You are on page 1of 14

APPENDIX 19 PIPER ALPHA

At 10.00 p.m. on July 6, 1988, an explosion occurred in A19.1. The Company, the Management,
the gas compression module of the Piper Alpha oil pro- and the Personnel
duction platform in the North Sea. A large pool fire took
The Piper Alpha oil platform was owned by a consor-
hold in the adjacent oil separation module, and a massive
tium consisting of Occidental Petroleum (Caledonia)
plume of black smoke enveloped the platform at and
Ltd, Texaco Britain Ltd, International Thomson plc, and
above the production deck, including the accommoda-
Texas Petroleum Ltd and was operated by Occidental.
tion. The pool fire extended to the deck below, where
The management concerned with the Piper platform
after 20 min it burned through a gas riser from the pipe-
included the following:
line connection between the Piper and Tartan platforms.
The gas from the riser burned as a huge jet flame. Most
Offshore Installation Manager Mr. C.D. Seaton
of those on board were trapped in the accommodation.
The lifeboats were inaccessible due to the smoke. Some Offshore Superintendent Mr. T.J. Scanlon
62 men escaped, mainly by climbing down knotted ropes Senior Maintenance Superintendent Mr. R.H. Seddon
or by jumping from a height, but 167 died, the majority Maintenance Superintendent Mr. K.D. White
in the quarters.
The Piper Alpha explosion and fire was the worst acci- Mr. A.C.B. Todd
dent which has occurred on an offshore platform.
Following the disaster, a Public Inquiry was set up Other personnel on duty on the evening of July 6 and
under the Public Inquiries Regulations Offshore referred to below include
Installations Regulations 1974 presided over by Lord
Cullen to establish the circumstances of the disaster and Lead maintenance hand Mr. A.G. Clark
its cause and to make recommendations to avoid similar Lead production operator Mr. R.A. Vernon
accidents in the future. The Inquiry’s report The Public Phase 1 operator Mr. R.M. Richard
Inquiry into the Piper Alpha Disaster (the Piper Alpha
Report, or Cullen Report) (Cullen, 1990) is the most com- Phase 2 operator Mr. E.C. Grieve
prehensive inquiry conducted in the United Kingdom Control room operator Mr. G. Bollands
into an offshore platform disaster, or indeed into any Instrument technician Mr. W.H. Young
process industry disaster, onshore or offshore.
The Piper Alpha Inquiry has been of crucial impor-
tance in the development of the offshore safety regime in A19.2. The Field and the Platform
the UK sector of the North Sea. Whereas Flixborough The Piper Alpha platform was located in the Piper field
was followed first by a Court of Inquiry and then by the some 110 miles north-east of Aberdeen. The platforms
Advisory Committee on Major Hazards, the Piper Alpha in the field and the pipeline connections between them
Inquiry not only discharged the function of an inquiry are shown in Figure A19.1.The Piper platform separated
into the specific disaster, but made recommendations for the fluid produced by the wells into oil, gas, and conden-
fundamental changes to the offshore safety regime which sate. The oil was pumped by pipeline to the Flotta oil
were accepted by the government. terminal in the Orkneys, the condensate being injected
The description of the Piper Alpha disaster given back into the oil for transport to shore. The gas was
below is necessarily a relatively brief one. Nevertheless, transmitted by pipeline to the manifold compression
it is somewhat fuller than that of the case histories in platform MCP-01, where it joined the major gas pipeline
the other appendices, for several reasons. It provides from the Frigg Field to St Fergus.
a good illustration of the work of an accident inquiry. There were two other platforms connected to Piper
It is replete with lessons on design and operation Alpha. Oil from the Claymore platform, also operated by
of hazardous installations. And it has had far-reaching Occidental, was piped to join the Piper oil line at the
consequences for the offshore safety regime. A fuller ‘Claymore T.’ Claymore was short of gas and was there-
account is given in the Piper Alpha Report. The daily fore connected to Piper Alpha by a gas pipeline so that it
transcripts, available in copyright libraries, also repay could import Piper gas. Oil from Tartan was piped to
study. An account from the viewpoint of one of the con- Claymore and then to Flotta and gas from Tartan was
sultants to the Inquiry has been given by Sylvester-Evans piped to Piper and thence to MCP-01.
(1991). Elevation views of the Piper Alpha platform, the layout
Selected references on Piper Alpha are given in of the production deck at the 84 ft level, and the
Table A19.1. layout of the deck below, the 68 ft level, are shown in

