(
Sp 01
10 V2
Void V21
To
V2010 (P)
18 V2138
V21 V2064 V2068 No.3
V2108
V2063
V2063
Cargo Tank
V2063
V2063
V2029
Spray
Pump
V2020 Dome
Vent 019
Mast V2 D
S) FW
8(
01
V2
Liq
No.5 201 0
uid
V2 20
V2
Cargo Tank
Va
016
po
Ni
V2
ur
tro Key
Liq
ge
n
uid
o mp Room
GC
Liq
LN V2100
uid
Va
Ni
5 V2052 V2138
01
po
2 31 V2
tro
3
V21 V21
ur
ge
r
Liq
V2051
ou
Vap ater
n
Liq
u
PI V2051
He
id
15
uid
V21 V2051
0 1 4
2 3 0 V21
3
V21 200
V21
3
V21 V2 V2051
.B 4A A
mp 061
1 6
V21 201 015 V2026
4 Co V V2 V2
V21
3 HD
r 1
To ou
3 1
V21 20
rs
ile Vap ater V21
1 4 V2 12 0 Vent Dome
Bo He 35 V2 Mast 003
V21 061 V2004 V2
V2
( S)
A 0 02
36 016
V2101 V2
13 V21 V2 A
V21 35 200 V2055 V2138
V21 .A V2 V2002 (P)
V2
mp
Co No.1
20
HD
V2054
3
V21
2 8 V2054 Cargo Tank
e 26
pac
V2
V21 V2054
39 id S er
20
V21 Vo Dry
V2
3A
4
Air 1 V2054
V23
V2
17 .
23
V21 mp
20
Co
13 5 V2027
4
2 14
V21 LD V21 V23
3
6
235 V2 315 212
V2 V nt Dome
G 15 Pla Vent 7
LN iser V23 e N 00
or pac To 2 Mast V2008 V2
Vap id S er
Vo Dry S)
V21
11 25 Air 6(
V21 m ans V2
00
39 Fro ng F ating V2103
Void re V21 ti
ula ce H
e
or
r F osphe circ a V2138 V2006 (P)
ate Re id Sp
He e Atm
a c V21
39
For
V o V2058 V2068
No.2
Sp V2057
V2057 Cargo Tank
V2057
V2057
22
V21 V2028
1 9
V21
V2
Dome
01
Vent 011
2
Mast V2
es ( S)
pac 0 10
S V2
Void V21
10
To V2108
V2010 (P)
18 V2138
V21 V2064 V2068 No.3
V2063
V2063
Cargo Tank
V2063
V2063
V2029
Spray
Pump
Dome
Vent 019
V2020 V2 D
FW
Mast
(S)
0 18
V2
V2109
V2066 V2138 V2018 (P)
No.4
V2065
V2065
Cargo Tank
V2065
A
V2065 015
V2
V2030 Spray
To Pump 0
Emergency 12
V2
Discharge Dome
Astern 023
V2024 V2 A 061 015
200 V2 V2
V2
S)
2(
00 A
V2 016
V2
352 061
V2002 (P) V2 V2
Liq
A
No.5 V2
352
201
uid
V2 200
Cargo Tank 235
2 V2
Va
V 6
po
01
Ni
V2
ur
tro
Engine Room
ge
IG Plant
Key
n
Inert Gas
Before air is introduced into the cargo system, it is essential that all Before the inert gas operation is stopped, it should be carefully checked that all
hydrocarbons are purged from the system to prevent the formation of ‘blind ends’ in the cargo system have been opened, such as cargo compressors,
flammable mixtures. The objective of this operation is to replace all the heaters, vaporiser, manifolds not in use, Whessoe gauge heads etc.
methane gas in the cargo tanks and cargo pipework with inert gas. This is
carried out as an intermediate step between warming up and aeration. The readings of the methane content in the cargo tanks and cargo lines, taken
by a portable gas detector, must be between 2% and 3% by volume at all
This procedure is basically the same as for inerting after refit, but with the locations.
following differences:
WARNING
1) Completion of each step in purging has the object of achieving If any piping or components are to be opened, the inert gas or nitrogen
a hydrocarbon concentration of 1% volume or less. must first be flushed out with dry-air. Take precautions to avoid
concentrations of inert gas or nitrogen in confined spaces which could be
2) Before starting the operation, it should be verified that the tank hazardous to personnel.
equator temperatures are above +5ºC.
At the end of the inerting process, aeration immediately follows. The inert gas
plant is not completely shut down, but is vented via the funnel while being
changed over to the air production mode. During the changeover to air
production, the valves will be lined up ready for aeration.
Company Directives
After heating the tanks, they are to be purged with inert gas to remove the cargo
vapour before air is admitted. This is to avoid the formation of an explosive
mixture. This gas freeing is to be accomplished by means of the inert gas plant,
the R22 cooler, with a dew point +5ºC, and an additional dehumidifier with a
dew point of -25ºC or lower.
Before the inert gas line is connected to the cargo system, the inert gas line
must be blown through with air using the inert gas blower to avoid any debris
entering the cargo system. The inert gas must not be introduced to the cargo
tanks before the tank shell temperature is above +5ºC, the inert gas system
containing between 2% - 3% O2 and the dew point is less than
-25ºC.
The O2 content of 2% normally ensures zero ppm CO, however the inert gas
must be checked for the presence of CO (carbon monoxide/soot) prior to
inerting the tanks.
The inert gas generator must not be forced to run in such a way that the
temperature after the R22 cooler increases to a temperature above 10ºC, +5ºC
is recommended. If the temperature of the inert gas is above 10ºC, some salt
from the sea water will be liberated (mostly chloride) and this will follow the
inert gas flow into the tanks.