2848
APPENDIX 19 Piper Alpha 2849

TABLE A19.1 Selected References on Piper Alpha

Report of the Public Inquiry


Cullen (1990)
Part 1 Evidence
F.H. Atkinson (1989) (Lloyds Register); Bakke (1989) (explosion simulation); Balfour (1989) (gas detectors); Bett (1989) (reciprocating
compressors); Bodie (1989) (Offshore Safety Superintendent); Bollands (1989) (Control Room Operator); Brading (1989) (Chairman, Occidental
Petroleum (Caledonia) Ltd); Burns (1989) (Shift Supervisor, MCP-01); A.G. Clark (1989) (Maintenance Lead Hand); M.R. Clark (1989)
(hydrocarbon inventory); Clayson (1989) (evacuation, escape and rescue); R.A. Cox (1989a) (damage to firewall, explosion simulation); R.A. Cox
(1989b) (damage by projectiles); R.A. Cox (1989c) (damage to electrical systems, ESD, F&G, fire protection systems); R.A. Cox (1989d) (damage
to risers); Cubbage (1989) (explosion effects analysis); J. Davidson (1989) (Operations Superintendent, Claymore); M.E. Davies (1989) (wind
tunnel modeling of gas dispersion); D.D. Drysdale (1989) (escalation of fire); J. Drysdale (1989) (hydrates, methanol injection); Gordon (1989)
(Manager, Loss Prevention Dept.); P.M. Grant (1989) (contractors); Grieve (1989) (Process Operator); Grogan (1989) (Vice-President
Engineering, Occidental); Guiomar (1989) (OIM, MCP-01); Henderson (1989) (Lead Operator); Jefferey (1989) (life rafts); Jenkins (1989) (DoEn
Inspector); Johnsen (1989) (hydrates, methanol injection); Leeming (1989) (OIM, Tartan); P. Lloyd (1989) (electrical systems); Lockwood (1989)
(Lead Production Operator, permits-to-work); Macallan (1989) (Production and Pipeline Manager); A.G. McDonald (1989) (telecommunications);
McGeough (1989) (safety training); McLaren (1989) (Lloyds Register, electrical); McNeill (1989) (rescue); McReynolds (1989) (Vice-President
Operations, Occidental); J.G. Marshall (1989) (ignition sources); Moreton (1989) (Production Supervisor, Tartan); J. Murray (1989) (gas
detectors); A.C. Palmer (1989) (damage by projectiles); Paterson (1989) (hydrates, methanol injection); Petrie (1989) (Director of Safety, DoEn);
Pillans (1989) (Lloyds Register, electrical); Rankin (1989) (supervisor, Score PSV certification team); G. Richards (1989) (OIM, back-to-back);
S.M. Richardson (1989a) (hydrates, methanol injection); S.M. Richardson (1989b) (gas pipelines); S.M. Richardson (1989c) (auto-ignition);
S.M. Richardson (1989d) (leaks); Ritchie (1989) (Managing Director, Score UK Ltd); K. Roberts (1989) (Facilities Engineer, Tartan);
G.G. Robertson (1989) (Safety Supervisor); J.B. Russell (1989) (hydrates, methanol injection); Saborn (1989) (standby vessel); Sandlin (1989)
(OIM, Claymore); Saville (1989a) (condensate admission to PSV 504 system); Saville (1989b) (leaks); Saville (1989c) (hydrates, methanol
injection); Saville (1989d) (pipe failure); Scanlon (1989) (Offshore Superintendent, maintenance); Scilly (1989) (explosion effects analysis);
Scothern (1989) (gas detectors); Seddon (1989) (Senior Maintenance Superintendent); Smyllie (1989) (flare); Tea (1989) (gas detectors); Thomson
(1989) (Lloyds Register); Todd (1989) (Maintenance Superintendent); Tucker (1989) (accommodation); P.C.A. Watts (1989) (flare); Whalley
(1989) (PSV recertification); W.P. Wood (1989) (DoTp surveys); Wottge (1989) (platform, facilities, and systems)
Part 2 Evidence
A.J. Adams (1989) (pipeline isolation, including subsea isolation valves); C.S. Allen (1989) (PTWs); Ashworth (1989) (process control and ESD);
Banks (1990) (maintenance supervisors); Baxendine (1989) (emergency command); van Beek (1989) (blast walls); Booth (1989) (escape routes);
Brandie (1989a) (safe havens); Brandie (1989b) (alternatives to standard fire water systems); Broadribb (1989) (subsea isolation valves);
Chamberlain (1989) (mitigation of vapor cloud explosions); R.A. Cox (1989c) (QRA); Cunningham (safety representatives); Dalzell (1989) (smoke
ingress into accommodation); Daniel (1989) (standby vessels); G.H. Davies (1989) (PTWs); Day (1989) (emergency power); Denton (1989)
(quality management systems); Doble (1989) (explosion prevention and mitigation Kittiwake); Drew (1989) (standby vessels); Ellice (1989)
(training of OIMs); Ellis (1989) (HSE view of QRA); J.D. Evans (1989) (smoke hoods); Ferrow (1989) (FSA); Fleishman (1989) (Gyda safety
evaluation); Gilbert (1989) (subsea isolation valves); Ginn (1989) (evacuation by helicopter); Gorse (1989) (FSA); Heiberg-Andersen (1990)
(evacuation, Norwegian sector); Higgs (1990) (offshore safety regime); Hodgkins (1989) (HSC DoEn Agency Agreement); Hogh (1989) (QRA);
M.J. Jones (1990) (training); Keenan (1989) (standby vessels); Kelleher (1989) (lifeboats); Kinloch (1989) (PTW); Kyle (1989) (PTWs); Lien
(1989) (escape systems); Littlejohn (1990) (offshore supervisors); Lyons (1989) (offshore safety regime); McIntosh (1989) (fire and explosion
protection); McKee (1990) (safety management); Macey (1989) (standby vessels); Matheson (1989) (offshore emergency medical team); V.C.
Marshall (1989d) (safety cases); Middleton (1989) (standby vessels); Nordgard (1990) (accommodation in Norwegian sector); Ognedal (1990)
(Norwegian offshore safety regime); Pape (1989) (HSE view on QRA); de la Pena (1990) (smoke hoods); Perrott (1989) (escape systems); Petrie
(1989, 1990) (life-saving appliances, offshore safety regime); Priddle (1990) (offshore safety regime); Rimington (1990) (onshore safety regime);
Rudd (1989) (evacuation); Scanlon (1989) (PTWs); Sefton (1989) (CIMAH, safety cases); R.A. Sheppard (1989) (safety management); Side (1989)
(rescue and evacuation); Spouge (1989) (options for accommodation); B.G. Taylor (1989) (offshore industry developments); Tveit (1990)
(Norwegian offshore safety regime, QRA); Vasey (1989) (mitigation of module explosions); I.G. Wallace (1989) (evacuation and escape); Willatt
(1989) (offshore pipeline connections)
Further Accounts
Anon. (1988g); Johnsen (1989, 1990); Boniface (1990a,c e); Redmond (1990); S.M. Richardson, Saville, and Griffiths (1990); Sylvester-Evans
(1990a,b, 1991); Tombs (1990); Lees (1991,1992a, 1994b); A. Singh (2010) (Inherently safe design); Ramsay (1994) (QRA); Kletz (1991, 2001,
2009); Palmer (1998) (Failure Analysis); Pask (2000) (Failure Analysis); Pickering (1994) (Legislative changes); Paté-Cornell (1993) (technical and
organizational factors); Jenkins (1990) (Life cycle safety management); Crawley (1999) (Safety Management); Shaw (1992) (QRA); Booth (1992)
(permit-to-work systems); Gordon (1998) (human factors); Mearns (1995) (Risk perception); Boh (2005) (blast walls); Flin (1996) (Risk
perception); Basra (1998) (human error); Bellamy (1994) (human factor); Lowesmith (2007) (Jet Fire Hazards); Kujath et al. (2010) (accident
model); Santos-Reyes (2009); Bai (2003) (Risk Assessment); Khan (2002) (Risk-based process safety assessment); Crawley (1997) (risk assessment);
Vinnem (1998) (QRA); Falck (2000) (QRA); Finucane (1999) (performance standards); Vinnem et al. (2006) (hazard risk indicators); Pula (2005)
(fire consequence models); Khan (2002) (Inherent safety); Vinnem (2011) (emergency preparedness); Skogdalen (2011) (QRA); Vinnem (2010);
Sawa (2010) (regulations); Onoufriou and Forbes (2001) (structural system reliability); Yun and Marsdenxb (2010) (Rescue strategies); Pula (2006)
(Fire and Explosion Consequence Analysis); Kjellén (2007); Krueger (2003) (fire hazard analysis); Høivik et al. (2009) (safety climate); Ren (2008)
(safety assessment); Mikkelsen et al. (2004); Mearns et al. (2003) (Safety climate and safety performance); Van Wingerden (1994); Trbojevic et al.
(1994) (Risk Analysis); Nicholls and Lowe (2004) (climate change).

Figures A19.2, A19.3, and A19.4 respectively. The produc- Module A was about 150 ft long east to west, 50 ft
tion deck level consisted of four modules, Modules A D. wide north to south, and 24 ft high. The other modules
Module A was the wellhead, Module B the oil separation were of approximately similar size. There were firewalls
module, Module C the gas compression module, and between Modules A and B, between Modules B and C,
Module D the power generation and utilities module. and between Modules C and D (the A/B, B/C, and C/D
2850 Lees’ Loss Prevention in the Process Industries

From The main production areas were equipped with a fire


Frigg Field and gas detection system. In C Module, the gas detection
system was divided into five zones: C1 and C2 in the
MCP-01 west and east halves of the module and C3, C4, and C5
at the three compressors, respectively.
The fire water deluge system consisted of ring mains
which delivered foam to Modules A C and part of
Gas to Module D and at the Tartan and MCP-01 pig traps and
St Fergus water at the condensate injection pumps. The fire pumps
18'' Gas were supplied from the main electrical supply but there
33·5 Miles were backup diesel-driven pumps.
The hydrocarbon inventory in the pipelines was
approximately as follows. The main oil line was 30 in. in
diameter and 30 miles long and held some 70,000 te of
oil. The gas line from Tartan was 18 in. in diameter and
To Flotta Terminal 11.5 miles long and held some 450 te; the gas line to
30'' Oil-127 Miles MCP-01 was 18 in. in diameter and 33.5 miles long and
30'' Oil held 1280 te; the gas line to Claymore was 16 in. in
16'' Gas diameter and 21.5 miles long and held 260 te.
Piper
21·5 Miles ‘A’