Liq
G
LN V2100
uid
Va
Ni
V2138
015 V2052
po
32 31 V2
tro
V21 V21
ur
ge
r
Liq
V2051
ou
Vap ater
n
Liq
uid
PI V2051
He 15
uid
V21 V2051
30 14
32 30 V21 V21 200
V2 1 V21 V2 V2051
p.B 14A 061
A
m V21 016 015 V2026
34 Co V2 V2 V2
V2 1 HD
r 31
To ou V21 201
ilers Vap ater V21
14 V2 120 Vent Dome
Bo He 35 V2 Mast 003
V21 061 V2004 V2
V2
S)
2(
00
36 0 16A V2101 V2
13 V21 V2 A
V2 1 35 200 V2055 V2138
V21 .A V2 V2002 (P)
V2
mp
Co No.1
20
HD
V2054
3
V21
28 V2054 Cargo Tank
e 126
pac
V2
V2 V2054
39 id S er
20
V21 Vo Dry
V2
3A
Air 14 V2054
V23
V2
17 p.
23
V21 m
20
13 Co 25 V2027
4
V21 V21 14
LD V23
3
35 15 26
V22 V23 V21 nt Dome
G 15 Pla Vent
LN iser V23 e N 007
or pac To 2 Mast V2008 V2
Vap id S er
Vo Dry (S)
V21
11 25 Air 6
V21 m ans V2
00
39 Fro ng F ating V2103
Void re V21 ti
ula ce H
e
or
r F osphe circ a V2138 V2006 (P)
ate Re id Sp
He e Atm
ac V21
39
For Vo V2058 V2068
No.2
Sp V2057
V2057 Cargo Tank
V2057
V2057
22
V21 V2028
19
V21
V2
Dome
01
Vent 011
2
Mast V2
s (S)
ace 0 10
Sp V2
Void V21
10
To V2108
V2010 (P)
18 V2138
V21 V2064 V2068 No.3
V2063
V2063
Cargo Tank
V2063
V2063
V2029
Spray
Pump
Dome
Vent 019
V2020 V2 D
FW
Mast
S)
8(
01
V2
V2109
V2066 V2138 V2018 (P)
No.4
V2065
V2065
Cargo Tank
V2065
A
V2065 015
V2
V2030 Spray
To Pump 0
Emergency V212
Discharge Dome
Astern 023
V2024 V2 A 061 015
200 V2 V2
V2
(S)
02 6A
V 20 01
V2
352 061
V2002 (P) V2 V2
Liq
A
No.5 V2
352
201
uid
V2 200
Cargo Tank 352 V2
Va
V2 6
po
201
Ni
V
ur
tro
Engine Room
ge
IG Plant
Key
n
Inert Gas
Position Description Valve dew point is better than -25°C. Close No.2 cargo tank filling valve V2007
Open Aft liquid ESD valve V2016A h) By sampling at the domes (bottom - middle - top) for HC content, Close No.3 cargo tank liquid header block valve V2012
Open Aft liquid manifold valve V2016 check and record the process developments, i.e. monitoring the Close No.3 cargo tank filling valve V2011
‘layer’ of the HC and the inert gas mixture which is gradually
Open No.1 cargo tank liquid header block valve V2004 rising during the process.. Close No.4 cargo tank liquid header block valve V2020
Open No.1 cargo tank filling valve V2003 Close No.4 cargo tank filling valve V2019
i) During tank inerting, the flow must be directed through the
Open No.2 cargo tank liquid header block valve V2008 sample points, gauge connections, compressor and vaporiser Close No.5 cargo tank liquid header block valve V2024
together with adjacent piping. Safety valves on the cargo tanks Close No.5 cargo tank filling valve V2023
Open No.2 cargo tank filling valve V2007
and pipelines, which may have ‘dead ends’ must also be purged.
Open No.3 cargo tank liquid header block valve V2012 d) Disconnect the flexible hose and replace the flange on the inert
gas supply line.
Open No.3 cargo tank filling valve V2011
Liq
LN V2100
uid
Va
Ni
V2138
015 V2052
po
32 31
tro
V21 V21 V2
ur
ge
r
Liq
V2051
ou
Vap ater
n
Liq
uid
V2051
PI He 15
uid
V21 V2051
30 14
32 30 V21 V21 200
V21 V21 V2 V2051
.B 14A
mp 061 A
Co V21 016 V2 015 V2026
34 V2 V2
V21 HD
r 31
To ou V21 201
ilers Vap ater V21
14 V2 120 Vent Dome
Bo He 35 V2 Mast 003
V21 061 V2004 V2
V2
(S)
A 02
36 016 V2101 V2
0
V2 A
13 V21 200 V2138
V21 35 V2 V2055
V21 .A V2002 (P)
V2
mp
Co No.1
20
HD
V2054
3
V21
28 V2054 Cargo Tank
e 26
pac
V2
V21 V2054
39 id S er
20
V21 Vo Dry
V2
3A
Air 14 V2054
V23
V2
17 .
23
V21 mp
20
13 Co 25 V2027
4
V21 V21 14
LD V23
3
V2006 (P)
35 15 26
V22 V23 V21 nt Dome
G 15 Pla Vent
LN iser V23 e N 007
or pac To 2 Mast V2008 V2
Vap id S er
Vo Dry 6(
S)
V21
11 2 5 Air 00
V21 m ans V2
39 Fro ng F ating V2103
Void re V21 ti
ula ce H
e
or
r F osphe circ a V2138
ate Re id Sp
He e Atm
ac V21
39
For
Vo V2058 V2068
No.2
Sp V2057
V2057 Cargo Tank
V2057
V2057
22
V21 V2028
19
V21
V2
Dome
01
Vent 011
2
Mast V2
s ( S)
ace 0 10
Sp V2
Void V21
10
To V2108
V2010 (P)
18 V2138
V21 V2064 V2068 No.3
V2063
V2063
Cargo Tank
V2063
V2063
V2029
Spray
Pump
Dome
Vent 019
V2020 V2 D
FW
Mast
(S)
0 18
V2
V2109
V2066 V2138 V2018 (P)
No.4
V2065
V2065
Cargo Tank
V2065
A
V2065 015
V2
V2030 Spray
To Pump
Emergency 120
V2
Discharge Dome
Astern 023
V2024 V2 200
A 061
V2 V2 015
S) V2
2(
00 A
V2 016
V2
061
V2002 (P) A V2
352
Liq
No.5 V2
201
uid
352 V2
Cargo Tank V2 200
2 V2
35
V2
Dry Air
Liq
G
LN V2100
uid
Va
Ni
V2138
015 V2052
po
32 31
tro
V21 V21 V2
ur
ge
r
Liq
V2051
ou
Vap ater
n
Liq
uid
V2051
PI He 15
uid
V21 V2051
30 14
32 30 V21 V21 200
V2 1 V21 V2 V2051
p.B 14A 061 A
Co
m V21 016 V2 015 V2026
34 V2 V2
V2 1 HD
r 31
To ou V21 201
ilers Vap ater V21
14 V2 120 Vent Dome
Bo He 35 V2 Mast 003
V21 061 V2004 V2
V2
S)
6A 2(
00
36 V 201 A
V2101 V2
13 V21 200 V2138
V2 1 35 V2 V2055
V21 .A V2002 (P)
V2
mp
Co No.1
20
HD
V2054
3
V21
28 V2054 Cargo Tank
e 126
pac
V2
V2 V2054
39 id S er
20
V21 Vo Dry
V2
3A
Air 14 V2054
V23
V2
17 p.
23
V21 m
20
13 Co 25 V2027
4
V21 V21 14
LD V23
3
V2006 (P)
35 15 26
V22 V23 V21 nt Dome
G 15 Pla Vent
LN iser V23 e N 007
or pac To 2 Mast V2008 V2
Vap id S er
Vo Dry (S)
V21
11 25 Air 06
0
V21 m ans V2
39 Fro ng F ating V2103
Void re V21 ti
ula ce H
e
or
r F osphe circ a V2138
ate Re id Sp
He e Atm
ac V21
39
For Vo V2058 V2068
No.2
Sp V2057
V2057 Cargo Tank
V2057
V2057
22
V21 V2028
19
V21
V2
Dome
01
Vent 011
2
Mast V2
s (S)
ace 0 10
Sp V2
Void V21
10
To V2108
V2010 (P)
18 V2138
V21 V2064 V2068 No.3
V2063
V2063
Cargo Tank
V2063
V2063
V2029
Spray
Pump
Dome
Vent 019
V2020 V2 D
FW
Mast
S)
8(
01
V2
V2109
V2066 V2138 V2018 (P)
No.4
V2065
V2065
Cargo Tank
V2065
A
V2065 015
V2
V2030 Spray
To Pump 0
Emergency V212
Discharge Dome
Astern 023
V2024 V2 200
A 061
V2 V2 015
V2
(S)
02
20 A
V 016
V2
061
V2002 (P) A V2
352
Liq
No.5 V2
201
uid
352 V2
Cargo Tank V2 200
V2
352
V2
Key
6
V 201
Inert Gas Plant in
Dry-Air Mode
Dry Air
To avoid corrosion during the periods that the cargo tanks are open, it is very
important that the tanks are vented with dry-air at all times. This is of vital
importance with 9% nickel steel tanks.
In relative humidity of less than 50%, corrosion will rarely take place.
However, the speed of corrosion increases rapidly when the relative humidity
exceeds 60%.
At all times during dry docking, the dew point temperature is to be kept more
than 3ºC lower than the cargo tank steel surface temperature and the relative
humidity is to be kept at 40% or lower.
During the dry docking period when the tanks may be open, air should be bled
into the cargo tanks and hold spaces through the ‘bottom’ line(s) and vented
out via the top.
To avoid any humid air being introduced into the cargo tank during this period,
the following additional precautions are to be taken:
A tent is to be rigged above all tank domes to avoid rain
from entering the tank
A prefabricated wooden hatch to cover the manhole is to
be fitted on all tanks which have to be entered
Avoid any more than two tanks being open at the same time
All entries into the cargo tanks are to be controlled by the vessel
Dry-air is to be bled into the tanks when entered
All tanks are to be closed when no work is taking place
A slight air overpressure is to be maintained
Insulation
Nitrogen
Blank Flange
Bleed
Rupture Disc
Removed
Rupture Disc
Skirt
Polystyrene
Leakage Pipes Insulation with
Stainless Steel
Cover
The cargo tank insulation is designed to meet the requirements of the ‘small
leak protection system’ i.e;
A leak starts as a ‘gas leak’. The tank insulation is not glued to the tank plate,
therefore it allows movement of a gas leak and thus the early detection of
leakage.
The insulation space (upper and lower hemisphere) is purged by N2 and the
outlet is monitored by the gas analyser regularly.
With the growth of the crack size, the leaked cargo will change its form to a
liquid-gas mixture, then to liquid.
Driving Water
V2004 V2015
V2014
Spool Piece
Turnable Spool
Piece
V1429
V1429
V42 Eductor Inlet Spool Piece Arrangement on Deck
Side
Water Ballast
Tank
Void
Space Cargo Discharge
Pump
Ejector
Bottom
Water Ballast
Tank
V40 Catch Basin
Tank Cross
Section
Key
LNG Liquid
2) Low temperature alarms at the temperature sensors in the a) Install the spool piece on the void space eductor return line to the Procedure to Inert the Void Space
surrounding areas. liquid header.
a) Prepare the inert gas plant in inert gas mode (see section 4.7.1 for
3) A general lowering of inner hull steel temperatures. b) Swing the spool piece on the LNG eductor drive line from the further detailed information) and start the inert gas production.
cargo pump discharge. When the oxygen content is between 2% and 3% and the dew
4) Possible liquid alarms in the surrounding areas. point between -25°C and -45°C, open valve V2354, upstream of
c) Open valve V2014, the LNG drive. the two non-return valves on the dry air/inert gas discharge line.