Claymore A19.3. The Process and the Plant


18'' Gas
11·5 Miles The fluid from the wellhead, containing oil, gas, conden-
sate, and water, passed through the wellhead ‘Christmas
trees’ to the two separators where the gas was separated
24'' Oil Tartan from the oil and water. The oil was then pumped into
‘A’ the main oil line. The gas was compressed first in three
centrifugal compressors to 675 psia, with some gas being
FIGURE A19.1 Pipeline connections of the Piper field (Sylvester- taken off at this point as fuel gas for the main generators,
Evans, 1991). Source: Courtesy of the Institution of Chemical Engineers. and then boosted in the first stage of two reciprocating
compressors to 1465 psia. Condensate was removed and
the gas was then further compressed in the second stage
of the reciprocating compressors to 1735 psia. The gas
firewalls, respectively); these firewalls were not designed then went three ways: to serve as lift gas at the wells, to
to resist blasts. MCP-01as export gas, or to flare. The plant could be
The pig traps for the three gas risers from Tartan and operated in two modes, which affected the method of
to MCP-01 and Claymore were on the 68 ft level. Also removing condensate. In the normal, or phase 2, mode,
on this level were the dive complex and the JT flash the gas passed from the first stage of the reciprocating
drum, the condensate suction vessel, and the condensate compressors to the Gas Conservation Module (GCM),
injection pumps. where it was dried. The gas was then cooled by reducing
There were four accommodation modules: the East the pressure across a turbo-expander so that condensate
Replacement Quarters (ERQ), the main quarters mod- was knocked out by the expansion and returned to the
ule; the Additional Accommodation East (AAE); the outlet of the JT flash drum, which was also the inlet of
Living Quarters West (LQW); and the Additional the second stage of the reciprocating compressors.
Accommodation West (AAW). Condensate from the GCM was passed to the JT flash
The control room was in a mezzanine level in the drum. The process could also revert to the original, or
upper part of D Module. It was located about one quar- phase 1 mode, dating from a period before the GCM
ter of the way along the C/D firewall from the west face. was installed to produce export quality gas, in which the
There were two flares on the south end of the plat- GCM was isolated and gas from the first stage of the
form, the east and west flares, and there was a heat shield reciprocating compressors was let down in pressure
around Module A to provide protection against the heat across the JT valve into the JT flash drum so that con-
from the flares. densate was knocked out by the Joule Thomson (JT)
Platform systems included the electrical supply system, effect and then passed as before into the second stage of
the fire and gas detection system, the fire water deluge the reciprocating compressors. Condensate from the JT
system, the emergency shut-down system, the communi- flash drum passed first to two parallel centrifugal con-
cations system, and the evacuation and escape system. densate booster pumps and then to two reciprocating
Electrical power was supplied by two main generators condensate injection pumps which pumped the conden-
which normally ran off the gas supply but could be fired sate into the main oil line. There was normally one con-
by diesel. There was a diesel-fired emergency generator densate injection pump line operating and one on
and also a drilling generator and an emergency drilling standby.
generator. In addition, there were uninterrupted power Each condensate injection pump was protected
supplies for emergency services. from overpressure on the delivery side by a single
APPENDIX 19 Piper Alpha 2851

North

Radio
room
Helideck
(174')
Derrick
East
Add Acc Replacement
East Quarters
HP flare Turbine exhausts
LP flare Gas
conservat’n Utility module
module Sub module
Drilling deck (107'')
A B C D
Gas
Wellheads Separation compression Production deck (84'')
East flare boom
DSF -------------- (68'')
Heat shield

Produced water
hydrocyclone packages

(a)

North
Helideck
Add Derrick
Quarters
accom
west west
Diesel S PE E
storage Diesel module
module
Pods Storage Mud Heat shield
module module module
107'' Level
C B
D Gas A
Compression Separation Wells
84'' Level West flare
68'' Level boom

Dive
package Dive
skid

(b)
FIGURE A19.2 The Pipe Alpha platform: (a) east elevation and (b) west elevation (Sylvester-Evans, 1991). Source: Courtesy of the Institution of
Chemical Engineers.

pressure safety valve (PSV). The PSV was on a separate were located in Module C, the relief line running up
relief line from the delivery head of the pump rather from the 68 ft level, where the pumps were located, to
than on the delivery line itself. The valve on pump A was the PSVs in Module C and back down to the condensate
PSV 504 and that on pump B was PSV 505. These valves suction vessel on the 68 ft level.
2852 Lees’ Loss Prevention in the Process Industries

45 hour 6 Hour
fire wall North
fire walls
Main oil Reciprocating
West flare export pumps compressors (x2)
boom
Emergency diesel
generator

Control room

Electrical
switch rooms

Wellheads
Manifolds
Gas turbines
Main production generators (x2)
separators
Fire pumps (x4)

Centrifugal
compressors (x3)

East flare
Module Module Module Module
boom
A B C D
FIGURE A19.3 The Piper Alpha platform: the production deck on the 84 ft level (Sylvester-Evans, 1991). Source: Courtesy of the Institution of
Chemical Engineers.
Decompression
Dive complex North
chambers (x2)

Oil lab Tartan riser (18')

Dive skid
platform Claymore pig trap
ESV

Claymore gas
Flare ko pot
Condy riser (16'')
pump
‘B’
Tartan pig trap
Condy Main export riser
and ESV pump
‘A’ Condensate (30'')
suction vessel
MCP-01 Pig trap
and ESV Control panel
JT Drum MCP -01 gas riser
(18'')

Produced Condensate booster


water pumps (x2)
package

FIGURE A19.4 The Piper Alpha platform: the 68 ft level (Sylvester-Evans, 1991). Source: Courtesy of the Institution of Chemical Engineers.
APPENDIX 19 Piper Alpha 2853