5) Possible gas alarms in the surrounding areas.
d) Open valves V2005 and V2015, the return from the void space b) Ensure the spoon blank between the IG outlet at the starboard
Any liquid flow from the upper hemisphere will be collected in the drain eductor. manifold and the void space aeration header is in the correct
channel formed by the upper ring stiffener of the skirt. There are four drain position.
pipes, port, starboard, forward and aft of the tanks, which lead any cargo e) Open valve V2005 - the filling valve to the tank.
leakage to the catch basin. Any liquid flow in the lower hemisphere will be led c) Open the void space air inlet valve V2303.
to the catch basin by a drain pipe at the south pole. f) Open valves V311 and V41 - the eductor inlet and outlet.
d) Take samples from the outlet pipe at the top of the void space to
Any liquid collecting in the catch basin will raise a liquid alarm via the DCS g) Start the cargo pump. LNG is drained from the catch basin test for hydrocarbon content. Also verify that the oxygen content
system. Whether the liquid is LNG cargo due to a tank leakage, or water due through valve V40 and discharged back to the cargo tank. of the inert gas remains between 2% and 3%.
to leakage from the water ballast tanks, can be determined by observing the gas
detector and the temperature indicators. A low temperature (-100º to -163ºC for On completion, the lines are allowed to warm up and vent back to the cargo e) When the hydrocarbon content sampled from the void space
LNG) indicates cargo leakage, while temperatures above 0ºC indicate water tank before being purged with nitrogen to ensure no LNG vapour remains. outlet falls below 1.5%, shut in the space, stop the inert gas supply
leakage. and shut down the inert gas plant. Reset the valve system for
aerating.
A bilge ejector is installed in the catch basin to empty the area when required.
If the basin has to be emptied of water, water supplied from the driving line Aeration is carried out in the same manner as inerting, using the inert gas plant
from the ejector feed pump is used as the driving force. The exhausted water operating in the dry air mode to supply dry-air.
is delivered overboard. After use, the flexible hoses must be disconnected and
the pipe ends blind-flanged. A needle valve, V1429, is located at each flange. The aeration operation is continued until the oxygen content, measured with a
Pressurised air from the working air system on deck is introduced to the ejector portable oxygen indicator, is about 21%.
pipe through these valves by means of quick connecting couplings and the air
will empty the ejector pipe of water through the drainpipe. In order to save time, the aeration of the void spaces can be carried out
simultaneously with gas freeing of the cargo tanks.
Depending on the size of the leak, liquid may find its way to the catch basin
located centrally below the affected tank. It is very important that the aeration of the void spaces must not start before
the warming up of the cargo tanks has been completed.
When LNG cargo has to be removed from the catch basin, the cargo is also
used as the eductor driving force.
The eductor driving force LNG is fed from the starboard side cargo pump of
the tank concerned, through the ejector pipe in the tank dome.
V2014
Turnable Spool
Piece Spool Piece
V1429
V1429
V42 Eductor Inlet Spool Piece Arrangement on Deck
Side
Water Ballast
Tank
Void
Space Cargo Discharge
Pump
Ejector
Bottom
Water Ballast
Tank
V40 Catch Basin
Tank Cross
Section
Key
Sea Water
7.3.1 Use of Eductors for Water Removal A bilge ejector is installed in the catch basin to empty the area when required.
If the basin has to be emptied of water, the procedure is as follows:
Ballast water leakage from the wing tanks to the void spaces can occur through a) Turn the spool pieces on the drive and outlet pipes and connect to
fractures in the inner hull plating. If the leakage remains undetected and water the drive water inlet line and overboard discharge.
accumulates in these spaces, ice may be formed. Ice accumulation can cause
deformation, and possible rupture, of the tank insulation. The resultant cold b) Open valve V20A, the ejector feed pump suction valve.
conduction paths forming in the insulation may cause cold spots to form.
c) Open valves V30 and 30A, the pump discharge valves.
To reduce the risk of damage from leakage, each cargo tank void space is
provided with water/leakage detection units. d) Open valve V41, the outlet to the overboard discharge line.
The leakage protection system also includes a method of collecting and e) Open valve V311, the eductor inlet.
accumulating small leaks of liquid cargo as well as water. This liquid is
collected in the catch basin under the cargo tank. The water leakage collects in f) Start the ejector feed pump.Water is drained from the catch basin
this basin, where the monitoring equipment is installed. The equipment through valve V40 and discharged overboard.
consists of a sample point for the gas detector, a liquid indicator and a
temperature indicator to raise alarms in the CCR via the DCS system. g) On completion, shut valves V311 and V41. Swing the spool
pieces. An air outlet valve is located at each flange enabling air
Any liquid collecting in the catch basin will raise a liquid alarm via the DCS from the working air system on deck to be introduced by means
system. Whether the liquid is LNG cargo due to a tank leakage, or water due of the quick connecting couplings. The air will empty the ejector
to leakage from the water ballast tanks, can be determined by observing the gas pipe of water through the drain line and valve V42.
detector and the temperature indicators. A low temperature (-100º to -163ºC for
LNG) indicates cargo leakage, while temperatures above OºC indicate water
leakage.
Liq
G
LN
uid
Va
5 V2138
Ni
01 V2052
V2
po
32 31
tro
V2100
V21 V21
ur
V2051
ge
r
Liq
ou
Vap ater
n
V2051
Liq
uid
He 15 200
uid
V21 V2 V2051
3 0 14
2 30 V21 V21 V2051
V 213 V21
mp
.B 14A 6 061 15A V2026
Co V21 V2
01 V2 V2
0
34 HD
V21 r 31
To ou 1
rs Vap ater V21 14 V 220 120 Vent Dome
B oile He V21 V2 Mast 00 3
35 061 V2004 V2
V21 V2
S)
2(
A V2101 00
m 016 0A V2
Fronifold 3 6 V2 20
13 V21 V2 V2055 V2138
Ma V21 35 V2002 (P)
V21 .A
V2
mp No.1
Co V2054
20
H D
3
28
V2054 Cargo Tank
V21 e 26 V2054
pac V21
V2
39 id S er
20
3A
Ai V23
1
V2
17 .
23
V21 mp V2027
Co
20
13 14
4
V21 LD V23
3
2 5
5 V21 15 26
V 223 V23 V21 G Dome
15 LN r Vent 007
V23 e To orise V2
pac Vap Mast V2008
id S er
G
LN iser Vo r Dry (S)
or 11 25 Ai 006
Vap V21 V21 V2
m ans V2103
d 39 Fro ing F ating
Voi re V21 t e
or
r F osphe c ir cula ace H V2138 V2006 (P)
ate Re id Sp V2058 V2068 No.2
He e Atm 39 V o
ac V21 For V2057
Sp
V2057
Cargo Tank
V2057
V2057
22
V21 V2028
19
V21
V2
Dome
01
Vent
011
2
Mast V2
S)
s 0(
ace V2
01
Sp 10
Void V21 V2108
To V2010 (P)
18 V2138
V21 V2064 V2068 No.3
V2063
V2063
Cargo Tank
V2063
V2063
V2029 Spray
Pump
Dome
Vent 019
V2020 V2
Mast D
8(
S) FW
01
V2
V2109
V2066 V2138 V2018 (P)
No.4
V2065
V2065
Cargo Tank
y
e nc
erg rge
V2065
m
E c ha V2065 015
A
V2
Dis stern Spray
A V2030
To Pump 120
V2
Dome
3
202 A 06 1
V2024 V 200 V2
V2
S) 015
0 2( V2
V 20 A
016
V2 061
V2002 (P) V2
Liq
No.5 201
uid
V2
Cargo Tank 200
V2
Va
6 Key
po
V201 Ni
ur
tro
Liq
ge
n
uid
LNG Liquid
LNG Vapour
Displaced LNG
7.4 Failure of Cargo Pumps - Emergency Discharge b) Complete normal unloading procedures and final gauging of the f) Monitor No. 5 cargo tank pressure increase and the cargo transfer
cargo, then sail from the port to an open sea area. rate. The tank pressure will rise rapidly during the first hour or so,
If the two cargo pumps in any one cargo tank fail, the remaining cargo can be then, as the tank level falls, the vapour pressure will have to be
transferred to any other tank by vapour pressurisation above the liquid in the c) Connect spool pieces at the inlet and outlet of the vaporiser. increased to maintain the flow. Regulate the cargo tank pressure
affected tank. The rate of transfer is controlled by regulating the pressure by throttling the liquid flow into the vaporiser.
within the tank. d) Open the manifold valves V2061, V2201 and V2200A and cool
down the transfer lines as required. (Note: The vaporiser must be monitored locally during this operation.)
The transfer operation would normally take place at sea after the completion of
unloading and gauging of the tanks. The ship would then return to complete the e) Select the Cargo Primary Window on the DCS display and carry g) Ensure that the tank pressure does not rise too close to the setting
unloading operation prior to the inerting, aerating and replacement of the out the normal safety checks. of the safety valve.
defective cargo pumps.
(Note: Under normal operating conditions, the LD compressor will be h) When the tank liquid level falls to approximately 2 metres, stop
Control of this operation would be by remote manual control from the DCS supplying boil-off gas to the boilers from all tanks through the gas heater. This the transfer of cargo by stopping No. 4 spray pump.
system in the CCR, with personnel available on deck for local monitoring. Full operation will be continued for No. 1, 2, 3 and 4 cargo tanks.)
safety precautions are to be implemented as for any normal cargo transfer i) Shut down the steam supply to the vaporiser.
operation. These include: The Transfer of Cargo
j) Set the valves as in the following table:
Fire hoses: laid out, pressurised a) Supply steam to the LNG vaporiser, opening steam supply valve
Dry powder system available V937A and when the LNG supply is stabilised, place the control Position Description Valve
valve V2203 in automatic control.
Safety personnel patrolling the cargo areas during the full Close LNG vaporiser supply valve V2203
operations of purging, cooldown and pressurised transfer
b) Adjust the vapour temperature out set point to -60ºC. Adjusting Close LNG vaporiser discharge valve V2235
of LNG.
the set point is described in the vaporiser manufacturer’s manual.
Close LNG vaporiser supply to vapour header valve V2118
Using this method, cargo is pressed up and displaced into the filling line by
c) Set the safety valves for operation on the HP pilot in order to Close Cargo tank No.5 vapour supply valve V2109
means of increased vapour pressure above the liquid. The increased pressure is
adjust the opening set point to 2.15 bar.
obtained by pumping LNG from cargo tanks No.3 or 4 using the spray pump Close Cargo tank No.4 spray discharge valve V2068
to the vaporisers. The vapour is introduced into the required tank through the
d) When the LNG liquid line header has cooled down, Set these Open No.4 cargo tank filling valves V2020, 2019
vapour line. The flow lines for LNG vapour, liquid LNG and for the displaced
valves as in the following table:
LNG are shown in illustration 7.4a. The illustration also shows the vapour Open No.5 cargo tank filling valves V2024, 2023
supply line to the other cargo tanks if required and the spray liquid suction Position Description Valve
from cargo tank No.3 if required. k) Reset No. 5 tank safety valves to their normal operating positions.
Open LNG vaporiser supply valve V2203
In order to avoid opening the safety valves, due to the increased pressure, the Open LNG vaporiser discharge valve V2235 l) The adjustment and readjustment of the safety valves is to be
valves are set for operation on the HP pilot. This is carried out by operating the carried out under the supervision of the Master and recorded in
Open LNG vaporiser supply to vapour header valve V2118
two-way three port ball valve via the interlock device. The opening set point is the ship’s log book.
thus increased to 2.15 bar. Open No.4 cargo tank filling valves V2020, 2019
Open No.5 cargo tank filling valves V2024, 2023 m) Restore all alarms to their normal operating settings.
The high pressure alarm is set to sound at 0.22 bar, so this alarm should be
inhibited. Open Cargo tank No.5 vapour supply valve V2108 n) Remove the spool pieces at the inlet and outlet of the vaporiser.
For this example, it is assumed the pumps have failed in cargo tank No.5. The Open Cargo tank No.4 spray pump discharge valve V2068
transfer of cargo from No.5 cargo tank to No.4 cargo tank is explained. No. 4 spray pump will now supply the LNG vaporiser to pressurise No.5 cargo
tank through valve V2109.
Procedure for an Emergency Discharge
a) Discharge the contents of No.1, 2, 3 and 4 cargo tanks, leaving e) Start No.4 cargo tank spray pump.
approximately 1500m3 in No.3 or No.4 cargo tanks. This quantity
of liquid will provide the required volume of vapour.
All terminals have their own requirements regarding when it is unsafe for a
vessel to remain alongside a terminal. These are normally outlined in the
terminal handbook.
g) Liaison with shore personnel to arrange for pilot and tugs and
additional support.
i) The vessel would either move away from the berth to a safe area,
under its own power with assistance of a standby tug or with
additional tugs/pilot summoned from shore.