In accordance with standard practice, methanol was gas plant. There was a possibility that if the gas supply
injected into the process at various points to prevent for- to the main generator was lost and if the changeover to
mation of hydrates which would tend to cause blockages. the alternative diesel fuel failed, the wells also would
have to be shut-down. It would then be necessary to
undertake a ‘black start.’
A19.4. Events Prior to the Explosion The lead operator came up to the control room. He
On July 6, there was a major work program on the plat- talked on the telephone with the lead maintenance hand
form. This included the installation of a new riser for the and it was agreed to attempt to start pump A. The lead
Chanter field and work on a prover and metering loop. operator signed off the permit for pump A so that it
The extra accommodation for the workforce was pro- could be electrically deisolated and restarted, and went
vided on the Tharos, a large floating fire fighting vessel back down to the pumps. The lead maintenance hand
anchored near the platform. Also near the platform were came down to the control room to organize the electri-
the standby vessel, the Silver Pit, a pipeline vessel, the cians to deisolate the pump. It is uncertain precisely
Lowland Cavalier, and Maersk anchor handling vessels what action the lead operator and the phase 1 operator
for the Tharos. took. They were observed at the pumps by the phase 2
The GCM was also out of service for changeout of the operator and an instrument fitter, but the evidence of
molecular sieve driers. In consequence, the plant opera- these witnesses was inconclusive. However, there was no
tion had reverted to the phase 1 mode so that the gas doubt that the lead operator intended to start pump A.
was relatively wet. About 9:55 p.m. the signals for the tripping of two of
The resulting increased potential for hydrate forma- the centrifugal compressors in Module C came up in the
tion was recognized by management onshore. The control room. This was followed by a low gas alarm in
increased methanol injection rates required were calcu- zone C3 on centrifugal compressor C. Then, the third
lated and communicated to the platform together with centrifugal compressor tripped. Before the control room
suggestions for the configuration of the methanol pumps. operator could take any action a further group of alarms
The methanol injection rates needed were some 12 times came up: three low gas alarms in zones C2, C4, and C5
greater than for normal phase 2 operation. and a high gas alarm. The operator had his hand out to
However, there was an interruption of the methanol cancel the alarms when he was blown across the room by
supply to the most critical point, at the JT valve, between the explosion.
4:00 and 8:00 p.m. that evening. Just prior to the explosion, personnel in workshops in
The operating condensate injection pump was pump B. Module D heard a loud screeching sound which lasted
Pump A was down for maintenance. There were three for about 30 s.
maintenance jobs to be done on this pump: (1) a full
24 month preventive maintenance (PM), (2) repair of the
pump coupling, and (3) recertification of PSV 504. In A19.5. The Explosion, the Escalation, and the
order to carry out the 24 month PM, the pump had Rescue
been isolated by closing the gas operated valves (GOVs) The initial explosion occurred at 10:00 p.m. It destroyed
on the suction and delivery lines but slip plates had not most of the B/C and C/D firewalls and blew across the
been inserted. Work on the coupling, which was suffering room the two occupants of the control room, the control
from a vibration problem, would not involve breaking room operator and the lead maintenance hand.
into the pump. The emergency shut-down (ESD) system operated,
With the pump in this state, with the GOVs closed closing the emergency shut-off valve (ESV) on the main
but without slip plate isolation, access was given to oil line and starting blowdown of the gas inventories to
remove PSV 504 for testing. It was taken off in the flare. The ESVs on the gas pipelines were not designed
morning of July 6 by a two-man team from the specialist to close on platform ESD; this would impose an undesir-
contractor Score UK Ltd. They were not able to restore able forced shut-down on the other platforms connected
the PSV that evening. The supervisor in this team came to Piper. Instead there were three separate shut-down
back to the control room some time before 6:00 p.m. to buttons for these ESVs in the control room.
suspend the permit-to-work (PTW) and the team then The explosion was followed almost immediately by a
went off duty, intending to put the PSV back the next large fireball which issued from the west side of Module B
day. and a large oil pool fire at the west end of that module.
At about 4:50 p.m. that day, just at shift changeover, The explosion and fire were witnessed by personnel on
the maintenance status of the pump underwent a change. the vessels lying off the platform. One witness on the
The maintenance superintendent decided that the Tharos was standing with camera at the ready. He took a
24 month PM would not be carried out and that work sequence of shots of the development of the fireball.
on the pump should be restricted to the repair of the The large oil pool fire gave rise to a massive smoke
pump coupling. plume which enveloped the platform from the produc-
About 9:50 p.m. that evening pump B tripped out on tion deck at the 84 ft level up.
the 68 ft level. The lead production operator and the The offshore installation manager (OIM) made his
phase 1 operator attempted to restart it but without suc- way to the radio room and had a Mayday signal sent.
cess. The loss of this pump meant that with pump A also The Tharos effectively took on the role of On-Scene
down, condensate would back up in the JT flash drum Commander. The Coast Guard station and Occidental
and within some 30 min would force a shut-down of the headquarters onshore were informed. Rescue helicopters
2854 Lees’ Loss Prevention in the Process Industries

and a Nimrod aircraft for aerial on-scene command were experiencing the explosion, simply walked down to the
dispatched. The flight time for the helicopters was about 20 ft level and was picked up without getting his feet
an hour. wet. Most survivors, however, were rescued from the sea.
Most of the personnel on the platform were in the Much of the rescue operation took place after the rup-
accommodation, the majority in the ERQ. Within the ture of the Tartan riser.
first minute, flames also appeared on the north face of The FRC of another vessel, the Sandhaven, was
the module, and the module was enveloped in the smoke destroyed with only one survivor. The FRC of the Silver
plume coming from the south. The escape routes from Pit made repeated runs to the platform; eventually it was
the module to the lifeboats were impassable. blown out of the water, and began to sink, returned to
At the 68 ft level, divers were working with one man the platform, and then finally sank; its crew was rescued
under water. They followed procedure, got the man up by helicopter.
and briefly through the decompression chamber. They At about 10:50 p.m. the MCP-01 riser ruptured and
were unable to reach the lifeboats, which were inaccessi- about 11:18 p.m. the Claymore riser ruptured. The pipe
ble due to the smoke. They therefore launched life rafts deck collapsed and the ERQ tipped. By 12.15 a.m. on
and climbed down by knotted rope to the lowest level, July 7 the north end of the platform had disappeared. By
the 20 ft level. the morning only Module A, the wellhead, remained
The drill crew also followed procedure and secured standing.
the wellhead.
The oil pool in Module B began to spill over onto the
68 ft level where another fire took hold. There were A19.6. The Investigation
drums of rigwash stored on that level which may have An investigation of the disaster was immediately under-
fed the fire. taken by the Department of Energy (DoEn) headed by
The fire water drench system did not operate. There Mr. Petrie. Two reports were issued, an interim report
was only a trickle of water from the sprinkler heads. (the Petrie Interim Report, or simply, the Petrie Report) and
The explosion disabled the main communications sys- a final report (the Petrie Final Report); the latter included
tem which was centered on Piper. The other platforms appendices on various technical studies commissioned.
were unable to communicate with Piper. They became The Petrie Report put forward two scenarios for the
aware that there was a fire on Piper, but did not appreci- hydrocarbon leak which led to the explosion: a leak from
ate its scale. They continued for some time in production the site of PSV 504 (Scenario A) and a leak due to inges-
and pumping oil. This pumping would have caused some tion of liquid into the reciprocating compressors
additional oil flow from the leak at Piper. (Scenario B).
Some 20 min after the initial explosion, the fire on the The Inquiry was presided over by a Scottish judge,
68 ft level led to the rupture of the Tartan riser on the Lord Cullen, assisted by three technical assessors. There
side outboard of the ESV. This resulted in a massive jet was a legal counsel to the Inquiry assisted by technical
flame which enveloped much of the platform. consultants to the Inquiry. Parties to the Inquiry
The emergency procedure was for personnel to report included Occidental, the DoEn, groups representing sur-
to their lifeboat, but in practice most evacuations would vivors and the trade unions, the contractors, the specialist
be by helicopter and personnel would be directed from contractor Score, several equipment manufacturers and
the lifeboats to the dining area on the upper deck of the for the second part, the UK Oil Operators Association
ERQ and then to the helideck. Personnel in the ERQ (UKOOA). Part 1 of the Inquiry dealt with the disaster
found the escape routes to the lifeboats blocked and and its background, Part 2 with the future. The Inquiry
waited in the dining area. The OIM told them that a heard some 280 witnesses in 180 days of evidence and
Mayday signal had been sent and that he expected heli- received some 840 productions, or documents.
copters to be sent to effect the evacuation. In fact the They began by considering whether to advise that the
helideck was already inaccessible to helicopters. debris of the platform should be raised from the sea bed.
Some 33 min into the incident, the Tharos picked up It was clear at an early stage that the size of leak sought
the signal. ‘People majority in galley. Tharos come. was of the order of 10 mm2. The evidence was that the
Gangway. Hoses. Getting bad.’ operation presented a number of problems and hazards,
No escape from the ERQ to the sea was organized by would involve considerable delay and might well not
the senior management. However, as the quarters began provide much useful information. The Inquiry decided
to fill with smoke, individuals filtered out by various not to pursue the matter.
routes and tried to make their escape. In seeking to find the cause of the leak, the Piper Alpha
Some men climbed down knotted ropes to the sea. Report begins with the evidence on the explosion itself.
Others jumped from various levels, including the heli- It concludes that the explosion was at 10:00 p.m., that it
deck at 174 ft. One man who had arrived only that after- was in Module C and in the south-east quadrant of that
noon on his first tour jumped from a high level. One module, that the fuel involved was condensate, that the
standing on pipes protruding from the pipe deck was leak gave rise to a gas cloud filling less than 25% of the
pushed off by another behind him who could no longer module, that the mass of fuel within the flammable
stand the heat of the pipes. region was some 30 80 kg, that the explosion was a def-
The vessels around the platform launched their fast lagration rather than a detonation, that the maximum
rescue craft (FRCs). The first man rescued, by the FRC peak overpressure was in the range 0.2 0.4 bar and that
of the Silver Pit, was the oil laboratory chemist, who, on the ignition source could not be identified. Evidence for
APPENDIX 19 Piper Alpha 2855