Li q
GC
LN
ui d
V2100
Va
015
Ni
V2052 V2138
p
V2
tro
32 31
ou
V21 V21
L iq
ge
r
r V2051
ou 120
u id
n
Li q
Vap ater V2 V2051
He
u id
15
V21 V2051
3 0 14
32 3 0 V21 V21 200 V2051
V21 V21 V2
.B 1 4A
016 061 0 15A
Co
mp V21 V2 V2 V2 V2026
34 HD
V 21 31 1
To r
220
ou V21
oile
rs Vap ater V21
14 V Vent Dome
B He 35 061
Mast 003
V21 V2 V2004 V2
S)
A 2(
016 A 00
36 V2 200
V2101 V2
1 3 V21 V2 V2138
V21 35 V2055
V21 .A V2002 (P)
V2
mp
Co No.1
20
V2054
HD
3
V21
28 V2054 Cargo Tank
e 126
pac
V2
V2 V2054
39 id S er
20
V21 Vo r Dry 4
V2
3A
1 V2054
Ai V23
V2
17 p.
23
V21 om
20
13 V2027
4
V21 C 14
LD V23
3
2 5
5 V21 15 26
V 223 V23 V21 nt
Pla Dome
15 N Vent
G
LN iser V23 e To 2 007
or pac Mast V2008 V2
Vap id S er
Vo r Dry S)
11 25 A i 6(
V21 V21 m ans V2
00
d 39 Fro ing F ating V2103
Voi re V21 t
cula ace H
e
or V2138
r F osphe c ir
Re id Sp
V2006 (P)
ate V2058 V2068
He e Atm
ac V21
39
Fo r Vo No.2
Sp V2057
V2057 Cargo Tank
V2057
V2057
22
V21 V2028
19
V21
V2
Dome
01
Vent 011
2
Mast V2
s (S)
ace 01
0
Sp V2
Void 10
To V21 V2108
V2010 (P)
18 V2138
V21 V2064 V2068 No.3
V2063
V2063
Cargo Tank
V2063
V2063
V2029
Spray
Pump
Dome
Vent 019
Mast V2020 V2 D
S) FW
8(
01
V2
V2109
V2066 V2138 V2018 (P)
No.4
V2065
V2065
Cargo Tank
V2065
A
015
V2065 V2
V2030 Spray
Pump
Dome
023 200
A 061
V2024 V2 V2
V2
015
S) V2
2(
00 A
V2 016
V2 061 120
V2002 (P) V2 V2
Liq
No.5 201
u
V2
id
200
Cargo Tank V2
Va
6
po
V201 Ni
ur
tro
Key
Liq
ge
n
uid
LNG Vapour
7.6 One Tank Operation 7.6.1 One Tank Warm Up m) Monitor the tank pressure and adjust the compressor(s) to
maintain the tank pressure between 0.04 bar and 0.2 bar.
It may be necessary for in-tank repairs to be carried out with the vessel in Normal gas burning is continued during this operation using vapour from all
service, in which one tank can be warmed up, inerted, aerated, entered and five tanks. In the first instance, normal boil-off gas procedures are followed n) When the tank pressure tends to decrease, stop the BOG burning.
work undertaken on the tank internals, i.e. change cargo pump, investigate and until this operation has stabilised, then the operation for warming up one tank
cure problems with tank gauging systems etc. using an HD compressor can be carried out. o) Monitor the tank temperatures, warm up is completed when the
cargo tank equator temperature is higher than -20°C.
The warm up, inerting and aeration can be carried out with the remaining cold Warm Up Procedure (No.3 Tank)
tanks providing boil-off gas for burning in the boilers. p) Stop the warm up, shut off the steam to the gas heaters and allow
It is assumed that all valves are closed prior to use. vapour to circulate for 10 minutes.
Aeration should be continued throughout the repair period to prevent ingress
of humid air to the cargo tank. a) Install the spool piece and open valves V2121 and V2125 to q) Shut down the HD compressor(s) and set up for inerting and
discharge the heated vapour to the liquid header. aerating the tank.
Tank venting is carried out by means of the gas header line.
b) Prepare the upper or lower gas heater for use.
Operation
CAUTION
At the discharge port, the tank to be worked on is discharged to the lowest The vapour heaters should be thoroughly preheated with steam before the
measurable level and after completion of custody transfer, as much as possible admission of methane vapour. This prevents ice formation.
is drained to another tank using the spray/stripping pump, if possible.
Sufficient heel for the voyage, together with an extra amount for cooling down c) Adjust the heater temperature set point for +75ºC.
the tank after completion of repairs, is retained in one of the other tanks.
CAUTION
When returning heated vapour to the cargo tanks, the temperature at the
heater outlet should not exceed +85ºC to avoid possible damage to the
cargo piping insulation and safety valves.
h) Open the heater inlet and outlet valves V2131 and V2132.
l) Send boil-off gas to the boilers; carry out steam dumping and vent
control in parallel to obtain stable boiler combustion.
Liq
LN V2100
uid
V2138
Va
V2052
015
Ni
32 31
po
V2
V21 V21
tro
V2051
ur
r
ge
ou
Liq
Vap ater V2051
n
Liq
He
uid
15
V21 V2051
uid
30 14
3 2 30 V21 V21 V2051
V2 1 V21 220
0
.B 4A V A
mp V21
1
061 015 V2026
Co 016 V2 V2
34 HD V2
V2 1
To ou
r
V2 131 1 Vent
iler
s Vap ater 4 220 Dome
Bo V21
1 V 120 Mast 003
He 3 5 V2 V2004 V2
V21 061
V2 (S)
2
V2101 00
A V2
36 016 A
13 V21 V2 200 V2055 V2138
V21 35 V2 V2002 (P)
V21 .A
V2
mp No.1
Co V2054
20
HD
3
28
V2054 Cargo Tank
V21 e 26 V2054
pac V21
V2
39 id S er
20
V21 Vo r Dry
14
V2054
V2
3A
A i
V23
V2
17 p.