these findings included the gas alarms in Module C; the reservations but indicated that a gas cloud of sufficient
screeching noise heard just prior to the explosion; testi- size could be formed.
mony of and photographs taken by observers on the sur- The next question considered was whether the explo-
rounding vessels of the fires just after the explosion; the sion of such a gas cloud could cause the damage
effects of the explosion, including the damage to the two observed. It was estimated that the B/C firewall would
firewalls in Module C; the effects of the explosion on the fail at an overpressure of 0.1 bar and the C/D firewall at
control room and its occupants; the lack of damage to an overpressure of 0.12 bar.
the heat shield on Module A and estimates of overpres- Simulations of the explosion of flammable mixtures in
sure based on some of the explosion effects, such as fire- the module had been commissioned prior to the Inquiry
wall damage and bodily translation of persons. at the Christian Michelsen Institute (CMI) by the DoEn
It was not initially clear how a gas cloud of sufficient and other parties. The simulations were performed using
size could develop without setting off certain gas alarms the FLACS computer code. Following the wind tunnel
which according to the evidence had not been triggered. work, the Inquiry commissioned a single further run for
In particular, there was a gas detector in the roof above a gas cloud in the south-east quadrant of Module C and
the site of PSV 504 or PSV 505 (the two valves were containing some 45 kg of propane within the flammable
close together) and another some 2 3 ft above floor level
among the heat exchangers between the reciprocating
and centrifugal compressors; both these detectors were
in C2 zone. However, the first gas alarm was in zone C3
at centrifugal compressor C. Accordingly, wind tunnel
tests were commissioned from BMT Fluid Mechanics to
explore the pattern of gas alarms for different types of Source
leak. Scenarios investigated included leaks of natural gas
1m
and of condensate, the one a buoyant and the other a
heavy gas; leaks from various points in the modules and
leaks from various types of source, including a leaking 3−4 m
flange and an open pipe. It was concluded by the investi-
gator that of the scenarios studied, only a leak from the 5m
site of PSV 504 or PSV 505 fitted the pattern of gas
alarms and, further, that this leak was a two-stage leak,
the first stage being small and the second relatively large.
It would have been this second stage which gave rise to
the gas cloud sought.
The experimental run of main interest simulated a leak
of 100 kg/min from PSV 504. Figure A19.5 shows the
contours of the lower flammability limit of the gas cloud
formed after 30 s from such a leak. The cloud would
not set off either of the gas detectors mentioned.
Figure A19.6 shows the mass of gas within the flammable
limit as a function of the leak flow rate after 30 s and at FIGURE A19.5 The flammable gas cloud for a leak of 100 kg/min in
infinite time. These results were subject to a number of the BMT wind tunnel tests: LEL (Piper Alpha Report, 1990).

50
‘Steady state’
Mass of hydrocarbon in gas cloud (kg)

t = 2 min
40

30 s after
30
release

20

10

FIGURE A19.6 Mass of fuel in 0


the flammable range in the BMT
0 50 100
wind tunnel (Piper Alpha Report,
1990). Release rate at position 1, propane (kg/min)
2856 Lees’ Loss Prevention in the Process Industries

limit. The simulation was subject to a number of reserva- that its sole PSV was off. The Inquiry concluded that the
tions but indicated that such an explosion could cause lead operator was indeed ignorant of this, even though
the firewall damage observed. this meant a serious breakdown in communication about
The simulation also provided an explanation of a point the work. It implied that that the PSV was off was not
which had seemed puzzling. The two occupants of the communicated in the handovers of the lead maintenance
control room were thrown by the explosion and experi- hand, the phase 1 operator and the lead production oper-
enced a rush of cold air, not hot gas. The simulation ator, and that the lead operator did not learn of it
showed that in the early stages of the explosion the con- through the PTW system.
trol room wall would be subject to a positive overpres- When he found that he was unable to put the PSV
sure and inrush of air, but that by the time the hot back that evening, the Score supervisor came up to the
combustion products approached the control room, the control room to suspend the permit. He was on his first
negative phase of the pressure pulse had set in, the veloc- tour as a supervisor and had had no training in the oper-
ity vectors had reversed, and the direction of air flow was ation of the PTW system in use on the platform. Whom
out of the control room into Module C. he spoke to and what transactions took place were
The two-stage nature of the leak also presented obscure. It was unclear how he knew that the procedure
another point of difficulty. Isolation of pump A was by in filling out the permit for suspension was to write
the closure of the GOVs on the suction and the delivery ‘SUSP’ in the gas test column.
lines. The suction GOV was electrically isolated and it In any event, the Score supervisor did not make a final
was uncertain whether power to it had been restored by inspection of the job site before going off work and evi-
the time of the initial explosion. In any event restoration dently the lead production operator did not inspect the
of the valve would involve reconnecting a pneumatic line job site either, although in both cases good practice
to the valve, which could quickly be done by an operator. required that this be done.
It was concluded that this connection was made and that Further, the leak would not have occurred if there had
the operator probably gave it a tweak to make sure the been a more positive isolation of the pump by means
valve movement was restored. This would have had the such as the use of a slip plate.
effect of admitting condensate to the relief line to PSV The explanation just described is that adopted in the
504, but not of filling it with condensate liquid, thus giv- Piper Alpha Report but several other scenarios for the leak
ing rise to the early, smaller leak. Subsequent opening of were also explored. One group of scenarios was con-
the valve and filling of the relief line with condensate liq- cerned with explanations of the leak from the blind
uid could then have caused the later, larger leak. flange following admission of condensate into pump A
Evidence was also heard on tests on leaks from blind other than lack of leak-tightness. They include the possi-
flanges. The flange at PSV 504 was a ring-type joint bilities of auto-ignition, shock loading, low temperature
(RTJ) flange. Three methods of tightening up were brittle fracture, and overpressurization by methanol
investigated: flogging up with a flogging spanner and injection. All of these were quickly ruled out except
hammer; hand tightening with a combination spanner; auto-ignition by compression of a flammable mixture
and finger tightening. The results showed that a flange formed in the relief line. The line had been left open for
in good condition which had been flogged up or hand an hour before the blind flange was put back on. It was
tightened did not leak. Even deterioration of the flange not possible to calculate whether auto-ignition would
would be unlikely to give the leak sought unless the dete- have occurred due to lack of data on auto-ignition prop-
rioration was gross. However, a finger-tightened flange erties of the multi-component mixture at the high pres-
could give a leak which was directionally downward and sures involved, some 300 bar. Moreover, company
was of the flow rate sought. documentation on the rating of the pipework was incon-
The Inquiry concluded that the explosion had been sistent so that it was uncertain whether the flange was a
caused by ignition of a gas cloud containing some 45 kg 900 or 1500 lb one. The expert evidence was that if
of hydrocarbon within the flammable range, arising from auto-ignition had occurred and the lower rating applied,
a two-stage leak, in the first stage perhaps some 4 kg/min a leak was possible, although whether it would have had
and in the second stage some 110 kg/min lasting some the required characteristics was another matter. An
30 s, coming from an orifice of equivalent diameter some account of this work on auto-ignition has been given by
8 mm2. S.M. Richardson, Saville, and Griffiths (1990).
There was no obvious explanation why the blind The scenario was considered that condensate liquid
flange was not leak-tight. Much evidence was led to the had backed up in the JT flash drum and thence into the
effect that an experienced and competent fitter would reciprocating compressors. There was evidence that on
not make up a blind flange which was not leak-tight. loss of pump B steps had been taken to reduce the con-
The Inquiry noted, however, that the decision not to densate make by unloading and recycling these compres-
proceed with the full 24 month PM on pump A was sors. The report concludes that there had been
taken just as shift handovers on the platform were start- insufficient time for backup to occur before the initial
ing so that some personnel may have been ignorant of explosion and that in addition both the conditions
this change in intent and that the lack of leak-tightness around the compressors and the expected action of pro-
of the blind flange may have been connected with the tective instrumentation were against this scenario.
status of pump A. A further scenario which emerged in the Inquiry was
The lead production operator clearly had the intention that the leak occurred from PSV 505 and that it was
to start pump A. It was difficult to explain this given fact caused by hydrate blockage. The interruption to the
APPENDIX 19 Piper Alpha 2857