23
V21 om 25
V2027
20
13 C 14
4
35 15 26
V22 V23 V21 nt Dome
G 15 Pla Vent 007
LN iser V23 pac
e N
To 2 Mast V2008 V2
or i d S er
Vap Vo r Dry S)
Ai 6(
11 25 00
V21 V21 m ans
V2
d 39 Fro ing F ating V2103
Voi re V21 t e
or cula ace H V2138 V2006 (P)
r F osphe c ir
Re id Sp
ate V2058 V2068 No.2
He e Atm 39 V o
ac V21 For V2057
Sp
V2057
Cargo Tank
V2057
V2057
22
V21 V2028
19
V21
V2
Dome
01
Vent
011
2
Mast V2
(S)
es 01
0
S pac V2
10
Void V21 V2108
To
V2138 V2010 (P)
18
V21 V2064 V2068 No.3
V2063
V2063
Cargo Tank
V2063
V2063
V2029 Spray
Pump
Dome
Vent 019
V2020 V2
Mast D
8(
S) FW
01
V2
V2109
V2066 V2138 V2018 (P)
No.4
V2065
V2065
Cargo Tank
V2065 * 1-5 Cargo Tank Valves 2100, 2101, 2103, 2108 and 2109
A
V2065 015 Must Be Shut On Tanks Not being Inerted
V2
V2030 Spray
Pump
120
V2
Dome
023
V2024 V2 A 061
200 V2
S) V2
2( 015
0 V2
V 20
6 A
201
352
V 061
V2002 (P)
V2 V2
Liq
A
No.5 352
V2 201
uid
V2
Cargo Tank 200
352 V2
Va
V2
016
po
Ni
V2
ur
tro
Engine Room
ge
IG Plant
Key
n
Inert Gas
7.6.2 One Tank Gas Freeing h) By sampling at the vapour dome, check the atmosphere of the
tank using a portable oxygen analyser. The oxygen content is to
The tank pressure in all tanks is to be reduced as much as possible prior to be between 2% and 3% and the dew point less between -25°C and
inerting as it is not possible to use the boil-off gas from the four remaining -45°C.
tanks during the inerting of No.3 cargo tank.
i) When the hydrocarbon content sampled from the tank outlet falls
Gas Freeing Procedure (No.3 Tank) below 1.5%, shut in the tank. On completion of inerting, stop the
inert gas supply and shut down the inert gas plant. Reset the valve
a) Prepare the dry-air/inert gas plant for operation in the inert gas system for aerating.
mode.
(Note: If No.3 tank is to remain without inerting shut the vapour header valve
b) Install the flexible connection between the flange at the end of the V2103 and pressurise the tank to 0.1 bar before shutting down the inert gas
inert gas/dry-air feeder line and the liquid manifold or access to plant.)
the liquid header.
j) Close the following valves:
c) Install the flexible connection between the flange on the vapour
header line to the flange at No.3 tank vent mast. Position Description Valve
e) Start the inert gas plant. When the oxygen content is between 2%
and 3% and the dew point is between -25°C and -45°C, open the
IG plant discharge valve V2353 and open the deck valves V2352
and V2352A to allow the inert gas to pass into the liquid header.
f) Monitor the tank pressure and adjust the opening of the fill valve
to maintain a uniform pressure.
Liq
G
LN V2100
uid
Va
V2138
015
Ni
V2052
po
32 31 V2
tro
V21 V21
ur
ge
Liq
r V2051
ou
Vap ater
n
Liq
V2051
uid
He 15
uid
V21 V2051
30 14
3 2 30 V2 1 V2 1 200 V2051
V21 V2 1 V2
.B 14A 061 15A
Co
mp V21 016 V2 V2
0 V2026
34 V2
V21 HD
To r 31 1
ou V21 220 120
oile
rs Vap ater V21
14 V V2
Vent Dome
B He 35 Mast 003
V21 061 V2004 V2
V2
S)
2(
A 00
36 016 0A V2101 V2
V21 V2 20
13 35 V2 V2138
V21 V21
V2055
V2002 (P)
p.A
V2
om No.1
2
C V2054
03
HD
V21
28 V2054 Cargo Tank
e 26
pac V21
V2
V2054
39 id S er
2
V21 Vo r Dry
03
14
V2
V2054
Ai V23
A
V2
17 .
2
V21 mp
34
25
2
13 Co 14 V2027
V21 V21
03
LD V23
35 15 26
V22 V23 V21 t
P lan Dome
15 Vent
G
LN iser V23 e N
To 2 007
or pac Mast V2008 V2
Vap id S er
Vo r Dry S)
11 25 Ai 6(
V21 V21 m ans V2
00
d 39 Fro ing F ating V2103
Voi V21 ula
t
eH
e
or here circ Spac V2138 V2006 (P)
rF p e
ate tmos R
Void V2058 V2068
e
H eA
ac V21
39
For No.2
Sp V2057
V2057 Cargo Tank
V2057
V2057
22
V21 V2028
19
V21
V2
Dome
01
Vent 011
2
Mast V2
e s 0 (S)
pac 01
S V2
Void V21
10
To V2108
V2010 (P)
18 V2138
V21 V2064 V2068 No.3
V2063
V2063
Cargo Tank
V2063
V2063
V2029
Spray
Pump
Dome
Vent 019
Mast V2020 V2 D
S) FW
8(
01
V2
V2109
V2066 V2138 V2018 (P)
No.4
V2065
V2065
Cargo Tank
V2065
01 5A
V2065 V2
V2030 Spray
Pump
120
V2
Dome
3
V2024 V 202 00A 061
V2
2 V2
S) 015
2( V2
00
V2 6A
201
V 061
V2002 (P) 352 V2
V2
Liq
2A
No.5 235 201
uid
V V2
Cargo Tank 200
2 V2
Va
V 235
016
po
Ni
Inert Gas Plant in V2 Key
ur
tro
Dry-Air Mode
ge
n
Fresh Air
Transfer can begin when the two Masters have ensured that all the pre-transfer This procedure will be carried out, under normal conditions, at anchor, though
checks and precautions have been completed and agreed them. Both ships if both Masters agree, unmooring can take place whilst under way.
should be prepared to disconnect and unmoor at short notice should anything
go wrong. Before unmooring begins, obstructions from the adjacent sides of both ships
should be cleared and the sequence and timing of the event be agreed by both
During transfer, ballast operations should be performed in order to keep the ships, and commenced at the request of the manoeuvring ship. Lines should be
trim and list of both vessels constant. Listing of either vessel should be avoided singled up fore and aft, then let go the remaining forward mooring allowing the
except for proper tank draining. Checks should also be kept on the weather, ships to drift away from each other, at which time the remaining after moorings
traffic in the area, and that all safety equipment is still in a state of readiness. are let go and the ships drift clear of each other. Neither ship should, at this
point, attempt to steam ahead or astern until their mid lengths are about two
Transfer can take place whilst the two vessels are at anchor. This is the most cables apart.
common method. Transfer can also take place whilst the two vessels are under
way, though this depends on there being adequate sea room, traffic conditions
and the availability of large diameter, high absorption fenders.