methanol supply to the JT valve lent credibility to this Following the initial explosion, a period of extended
scenario. Experimental work commissioned showed that flaring occurred which greatly exceeded that to be
hydrates would form under the conditions pertaining at expected from the flaring of the gas inventory on the
the JT valve during the partial loss of methanol supply if platform. The report accepted that the most probable
the temperature at the valve fell below a critical value; it explanation was a failure of the Claymore ESV to close
had in fact been below this temperature on July 5. The fully.
expert evidence was that hydrates could pass through to The main communications for the Piper field were
the condensate injection pumps and cause blockage there centered on Piper. The system was knocked out by the
some 2 h after restitution of the full methanol supply. initial explosion, so that the other platforms were unable
There were several versions of the scenario all leading to to communicate with Piper and had difficulty communi-
blockage of hydrate at PSV 505 and overrunning of the cating with the shore.
pump so that the delivery pressure rose to a value high The report details a number of management weak-
enough to cause rupture of the valve, which was the nesses. There were severe and numerous defects in the
weakest point in the line. The report does not rule out PTW system. For example, it violated more than half of
this scenario, but regards it as less likely than the pre- the main points in the code of practice on PTWs issued
ferred one. by the Oil Industry Advisory Committee (OIAC). The
Finally, the consultants to the Inquiry reviewed a large system was operated rather casually. The training of the
number of other scenarios which were not purely theo- specialist contractor’s supervisor in the permit system
retical but had some link with the information available operated on the platform was found to be inadequate.
at the time, which included a HAZOP study, past equip- With regard to handovers, the company had been
ment failures, and process conditions that evening. None prosecuted only a year before for a fatality and had
was found convincing by the Inquiry. pleaded guilty. The report takes the view that a failure in
Turning to the escalation, the causes of the oil pool handover procedures was a factor in that accident.
fire and the fireball which occurred in Module B within A number of different types of audits were performed
seconds of the explosion in Module C were unclear. The by the company, by its partners, by loss prevention spe-
Inquiry heard evidence on the type, number, velocity, cialists, and so on. None of these had revealed the defects
and impact effects of the projectiles which would have in the PTW which became apparent very quickly at the
resulted from the destruction of the B/C firewall. The Inquiry.
condensate injection line ran from Module C through The report is critical of the handling of the emergency
into Module B where it joined the main oil line. The by the senior management on the platform and in partic-
report concludes that probably the fireball was caused by ular of the failure to recognize that helicopter evacuation
a missile rupturing this line near the main oil pumps at was not possible and to take command of the situation
the west face of Module B. and organize escape from the ERQ.
Estimates of the size of the oil pool fire indicated that The decision to keep the platform operating despite
the supply of oil to the fire probably exceeded the oil the large workload is another matter of which the report
inventory of the separators and that there was a leak of oil is critical.
from the main oil line through the main oil line EVS The report states that the company had no system to
which was not fully closed. This leak would be aggravated ensure that all projects were subject to formal safety
by continued pumping of oil by the other platforms. assessment. Certain techniques such as HAZOP were
The fire water deluge system did not work. The initial used on some projects and quantitative estimates had
explosion knocked out the main power supplies. It may been made in some studies, but the approach was unsys-
also have damaged the water pumps and the water mains. tematic. The report takes the view that as a consequence
In any event, it was the practice on Piper to put the pumps the hazards presented by the hydrocarbon inventory on
on manual start when divers were in the water and thus in the platform and particularly in the pipelines had not
possible danger of being sucked into the pump intakes, been systematically addressed.
and they were on manual start that evening. The start Part 2 of the Inquiry was concerned with the future
controls were at the pumps themselves. After the explo- offshore safety regime. The context was not only the
sion occurred an attempt was made to get through to the Piper Alpha disaster but also the changes taking place in
pumps to start them by personnel wearing breathing the North Sea oil province. The exploitable oil and gas
apparatus, but to no avail. Further evidence was given of fields were becoming smaller and the technology to
quite extensive blockage caused by corrosion products in develop them was becoming more varied.
the fire water deluge system, which operated on sea water, The evidence in Part 1 revealed serious weaknesses in
a problem which had persisted for some years. the company management. It was an issue that the DoEn
The initial explosion caused the operation of the plat- had not discovered these weaknesses. The report is criti-
form ESD. This could have occurred through loss of the cal of the relative lack of emphasis placed by the
main power supply and/or rupture of a pneumatic ring Department on the assessment of management and man-
main. Also, although dazed by the explosion, the control agement systems.
room operator pressed the platform ESD button. He did In contrast to the British onshore and Norwegian off-
not, however, press the buttons to close the ESVs on the shore regimes, which had both moved increasingly
three gas pipelines. Evidently, these did close but their toward goal-setting regulations, the British offshore
closure was due rather to the effects of the initial explo- regime relied excessively on prescriptive regulations and
sion on power supplies to the valves. associated guidance.
2858 Lees’ Loss Prevention in the Process Industries

The deficiencies of such a regime were illustrated in


the regulations concerning fire protection, which had a TABLE A19.2 Some Lessons of Piper Alpha
number of defects. Passive and active fire protection Regulatory control of offshore installations
were covered by two separate sets of regulations. The Quality of safety management
regulations, and associated guidance, for active fire pro- Safety management system
tection led in practice to systems based on delivery of a Documentation of plant
uniform quantity of water over large areas of a platform,
Fallback states in plant operation
deluge systems prone to blockage and massive water
Permit-to-work systems
pumps. Fire protection was not integrated with explosion
protection. Isolation of plant for maintenance
The report states that the approach taken by the Training of contractors personnel
DoEn to the control of the major hazards from hydro- Disabling of protective equipment by explosion itself
carbons at high pressure did not impress as an effective Offshore installations: control of pressure systems for hydrocarbons
one. Further, the inspectorate had relatively little exper- at high pressure
tise in this area. Offshore installations: limitation of inventory on installation and in
Following the Piper Alpha disaster the DoEn brought its pipelines
in regulations to require ESVs to be placed nearer to sea Offshore installations: emergency shut-down system
level and for the valves to be of full ESV standard. The Offshore installations: fire and explosion protection
report notes that of the 400 risers covered by the regula- Offshore installations: temporary safe refuge
tions, some 70 required modification in the latter respect. Offshore installations: limitation of exposure of personnel
The regime made little use of formal safety assessment Offshore installations: formal safety assessment
(FSA). This was in contrast to the regulatory use of FSA Offshore installations: safety case
onshore, and in particular the onshore safety case. The Offshore installations: use of wind tunnel tests and explosion
DoEn had in fact explicitly rejected the concept of an simulations in design
offshore safety case. This policy also contrasted with the The explosion and fire phenomena
situation in the Norwegian sector, where a concept safety Explosions in semi-confined modules
evaluation (CSE) was required. Quantitative risk assess- Pool fires
ment is required in a CSE and is often necessary to fulfill
Jet flames
the requirements of a safety case.
Publication of reports of accident investigations
Considerable evidence was heard on quantitative risk
assessment (QRA). The burden of this evidence was that
QRA is in regular use in many companies as an aid to
decision-making both for onshore and offshore installa-
A19.7.1.2. Quality of Safety Management
tions and that there was no serious impediment to this
The Piper Alpha Report is critical of the quality of man-
from any problems of overall methodology, frequency
agement, and particularly safety management, in the
estimation, consequence modeling, or risk criteria.
company.
In contrast to the HSE, the DoEn was not well
It was not that the company did not put effort into
equipped to operate a regime based on goal-setting regu-
safety. On the contrary, there were numerous meetings
lations and FSA. It had no experts in FSA or fire
and much training on safety. The problem was the qual-
protection.
ity of these activities.
A number of recommendations which would have met
Many managers had come up through the ranks and
some of the points on which the DoEn was criticized
had minimal qualifications. The culture tended to be
had been made in the Burgoyne Report (Burgoyne, 1980),
somewhat in-grown and insufficiently self-critical.
but had not been implemented.
These defects manifested themselves in various ways
such as in the toleration of poor practices in plant isola-
A19.7. Some Lessons of Piper Alpha tion and operation of the PTW system; in the failure to
appreciate the ineffectiveness of the audits done; in the
A19.7.1. Some Lessons failure to address the major hazard problem and to use
Lessons from the Piper Alpha disaster are considered in FSA. The report comments:
this section with the exception of the recommendations
Senior management were too easily satisfied that the
of the report on the offshore safety regime which are
PTW system was being operated correctly, relying on the
considered in Section A19.8. A list of some of the lessons
absence of any feedback of problems as indicating that all
is given in Table A19.2. Many apply particularly to off-
was well. They failed to provide the training necessary to
shore installations, but others are of more general
ensure that an effective PTW system was operated in
applicability.
practice. In the face of a known problem with the deluge
A19.7.1.1. Regulatory Control of Offshore system they did not personally become involved in probing
Installations the extent of the problem and what should be done to
The Piper Alpha disaster exposed weaknesses in the resolve it as soon as possible. They adopted a superficial
offshore regulatory regime which have already been response when issues of safety were raised by others, . . .
described. The lessons drawn are seen in the recommen- They failed to ensure that emergency training was being
dations given in Section A19.8. provided as they intended. Platform personnel and
APPENDIX 19 Piper Alpha 2859

management were not prepared for a major emergency as condensate was admitted to a pump from which the PSV
they should have been (para 14.52). had been removed and hence to the disaster. The Piper
Alpha Report devotes considerable attention to the need
A crucial weakness was failure to appreciate that
for an effective system.
absence of feedback to management about problems is
almost certainly an indicator not that there are no pro- A19.7.1.7. Isolation of Plant for Maintenance
blems but that there are, and they could be serious. Of The Piper Alpha Report states that the disaster would not
one OIM the report states, ‘His approach seemed to be, have occurred if pump A had been positively isolated so
in his own words, “surely that is all you are concerned that condensate could not be admitted. Positive isolation is
with about the permit system . . . If the system is working not achieved by shutting a valve but requires means such as
and no problems are identified . . . then you should be rea- insertion of a slip plate or removal of a pipe section.
sonably happy with it, surely?”. . . He had been surprised
by the number of deficiencies in the operation of the per- A19.7.1.8. Training of Contractors’ Personnel
mit system which had been revealed in the Inquiry. He The proportion of contractors’ personnel on an offshore
had checked this out and found it to be true.’ Of another installation can be as high as 70%. The offshore scene
manager the report states that he said ‘he knew that the therefore exemplifies in extreme form a problem which
system was monitored on a daily basis by safety personnel. applies to onshore plants also. This is the need to train
By the lack of feedback he “knew that things were going contractors’ personnel in the company’s operating and
all right and there was no indication that we had any sig- emergency systems and procedures. Failure to train a
nificant permit to work problems”’ (para 14.26). contractor’s supervisor in the operation of the PTW sys-
tem on Piper meant that he was unfamiliar with a feature
A19.7.1.3. Safety Management System of the system which turned out to be a critical one.
Onshore the quality of the management and the manage-
ment system are of prime concern to the HSE in its A19.7.1.9. Disabling of Protective Equipment by
inspections in general and in the safety case in particular. Explosion Itself
In submitting a safety case, a company will often give The initial explosion on Piper disabled large parts of the
extensive documentation on its systems. Nevertheless, in protective systems, including power supplies and fire
the regulations the formal requirements on management water supplies. It illustrates the importance of taking this
are fairly minimal. factor into account in design and in FSA.
The Inquiry heard evidence in favor of the assurance of A19.7.1.10. Offshore Installations: Control of
safety through the use of quality assurance to standards Pressure Systems for Hydrocarbons at High Pressure
such as BS 5750 and ISO 9000. It also heard evidence on An offshore production platform contains a large amount
the need for better qualified management, including a of plant containing hydrocarbons at high pressure. The
proposed requirement for all OIMs to be graduates. feed to this plant is from the wells, which can sometimes
The concept of a safety management system goes part behave in an unpredictable way. The pipelines connected
way toward these insofar as the system itself is based on to the platform contain large quantities of hydrocarbon,
principles similar to those of quality assurance and covers the high pressure gas pipelines constituting a particularly
the question of management quality. serious hazard.
A19.7.1.4. Documentation of Plant There needs therefore to be a comprehensive system
The discrepancies in the documentation concerning the for the control of the total pressure system, covering
rating of the flange on PSV 504 have already been men- design, fabrication, installation, operation, inspection,
tioned. The Inquiry in fact heard of a number of other maintenance and modification, and including control of
defects in the documentation of the plant. Failure to such features as materials of construction, lifting of loads,
maintain correct records can have serious consequences. and so on, and personnel need to be trained in the pur-
poses and operation of system.
A19.7.1.5. Fallback States in Plant Operation
The loss of the working condensate pump on Piper cre- A19.7.1.11. Offshore Installations: Limitation of
ated a situation where operating personnel were under Inventory on Installation and in its Pipelines
some pressure to start the other pump and avoid a gas The scale of the Piper disaster was due primarily to the
plant shut-down with its possible escalation to a total large inventory of the three high pressure gas pipelines
shut-down, loss of power, and the need for a ‘black start.’ connected to the platform. The Inquiry heard evidence
In this case, the pressure was created partly by the view on the practicalities of reducing the number of gas pipe-
which an individual took of the probability that the lines connected to a platform. There are many technical
changeover of the main generators from gas to diesel problems involved, but the point has been made that
would fail. This illustrates the desirability of ensuring such reduction should be a design objective.
that plants have fallback states short of total shut-down. The main inventory of hydrocarbons in process on a
In this case, the problem was in the reliability of change- platform is in the separators. The massive oil pool fire
over, a type of problem which may lie with design or on Piper was fed from the separators. The Piper Alpha
with maintenance. Report recommends that methods of dumping this inven-
tory be explored.
A19.7.1.6. Permit-to-Work Systems Evidence was also heard that in some cases the main
The defects in the PTW system have already been inventory of hydrocarbons on a platform might be the
described. These defects led directly to a situation where diesel fuel.
2860 Lees’ Loss Prevention in the Process Industries