Underway Transfer
Drifting Transfer
Completion of Transfer
After transfer has been completed and before unmooring, all hoses should be
purged, manifolds securely blanked and the relevant authorities informed that
transfer is complete.
WARNING
The jettisoning of cargo is an emergency operation. It should only be
carried out to avoid serious damage to the cargo tank and/or inner hull
steel structure.
c) All accommodation and other openings and all vent fans must be
secured.
Weather conditions, and the heading of the vessel relative to the wind, must be
considered so that the jettisoned liquid and resultant vapour cloud will be
carried away from the vessel. In addition, if possible, avoid blanketing the
vapour with exhaust gases from the funnel.
The discharge rate must be limited to the capacity of one cargo pump only and,
if necessary, reduced to allow acceptable dispersal within the limits of the
prevailing weather conditions.
WARNING
Too rapid a flow of LNG will result in rapid phase transfer (RPT) when
the liquid hits the sea water.
7.9 General Emergency Procedures Try to control the direction of the dispersion with the fire hose water spray, 7. Tank Overpressure
dilute the gas with water spray, heating the relatively cold gas to increase its
1. Mooring Failure buoyancy. During Cooldown or Loading
If any of the mooring lines should break, or a winch starts to pay out on a The off-duty crew are to be called out to prepare for fire fighting. If the high-pressure alarm is released and the pressure is still rising after
mooring line, the CCR is to be notified at once. Corrective action is to be taken reducing the cooldown rate/loading rate, the following action shall be taken:
as soon as possible. 4. Fire in the Tank Vent Mast
The cooldown/loading is to be stopped immediately and the reason for the high
If the vessel starts moving, the CCR has to be informed and ESD to be If vent mast fire, the following to be considered: tank pressure is to be investigated. The terminal is to be advised.
released. The cargo operation shall not resume until the reason why the vessel
has moved is established and the corrective action taken. 1. Stop venting immediate, or detect the gas leakage from the safety The cooldown/loading shall not continue until the tank pressure is under
valves. control and accepted by the terminal.
If the OOW observes a change in the weather conditions, or recognises an
unannounced vessel passing nearby, the CCR shall be notified and the 2. Inject any kind of inert gas (IG) into the vent mast. During Discharging
moorings shall be carefully observed.
3. Spray the masthead with water. The terminal has to be ordered to stop the return gas blower and vapour
2. Cargo Leakage on Deck manifold valve to be closed.
5. Cargo Tank Overfill
The CCR is to be informed immediately about the observation and the extent The terminal is to be advised that the discharging will be stopped and that the
of the leakage is to be reported. If any sign that a cargo tank is overfilled during a cargo operation, the manifold valves will be closed until the situation is clarified.
operation is to be stopped immediately and the terminal is to be advised.
Discharging rate/loading rate is to be reduced or stopped until the situation is As soon as agreed with the terminal, open the vapour valve and vent the return
under control. The terminal is to be informed. The situation is to be assessed and corrective action is to be taken. gas to the shore flare or burn the excess BOG on the boilers, until the pressure
in the cargo tanks is under control.
If unable to stop the leakage, the cargo operation shall be suspended until the The vapour line is to be inspected to find out if any liquid has entered it and
problem is solved. the LNG compressors are to be stopped accordingly in order to avoid liquid Continue the discharging when the reason for the high tank pressure is
slugs. established and agreed by the terminal.
Water shall be used to protect the steel and dilute the gas.
If possible, the excess cargo is to be transferred to another cargo tank. 8. Uncontrolled Venting
3. Cargo Line Burst
The ‘overfilled’ cargo tank is to be closely monitored during the remaining If any uncontrolled venting should take place, all cargo operations are to be
The ESD system is to be activated, the CCR is to be informed accordingly and loading. stopped immediately.
the general alarm raised.
6. Leakage in Cargo Compressor Room Check that all openings in the deckhouse and superstructure are closed to
The terminal is to be informed immediately according to the terminal’s safety minimise the possibility to vapour entry.
checklist procedures. If any alarm comes from the gas detection system, indicating a high gas
concentration in the cargo compressor room, the room has to be inspected with If alongside, the terminal is to be advised.
All cargo operations are to be suspended, valves closed and if possible the caution (enclosed space entry procedure is to be followed), and action is to be
fractured section to be isolated as much as possible. taken to correct the gas leakage. If at sea, try to change course, related to the wind and the vessel’s speed, to
minimise the risk for any gas vapour to enter the superstructure.
All ventilation is to be closed, or stopped. Be sure that the ventilation fan is running, and no gas has accumulated.
Identify the gas leakage and try to isolate the gas-leaking source.
Smoking, naked lights and the use of electric switches everywhere onboard, Be sure that the gas analyser and ventilation are operating at all times.
are not to be used until the area is declared as gas free. Spray the vent mast with water in order to heat and increase the vapour
buoyancy.
Fire hoses and water sprays must be ready for immediate use in the fractured
area of the vessel’s hull, in order to protect the mild steel and to disperse the
liquid overboard.
The terminal safety checklist is to be followed and the cargo operations are to
be stopped while the electrical storm is passing the vessel, terminal and plant.
The cargooperation may continue as soon as the electrical storm has passed
and is agreed by the terminal.
2. Contact the terminal and inform that the cargo operation may be
stopped.