The alternative method of preventing the hydrocarbon application of the principle to other aspects such as the
inventory from feeding a fire is emergency isolation, location of workshops.
which is considered next.
A19.7.1.16. Offshore Installations: Formal Safety
A19.7.1.12. Offshore Installations: Emergency Assessment
Shut-Down System The evidence showed that many companies which oper-
The ESD system on Piper operated, shut-down ESVs, ate installations onshore and offshore have formal sys-
and blew the gas inventory on the platform down to tems for safety assessment and practice FSA routinely,
flare. that FSA has considerable benefits in the design and
Nevertheless, the accident drew attention to a number operation of plant and that it provides a suitable basis for
of problems in effecting isolation, some specific to off- dialogue between the company and the regulatory body.
shore platforms and some more generally applicable.
The Tartan riser ruptured on the outboard side of the A19.7.1.17. Offshore Installations: Safety Case
ESV so that closure of this valve was of no avail. It is A safety case is a particular form of FSA. The evidence
clear that an ESV needs to be located as close to the sea indicated that a safety case is as applicable offshore as
level as practical in order to minimize this risk. onshore and that it is a suitable means for the company
It is possible to go one step further and install a subsea to demonstrate to the regulatory body that it has identi-
isolation valve, but this is for consideration on a case-by- fied the major hazards of its installation and has them
case basis. under control.
Both types of isolation valve received considerable A19.7.1.18. Offshore Installations: Use of Wind
attention in the Inquiry. However, neither will be effec- Tunnel Tests and Explosion Simulations in Design
tive unless it achieves tight shut-off. The evidence that Wind tunnel tests and explosion simulations were used in
the main oil line and the Claymore gas line ESVs did the Inquiry to investigate the cause of the explosion, but
not shut-off tightly emphasizes the importance of this evidence was also heard of their value in platform design.
feature. Wind tunnels may be used to assess the effectiveness
Moreover, in order to be effective the ESD system has of ventilation and of the gas detection system in a mod-
to be activated. The fact that on Piper closure of the ule, the wind conditions at the helideck and the move-
three gas line ESVs was not part of the platform ESD ment of smoke from oil pool fires. Explosion simulations
but had to be effected for each line separately by manual may be used to investigate the effect of different module
pushbutton, that these buttons were not pushed and that layouts on explosion overpressures and to assess the
closure only occurred due to loss of power shows that effectiveness of blast walls.
this problem also is not a trivial one.
A19.7.1.19. The Explosion and Fire Phenomena
A19.7.1.13. Offshore Installations: Fire and The Piper disaster drew attention to several important
Explosion Protection aspects of explosion and fire on offshore installations.
An offshore installation is not in general able to call on These include explosions in semi-confined modules, oil
outside assistance comparable with that available from the pool fires, and jet flames.
fire brigade to an onshore plant. It must be self-reliant. Explosions in semi-confined and congested modules
This implies that both protection against, and mitiga- are a hazard which assumes particular significance off-
tion of, fire and explosion on the one hand and fire fight- shore. Although major progress has been made in the
ing on the other are of particular importance and that last decade in simulating such explosions and developing
both the hazard assessment and the design and operation design methods, this remains an area where further work
of the plant must be of high quality. is needed.
A19.7.1.14. Offshore Installations: Temporary Oil pool fires onshore are relatively well understood,
Safe Refuge but this does not apply to the behavior of such a pool
It is clear from the Piper disaster that there needs to be a fire on an offshore platform. Aspects of some importance
temporary safe refuge (TSR) where personnel can shelter are design to prevent accumulation of an oil pool in the
in an emergency and where the emergency can be con- first place and the massive smoke plume from such a fire.
trolled and evacuation organized. Jet flames, including jet flames from risers, are particu-
This TSR will normally be the accommodation. In larly important for offshore platforms. In this case, a
most cases, it will be on the production platform itself, number of models developed for flares and flames on
but it may be on a separate accommodation platform. onshore plant are available, including pipelines, which
The protection of the TSR from ingress of smoke and can be applied offshore.
fumes from outside and from generation of fumes by Evidence given indicated that in considering the haz-
fires playing on the outside needs careful attention. ard of a jet flame from a riser, the worst case was not
Measures require to be taken to prevent smoke ingress necessarily a full bore rupture but a partial rupture, since
through doors and through the ventilation system. the latter is sustained for a longer period.
A19.7.1.15. Offshore Installations: Limitation of A19.7.1.20. Publication of Reports in Accident
Exposure of Personnel Investigation
The concept of a TSR is a particular application of The Inquiry heard that the company had a policy of
the more general principle of limitation of exposure of severely restricting circulation of accident investigation
personnel. The Inquiry also heard evidence of the reports.
APPENDIX 19 Piper Alpha 2861

TABLE A19.3 Outline of a Model of a Typical Accident TABLE A19.4 Some Elements of the Safety Management
System
Deficiencies in
Organizational structure
Initial event: gas explosion Operational control
Management personnel standards
Escalation 1: explosion Hazard identification, assessment, and
damage management Training for operations and emergencies
Explosion mitigation Safety assessment
Escalation 2: oil pool fire Hazard identification, assessment, and Design procedures
management Procedures, for operations, maintenance, modifications, and
Fire mitigation and fire fighting emergencies
Inter-platform emergency planning Management of safety by contractors in respect of their work
Escalation 3: riser rupture Hazard identification, assessment, and Involvement of the workforce (operator’s and contractors’) in safety
management Accident and incident reporting, investigation, and follow-up
Fire protection of risers Monitoring and auditing of the operation of the system
Escalation 4: Hazard identification, assessment, and Systematic re-appraisal of the system in light of experience of the
accommodation failure management operator and industry
TSR fire and smoke protection
Emergency command and control

case, it is required that the operator should demonstrate


Likewise, the DoEn did not make public reports on that the installation has a TSR in which the personnel on
major offshore accidents. This contrasts markedly with the installation may shelter while the emergency is
the HSE policy of issuing reports on major accidents, brought under control and evacuation organized.
many of which are referred to in this book. Further, it is recommended that this demonstration
should be by QRA. This means that there must be crite-
A19.7.2. An Accident Model ria which define the failure of the TSR and criteria for
its endurance time and its failure frequency. The criteria
The outline of a model of the accident highlights the
may then be met by reducing the frequency of accidental
role played by some of the features just mentioned events, by increasing the durability of the TSR or by
(Table A19.3): some combination of these.
The recommendation on the safety case includes a
A19.8. Recommendations on the Offshore requirement that the operator should demonstrate that it
Safety Regime has a safety management system (SMS) to ensure the safe
The Piper Alpha Report makes recommendations for fun- design and operation of the installation. This SMS
damental changes in the offshore safety regime. should draw on quality assurance principles similar to
The basis of the recommendations is that the responsibil- those of BS 5750 and ISO 9000. The elements of the
ity for safety should lie with the operator of the installation SMS should include those listed in Table A19.4. They
and that nothing in the regime should detract from this. include management personnel standards.
The offshore regime envisaged in the recommenda- Various measures related to hardware were urged at
tions is one in which the emphasis is on the operator the Inquiry. These included the provision of separate
demonstrating to the regulatory authority the safe design accommodation platforms, the installation of subsea iso-
and operation of its installation rather than demonstrat- lation valves and blast walls, the use of freefall lifeboats
ing mere compliance with regulations. In this regime, and purpose-built standby vessels. The report takes the
the preferred form of regulations is goal-setting rather view, however, that in accordance with its basic philoso-
than prescriptive. phy such matters should be dealt with as part of the
The recommendations envisage that FSA will play a demonstration of safe design and operation.
major role. It may be used to demonstrate compliance The report considers that the then current regulatory
with a goal-setting regulation or with the general body, the DoEn, is unsuitable as the body to be charged
requirements of the HSWA. with implementing the new regime and recommends the
A central feature of the regime proposed is the safety transfer of responsibility for offshore safety to the HSE.
case for the installation. This safety case is broadly simi- These recommendations were accepted immediately
lar to that required for onshore installations but there by the government and the new regime under the HSE
are some important differences. In the offshore safety began in April 1991.

You might also like